Real-time monitoring equipment based on digital twin technology and monitoring method thereof

Through digital twin technology combining real-time monitoring equipment with gravity sensors and hydraulic cylinders, the problem of weight monitoring of construction materials in smart construction sites is solved, ensuring the stability of construction progress and cost.

CN118890550APending Publication Date: 2024-11-01HANGZHOU WUSHENG INTELLIGENT CONSTRUCTION TECHNOLOGY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410912708.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-09
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

Existing smart construction site technology cannot monitor the weight of construction materials in real time, resulting in less transportation of construction materials or being accidentally pulled away, affecting construction progress and costs.

Method used

Real-time monitoring equipment based on digital twin technology, including construction site entry and exit boards, load-bearing boards, gravity sensors and hydraulic cylinders, uses monitoring mechanisms to capture vehicle information, detect cargo weight, and move mismatched vehicles to one side for manual inspection. , ensure the accuracy and efficiency of material monitoring.

Benefits of technology

Real-time monitoring of the weight of vehicles and cargoes entering and leaving the construction site is achieved, reducing material losses, improving the stability of construction progress and material management efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118890550A_ABST
    Figure CN118890550A_ABST
Patent Text Reader

Abstract

The invention discloses real-time monitoring equipment based on a digital twinning technology and a monitoring method thereof. The real-time monitoring equipment comprises construction site in-out plates, and lifting interception columns and monitoring mechanisms are arranged on the construction site in-out plates; the bearing plate is movably connected to the foundation pit, the foundation pit comprises a vehicle weighing area, a bearing plate descending area and a bearing plate ascending area, a side plate is arranged on the side, close to the construction site access plate, of the vehicle weighing area, a gravity sensor is arranged on the top face of the side plate, and a jacking mechanism is connected to the side plate; auxiliary supporting mechanisms are arranged in the vehicle weighing area and the bearing plate descending area. And a control box. According to the invention, not only can vehicles entering and exiting a construction site be identified and cargo weight be monitored, but also vehicles which are not matched with the cargo weight can be moved to one side for manual inspection, so that the phenomenon that construction materials are not transported or are pulled away accidentally is reduced, the material monitoring efficiency is improved, and the construction cost is reduced. And real-time data display can be carried out through a digital twinning technology, so that stable construction progress is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to real-time monitoring equipment and a monitoring method thereof based on digital twin technology. Background Art

[0002] A smart construction site refers to the use of information technology to accurately design and simulate construction projects through a three-dimensional design platform. It focuses on construction process management to establish an information ecosystem for construction projects that is interconnected, collaborative, intelligently produced, and scientifically managed. It also conducts data mining and analysis on engineering information collected through the Internet of Things in a virtual reality environment, provides process trend forecasts and expert plans, and realizes visual and intelligent management of engineering construction, so as to improve the level of information technology in engineering management and gradually achieve green and ecological construction.

[0003] Smart construction sites will implant more high-tech technologies such as artificial intelligence, sensing technology, virtual reality, etc. into various objects such as buildings, machinery, personnel wearable devices, site entry and exit checkpoints, etc., and they are generally interconnected to form an "Internet of Things", and then integrated with the "Internet" to achieve the integration of project management and construction sites.

[0004] Although current smart construction sites can identify vehicles entering and leaving the site, they are unable to monitor the real-time weight of construction materials loaded on the vehicles, resulting in construction materials being under-transported or accidentally pulled away, which not only increases construction costs but also affects construction progress. Summary of the invention

[0005] The purpose of the present invention is to provide a technical solution of real-time monitoring equipment and monitoring method based on digital twin technology to address the shortcomings of the prior art. It can not only identify vehicles entering and leaving the construction site and monitor the weight of cargo, but also move vehicles that do not match the cargo weight to one side for manual inspection, thereby reducing the occurrence of construction materials being under-transported or accidentally pulled away, improving the efficiency of material monitoring, and can display real-time data through digital twin technology to ensure steady progress of construction.

[0006] In order to solve the above technical problems, the present invention adopts the following technical solutions:

[0007] Real-time monitoring equipment based on digital twin technology, characterized by:

[0008] Two construction site access panels, both of which are equipped with lifting interception columns for intercepting vehicles entering and leaving the construction site and monitoring mechanisms for photographing vehicles entering and leaving the construction site;

[0009] At least two bearing plates, the bearing plates are movably connected to the foundation pit, the foundation pit includes a vehicle weighing area, a bearing plate descending area and a bearing plate ascending area, the bearing plate descending area and the bearing plate ascending area are located on both sides of the vehicle weighing area, the vehicle weighing area is located between two construction site access plates, a side plate is provided on the side of the vehicle weighing area close to the construction site access plate, a gravity sensor is provided on the top surface of the side plate, a jacking mechanism is connected to the side plate, a groove is provided in the vehicle weighing area and the bearing plate descending area, an auxiliary supporting mechanism for supporting the jacking mechanism is provided in the groove, a moving mechanism for lateral movement of the bearing plate is provided between the vehicle weighing area, the bearing plate descending area and the bearing plate ascending area, a first hydraulic cylinder and a third hydraulic cylinder are provided at the bottom and side of the bearing plate ascending area respectively, and the third hydraulic is connected to a third L-shaped plate;

[0010] and a control box, which is connected to a monitoring mechanism, a gravity sensor, a jacking mechanism, an auxiliary supporting mechanism, a moving mechanism, a first hydraulic cylinder and a third hydraulic cylinder. Through the design of the above structure, not only can the vehicles entering and leaving the construction site be identified and the weight of the cargo be monitored, but also the vehicles that do not match the cargo weight can be moved to one side for manual inspection, thereby reducing the occurrence of insufficient transportation of construction materials or accidental pulling away of construction materials, improving the efficiency of material monitoring, and real-time data display through digital twin technology to ensure steady progress of construction.

[0011] Furthermore, the monitoring mechanism includes a lifting assembly, a beam and a monitoring assembly. The lifting assembly is connected to both sides of the construction site access plate. The beam is arranged between the two lifting assemblies. A first baffle is arranged on the beam. A second motor is arranged on the first baffle on one side. The second motor is connected to the first baffle on the other side through a second screw. The monitoring assembly is connected to the first screw and the beam. The lifting assembly can drive the beam and the monitoring assembly to move up and down synchronously to meet the identification requirements of vehicles of different heights. The second motor can drive the second screw to rotate, and then drive the monitoring assembly to move horizontally along the beam to adjust the horizontal position of the monitoring assembly. The operation is convenient and quick.

[0012] Furthermore, the lifting assembly includes a base plate, a top plate, a guide rod and a first motor. The base plate is fixed to the construction site entry and exit plate, the top plate is connected to the base plate through the guide rod, the first motor is arranged on the base plate, the first motor is connected to the top plate through the first screw, the crossbeam is connected to the guide rod and the first screw, and the first motor drives the first screw to rotate, thereby driving the crossbeam to move up and down along the guide rod, thereby meeting the height adjustment requirements of the monitoring assembly.

[0013] Furthermore, the monitoring component includes a vertical plate, a horizontal plate, a driving motor, a rotating plate and a monitoring camera. The horizontal plate is vertically connected to the vertical plate, a reinforcing plate is provided between the vertical plate and the horizontal plate, a first L-shaped plate is provided on the vertical plate above the horizontal plate, a pressure plate and a first booster block connected to the first screw are provided on the first L-shaped plate, the rotating plate is connected to the driving motor through a gear set, the driving motor is connected to the bottom of the horizontal plate through a U-shaped frame, an auxiliary rod is provided on the rotating plate, the auxiliary rod is movably connected to the pressure plate, the monitoring camera is connected to the electric cylinder through an electric push rod, the electric cylinder is provided on the rotating plate, and a first slide rail is symmetrically provided on the bottom surface of the monitoring camera, a first slider is connected to the first slide rail, the first slider is rotatably connected to the support plate, and the bottom end of the support plate is fixed to the rotating plate The plate is designed with the first L-shaped plate, the vertical plate and the horizontal plate, so that the entire monitoring assembly can be mounted on the crossbeam, and the movement is stable and reliable. The U-shaped frame improves the stability and reliability of the installation of the driving motor. The driving motor can drive the rotating plate to rotate through the gear set, so as to meet the angle adjustment of the monitoring camera in the horizontal direction and increase the monitoring range. An arc groove is arranged on the pressure plate, and the auxiliary rod can move along the arc groove, so as to improve the stability and reliability of the rotating plate during the rotation process. The electric cylinder drives the electric push rod to move up and down, and then can drive the monitoring camera to rotate along the supporting plate, so as to meet the angle adjustment requirement of the monitoring camera in the vertical plane. The first slider and the first slide rail can realize the movement requirement of the monitoring camera during the rotation process.

[0014] Furthermore, the supporting mechanism includes a second L-shaped plate, a hydraulic jack, a third motor, a second baffle and a third screw. The second L-shaped plate horizontally passes through the first guide groove on the side plate. The hydraulic jacks are distributed on the top surface of the second L-shaped plate. The bottom surface of the second L-shaped plate is provided with a second booster block. The third motor and the second baffle are arranged on the outer side of the side plate. The third motor is connected to the second baffle through the third screw. The second booster block is connected to the third screw. The bearing plate can be supported by the hydraulic jack to improve the stability and reliability of the bearing plate during movement. The third screw is driven to rotate by the third motor, and then the second L-shaped plate can be driven to move along the first guide groove on the side plate through the second booster block, thereby meeting the requirements for movement of the bearing plate.

[0015] Furthermore, the auxiliary support mechanism includes a base plate, a horizontal adjustment component, a retractable and deployable component and a lifting plate. The base plate is connected to the groove through the horizontal adjustment component, and the lifting plate is connected to the base plate through the retractable and deployable component. The base plate is driven to move horizontally along the groove through the horizontal adjustment component, thereby meeting the transportation requirements of the carrier plate. The retractable and deployable component can drive the lifting plate to move up and down, thereby meeting the support requirements of the top support mechanism.

[0016] Furthermore, the horizontal adjustment component includes a fourth motor, a fourth screw, a third booster block, a third slide rail and a third slider. The fourth motor and the third slide rail are arranged in the groove. The fourth motor is connected to the fourth screw. The third booster block and the third slider are both arranged on the bottom surface of the substrate. The third booster block is connected to the fourth screw. The third slider slides along the third slide rail. The fourth screw is driven to rotate by the fourth motor, and then the substrate can be driven to move horizontally along the groove by the third booster block, thereby meeting the conveying requirements of the carrying plate. The third slide rail and the third slider improve the stability and reliability of the substrate during movement.

[0017] Furthermore, the folding and unfolding assembly includes a second slide rail, a support block, a second hydraulic cylinder and a double-layer folding and unfolding frame, the second slide rail and the support block are all arranged on the base plate, the second slide rail is slidably connected with a second sliding block, the bottom of the double-layer folding and unfolding frame is rotatably connected to the second sliding block and the support block, one side of the top of the double-layer folding and unfolding frame is rotatably connected to the lifting plate, the lifting plate is provided with a third guide groove, the other side of the top of the double-layer folding and unfolding frame is slidably connected to the third guide groove through the guide block, a through groove is provided on the base plate, the second hydraulic cylinder is rotatably connected in the through groove, a booster rod is provided between the two second sliding blocks, the booster rod is connected to the hydraulic cylinder of the second hydraulic cylinder, and the booster rod is driven horizontally by the second hydraulic cylinder through the hydraulic cylinder, and then the second sliding block can be driven to move horizontally along the second slide rail to realize the expansion or folding requirement of the double-layer folding and unfolding frame, and the guide block is driven by the double-layer folding and unfolding frame to move along the third guide groove on the lifting plate to realize the height adjustment of the lifting plate to meet the support requirements of the top supporting mechanism.

[0018] Furthermore, the moving mechanism includes a fifth motor, a fifth screw, a fourth booster block and a moving plate. The fifth motor is connected to the second guide groove. The two ends of the fifth screw are respectively connected to the fifth motor and the inner wall of the foundation pit. The moving plate is connected to the fifth screw through the fourth booster block. The fourth booster block moves along the second guide groove. A clamping block is provided on the top surface of the moving plate, and a clamping slot is provided on the bearing plate. The clamping block and the clamping block match each other. The fifth screw is driven to rotate by the fifth motor, and then the moving plate can be driven to move along the second guide groove by the fourth booster block, thereby meeting the conveying requirements of the bearing plate. The design of the clamping block and the clamping slot improves the stability and reliability of the bearing plate during conveying.

[0019] The monitoring method of the real-time monitoring device based on the digital twin technology as described above is characterized by comprising the following steps:

[0020] S1. Use the monitoring mechanism to photograph vehicles entering and leaving the construction site, obtain vehicle information, and then transmit the data to the digital twin management module through the control module in the control box via the signal transceiver module and store it in the database module;

[0021] S2, according to the identified vehicle information, the hydraulic pump is controlled to work, the lifting and intercepting column on the construction site access plate close to the vehicle side is lowered, the vehicle is driven into the load-bearing plate in the middle, and the lifting and intercepting column is raised;

[0022] S3. Then, the weight of the vehicle and the cargo is detected by the gravity sensor. The control module in the control box transmits the data to the digital twin management module through the signal transceiver module and stores it in the database module. After the weight and vehicle information match, the lifting interception column descends, and the vehicle enters the construction site for unloading or drives out of the construction site;

[0023] S4. When the weight and vehicle information do not match, the lifting interception columns on the access plates on both sides of the construction site do not descend, and the supporting mechanism and the auxiliary supporting mechanism cooperate to move the load-bearing plate carrying the vehicle horizontally to the load-bearing plate descending area, and at the same time, the load-bearing plate located in the load-bearing plate ascending area rises and is pushed horizontally into the vehicle weighing area;

[0024] S5, manually inspecting the vehicles and cargoes in the lowering area of ​​the load plate, and after the vehicles are qualified, driving the vehicles away from the load plate in the lowering area of ​​the load plate, retracting the auxiliary support mechanism into the groove, horizontally moving the load plate in the lowering area of ​​the load plate to the ascending area of ​​the load plate by the moving mechanism, and lifting the load plate to the top of the ascending area of ​​the load plate by the first hydraulic cylinder, while moving the moving mechanism into the lowering area of ​​the load plate;

[0025] S6. Finally, the jacking mechanism and the auxiliary support mechanism are moved to the vehicle weighing area, and the auxiliary support mechanism is unfolded to support the jacking mechanism. The jacking mechanism supports the load-bearing plate in the vehicle weighing area to monitor the next vehicle.

[0026] The monitoring method has simple steps and can not only realize accurate identification of vehicles, but also accurately weigh vehicles and loaded goods. Vehicles that exceed the set weight value can be manually inspected, which greatly reduces the loss of construction materials and ensures the construction progress.

[0027] The present invention has the following beneficial effects due to the adoption of the above technical solution:

[0028] 1. The present invention can not only identify vehicles entering and leaving the construction site and monitor the weight of cargo, but also move vehicles that do not match the cargo weight to one side for manual inspection, thereby reducing the occurrence of construction materials being under-transported or accidentally pulled away, improving the efficiency of material monitoring, and can display real-time data through digital twin technology to ensure steady progress of construction.

[0029] 2. Through the design of the first L-shaped plate, the vertical plate and the horizontal plate, it is convenient to mount the entire monitoring assembly on the crossbeam, and the movement is stable and reliable. The U-shaped frame improves the stability and reliability of the installation of the driving motor. The driving motor can drive the rotating plate to rotate through the gear set to meet the angle adjustment of the monitoring camera in the horizontal direction and increase the monitoring range. An arc groove is arranged on the pressure plate, and the auxiliary rod can move along the arc groove, which improves the stability and reliability of the rotating plate during the rotation process. The electric cylinder drives the electric push rod to move up and down, and then the monitoring camera can be driven to rotate along the support plate, which meets the angle adjustment requirement of the monitoring camera in the vertical plane. The first slider and the first slide rail can realize the movement requirement of the monitoring camera during the rotation process.

[0030] 3. The load-bearing plate can be supported by a hydraulic jack to improve the stability and reliability of the load-bearing plate when it moves. The third motor drives the third screw to rotate, and then the second booster block drives the second L-shaped plate to move along the first guide groove on the side plate, thereby meeting the requirements for the movement of the load-bearing plate.

[0031] 4. The horizontal adjustment component drives the substrate to move horizontally along the groove, thereby meeting the transportation requirements of the carrier plate. The retracting and unfolding component can drive the lifting plate to move up and down, meeting the support requirements of the top support mechanism.

[0032] 5. The fifth motor drives the fifth screw to rotate, and then the fourth booster block drives the movable plate to move along the second guide groove, thereby meeting the conveying requirements of the carrier plate. The design of the card block and the card slot improves the stability and reliability of the carrier plate during conveying.

[0033] 6. The monitoring method of the present invention has simple steps and can not only realize accurate identification of vehicles, but also accurately weigh vehicles and loaded goods. Vehicles that exceed the set weight value can be manually inspected, which greatly reduces the loss of construction materials and ensures the construction progress. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] The present invention will be further described below in conjunction with the accompanying drawings:

[0035] Figure 1 It is a structural schematic diagram of a monitoring device in a real-time monitoring device and a monitoring method thereof based on digital twin technology of the present invention;

[0036] Figure 2 It is a structural schematic diagram of the monitoring component in the present invention;

[0037] Figure 3 It is a schematic diagram of the structure of the vehicle weighing area, the load-bearing plate descending area and the load-bearing plate ascending area in the present invention;

[0038] Figure 4 It is a structural schematic diagram of the jacking mechanism in the present invention;

[0039] Figure 5 It is a structural schematic diagram of the auxiliary support mechanism in the present invention;

[0040] Figure 6 for Figure 5 Structural diagram of the middle A direction;

[0041] Figure 7 It is a structural schematic diagram of the moving mechanism in the present invention;

[0042] Figure 8 It is a connection diagram of the modules in the present invention;

[0043] Fig. 9 It is a flow chart of the monitoring method in the present invention.

[0044] In the figure: 1-site access plate; 2-carrying plate; 3-control box; 4-lifting interception column; 5-bottom plate; 6-top plate; 7-guide rod; 8-first motor; 9-first screw; 10-crossbeam; 11-first baffle; 12-second motor; 13-second screw; 14-monitoring assembly; 15-foundation pit; 16-vertical plate; 17-horizontal plate; 18-reinforcement plate; 19-first L-shaped plate; 20-first booster block; 21-pressing plate; 22-rotating plate; 23-U-shaped frame; 24-driving motor; 25-gear set; 26-monitoring camera; 27-electric push rod; 28-first slide rail; 29-first slider; 30-support plate; 31-card slot; 32-side plate; 33-gravity sensor; 34-first guide slot; 35-support mechanism; 36-groove; 37 - auxiliary support mechanism; 38 - second guide groove; 39 - moving mechanism; 40 - first hydraulic cylinder; 41 - second L-shaped plate; 42 - hydraulic jack; 43 - third motor; 44 - second baffle; 45 - third screw; 46 - second booster block; 47 - base plate; 48 - second slide rail; 49 - support block; 50 - second slider; 51 - through groove; 52 - second hydraulic cylinder; 53 - booster rod; 54 - double-layer storage and exhibition rack; 55 - lifting plate; 56 - third guide groove; 57 - guide block; 58 - fourth motor; 59 - fourth screw; 60 - third booster block; 61 - third slide rail; 62 - third slider; 63 - fifth motor; 64 - fifth screw; 65 - fourth booster block; 66 - moving plate; 67 - clamping block; 68 - third hydraulic cylinder; 69 - third L-shaped plate. DETAILED DESCRIPTION

[0045] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present invention will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.

[0046] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only embodiments of a part of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0047] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions.

[0048] like Figures 1 to 8 As shown, the real-time monitoring device based on digital twin technology of the present invention includes two construction site access plates 1, at least two load-bearing plates 2 and a control box 3, in which a control module, a hydraulic pump, a signal transceiver module and a power module are arranged. The control terminal is provided with a digital twin management module and a database module. Among them, the control module, the signal transceiver module, the power module, the digital twin management module and the database module are all commonly used modules in the prior art and are not described in detail.

[0049] The construction site access plate 1 is provided with a lifting interception column 4 for intercepting vehicles entering and leaving the construction site and a monitoring mechanism for photographing vehicles entering and leaving the construction site.

[0050] The monitoring mechanism includes a lifting assembly, a beam 10 and a monitoring assembly 14. The lifting assembly is connected to both sides of the construction site access plate 1. The beam 10 is arranged between the two lifting assemblies. A first baffle 11 is provided on the beam 10. A second motor 12 is provided on the first baffle 11 on one side. The second motor 12 is connected to the first baffle 11 on the other side through a second screw 13. The monitoring assembly 14 is connected to the first screw 9 and the beam 10. The lifting assembly can drive the beam 10 and the monitoring assembly 14 to move up and down synchronously to meet the identification requirements of vehicles of different heights. The second motor 12 can drive the second screw 13 to rotate, and then drive the monitoring assembly 14 to move horizontally along the beam 10 to adjust the horizontal position of the monitoring assembly 14. The operation is convenient and quick.

[0051] The lifting assembly includes a base plate 5, a top plate 6, a guide rod 7 and a first motor 8. The base plate 5 is fixed to the construction site access plate 1. The top plate 6 is connected to the base plate 5 through the guide rod 7. The first motor 8 is arranged on the base plate 5. The first motor 8 is connected to the top plate 6 through the first screw 9. The crossbeam 10 is connected to the guide rod 7 and the first screw 9. The first motor 8 drives the first screw 9 to rotate, and then the crossbeam 10 can be driven to move up and down along the guide rod 7, thereby meeting the height adjustment requirements of the monitoring assembly 14.

[0052] The monitoring assembly 14 includes a vertical plate 16, a horizontal plate 17, a driving motor 24, a rotating plate 22 and a monitoring camera 26. The horizontal plate 17 is vertically connected to the vertical plate 16. A reinforcing plate 18 is provided between the vertical plate 16 and the horizontal plate 17. A first L-shaped plate 19 is provided on the vertical plate 16 above the horizontal plate 17. A pressing plate 21 and a first boosting block 20 connected to the first screw 9 are provided on the first L-shaped plate 19. The rotating plate 22 is connected to the driving motor 24 through a gear set 25. The driving motor 24 is connected to the bottom of the horizontal plate 17 through a U-shaped frame 23. An auxiliary rod is provided on the rotating plate 22, and the auxiliary rod is movably connected to the pressing plate 21. The monitoring camera 26 is connected to the electric cylinder through an electric push rod 27. The electric cylinder is provided on the rotating plate 22. A first slide rail 28 is symmetrically provided on the bottom surface of the monitoring camera 26. A first slider 29 is connected to the first slide rail 28. The first slider 29 is rotatably connected to the support plate 30. The bottom end of the support plate 30 is fixed on the rotating plate 22. Through the design of the first L-shaped plate 19, the vertical plate 16 and the horizontal plate 17, the entire monitoring assembly 14 is conveniently mounted on the crossbeam 10, and the movement is stable and reliable. The U-shaped frame 23 improves the stability and reliability of the installation of the driving motor 24. The driving motor 24 can drive the rotating plate 22 to rotate through the gear set 25, so as to meet the angle adjustment of the monitoring camera 26 in the horizontal direction and increase the monitoring range. An arc groove is provided on the pressure plate 21, and the auxiliary rod can move along the arc groove, which improves the stability and reliability of the rotating plate 22 during the rotation process. The electric push rod 27 is driven up and down by the electric cylinder, and then the monitoring camera 26 can be driven to rotate along the support plate 30, so as to meet the angle adjustment requirement of the monitoring camera 26 in the vertical plane. The first slider 29 and the first slide rail 28 can realize the movement requirement of the monitoring camera 26 during the rotation process.

[0053] The load-bearing plate 2 is movably connected to the foundation pit 15, which includes a vehicle weighing area, a load-bearing plate 2 lowering area and a load-bearing plate 2 rising area. The load-bearing plate 2 lowering area and the load-bearing plate 2 rising area are located on both sides of the vehicle weighing area, and the vehicle weighing area is located between the two construction site entry and exit plates 1.

[0054] A side plate 32 is provided on one side of the vehicle weighing area close to the construction site access plate 1, a gravity sensor 33 is provided on the top surface of the side plate 32, a jacking mechanism 35 is connected to the side plate 32, and the jacking mechanism 35 includes a second L-shaped plate 41, a hydraulic jack 42, a third motor 43, a second baffle plate 44 and a third screw 45, the second L-shaped plate 41 horizontally passes through the first guide groove 34 on the side plate 32, the hydraulic jack 42 is distributed on the top surface of the second L-shaped plate 41, the bottom surface of the second L-shaped plate 41 is provided with a second booster block 46, and the third motor 43 is provided on the bottom surface of the second L-shaped plate 41. The machine 43 and the second baffle plate 44 are arranged on the outer side of the side plate 32. The third motor 43 is connected to the second baffle plate 44 through the third screw 45. The second booster block 46 is connected to the third screw 45. The load-bearing plate 2 can be supported by the hydraulic jack 42 to improve the stability and reliability of the load-bearing plate 2 when moving. The third motor 43 drives the third screw 45 to rotate, and then the second booster block 46 can drive the second L-shaped plate 41 to move along the first guide groove 34 on the side plate 32, thereby meeting the requirements for moving the load-bearing plate 2.

[0055] A groove 36 is provided in the vehicle weighing area and the descending area of ​​the load-bearing plate 2. An auxiliary support mechanism 37 for supporting the jacking mechanism 35 is provided in the groove 36. The auxiliary support mechanism 37 includes a base plate 47, a horizontal adjustment component, a retractable and deployable component and a lifting plate 55. The base plate 47 is connected to the groove 36 through the horizontal adjustment component. The lifting plate 55 is connected to the base plate 47 through the retractable and deployable component. The base plate 47 is driven to move horizontally along the groove 36 through the horizontal adjustment component, thereby meeting the transportation requirements of the load-bearing plate 2. The retractable and deployable component can drive the lifting plate 55 to move up and down, thereby meeting the support requirements for the jacking mechanism 35.

[0056] The horizontal adjustment component includes a fourth motor 58, a fourth screw 59, a third booster block 60, a third slide rail 61 and a third slider 62. The fourth motor 58 and the third slide rail 61 are arranged in the groove 36. The fourth motor 58 is connected to the fourth screw 59. The third booster block 60 and the third slider 62 are both arranged on the bottom surface of the base plate 47. The third booster block 60 is connected to the fourth screw 59. The third slider 62 slides along the third slide rail 61. The fourth screw 59 is driven to rotate by the fourth motor 58, and then the base plate 47 can be driven by the third booster block 60 to move horizontally along the groove 36 to meet the conveying requirements of the supporting plate 2. The third slide rail 61 and the third slider 62 improve the stability and reliability of the base plate 47 when moving.

[0057] The folding and unfolding assembly includes a second slide rail 48, a support block 49, a second hydraulic cylinder 52 and a double-layer folding and unfolding frame 54. The second slide rail 48 and the support block 49 are both arranged on the base plate 47. The second slide rail 48 is slidably connected with a second slider 50. The bottom of the double-layer folding and unfolding frame 54 is rotatably connected to the second slider 50 and the support block 49. One side of the top of the double-layer folding and unfolding frame 54 is rotatably connected to the lifting plate 55. The lifting plate 55 is provided with a third guide groove 56. The other side of the top of the double-layer folding and unfolding frame 54 is slidably connected to the third guide groove 56 through a guide block 57. The base plate 47 is provided with a through groove 51. The second hydraulic cylinder 52 is rotatably connected in the through groove 51, and a booster rod 53 is provided between the two second sliding blocks 50. The booster rod 53 is connected to the hydraulic cylinder of the second hydraulic cylinder 52. The booster rod 53 is driven by the second hydraulic cylinder 52 to move horizontally through the hydraulic cylinder, and then the second sliding block 50 can be driven to move horizontally along the second slide rail 48 to achieve the expansion or folding requirements of the double-layer folding and exhibition rack 54. The double-layer folding and exhibition rack 54 drives the guide block 57 to move along the third guide groove 56 on the lifting plate 55 to adjust the height of the lifting plate 55 to meet the support requirements of the jacking mechanism 35.

[0058] A moving mechanism 39 for lateral movement of the carrying plate 2 is provided between the vehicle weighing area, the lowering area of ​​the carrying plate 2 and the rising area of ​​the carrying plate 2. The moving mechanism 39 includes a fifth motor 63, a fifth screw 64, a fourth booster block 65 and a moving plate 66. The fifth motor 63 is connected to the second guide groove 38. The two ends of the fifth screw 64 are respectively connected to the fifth motor 63 and the inner wall of the foundation pit 15. The moving plate 66 is connected to the fifth screw 64 through the fourth booster block 65. The fourth booster block 65 moves along the second guide groove 38. A clamping block 67 is provided on the top surface of the moving plate 66. A clamping groove 31 is provided on the carrying plate 2. The clamping block 67 matches the clamping block 67. The fifth screw 64 is driven to rotate by the fifth motor 63, and then the moving plate 66 can be driven to move along the second guide groove 38 by the fourth booster block 65, thereby meeting the conveying requirements of the carrying plate 2. The design of the clamping block 67 and the clamping groove 31 improves the stability and reliability of the carrying plate 2 during conveying.

[0059] The bottom and side of the lifting area of ​​the carrying plate 2 are respectively provided with a first hydraulic cylinder 40 and a third hydraulic cylinder 68 , and the third hydraulic cylinder is connected to a third L-shaped plate 69 .

[0060] The control box 3 is connected to the monitoring mechanism, the gravity sensor 33, the jacking mechanism 35, the auxiliary support mechanism 37, the moving mechanism 39, the first hydraulic cylinder 40 and the third hydraulic cylinder 68; through the design of the above structure, not only can the vehicles entering and leaving the construction site be identified and the weight of the cargo be monitored, but also the vehicles that do not match the cargo weight can be moved to one side for manual inspection, thereby reducing the occurrence of construction materials being under-transported or accidentally pulled away, improving the efficiency of material monitoring, and can display real-time data through digital twin technology to ensure steady progress of construction.

[0061] like Fig. 9 As shown, the monitoring method of the real-time monitoring device based on the digital twin technology of the present invention includes the following steps:

[0062] S1. Use the monitoring mechanism to shoot vehicles entering and leaving the construction site, obtain vehicle information, and then transmit the data to the digital twin management module through the control module in the control box 3 via the signal transceiver module, and store it in the database module;

[0063] S2, according to the identified vehicle information, the hydraulic pump is controlled to work, the lifting and intercepting column 4 on the construction site access plate 1 close to the vehicle side is lowered, the vehicle is driven into the load-bearing plate 2 located in the middle, and the lifting and intercepting column 4 is raised;

[0064] S3, then the weight of the vehicle and the cargo is detected by the gravity sensor 33, the control module in the control box 3 transmits the data to the digital twin management module via the signal transceiver module, and stores it in the database module. After the weight and vehicle information match, the lifting interception column 4 is lowered, and the vehicle enters the construction site for unloading or drives out of the construction site;

[0065] S4, when the weight and vehicle information do not match, the lifting interception columns 4 on the construction site access plates 1 on both sides do not descend, and the supporting mechanism 35 and the auxiliary supporting mechanism 37 cooperate to move the load-bearing plate 2 carrying the vehicle horizontally to the lowering area of ​​the load-bearing plate 2, and at the same time, the load-bearing plate 2 located in the rising area of ​​the load-bearing plate 2 rises and is horizontally pushed into the vehicle weighing area;

[0066] S5, manually inspect the vehicles and goods in the descending area of ​​the load-bearing plate 2, and after the vehicles are qualified, drive the vehicles away from the load-bearing plate 2 in the descending area of ​​the load-bearing plate 2, retract the auxiliary support mechanism 37 into the groove 36, horizontally move the load-bearing plate 2 in the descending area of ​​the load-bearing plate 2 to the ascending area of ​​the load-bearing plate 2 through the moving mechanism 39, lift the load-bearing plate 2 to the top of the ascending area of ​​the load-bearing plate 2 through the first hydraulic cylinder 40, and move the moving mechanism 39 into the descending area of ​​the load-bearing plate 2;

[0067] S6. Finally, the lifting mechanism 35 and the auxiliary supporting mechanism 37 are moved to the vehicle weighing area, and the auxiliary supporting mechanism 37 is unfolded to support the lifting mechanism 35. The lifting mechanism 35 supports the load-bearing plate 2 located in the vehicle weighing area to monitor the next vehicle.

[0068] The monitoring method has simple steps and can not only realize accurate identification of vehicles, but also accurately weigh vehicles and loaded goods. Vehicles that exceed the set weight value can be manually inspected, which greatly reduces the loss of construction materials and ensures the construction progress.

[0069] The above are only specific embodiments of the present invention, but the technical features of the present invention are not limited thereto. Any simple changes, equivalent replacements or modifications made based on the present invention to achieve basically the same technical effects are all included in the protection scope of the present invention.

Claims

1. Real-time monitoring equipment based on digital twin technology, Features: include Two construction site access panels, each of which is provided with a lifting interception column for intercepting vehicles entering and leaving the construction site and a monitoring mechanism for photographing vehicles entering and leaving the construction site; At least two bearing plates, the bearing plates are movably connected to the foundation pit, the foundation pit comprises a vehicle weighing area, a bearing plate descending area and a bearing plate ascending area, the bearing plate descending area and the bearing plate ascending area are located on both sides of the vehicle weighing area, the vehicle weighing area is located between the two construction site access plates, a side plate is provided on the side of the vehicle weighing area close to the construction site access plate, a gravity sensor is provided on the top surface of the side plate, a jacking mechanism is connected to the side plate, a groove is provided in the vehicle weighing area and the bearing plate descending area, an auxiliary supporting mechanism for supporting the jacking mechanism is provided in the groove, a moving mechanism for lateral movement of the bearing plate is provided between the vehicle weighing area, the bearing plate descending area and the bearing plate ascending area, a first hydraulic cylinder and a third hydraulic cylinder are provided at the bottom and side of the bearing plate ascending area respectively, and the third hydraulic is connected to a third L-shaped plate; and a control box, wherein the control box is connected to the monitoring mechanism, the gravity sensor, the jacking mechanism, the auxiliary supporting mechanism, the moving mechanism, the first hydraulic cylinder and the third hydraulic cylinder.

2. The real-time monitoring device based on digital twin technology according to claim 1, Features: The monitoring mechanism includes a lifting assembly, a beam and a monitoring assembly. The lifting assembly is connected to both sides of the construction site access plate. The beam is arranged between the two lifting assemblies. A first baffle is arranged on the beam. A second motor is arranged on the first baffle on one side. The second motor is connected to the first baffle on the other side through a second screw. The monitoring assembly is connected to the first screw and the beam.

3. The real-time monitoring device based on digital twin technology according to claim 2, Features: The lifting assembly includes a bottom plate, a top plate, a guide rod and a first motor. The bottom plate is fixed to the construction site access plate, the top plate is connected to the bottom plate through the guide rod, the first motor is arranged on the bottom plate, the first motor is connected to the top plate through a first screw, and the crossbeam is connected to the guide rod and the first screw.

4. The real-time monitoring device based on digital twin technology according to claim 3, Features: The monitoring assembly includes a vertical plate, a horizontal plate, a driving motor, a rotating plate and a monitoring camera, the horizontal plate is vertically connected to the vertical plate, a reinforcing plate is provided between the vertical plate and the horizontal plate, a first L-shaped plate is provided on the vertical plate above the horizontal plate, a pressure plate and a first booster block connected to the first screw are provided on the first L-shaped plate, the rotating plate is connected to the driving motor through a gear set, the driving motor is connected to the bottom of the horizontal plate through a U-shaped frame, an auxiliary rod is provided on the rotating plate, the auxiliary rod is movably connected to the pressure plate, the monitoring camera is connected to an electric cylinder through an electric push rod, the electric cylinder is provided on the rotating plate, and a first slide rail is symmetrically provided on the bottom surface of the monitoring camera, a first slider is connected to the first slide rail, the first slider is rotatably connected to a support plate, and the bottom end of the support plate is fixed to the rotating plate.

5. The real-time monitoring device based on digital twin technology according to claim 1, Features: The supporting mechanism includes a second L-shaped plate, a hydraulic jack, a third motor, a second baffle and a third screw. The second L-shaped plate horizontally passes through the first guide groove on the side plate. The hydraulic jack is distributed on the top surface of the second L-shaped plate. The bottom surface of the second L-shaped plate is provided with a second booster block. The third motor and the second baffle are arranged on the outer side surface of the side plate. The third motor is connected to the second baffle through the third screw, and the second booster block is connected to the third screw.

6. The real-time monitoring device based on digital twin technology according to claim 1, Features: The auxiliary support mechanism comprises a base plate, a horizontal adjustment component, a retractable and extendable component and a lifting plate. The base plate is connected to the groove through the horizontal adjustment component, and the lifting plate is connected to the base plate through the retractable and extendable component.

7. The real-time monitoring device based on digital twin technology according to claim 6, Features: The horizontal adjustment component includes a fourth motor, a fourth screw rod, a third booster block, a third slide rail and a third slider. The fourth motor and the third slide rail are arranged in the groove, the fourth motor is connected to the fourth screw rod, the third booster block and the third slider are both arranged on the bottom surface of the substrate, the third booster block is connected to the fourth screw rod, and the third slider slides along the third slide rail.

8. The real-time monitoring device based on digital twin technology according to claim 6, Features: The folding and unfolding assembly includes a second slide rail, a support block, a second hydraulic cylinder and a double-layer folding and unfolding frame, the second slide rail and the support block are both arranged on the base plate, a second slider is slidably connected to the second slide rail, the bottom of the double-layer folding and unfolding frame is rotatably connected to the second slider and the support block, one side of the top of the double-layer folding and unfolding frame is rotatably connected to the lifting plate, a third guide groove is arranged on the lifting plate, the other side of the top of the double-layer folding and unfolding frame is slidably connected to the third guide groove through a guide block, a through groove is arranged on the base plate, the second hydraulic cylinder is rotatably connected to the through groove, a booster rod is arranged between the two second sliders, and the booster rod is connected to the hydraulic cylinder of the second hydraulic cylinder.

9. The real-time monitoring device based on digital twin technology according to claim 1, Features: The moving mechanism includes a fifth motor, a fifth screw, a fourth booster block and a moving plate, the fifth motor is connected to the second guide groove, the two ends of the fifth screw are respectively connected to the fifth motor and the inner wall of the foundation pit, the moving plate is connected to the fifth screw through the fourth booster block, the fourth booster block moves along the second guide groove, a clamping block is provided on the top surface of the moving plate, a clamping slot is provided on the supporting plate, and the clamping block matches the clamping block.

10. The monitoring method for real-time monitoring equipment based on digital twin technology according to any one of claims 1 to 9, Features The following steps are involved: S1. Use the monitoring mechanism to photograph vehicles entering and leaving the construction site, obtain vehicle information, and then transmit the data to the digital twin management module through the control module in the control box via the signal transceiver module and store it in the database module; S2, according to the identified vehicle information, the hydraulic pump is controlled to work, the lifting and intercepting column on the construction site access plate close to the vehicle side is lowered, the vehicle is driven into the load-bearing plate in the middle, and the lifting and intercepting column is raised; S3. Then, the weight of the vehicle and the cargo is detected by the gravity sensor. The control module in the control box transmits the data to the digital twin management module through the signal transceiver module and stores it in the database module. After the weight and vehicle information match, the lifting interception column descends, and the vehicle enters the construction site for unloading or drives out of the construction site; S4. When the weight and vehicle information do not match, the lifting interception columns on the access plates on both sides of the construction site do not descend, and the supporting mechanism and the auxiliary supporting mechanism cooperate to move the load-bearing plate carrying the vehicle horizontally to the load-bearing plate descending area, and at the same time, the load-bearing plate located in the load-bearing plate ascending area rises and is pushed horizontally into the vehicle weighing area; S5, manually inspecting the vehicles and cargoes in the lowering area of ​​the load plate, and after the vehicles are qualified, driving the vehicles away from the load plate in the lowering area of ​​the load plate, retracting the auxiliary support mechanism into the groove, horizontally moving the load plate in the lowering area of ​​the load plate to the ascending area of ​​the load plate by the moving mechanism, and lifting the load plate to the top of the ascending area of ​​the load plate by the first hydraulic cylinder, while moving the moving mechanism into the lowering area of ​​the load plate; S6. Finally, the jacking mechanism and the auxiliary support mechanism are moved to the vehicle weighing area, and the auxiliary support mechanism is unfolded to support the jacking mechanism. The jacking mechanism supports the load-bearing plate in the vehicle weighing area to monitor the next vehicle.