Method for planning and measuring water depth of pool for aircraft splash test

Through the water depth measurement and adjustment method based on runway geographic information and landing gear tire layout in aircraft splashing test, the problem of uneven water depth distribution is solved, the water depth uniformity and test requirements are met, and the stability of the test results is improved. and data integrity.

CN118960672APending Publication Date: 2024-11-15COMMERCIAL AIRCRAFT CORP OF CHINA LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410981837.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-22
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The prior art is difficult to meet the water depth requirements of EASA AMC25.1091(d)(2) and FAA AC25.1091(d)(2) in aircraft splash tests, resulting in uneven water depth distribution, affecting the test results and impact of aircraft structure. Load.

Method used

By selecting elevation mapping points and water depth measurement points based on runway geographic information and aircraft landing gear tire layout, the water depth distribution in the pool is calculated and adjusted to ensure water depth uniformity and compliance with test requirements.

Benefits of technology

The uniformity and accuracy of water depth distribution are achieved, the test requirements of aircraft splash tests are met, the error and test failure rate caused by water depth differences are reduced, and detailed water depth data is provided to support test analysis and performance model correction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118960672A_ABST
    Figure CN118960672A_ABST
Patent Text Reader

Abstract

The invention relates to a water depth planning and water depth measuring method for a pool for an aircraft splash test. The method comprises the following steps: selecting an elevation surveying and mapping point on a runway based on geographic information of the runway of an airport for carrying out an aircraft splash test; according to the undercarriage tire layout of the test aircraft, selecting water depth measurement points at the tire sliding track at predetermined intervals along the course; surveying and mapping the elevation at the elevation surveying and mapping point on the runway to obtain an elevation data set of the runway; calculating the water depth distribution on the planned runway based on the elevation data set of the runway and the test requirements of the aircraft splash test, and calculating the water depth requirements at the predetermined water depth measurement points; based on the water depth distribution on the runway, arranging a pool dam body at a preset position of the runway; performing water injection or water drainage operation on the pool to adjust the water depth in the pool; measuring the water depth at each water depth measuring point; and determining whether a water depth requirement is met, and continuing the method until the water depth requirement is met and ending the method.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to a method for planning and measuring the water depth of a water pool for an aircraft water splash test, and specifically, the water depth of the water pool is designed based on the runway pavement elevation information in view of the runway water accumulation condition required by the aircraft water splash test, thereby providing the runway water accumulation environment required by the test. The present invention belongs to the field of flight tests. Background Art

[0002] In order to verify that the water splashed by the landing gear tires when the aircraft takes off and lands on a flooded runway will not have an adverse effect on the aircraft's engine, APU, atmospheric data system and other systems and the fuselage structure, and to obtain the aircraft's performance data, it is usually necessary to carry out aircraft water splash and contaminated runway performance tests, referred to herein as aircraft water splash tests.

[0003] In order to simulate the runway water accumulation environment, it is necessary to build a water pool on the runway to retain the water depth required for the aircraft splash test, and the water depth distribution at various locations on the runway needs to be reasonably controlled to meet the water accumulation environment specified by the test requirements of the aircraft splash test.

[0004] Although the water splash test for transport aircraft is mentioned in FAA, EASA and my country's CCAR-25, it is limited to airworthiness clauses and requirements. At present, airworthiness authorities such as CAAC, FAA and EASA and third-party organizations have provided guidance on the water depth requirements for aircraft water splash tests. Among them, FAA AC25.1091(d)(2) points out that a water depth of 0.5 inches (about 12.7mm) is a recognized standard. The test can be carried out in a specially built pool, and more than 90% of the water surface of the test pool should maintain the selected water depth. In addition, EASA AMC25.1091(d)(2) recommends that the water depth required for the test should be a minimum of 13mm and an average of 19mm. In addition, SAE AIR1904b recommends that water depth measurements be made on the tire taxi track of the aircraft's landing gear.

[0005] In modern airports, for the sake of rapid drainage, runways are usually built with a certain slope, which makes it impossible for water to remain at a certain depth on the runway surface. This results in uneven distribution of water depth on the runway surface, making it difficult to create a runway water accumulation environment that meets the requirements of aircraft splash test.

[0006] The water depth in the pool will directly affect the results of the water splash test. Through the analysis of the impact of water depth on the water splash trajectory, the intensity of the water splash increases with the increase of water depth, aircraft speed and landing gear tire load, and under the same conditions, the deeper the water depth, the greater the splash intensity. Under the water depth conditions that meet the airworthiness requirements, the additional water depth will cause greater impact loads on the aircraft body structure and pipelines, which will reduce the pass rate of the aircraft water splash test to a certain extent. Therefore, according to the test requirements of the aircraft water splash test, reasonably setting the water depth measurement point and the target water depth and accurately controlling the water depth are the keys to fully verify the terms and efficiently complete the test.

[0007] The area of ​​the water pool for the aircraft splash test is relatively large, and the water depth measurement method needs to represent both the overall water depth of the water pool area and the local water depth at the landing gear tire track. In addition, due to the structural characteristics of the water pool, there are inevitable leakage and evaporation. The water depth measurement should be easy to implement and can be completed in a short time to ensure that during the aircraft splash test, the water depth conditions meet the test requirements when the aircraft taxis through the water pool.

[0008] In the prior art, there are two main methods for measuring the water depth of a water pool for an aircraft splash test.

[0009] One is a water depth measurement method based on the average slope of the runway pavement. According to FAA AC 25.1091(d)(2), the FAA has proposed an area-based water depth requirement for the water depth of the aircraft splash test. In order to meet this requirement, some third-party organizations have proposed a water depth measurement method based on the average slope of the runway pavement. This method uses measurement and other methods to obtain the elevation of the entire area of ​​the runway where the pool is to be built, obtain the average longitudinal and transverse slopes of the runway, and calculate the water depth distribution in the planned pool based on these two average slope values. At the critical position corresponding to the area that meets the water depth distribution, that is, at the boundary position corresponding to 90% of the area of ​​the test pool, multiple measurement points are selected to measure the water depth. When it is confirmed that the water depth at the critical position of the pool meets the test requirements, it can be indirectly guaranteed that the water depth of the pool meets the requirements of the aircraft splash test.

[0010] However, although this method requires few locations to be measured and is easy to implement, its disadvantage is that the airport runway surface is prone to different slopes due to construction errors, maintenance, etc., and in severe cases, the error from the average slope is large, which may lead to large non-uniformity in the water depth in the pool calculated based on the average slope. This will cause the splash trajectory generated by the aircraft taxiing in the pool to fluctuate during the aircraft splash test, which will seriously affect the interpretation of the test results. In addition, measuring the water depth only at the critical position of the pool is prone to lack of water depth information at the tire taxiing track of the aircraft landing gear, that is, it is impossible to directly measure the relationship between the water depth at the tire taxiing track and the test results, and it is impossible to know whether the water depth meets the requirements of FAA AC25.1091(d)(2) and also meets the requirements of EASA AMC25.1091(d)(2).

[0011] Another main method is the water depth measurement method based on the tire taxi track of the aircraft landing gear. This method is mainly used to demonstrate compliance with EASA AMC25.1091(d)(2). Among them, the tire taxi track of the landing gear is determined according to the aircraft landing gear tire layout before the test, that is, the change of the tire taxi track can be ignored. This method selects water depth measurement points at or near the tire taxi track of the aircraft landing gear. During the test, the water depth is adjusted and the average and maximum values ​​of each measurement point are calculated until the water depth at or near the tire taxi track meets the airworthiness requirements.

[0012] However, although this method is also easy to implement, it does not know the runway information. It is impossible to plan the water depth distribution in the pool before arranging the pool dam. If a large difference in water depth is found after filling, it is necessary to refill or drain water. Similarly, due to the lack of basic runway information, it is impossible to characterize the area that meets the test water depth conditions as a percentage of the total area, that is, it is impossible to know whether it meets the requirements of FAAAC25.1091(d)(2) when it meets the requirements of EASA AMC25.1091(d)(2).

[0013] Therefore, there is an urgent need to propose a method for water depth planning and water depth measurement of a water pool for aircraft splash test, so as to provide the runway water environment required for the aircraft splash test and meet the requirements of both EASA AMC25.1091(d)(2) and FAA AC25.1091(d)(2). Summary of the invention

[0014] In view of the above-mentioned problems in the prior art, an object of the present invention is to provide a method for water depth planning and water depth measurement of a water pool used for an aircraft water splash test, so as to provide a runway water accumulation environment required for the aircraft water splash test.

[0015] In a first example of the method, the method includes: selecting elevation mapping points on the runway based on geographic information of the runway of an airport where an aircraft splash test is conducted; selecting water depth measurement points at predetermined intervals along the heading at the tire taxi track according to the landing gear tire layout of the test aircraft; obtaining an elevation data set of the runway by mapping the elevations at the elevation mapping points on the runway; calculating the water depth distribution on the planned runway based on the elevation data set of the runway and the test requirements of the aircraft splash test, and calculating the water depth requirements at predetermined water depth measurement points; arranging a pool dam at a predetermined position on the runway based on the water depth distribution on the runway; filling or draining the pool to adjust the water depth in the pool; measuring the water depth at each water depth measurement point; and determining whether the water depth requirement is met, and the method continues until the water depth requirement is met and the method ends.

[0016] In a second example of the method, optionally including the first example, the plurality of elevation mapping points are selected to be arranged in an array as a whole, and the interval distance between the elevation mapping points is in a range of 2 meters to 8 meters.

[0017] In a third example of the method, which optionally includes one or more of the first example and the second example, a water depth requirement at any position in the pool including the water depth measurement point is obtained by interpolation calculation.

[0018] In a fourth example of the method, optionally including one or more of the first to third examples, the overall area of ​​the area meeting the water depth requirement of the pool is obtained by integrating the areas of the area meeting the water depth requirement at different positions of the pool.

[0019] In the fifth example of the method, one or more of the first to fourth examples are optionally included, and the area ratio of the water pool that meets the water depth requirement is obtained by comparing the overall area of ​​the area of ​​the water pool that meets the water depth requirement with the total area of ​​the water pool to determine whether the area ratio requirement in the test requirements of the aircraft water splash test is met.

[0020] In a sixth example of the method, one or more of the first to fifth examples are optionally included, and the water depth requirements of the water pool at the tire taxi track of the aircraft's landing gear are arithmetic averaged to obtain the water depth requirements at the tire taxi track of the landing gear to determine whether the water depth requirements at the tire taxi track of the landing gear in the test requirements of the aircraft splash test are met.

[0021] In a seventh example of the method, optionally including one or more of the first to sixth examples, the pool includes ten pool blocks adjacent to each other in the heading direction of the runway, and includes five pool blocks adjacent to each other in the span direction of the runway.

[0022] In an eighth example of the method, optionally including one or more of the first to seventh examples, the water pool is arranged in the range of 20m-40m in the span direction of the aircraft, and / or the water pool is arranged in the range of 50m-150m in the heading direction of the aircraft.

[0023] In a ninth example of the method, one or more of the first to eighth examples may be optionally included, adjusting the water depth in the pool, measuring the water depth, and completing an aircraft splash test within a predetermined test time to reduce errors in the pool caused by leakage and evaporation.

[0024] In the tenth example of the method, one or more of the first to ninth examples are optionally included, measuring the change of water depth in the pool at predetermined time intervals to obtain the water depth reduction rate; calculating the compensation water volume by the water depth reduction rate and the predetermined test time, and adding the compensation water volume to the pool when filling or draining the pool to reduce the error caused by leakage and evaporation of the pool.

[0025] The method for water depth planning and water depth measurement of a water pool for an aircraft splash test of the present invention is based on a runway pavement elevation data set and is used to simulate the runway water environment required for an aircraft splash test. Compared with the existing water pool water depth measurement method, the necessary runway data and detailed water depth information are obtained, which can meet the requirements of both EASA AMC25.1091(d)(2) and FAAAC25.1091(d)(2).

[0026] The present invention can ensure the uniformity of water depth distribution in the pool area. By mapping the runway elevation and planning the water depth distribution in the pool based on this, areas with uneven water depth can be identified in advance, and adjustments can be made to improve the uniformity of water depth while satisfying the test requirements as a whole. Repeated adjustments due to large differences in water depth after water injection are avoided.

[0027] The present invention can ensure the integrity of water depth data. The water depth measurement method based on the average slope of the runway and the water depth measurement method based on the tire taxiing track of the aircraft landing gear only record the information of the selected water depth measurement points, and cannot characterize the water depth information at other locations. When there is a need, the water depth at other locations needs to be extrapolated based on the average slope of the runway, and unexpected errors usually occur. The method proposed in the present invention provides high-resolution runway elevation information, and complete and high-precision water depth information can be obtained based on this model, providing a good basis for the analysis of the results of the aircraft splash test and the correction of the aircraft performance model.

[0028] The water depth measurement method proposed in the present invention provides complete and detailed water depth data in the pool area, providing a good basis for subsequent work such as test data analysis. The present invention improves the uniformity of water depth distribution in the aircraft splash test while meeting the test requirements by identifying areas with large water depth differences and making adjustments before the test, ensuring that the splash track of the aircraft landing gear tire is stable and continuous. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] In order to describe the implementation of the above and other features of the present invention, a more particular description of the invention briefly described above will be presented with reference to the exemplary embodiments of the invention shown in the accompanying drawings. It will be understood that these drawings only depict exemplary embodiments of the invention and should not be considered as limiting the scope thereof. The invention will be described and explained through the use of the accompanying drawings and with additional features and details. In the drawings:

[0030] Figure 1 is a flow chart of a method for water depth planning and water depth measurement of a water pool for an aircraft splash test according to an embodiment of the present invention;

[0031] Figure 2 is a three-dimensional schematic diagram of the elevation of a runway according to an embodiment of the present invention;

[0032] Figure 3 is a schematic diagram of the layout of a pool according to an embodiment of the present invention;

[0033] Figure 4 is a schematic diagram of a partial area of ​​a pool according to an embodiment of the present invention;

[0034] Figure 5 is a schematic diagram of water depth measurement points in a pool according to an embodiment of the present invention;

[0035] Figure 6 is a contour map of water depth distribution in a pool according to an embodiment of the present invention;

[0036] Figure 7 is a contour map of 12.7 mm water depth in a pool according to an embodiment of the present invention.

[0037] The drawings are approximately drawn to scale, however, the dimensions in the drawings are only schematic and not necessarily drawn strictly to scale, but are intended to provide a clearer illustration. In other embodiments, other relative dimensions may be used.

[0038] Here and throughout the following, identical features appearing in different figures are denoted by identical or similar reference numerals.

[0039] List of reference numerals:

[0040] 10 Runway

[0041] 11 Runway centre line

[0042] 20 Pool

[0043] 21 Span towards the pool dam

[0044] 22 Heading to the dam of the water pool

[0045] 30 Airplane

[0046] 31 Main landing gear tires

[0047] 32 Nose gear tire DETAILED DESCRIPTION

[0048] As used herein, the terms "comprising," "having," "including," and variations thereof are intended to serve as open-ended transitional phrases, terms or words requiring the presence of specified elements / steps and also allowing for the presence of other elements / steps.

[0049] In the present invention, unless explicitly stated to the contrary, the terms "first", "second", etc. are not intended to indicate any difference in order, position, quantity or importance, but are merely used as labels to distinguish different positions and components, to distinguish one element, component, region and / or position from another element, component, region and / or position.

[0050] The term "approximately" can be used to include any numerical value that can be varied without changing the basic function of the numerical value. Generally, the term "approximately" can refer to plus or minus 10% of the indicated number. When used with a range, "approximately" also discloses a range defined by the absolute values ​​of the two endpoints, for example, "about 2 to 4" also discloses a range of "from 2 to 4". All ranges disclosed herein include the endpoints described and are independently combinable (for example, a range of "from 2 to 4" includes endpoints 2 and 4 and all intermediate values).

[0051] The numerical value used in this article should be understood to include the same numerical value when reduced to the same number of significant digits, and the numerical value that differs from the numerical value is less than the experimental error of the conventional measurement technology of the type described in this application to determine the numerical value. Finally, the numerical value provided in each embodiment is only used as an example, and is not intended to limit the scope of the invention.

[0052] The present invention will be further described below in conjunction with specific embodiments and drawings. More details are elaborated in the following description to facilitate a full understanding of the present invention. However, the present invention can obviously be implemented in a variety of other ways different from the description herein. Those skilled in the art can make similar generalizations and deductions based on actual application situations without violating the connotation of the present invention. Therefore, the protection scope of the present invention should not be limited by the content of this specific embodiment.

[0053] Figure 1 A flow chart of a method for water depth planning and water depth measurement of a water pool for an aircraft splash test according to an embodiment of the present invention is shown.

[0054] The method 100 for water depth planning and water depth measurement of a water pool for an aircraft splash test according to the present invention includes at 101 a step of selecting elevation survey points.

[0055] The method 100 proposed in the present invention is based on the elevation data of the runway pavement. Therefore, before the aircraft water splash test, based on the geographical information of the runway 10 of the airport where the aircraft water splash test is carried out, elevation surveying points can be selected at smaller intervals for the area on the runway 10 where the water pool 20 may be set and the area at the tire taxiing track of the main landing gear tires 31 and the front landing gear tires 32 of the aircraft 30.

[0056] Preferably, the plurality of elevation surveying points are arranged as an array as a whole so as to cover the runway surface of the runway 10 without omission.

[0057] The interval between the elevation survey points may be in the range of 1 meter to 8 meters. Considering the accuracy requirements and workload of surveying the runway elevation, for the area of ​​the runway pavement where the pool 20 may be set, the interval between the elevation survey points may be about 5 meters; in addition, for the area at the tire taxiing track of the main landing gear tire 31 and the front landing gear tire 32 of the aircraft 30, the interval between the elevation survey points may be about 2 meters.

[0058] Preferably, a runway coordinate system having a horizontal axis and a vertical axis is set for the runway 10, and the aforementioned elevation surveying points are marked and recorded according to the coordinate system for the subsequent steps of surveying and recording data.

[0059] In a non-limiting example, the method 100 includes a step of selecting water depth measurement points at 102. In the area of ​​the pool 20, water depth measurement points are selected at predetermined intervals along the heading at each tire taxiing track, and the interval distance between the water depth measurement points may be in the range of about 2 meters to 8 meters. Considering the uniformity of water depth distribution and the actual workload, for the area of ​​the runway pavement where the pool 20 may be set, the interval distance between the water depth measurement points along the heading may be about 5 meters.

[0060] In one non-limiting example, the method 100 of the present invention includes, at 103, the step of mapping the elevation of the runway.

[0061] By mapping the elevations of the elevation mapping points on the runway in detail, a set of runway elevation data is obtained, hereinafter referred to as the elevation data set H. θ , and a three-dimensional model of the runway elevation can be established to facilitate display and subsequent planning steps. The discrete form of the elevation data is shown in formula (1).

[0062] H x,y =H(x, y) Formula (1)

[0063] In formula (1):

[0064] x and y are the coordinates of the horizontal and vertical axes based on the runway coordinate system;

[0065] H x,y is the elevation of the runway surface of runway 10 at coordinates x,y.

[0066] Figure 2 A three-dimensional schematic diagram schematically shows the elevation of a runway according to an embodiment of the present invention.

[0067] from Figure 2 It can be seen that the runway centerline 11 of the runway 10 has the maximum elevation and gradually descends along the span direction. This is to enable the accumulated water to be quickly drained from the runway when there is water on the runway.

[0068] Figure 3 The layout of the water pool according to the embodiment of the present invention is schematically shown. The runway 10 includes a runway centerline 11 , and in the aircraft water splash test, the flight trajectory of the aircraft 30 is approximately along the runway centerline 11 .

[0069] The layout range of the preset pool 20 is as follows Figure 3 As shown, the length direction of the pool 20 is arranged along the heading of the runway 10, and the width direction of the pool 20 is approximately centered on the runway centerline 11. The specific arrangement of the pool 20 will depend on the calculation results of the subsequent water depth distribution planning and water depth requirement steps of the method 100.

[0070] Figure 4 A partial area of ​​a pool according to an embodiment of the present invention is schematically shown, wherein the distribution of elevation mapping points and water depth measurement points is depicted. The elevation mapping points are selected at preset intervals in the area of ​​the runway 10 where the pool 20 may be set, and the elevation mapping points are selected at smaller intervals in the area of ​​the tire taxiing tracks of the main landing gear tires 31 and the front landing gear tires 32 of the aircraft 30. In the area where the pool 20 may be set, water depth measurement points are selected at the tire taxiing tracks at predetermined intervals along the heading.

[0071] In one non-limiting example, the method 100 of the present invention includes, at 104 , the step of planning a water depth distribution and a water depth requirement.

[0072] The water depth distribution on the planned runway is calculated based on the runway elevation information obtained by mapping and the test requirements of the aircraft splash test. Specifically, the water depth requirement at any position of the pool (including the water depth measurement points marked in advance) can be obtained by interpolation calculation when the overall water depth meets the test requirements, so that the water depth requirement at the predetermined water depth measurement point can be calculated. The water depth requirement is shown in formula (2).

[0073] D x,y =D(x, y, H Θ , d0) Formula (2)

[0074] In formula (2):

[0075] x and y are the coordinates of the horizontal and vertical axes based on the runway coordinate system;

[0076] H θ is a collection of elevation data;

[0077] D x,y is the calculated water depth at the position with coordinates x,y;

[0078] d0 is the water depth requirement for the aircraft splash test.

[0079] When planning the pool, the requirements of the aircraft splash test need to be considered, so a specified length is required in the heading direction of the runway. For example, the length of the pool 20 in the heading direction can preferably be arranged in the range of about 50m-150m, more preferably 100m.

[0080] In addition, the water pool 20 needs to cover the position of the aircraft engine in the span direction of the runway, and considering the transmission of pressure waves in the water pool 20, preferably, the water pool 20 can be within a range of 10-20 m on each side from the runway centerline 11 in the span direction, more preferably 15 m on each side, that is, it is preferably arranged in a total range of 20 m-40 m in the span direction, more preferably 30 m in total.

[0081] In particular, for the area-based water depth requirement proposed in FAAAC25.1091(d)(2), the overall area of ​​the area that meets the water depth requirement is obtained by integrating the areas of the area that meets the water depth requirement at different locations of the pool. The area ratio of the pool that meets the water depth requirement is obtained by comparing the overall area of ​​the area that meets the water depth requirement with the total area of ​​the pool to determine whether it meets the area ratio requirement in the aircraft splash test requirements. Among them, the overall area of ​​the pool is shown in formula (3), and the area ratio formula is shown in formula (4).

[0082]

[0083] In formula (3) and formula (4):

[0084] x and y are the coordinates of the horizontal and vertical axes based on the runway coordinate system;

[0085] D x,y is the calculated water depth at the position with coordinates x,y;

[0086] d0 is the water depth requirement for the aircraft splash test;

[0087] A| D>d0 It is the area where the water depth is calculated to be greater than the water depth requirement for the aircraft splash test;

[0088] A0 is the overall area of ​​the planned pool;

[0089] φ is the area ratio that meets the water depth requirement.

[0090] In addition, considering the water depth requirements of the area at the tire taxiing track of the main landing gear tire 31 and the front landing gear tire 32 of the aircraft 30, the water depth requirements of the pool at the tire taxiing track of the aircraft's landing gear are arithmetically averaged to obtain the water depth requirements at the location of the tire taxiing track of the landing gear, that is, by arithmetically averaging formula (2), it is determined whether the water depth requirements at the location of the tire taxiing track of the landing gear in the test requirements of the aircraft splash test are met.

[0091] In one non-limiting example, the method 100 of the present invention includes, at 105, the step of arranging a pool weir.

[0092] Taking into account the differences in runway pavement elevations at different locations on the runway 10, in order to create test conditions with relatively uniform water depth and isolate the impact of water surface disturbances at different locations on the test, the pool 20 on the runway 10 can be divided into multiple independent blocks, that is, at the location where the pool 20 is expected to be set up, the periphery of the pool 20 is established and divided into various blocks by means of a span-wise pool dam 21 and a heading pool dam 22.

[0093] Figure 5 The depth measurement points in the pool 20 according to an embodiment of the present invention are schematically shown. As shown, the pool 20 includes ten pool blocks adjacent to each other in the heading direction of the runway 10, and includes five pool blocks adjacent to each other in the span direction of the runway 10, wherein the sizes of the various pool blocks may be the same or different. The various pool blocks are separated by the span-wise pool dam 21 and the heading pool dam 22 and remain independent of each other, and the heights of the span-wise pool dam 21 and the heading pool dam 22 are approximately 100 mm-200 mm.

[0094] In addition, if in the aforementioned steps of mapping the runway elevation, or planning the water depth distribution and water depth requirements, it is found that there are areas with large differences in water depth distribution in the pool 20, the area can also be divided into blocks for adjustment to ensure that the overall water depth of the pool 20 meets the requirements.

[0095] In a non-limiting example, the method 100 of the present invention includes a step of adjusting the water depth in the pool 20 at 106. In this step, the pool will be filled or drained according to the calculated water depth requirements in the previous steps and possible further needs for water depth in subsequent steps.

[0096] The effects of pool leakage and evaporation can be considered when adjusting the water depth, and the errors caused by them can be minimized as much as possible. Preferably, the water depth in the pool is adjusted, the water depth is measured, and the aircraft splash test is completed within a predetermined test time to reduce the errors caused by pool leakage and evaporation.

[0097] In a preferred embodiment, when filling or draining a pool, a compensation amount of water may be added to the pool to reduce the error caused by leakage and evaporation of the pool, wherein the compensation amount of water is calculated by combining the water depth reduction rate described below and the predetermined test time.

[0098] After the dam of the pool is built, the water depth in the pool is measured multiple times at a fixed position at a certain time interval, preferably in multiple blocks of the pool, to obtain the rate of decrease of water depth due to leakage and evaporation. For example, but not limited to, at intervals of 5 minutes, continuous measurement for 30 minutes, to obtain the rate of decrease of water depth within 30 minutes.

[0099] In a non-limiting example, the method 100 of the present invention includes a step of measuring water depth at 107. In this step, the water depth at each water depth measurement point is measured, such as Figure 5 The points in the figure are arranged roughly in an array, except that they are slightly deviated in the span direction near the center line 11.

[0100] In a non-limiting example, the method 100 of the present invention includes a step of determining whether the water depth requirement is met at 108. Before the aircraft splash test begins, the water pool has been filled with water and the water depth at each measuring point has been measured. If the water depth at each water depth measuring point meets the requirement, it is ensured that the water depth of the water pool as a whole meets the requirement, and the method ends. If any of the water depths at each water depth measuring point does not meet the water depth requirement, the water depth in the water pool is readjusted and the water depth at each water depth measuring point is measured until the water depth at each water depth measuring point meets the requirement.

[0101] Figure 6 is a contour map of water depth distribution in the pool 20 according to an embodiment of the present invention. Figure 7This is a 12.7mm water depth contour map in a water pool according to an embodiment of the present invention. Through the water depth planning and water depth measurement method of the water pool for aircraft splash test in this article, the water depth of each measuring point meets the requirements during the aircraft splash test in one embodiment, which can ensure that the water depth of 90% of the water pool area is greater than 12.7mm ( Figure 6 ), and ensure that the water depth at the position of the tire taxiing track of the main landing gear tire 31 and the front landing gear tire 32 of the aircraft 30 is about 12.7 mm ( Figure 7 ).

[0102] In order to make the purpose, technical solution and advantages of the embodiments of the present invention more clear, the technical solution of the present invention is clearly and completely described above in combination with the specific embodiments of the present invention and the accompanying drawings.

[0103] Although various embodiments have been described above, it should be understood that the embodiments described are part of the embodiments of the present invention, rather than all embodiments, and they are presented in an exemplary rather than limiting manner. It is obvious to those skilled in the relevant art that the disclosed subject matter can be implemented in other specific forms without departing from its spirit and essential features.

[0104] In the process, various elements that are important to the present invention or are conducive to further developing the present invention will be mentioned in the content of the specific examples, but some of these elements can also be used to further develop the present invention when they are separated from the content of the corresponding examples and other features of the corresponding examples. Therefore, the embodiments described above are considered to be illustrative and non-restrictive in all aspects and are not used as a basis for any limitation of the present invention.

[0105] Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work belong to the scope of protection of the present invention. The present disclosure also includes various modifications and modifications within the equivalent scope. In addition, various combinations and methods, further including only one element, more than one or less than one other combinations and methods also belong to the scope and scope of thought of the present disclosure.

Claims

1. A method for water depth planning and water depth measurement of a pool for aircraft splash test, characterized in that: The method comprises: Based on the geographic information of the runway of the airport where the aircraft water splash test is carried out, selecting elevation survey points on the runway; According to the landing gear tire layout of the test aircraft, water depth measurement points are selected at predetermined intervals along the heading at the tire taxi track; Obtaining an elevation data set of the runway by mapping the elevations at the elevation mapping points on the runway; Calculating and planning the water depth distribution on the runway based on the elevation data set of the runway and the test requirements of the aircraft water splash test, and calculating the water depth requirements at predetermined water depth measurement points; Arranging a water pool dam at a predetermined position of the runway based on the water depth distribution on the runway; Filling or draining the pool to adjust the water depth in the pool; measuring the water depth at each of the water depth measurement points; and Determine whether the water depth requirement is met, If any of the water depths at the water depth measurement points does not meet the water depth requirement, the water depth in the pool is readjusted and the water depths at the water depth measurement points are measured until the water depths at the water depth measurement points meet the requirement, and If the water depths at all the water depth measurement points meet the requirements, it is ensured that the water depth of the pool as a whole meets the requirements, and the method ends.

2. The method according to claim 1, characterized in that: The plurality of elevation surveying points are selected to be arranged in an array as a whole, and the interval distance between the elevation surveying points is in the range of 2 meters to 8 meters.

3. The method according to claim 1, characterized in that The water depth requirement at any position in the pool including the water depth measurement point is obtained by interpolation calculation.

4. The method according to claim 3, characterized in that The overall area of ​​the area of ​​the pool that meets the water depth requirement is obtained by integrating the areas of the area that meets the water depth requirement at different positions of the pool.

5. The method according to claim 4, characterized in that The area ratio of the water pool that meets the water depth requirement is obtained by comparing the overall area of ​​the region of the water pool that meets the water depth requirement with the total area of ​​the water pool to determine whether it meets the area ratio requirement in the test requirements of the aircraft water splash test.

6. The method according to claim 3, characterized in that The water depth requirement of the water pool at the tire taxiing track of the aircraft's landing gear is obtained by taking the arithmetic average of the water depth requirements of the water pool at the tire taxiing track of the aircraft's landing gear, so as to determine whether the water depth requirement at the tire taxiing track of the landing gear in the test requirements of the aircraft's water splash test is met.

7. The method according to claim 1, characterized in that The water pool includes ten water pool blocks adjacent to each other in the heading direction of the runway, and includes five water pool blocks adjacent to each other in the span direction of the runway.

8. The method according to claim 1, characterized in that The water pool is arranged within a range of 20m-40m in the span direction of the aircraft, and / or The water pool is arranged within a range of 50m-150m in the heading direction of the aircraft.

9. The method according to claim 1, characterized in that: The water depth in the water pool is adjusted, the water depth is measured, and the aircraft splash test is completed within a predetermined test time to reduce errors caused by leakage and evaporation in the water pool.

10. The method according to claim 9, characterized in that The change of the water depth in the water pool is measured at predetermined time intervals to obtain the water depth reduction rate, the compensation water volume is calculated according to the water depth reduction rate and the predetermined test time, and when the water pool is filled with water or drained with water, the compensation water volume is increased to the water pool to reduce the error caused by leakage and evaporation of the water pool.