Movable emergency resource in-disaster position pre-scheduling system
By designing a mobile emergency resource location pre-scheduling system in disasters, decoupling the transport vehicles and mobile energy storage, predicting the typhoon wind farm and optimizing the access location, the distribution system failure problem caused by extreme weather is solved and the power system is stabilized Improvement of sexual and cost-effectiveness.
Patent Information
- Application Number
- CN202410986517.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-23
- Publication Date
- 2024-11-12
AI Technical Summary
Extreme weather causes power distribution system failures, resulting in power interruption and economic losses. The existing mobile energy storage applications are not fully explored and costly. Reasonable pre-scheduling is required before the disaster to ensure economic feasibility.
Design a mobile emergency resource location pre-scheduling system, and optimize mobile energy storage by decoupling transport vehicles and mobile energy storage, establish a spatio-temporal network model, predict typhoon wind farms, and use stress-intensity interference model and Monte Carlo sampling to optimize mobile energy storage access location to minimize load downtime.
It improves the stability of the power system in extreme weather, reduces the failure time of the distribution network, reduces investment costs, and achieves optimal access to mobile energy storage in all fault scenarios, reducing system losses.
Smart Images

Figure CN118944066A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of power system optimization operation, and in particular to a mobile emergency resource disaster location pre-dispatching system. Background Art
[0002] The distribution system is vulnerable to extreme weather (such as floods, storms, earthquakes, ice and snow, etc.), which increases the probability of failure of key equipment and causes extensive and severe damage to the power grid, resulting in many customers without electricity for several days, sometimes even for more than a week, causing huge economic impact and social losses. Actively dispatching various resources to provide emergency power to the distribution network can effectively reduce the power outage losses caused by extreme weather. In order to speed up recovery, a resilient response strategy is essential when the distribution network is threatened by natural disasters.
[0003] Mobile Energy Storage System (MESS) is an effective elastic resource with convenient mobility and large storage capacity. It is suitable for various response stages to enhance system resilience. When extreme weather causes long-term power outages in the distribution system, they are one of the most effective response resources. At present, the application of mobile energy storage has not been fully explored, and the capital cost of mobile energy storage devices is relatively high. Therefore, in order to ensure its economic feasibility, it must be reasonably pre-dispatched before the disaster. Summary of the invention
[0004] In order to improve the stability of the power system in extreme weather conditions, ensure the power supply stability of the loads after disasters such as storms, ice and snow, and reduce the failure time of the distribution network, the present invention provides a mobile emergency resource disaster location pre-dispatching system.
[0005] The solution adopted by the present invention to solve the technical problem is:
[0006] A mobile emergency resource disaster location pre-dispatching system comprises the following steps:
[0007] Step 1. Decouple the transport vehicle from the mobile energy storage. The mobile energy storage is transported by the vehicle as an independent unit. The transport vehicle can transport multiple energy storage units at the same time, further improving the temporal and spatial flexibility of the mobile energy storage.
[0008] Step 2. Consider the economic feasibility of mobile energy storage units, analyze the value they generate to the power system under normal operation, ensure the economic feasibility of mobile energy storage, and minimize investment costs;
[0009] Step 3. Obtain typhoon data and geographic data, predict the distribution of typhoon wind fields, establish a comprehensive wind field model based on extreme value distribution, and make accurate wind speed predictions;
[0010] Step 4. Using an improved stress-strength interference model to determine the failure probability of the distribution line;
[0011] Step 5. Through Monte Carlo sampling, random fault scenarios of the distribution network can be obtained, and the SBR algorithm is used to remove low-probability scenarios to reduce the calculation time;
[0012] Step 6. Calculate the travel time between nodes based on the traffic volume of the road network, and integrate the transfer time constraint into the scheduling model of mobile energy storage;
[0013] Step 7. Taking minimizing the continuous load outage time as the objective function, establish the optimal access location model of mobile energy storage, and then determine the travel time of each section of the road network system through the road network traffic flow, and dispatch the mobile energy storage to the optimal location so that the expected access time to the network is minimized in all possible fault scenarios, thereby achieving the goal of minimizing the expected load loss in all fault scenarios.
[0014] In the step 1 disclosed in this embodiment, the transport vehicle is decoupled from the mobile energy storage, and the mobile energy storage is transported by the vehicle as an independent unit. The transport vehicle can transport multiple energy storage units at the same time, further improving the temporal and spatial flexibility of the mobile energy storage.
[0015] Most of the existing mobile energy storage uses containerized energy storage and is deployed using transport vehicles. Structurally, these energy storage devices are separable from the transport vehicles themselves. Based on the vehicle routing problem with time windows, a mobile energy storage vehicle scheduling model based on a spatiotemporal network model is established, and its objective function is:
[0016]
[0017] Where V represents the set of all nodes in the transportation network; K represents the set of transportation vehicles; v ij,k represents the cost of vehicle k serving arc ij; e ij,k is a 0-1 variable; As a decision variable, when vehicle k serves arc ij, its value is 1, and v ij,k The cost is 0 otherwise;
[0018] The constraints satisfied by the model are as follows:
[0019] (1) Time window constraints
[0020]
[0021] (2) Vehicle capacity constraints
[0022]
[0023] (3) Traffic balance constraints
[0024]
[0025] The space-time network is used to establish the path model of mobile energy storage to characterize the space-time state of mobile energy storage during operation; the space-time network model constructs a coordinate system with time as the horizontal axis and traffic nodes as the vertical axis; the arcs between each node are used to represent all possible states of the transport vehicle in each time period, and its objective function is as follows:
[0026]
[0027] Where Ξ is the set of space-time network arcs; Π is the set of mobile energy storage vehicles; Υ is the set of scheduling periods, and each step corresponds to a period; C ij is the transportation cost through arc ij; L ij,ν,t is a 0-1 variable. If the mobile energy storage vehicle v stands on arc ij in time period t, then L ij,ν,t =1, otherwise L ij,ν,t =0;
[0028] The constraints are as follows:
[0029]
[0030] It means that the mobile energy storage vehicle v can only and must be located on a certain arc in time period t;
[0031]
[0032] It means that the starting node of the arc where the mobile energy storage vehicle v is located in time period t is the same as the ending node of the arc where the mobile energy storage vehicle v is located in time period t-1, that is, the inflow of each node is equal to the outflow;
[0033]
[0034] This constraint represents the starting and ending states of the mobile energy storage train v, where L v,0 and L v,T are the starting position and ending position of the mobile energy storage train v. Generally, the mobile energy storage vehicle should return to the initial position at the end of the dispatch, i.e., L v,0 =L v,T .
[0035] In the step 2 disclosed in this embodiment, the economic efficiency of the mobile energy storage unit is taken into consideration, and the value generated to the power system under normal operation is analyzed to ensure the economic efficiency of the mobile energy storage and reduce the investment cost as much as possible;
[0036] Mobile energy storage devices can not only provide users with emergency power supply when the system fails, but also give full play to their own energy migration characteristics in time and space to achieve the purpose of "peak shaving and valley filling", thereby reducing system operating costs.
[0037] In the step 3 disclosed in this embodiment, typhoon data and geographic data are obtained to predict the distribution of the typhoon wind field, and a comprehensive wind field model based on extreme value distribution is established to perform accurate wind speed prediction;
[0038] The extreme wind speed can be fitted into extreme value i distribution, Weibull distribution and Gamma distribution;
[0039] First, under the three distribution assumptions, different methods are used to estimate the shape, location and scale parameters of each point. In order to measure the accuracy of parameter estimation, the goodness of fit metric related to machine learning is used to measure the fit distribution function F(v) and the empirical distribution function F n (v) Deviation between;
[0040] Second, for each distribution hypothesis, the optimal estimation method is selected and the best parameters and goodness-of-fit measures are recorded;
[0041] Finally, the goodness-of-fit indices of the three distribution hypotheses are compared to obtain the best fit index, and the corresponding distribution F is selected for each point. b (v) and parameters;
[0042] In this way, the optimal distribution L for each point can be obtained from these three distributions b (v), extreme wind speed refers to the wind speed value exceeding a certain wind speed v once every X years 0 The wind speed value is expressed as p v {V>v 0}=1-L b (v 0 )=1 / X, where V is the random variable of wind speed;
[0043] Therefore, the wind speed with a period of X years is in is the function L b The reciprocal of (v), finally V X is the final wind speed.
[0044] In the step 4 disclosed in this embodiment, an improved structural fragility model of stress-strength interference theory is adopted;
[0045] The distribution line is assumed to be composed of concrete poles, and the poles support a three-phase symmetrical layout of conductors. The wind speed v at each pole can be provided by the wind field model. Due to the different terrains where the poles are located, the wind direction is generated randomly; the calculation of the wind load acting on the conductors and poles is given by the following two equations:
[0046]
[0047] The calculation of the conductor's cross-sectional stress σ is shown in the formula:
[0048] σ(v)=W c / S c
[0049] In addition to the wind load on the pole, the pole also bears the wind load from the traction wire; the wind load acts on the pole at the halfway point, generating a bending moment M at the pole root. 1 , the calculation formula is:
[0050] M 1 (v) = W p (ll 2 ) / 2
[0051] The extreme root bending moment M caused by wind load on the traction conductor 2 The calculation is as shown in the formula:
[0052] M 2 (v)=2W c l 1 +W c (ll 2 )
[0053] The composite root bending moment M of the rod is M 1 With M 2 The vector sum, its modulus calculation formula is:
[0054]
[0055] The cross-sectional stress φ and the root bending moment M are both functions of the wind speed v, collectively known as the component wind load effect, represented by the variable w; the component strength is represented by e and obeys the normal distribution; failure occurs when the component strength is less than the wind load; the structural vulnerability model is represented by the normal cumulative distribution function Φ(w), as shown in the formula:
[0056]
[0057] in, is the normal probability density function of the component intensity.
[0058] In the disclosed embodiment, in step 4, the failure probability of the power distribution line is determined;
[0059] The failure probability of the distribution line is calculated based on the structural vulnerability model of the stress-strength interference theory, which indicates the uncertainty of the damage to the distribution line. It can be seen from the wind field model in claim 2 that the wind speed is subject to the optimal distribution F b (v); in addition, w is a quadratic function of v, so the wind load effect should also be a random variable, denoted as w(v), and obey the composite distribution shown in the following formula:
[0060] F(w)=pw{W(V)≤w}=p v {V≤W -1 (w)}
[0061] =F b [W -1 (w)]
[0062] According to the stress-strength interference theory, the unique failure probability of a component is the convolution of the composite distribution of the fragility function and the wind load effect:
[0063]
[0064]
[0065] σ δ =ε 1 σ μ
[0066] M μ =γM exam
[0067] M δ =ε 2 M μ
[0068] According to the series reliability model, the failure probability of distribution line ij is as follows:
[0069]
[0070] Thus the failure probability is calculated.
[0071] In the step 5 disclosed in this embodiment, a random fault scenario of the power distribution network is obtained;
[0072] The acquisition of random fault scenarios, the generation and restoration of fault scenarios by Monte Carlo algorithm, the uncertainty modeling of distribution line damage, and then the removal of low-probability scenarios by SBR algorithm can effectively reduce the calculation time.
[0073] In the step 6 disclosed in this embodiment, a mobile energy storage device path selection method considering the influence of traffic flow is established;
[0074] The method for determining the traffic flow of a road network based on equilibrium theory is as follows: for a certain road section, the relationship between the time of passing through the road section and the traffic flow of the road section is:
[0075]
[0076] Where ζ is a road section; τ ζ is the required travel time to pass the road segment ζ; is the free travel time of section ζ, which is the travel time required when the traffic flow is equal to the design flow; is the design flow of section ζ; f ζ is the actual flow of the road section ζ; ψ is the set of road sections;
[0077] For the traffic assignment problem, the first and second principles of Wardrop are used: all users choose the path with the shortest time for themselves, and the total travel time of all vehicles in the network is minimized; assuming that the vehicle needs to reach the destination d from the departure point o, the optimal model of system flow is established as:
[0078]
[0079] In the formula, q od For all OD (origin-destination) pairs between o and d; is the flow on path k between o and d; It is a 0-1 variable. When it is equal to 1, it means that the section ζ is on the path k between o and d. When it is equal to 0, it means that the section ζ is not on the path k between o and d.
[0080] In the step 6 disclosed in this embodiment, the path selection of the mobile energy storage is determined based on the shortest time;
[0081] Usually, the number of mobile energy storage is relatively small, and the impact on network traffic is small and can be ignored; therefore, after obtaining the traffic of each section, the formula
[0082]
[0083] Determine the travel time of mobile energy storage on this road section.
[0084] In the step 7 disclosed in this embodiment, the optimal access position model of the mobile energy storage is established with minimizing the continuous outage time of the load as the objective function, and then the travel time of each section of the road network system can be determined by the road network traffic flow, and the mobile energy storage is dispatched to the optimal position, so that the expected access time to the network is minimized in all possible fault scenarios, thereby achieving the purpose of minimizing the expected load loss in all fault scenarios;
[0085] After a distribution network failure occurs, the pre-disaster location dispatching can enable the mobile energy storage to reach the access point as quickly as possible to supply power to the distribution network load and reduce the load loss. The objective function of the mobile energy storage pre-configuration model taking into account the impact of random failures and traffic flow: The purpose of mobile energy storage access is to reduce the system losses caused by disasters; therefore, the objective function of the model is to minimize the total operating cost of the system (including the operating cost of mobile energy storage and the system load loss cost):
[0086]
[0087] Where S is the set of fault scenarios; is the operating cost of the scenario; θ is the linear aging coefficient of the mobile energy storage device; C mes Cost of equipment for mobile energy storage; is the charging and discharging power of the mth mobile energy storage at node i at time t in scenario s, where discharging is positive and charging is negative; is the load loss of node i; is the load reduction at node i at time t in scenario s;
[0088] Constraints of the mobile energy storage pre-configuration model considering random failures and traffic flow:
[0089] ① Flow constraint part
[0090]
[0091]
[0092] V min ≤V i,t,s ≤V max
[0093]
[0094] In the formula, is the active power flow of line ij at time t in scenario s; is the reactive power flow of line ij at time t in scenario s; is the load of node j at time t; v j,t,s is the voltage of node i at time t in scenario s; r ij 、x ij are the resistance and reactance of line ij respectively; is the active output of the generator at node i at time t in scenario s; is the active output of the generator at node i at time t in scenario s;
[0095] For the faulted line, the power flow is zero:
[0096]
[0097] Where, L o is the fault line set;
[0098] ②Operation constraints of energy storage equipment:
[0099]
[0100]
[0101] u m,i,t,s -u m,i,t+1,s ≤1-u m,j,t+Δ,s ,
[0102]
[0103] In the formula, e m,t,s is the power of the mth mobile energy storage at time t in scenario s; is the maximum capacity of mobile energy storage; u m,i,t,s is the location variable of the mobile energy storage. In scenario s, the value is 1 when the mth mobile energy storage is at node i at time t, otherwise it is 0. K is the power factor of the mobile energy storage. K mes The charging and discharging efficiency of mobile energy storage; N is the maximum number of mobile energy storage devices that can be connected to the node; MES is the total amount of mobile energy storage in the system; loc m,i is the initial position variable of the mobile energy storage. When it is equal to 1, it means that the mobile energy storage numbered m is dispatched to position i.
[0104] Positive effects:
[0105] Before the distribution network is damaged by extreme weather, the present invention establishes a random prediction model for disasters and a failure rate model for the distribution system, obtains random failure scenarios of the distribution network through Monte Carlo sampling, and establishes a mobile energy storage access point optimization model with minimum load loss as the objective function through the failure scenario. Then, the travel time of each section of the road network system is determined by the traffic volume of the road network, and the mobile energy storage is dispatched to the optimal position. In all possible failure scenarios, the expected access time of the mobile energy storage to the network is minimized, thereby achieving the purpose of minimizing the expected load loss in all failure scenarios. BRIEF DESCRIPTION OF THE DRAWINGS
[0106] Figure 1 This is a flow chart of an embodiment of the present application;
[0107] Figure 2 This is a schematic diagram of the decoupling of the transport vehicle and mobile energy storage in an embodiment of the present application. DETAILED DESCRIPTION
[0108] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. Although the embodiments of the present invention have been shown and described, it can be understood by those of ordinary skill in the art that various changes, modifications, substitutions and variations can be made to these embodiments without departing from the principles and spirit of the present invention, and the scope of the present invention is defined by the attached claims and their equivalents. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without making creative work are within the scope of protection of the present invention.
[0109] like Figure 1 As shown, the present invention provides a pre-scheduling strategy for mobile emergency resources in disaster locations, comprising the following steps:
[0110] S01: Decouple the transport vehicle from the mobile energy storage. The mobile energy storage is transported by vehicles as an independent unit. The transport vehicle can transport multiple energy storage units at the same time, further improving the spatiotemporal flexibility of mobile energy storage. A mobile energy storage vehicle scheduling model based on the spatiotemporal network model is established, and its objective function is:
[0111]
[0112] Where V represents the set of all nodes in the transportation network; K represents the set of transportation vehicles; v ij,k represents the cost of vehicle k serving arc ij; e ij,k is a 0-1 variable; As a decision variable, when vehicle k serves arc ij, its value is 1, and v ij,k otherwise it is 0.
[0113] The constraints satisfied by the model are as follows:
[0114] (1) Time window constraints
[0115]
[0116] (2) Vehicle capacity constraints
[0117]
[0118] (3) Traffic balance constraints
[0119]
[0120] The space-time network is used to establish the path model of mobile energy storage to characterize the space-time state of mobile energy storage during operation. The space-time network model constructs a coordinate system with time as the horizontal axis and traffic nodes as the vertical axis. The arcs between each node represent all possible states of the transport vehicle in each time period, and its objective function is as follows:
[0121]
[0122] Where Ξ is the set of space-time network arcs; Π is the set of mobile energy storage vehicles; Υ is the set of scheduling periods, and each step corresponds to a period; C ij is the transportation cost through arc ij; L ij,ν,t is a 0-1 variable. If the mobile energy storage vehicle v stands on arc ij in time period t, then L ij,ν,t =1, otherwise L ij,ν,t =0.
[0123] The constraints are as follows:
[0124]
[0125] It means that the mobile energy storage vehicle v can only and must be located on a certain arc in time period t.
[0126]
[0127] It means that the starting node of the arc where the mobile energy storage vehicle v is located in time period t is the same as the ending node of the arc where the mobile energy storage vehicle v is located in time period t-1, that is, the inflow of each node is equal to the outflow.
[0128]
[0129] This constraint represents the starting and ending states of the mobile energy storage train v, where L v,0 and L v,T are the starting position and ending position of the mobile energy storage train v. Generally, the mobile energy storage vehicle should return to the initial position at the end of the dispatch, i.e., L v,0 =L v,T .
[0130] S02: Consider the economic feasibility of mobile energy storage units. Mobile energy storage devices can not only provide users with emergency power when the system fails, but also give full play to the migration characteristics of their own energy in time and space to achieve the purpose of "peak shaving and valley filling", thereby reducing system operating costs.
[0131] S03: Based on historical statistical data, a comprehensive wind field model is established to calculate its extreme wind speed.
[0132] The 72-hour extreme wind speed database provided by meteorological and power companies is taken as input, which includes hourly data with a geographical resolution of one square kilometer before the typhoon landfall.
[0133] First, under the three distribution assumptions, different methods are used to estimate the shape, location and scale parameters of each point. Second, for each distribution assumption, the optimal estimation method is selected, and the optimal parameters and goodness of fit metrics are recorded. Finally, the goodness of fit indicators of the three distribution assumptions are compared to obtain the best fit indicator, and the corresponding distribution F is selected for each point. b (v) and parameters.
[0134] Therefore, the wind speed with a period of X years is in is the function L b The reciprocal of (v), finally V X is the final wind speed.
[0135] S04: Based on the structural fragility model of stress-strength interference theory, the failure probability of the distribution line is calculated to express the uncertainty of the damage of the distribution line.
[0136] S041: Establish a structural vulnerability model based on stress-strength interference theory.
[0137] The distribution line is assumed to be composed of concrete poles, and the poles support a three-phase symmetrical layout of conductors. The wind speed v at each pole can be provided by the wind field model. Due to the different terrains where the poles are located, the wind direction is generated randomly. The calculation of the wind load acting on the conductors and poles is given by the following two equations:
[0138]
[0139]
[0140] The cross-sectional stress φ of the conductor is calculated as shown in the formula:
[0141] σ(v)=W c / S c
[0142] In addition to the wind load on the pole, the pole also bears the wind load from the traction wire. The wind load acts on the pole at the halfway point, generating a bending moment M at the pole root. 1 , the calculation formula is:
[0143] M 1 (v) = W p (ll 2 ) / 2
[0144] The extreme root bending moment M caused by wind load on the traction conductor 2 The calculation is as shown in the formula:
[0145] M 2 (v)=2W c l 1 +W c (ll 2 )
[0146] The composite root bending moment M of the rod is M 1 With M 2 The vector sum, its modulus calculation formula is:
[0147]
[0148] The cross-sectional stress φ and the root bending moment M are both functions of the wind speed v, collectively known as the component wind load effect, represented by the variable w. The component strength is represented by e and obeys the normal distribution. Failure occurs when the component strength is less than the wind load. The structural vulnerability model is represented by the normal cumulative distribution function Φ(w), as shown in the formula:
[0149]
[0150] in, is the normal probability density function of the component intensity.
[0151] S042: Calculate the failure probability of the distribution line, indicating the uncertainty of the damage to the distribution line.
[0152] From the established wind field model, it can be seen that the wind speed follows the optimal distribution F b (v). In addition, w is a quadratic function of v, so the wind load effect should also be a random variable, denoted as w(v), and obey the composite distribution shown in the following formula:
[0153] F(w)=pw{W(V)≤w}=p v {V≤W -1 (w)}
[0154] =F b [W -1 (w)]
[0155] According to the stress-strength interference theory, the unique failure probability of a component is the convolution of the composite distribution of the fragility function and the wind load effect:
[0156]
[0157] σ δ =ε 1 σ μ
[0158] M μ =γM exam
[0159] M δ =ε 2 M μ
[0160] According to the series reliability model, the failure probability of distribution line ij is as follows:
[0161]
[0162] In this way, the failure probability of each line section under hurricane disaster can be calculated.
[0163] S05: Generate and restore the fault scenario.
[0164] The scenario generation algorithm for distribution line damage uncertainty modeling is Monte Carlo sampling, in which the damage state of the distribution line is determined by the threshold method. Then the SBR algorithm is used to remove low-probability scenarios, which can effectively reduce the calculation time.
[0165] S06: Determine the coupling nodes of the road network and the electrical network, establish the coupling network topology, use the traffic distribution model to obtain the traffic flow on each road section according to the number and flow direction of vehicles in the set network, and use the road resistance function to obtain the travel time on each road section.
[0166] S061: A mobile energy storage device path selection method considering the impact of traffic flow was established.
[0167] The method for determining the traffic flow of a road network based on equilibrium theory is as follows: for a certain road section, the relationship between the time of passing through the road section and the traffic flow of the road section is:
[0168]
[0169] Where ζ is a road section; τ ζ is the required travel time to pass the road segment ζ; is the free travel time of section ζ, which is the travel time required when the traffic flow is equal to the design flow; is the design flow of section ζ; f ζ is the actual flow of section ζ; ψ is the set of sections.
[0170] For the traffic assignment problem, Wardrop's first and second principles are used: all users choose the path with the shortest time for themselves, and the total travel time of all vehicles in the network is minimized. Assuming that the vehicle needs to go from the departure point o to the destination d, the optimal system flow model is established as:
[0171]
[0172] In the formula, q odFor all OD (origin-destination) pairs between o and d; is the flow on path k between o and d; It is a 0-1 variable. When it is equal to 1, it means that the section ζ is on the path k between o and d. When it is equal to 0, it means that the section ζ is not on the path k between o and d.
[0173] S062: Determine the path selection for mobile energy storage based on the shortest time.
[0174] Usually, the number of mobile energy storage is relatively small, and the impact on network traffic is small and can be ignored; therefore, after obtaining the traffic of each section, the formula
[0175]
[0176] Determine the travel time of mobile energy storage on this road section.
[0177] At this time, to determine the route between two points, you only need to list all the paths between the two points, calculate the sum of the time of all sections on each path, and you can determine the time required for the path. Compare the time taken by all paths to select the path with the shortest time.
[0178] S07: The purpose of mobile energy storage access is to reduce the losses of the system caused by disasters. To this end, an objective function of the mobile energy storage pre-configuration model taking into account the impact of random failures and traffic flow is established. The objective function is to minimize the total operating cost of the system (including the operating cost of mobile energy storage and the system load loss cost):
[0179]
[0180] Where S is the set of fault scenarios; is the operating cost of the scenario; θ is the linear aging coefficient of the mobile energy storage device; C mes Cost of equipment for mobile energy storage; is the charging and discharging power of the mth mobile energy storage at node i at time t in scenario s, where discharging is positive and charging is negative; is the load loss of node i; is the load reduction at node i at time t in scenario s.
[0181] S071: Power flow constraint part of the mobile energy storage pre-configuration model considering random faults and traffic flow:
[0182]
[0183]
[0184] V min ≤V i,t,s≤V max
[0185]
[0186] In the formula, is the active power flow of line ij at time t in scenario s; is the reactive power flow of line ij at time t in scenario s; is the load of node j at time t; v j,t,s is the voltage of node i at time t in scenario s; r ij 、x ij are the resistance and reactance of line ij respectively; is the active output of the generator at node i at time t in scenario s; is the active output of the generator at node i at time t in scenario s.
[0187] For the faulted line, the power flow is zero:
[0188]
[0189] Where, L o is the set of fault lines.
[0190] S072: Energy storage equipment operation constraints of the mobile energy storage pre-configuration model taking into account random failures and traffic flow:
[0191]
[0192] u m,i,t,s -u m,i,t+1,s ≤1-u m,j,t+Δ,s ,
[0193]
[0194] In the formula, e m,t,s is the power of the mth mobile energy storage at time t in scenario s; is the maximum capacity of mobile energy storage; u m,i,t,s is the location variable of the mobile energy storage. In scenario s, the value is 1 when the mth mobile energy storage is at node i at time t, otherwise it is 0. K is the power factor of the mobile energy storage. K mes The charging and discharging efficiency of mobile energy storage; N is the maximum number of mobile energy storage devices that can be connected to the node; MES is the total amount of mobile energy storage in the system; loc m,i is the initial position variable of the mobile energy storage. When it is equal to 1, it means that the mobile energy storage numbered m is dispatched to position i.
[0195] S08: Solve the objective function; use the variance coefficient of the objective function as the convergence criterion and set the convergence condition; when the convergence condition is met, output the result, otherwise return to S05.
[0196] S09: Output the distribution of the optimal access positions, and select the solution with the highest occurrence frequency as the optimal solution of the model.
[0197] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A mobile emergency resource disaster location pre-dispatching system, characterized by: The following steps are involved: Step 1. Decouple the transport vehicle from the mobile energy storage. The mobile energy storage is transported by the vehicle as an independent unit. The transport vehicle can transport multiple energy storage units at the same time, further improving the temporal and spatial flexibility of the mobile energy storage. Step 2. Consider the economic feasibility of mobile energy storage units, analyze the value they generate to the power system under normal operation, ensure the economic feasibility of mobile energy storage, and minimize investment costs; Step 3. Obtain typhoon data and geographic data, predict the distribution of typhoon wind fields, establish a comprehensive wind field model based on extreme value distribution, and make accurate wind speed predictions; Step 4. Using an improved stress-strength interference model to determine the failure probability of the distribution line; Step 5. Through Monte Carlo sampling, random fault scenarios of the distribution network can be obtained, and the SBR algorithm is used to remove low-probability scenarios to reduce the calculation time; Step 6. Calculate the travel time between nodes based on the traffic volume of the road network, and integrate the transfer time constraint into the scheduling model of mobile energy storage; Step 7. Taking minimizing the continuous load outage time as the objective function, establish the optimal access location model of mobile energy storage, and then determine the travel time of each section of the road network system through the road network traffic flow, and dispatch the mobile energy storage to the optimal location so that the expected access time to the network is minimized in all possible fault scenarios, thereby achieving the goal of minimizing the expected load loss in all fault scenarios.
2. A mobile emergency resource disaster location pre-dispatching system according to claim 1, characterized in that: In step 1, the transport vehicle is decoupled from the mobile energy storage, and the mobile energy storage is transported by the vehicle as an independent unit. The transport vehicle can transport multiple energy storage units at the same time, further improving the temporal and spatial flexibility of the mobile energy storage; Most of the existing mobile energy storage uses containerized energy storage and is deployed using transport vehicles. Structurally, these energy storage devices are separable from the transport vehicles themselves. Based on the vehicle routing problem with time windows, a mobile energy storage vehicle scheduling model based on a spatiotemporal network model is established, and its objective function is: Where V represents the set of all nodes in the transportation network; K represents the set of transportation vehicles; v ij,k represents the cost of vehicle k serving arc ij; e ij,k is a 0-1 variable; As a decision variable, when vehicle k serves arc ij, its value is 1, and v ij,k The cost is 0 otherwise; The constraints satisfied by the model are as follows: (1) Time window constraints: (2) Vehicle capacity constraints: (3) Traffic balance constraints: The space-time network is used to establish the path model of mobile energy storage to characterize the space-time state of mobile energy storage during operation; the space-time network model constructs a coordinate system with time as the horizontal axis and traffic nodes as the vertical axis; the arcs between each node are used to represent all possible states of the transport vehicle in each time period, and its objective function is as follows: Where Ξ is the set of space-time network arcs; Π is the set of mobile energy storage vehicles; Υ is the set of scheduling periods, and each step corresponds to a period; C ij is the transportation cost through arc ij; L ij,ν,t is a 0-1 variable. If the mobile energy storage vehicle v stands on arc ij in time period t, then L ij,ν,t =1, otherwise L ij,ν,t =0; The constraints are as follows: It means that the mobile energy storage vehicle v can only and must be located on a certain arc in time period t; It means that the starting node of the arc where the mobile energy storage vehicle v is located in time period t is the same as the ending node of the arc where the mobile energy storage vehicle v is located in time period t-1, that is, the inflow of each node is equal to the outflow; This constraint represents the starting and ending states of the mobile energy storage train v, where L v,0 and L v,T are the starting position and ending position of the mobile energy storage train v. Generally, the mobile energy storage vehicle should return to the initial position at the end of the dispatch, i.e., L v,0 =L v,T .
3. A mobile emergency resource disaster location pre-dispatching system according to claim 2, characterized in that: In step 2, the economic efficiency of the mobile energy storage unit is taken into consideration, and the value it generates to the power system under normal operation is analyzed to ensure the economic efficiency of the mobile energy storage and reduce the investment cost as much as possible; Mobile energy storage devices can not only provide users with emergency power when a system failure occurs, but also give full play to their own energy migration characteristics in time and space to achieve the purpose of "peak shaving and valley filling", thereby reducing system operating costs.
4. A mobile emergency resource disaster location pre-dispatching system according to claim 3, characterized in that: In step 3, typhoon data and geographic data are obtained, the distribution of the typhoon wind field is predicted, and a comprehensive wind field model based on extreme value distribution is established to perform accurate wind speed prediction; The extreme wind speed can be fitted into extreme value i distribution, Weibull distribution and Gamma distribution; First, under the three distribution assumptions, different methods are used to estimate the shape, location and scale parameters of each point. In order to measure the accuracy of parameter estimation, the goodness of fit metric related to machine learning is used to measure the fit distribution function F(v) and the empirical distribution function F n (v) Deviation between; Second, for each distribution hypothesis, the optimal estimation method is selected and the best parameters and goodness-of-fit measures are recorded; Finally, the goodness-of-fit indices of the three distribution hypotheses are compared to obtain the best fit index, and the corresponding distribution F is selected for each point. b (v) and parameters; In this way, the optimal distribution L for each point can be obtained from these three distributions b (v), extreme wind speed refers to the wind speed value exceeding a certain wind speed v0 once every X years, expressed as probability p v {V>v0}=1-L b (v0) = 1 / X, where V is the random variable of wind speed; Therefore, the wind speed with a period of X years is in is the function L b The reciprocal of (v), finally V X is the final wind speed.
5. A mobile emergency resource disaster location pre-dispatching system according to claim 4, characterized in that: In the step 4, an improved structural fragility model of stress-strength interference theory is adopted; The distribution line is assumed to be composed of concrete poles, and the poles support a three-phase symmetrical layout of conductors. The wind speed v at each pole can be provided by the wind field model. Due to the different terrains where the poles are located, the wind direction is generated randomly; the calculation of the wind load acting on the conductors and poles is given by the following two equations: The calculation of the conductor's cross-sectional stress σ is shown in the formula: σ(v)=W c / S c In addition to the wind load on the pole, the pole also bears the wind load from the traction wire; the force point of the wind load on the pole is halfway, generating a bending moment M1 at the root of the pole, and the calculation formula is: M1(v)=W p (l-l2) / 2 The calculation of the extreme root bending moment M2 caused by the wind load of the traction conductor is shown as follows: <h2 style=";text-align:left;direction:ltr">M2(v) = 2W<h2 style=";text-align:left;direction:ltr"> c <h2 style=";text-align:left;direction:ltr"> l1+W<h2 style=";text-align:left;direction:ltr"> c <h2 style=";text-align:left;direction:ltr"> (l-l2) The composite root bending moment M of the rod is the vector sum of M1 and M2, and its modulus calculation formula is: The cross-sectional stress φ and the root bending moment M are both functions of the wind speed v, collectively known as the component wind load effect, represented by the variable w; the component strength is represented by e and obeys the normal distribution; failure occurs when the component strength is less than the wind load; the structural vulnerability model is represented by the normal cumulative distribution function Φ(w), as shown in the formula: in, is the normal probability density function of the component intensity.
6. A mobile emergency resource disaster location pre-dispatching system according to claim 5, characterized in that: In the step 4, the failure probability of the distribution line is determined; The failure probability of the distribution line is calculated based on the structural vulnerability model of the stress-strength interference theory, which indicates the uncertainty of the damage to the distribution line. It can be seen from the wind field model in claim 2 that the wind speed is subject to the optimal distribution F b (v); in addition, w is a quadratic function of v, so the wind load effect should also be a random variable, denoted as w(v), and obey the composite distribution shown in the following formula: F(w)=pw{W(V)≤w}=p v {V≤W -1 (w)} =F b [W -1 (w)] According to the stress-strength interference theory, the unique failure probability of a component is the convolution of the composite distribution of the fragility function and the wind load effect: s δ =ε1σ μ M μ =γM exam M δ =ε2M μ According to the series reliability model, the failure probability of distribution line ij is as follows: Thus the failure probability is calculated.
7. A mobile emergency resource disaster location pre-dispatching system according to claim 6, characterized in that: In the step 5, a random fault scenario of the power distribution network is obtained; The acquisition of random fault scenarios, the generation and restoration of fault scenarios by Monte Carlo algorithm, the uncertainty modeling of distribution line damage, and then the removal of low-probability scenarios by SBR algorithm can effectively reduce the calculation time.
8. The mobile emergency resource disaster location pre-dispatching system according to claim 7, characterized in that: In step 6, a mobile energy storage device path selection method considering the impact of traffic flow is established; The method for determining the traffic flow of a road network based on equilibrium theory is as follows: for a certain road section, the relationship between the time of passing through the road section and the traffic flow of the road section is: Where ζ is a road section; τ ζ is the required travel time to pass the road segment ζ; is the free travel time of section ζ, which is the travel time required when the traffic flow is equal to the design flow; is the design flow of section ζ; f ζ is the actual flow of the road section ζ; ψ is the set of road sections; For the traffic assignment problem, the first and second principles of Wardrop are used: all users choose the path with the shortest time for themselves, and the total travel time of all vehicles in the network is minimized; assuming that the vehicle needs to reach the destination d from the departure point o, the optimal model of system flow is established as: In the formula, q od For all OD (origin-destination) pairs between o and d; is the flow on path k between o and d; It is a 0-1 variable. When it is equal to 1, it means that the section ζ is on the path k between o and d. When it is equal to 0, it means that the section ζ is not on the path k between o and d.
9. A mobile emergency resource disaster location pre-dispatching system according to claim 8, characterized in that: In step 6, the path selection of mobile energy storage is determined based on the shortest time; Usually, the number of mobile energy storage is relatively small, and the impact on network traffic is small and can be ignored; therefore, after obtaining the traffic of each section, the formula can be used: Determine the travel time of mobile energy storage on this road section.
10. A mobile emergency resource disaster location pre-dispatching system according to claim 9, characterized in that: In step 7, the optimal access position model of mobile energy storage is established with minimizing the continuous outage time of load as the objective function, and the travel time of each section of the road network system can be determined by the road network traffic flow, and the mobile energy storage is dispatched to the optimal position so that the expected access time to the network is minimized in all possible fault scenarios, thereby achieving the purpose of minimizing the expected load loss in all fault scenarios; After a distribution network failure occurs, pre-disaster location scheduling can enable mobile energy storage to reach the access point as quickly as possible to supply power to the distribution network load to reduce load loss; Objective function of the mobile energy storage pre-configuration model taking into account the impact of random failures and traffic flow: The purpose of mobile energy storage access is to reduce the system losses caused by disasters; therefore, the objective function of the model is to minimize the total operating cost of the system (including the operating cost of mobile energy storage and the system load loss cost): Where S is the set of fault scenarios; is the running cost of the scenario; is the linear aging coefficient of the mobile energy storage device; C mes Cost of equipment for mobile energy storage; is the charging and discharging power of the mth mobile energy storage at node i at time t in scenario s, where discharging is positive and charging is negative; is the load loss of node i; is the load reduction at node i at time t in scenario s; Constraints of the mobile energy storage pre-configuration model considering random failures and traffic flow: ① Flow constraint part: In min ≤V i,t,s ≤V max In the formula, is the active power flow of line ij at time t in scenario s; is the reactive power flow of line ij at time t in scenario s; is the load of node j at time t; v j,t,s is the voltage of node i at time t in scenario s; r ij 、x ij are the resistance and reactance of line ij respectively; is the active output of the generator at node i at time t in scenario s; is the active output of the generator at node i at time t in scenario s; For the faulted line, the power flow is zero: Where, L o is the fault line set; ②Operation constraints of energy storage equipment: in m,i,t,s -in m,i,t+1,s ≤1-in m,j,t+Δ,s , In the formula, e m,t,s is the power of the mth mobile energy storage at time t in scenario s; is the maximum capacity of mobile energy storage; u m,i,t,s is the location variable of the mobile energy storage. In scenario s, the value is 1 when the mth mobile energy storage is at node i at time t, otherwise it is 0. K is the power factor of the mobile energy storage. K mes The charging and discharging efficiency of mobile energy storage; N is the maximum number of mobile energy storage devices that can be connected to the node; MES is the total amount of mobile energy storage in the system; loc m,i is the initial position variable of the mobile energy storage. When it is equal to 1, it means that the mobile energy storage numbered m is dispatched to position i.