Method for determining timing for requesting musim gap

By establishing multi-network connections in MUSIM user equipment and calculating and requesting the timing of MUSIM gaps, the problem of MUSIM gap configuration in carrier aggregation and dual-connection scenarios is solved, and efficient network resource management and operation efficiency is achieved.

CN119014122APending Publication Date: 2024-11-22SAMSUNG ELECTRONICS CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202380032983.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Priority Date
2022-04-07
Filing Date
2023-04-06
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

In carrier aggregation and dual connection scenarios, effective configuration and request of multi-user identity module (MUSIM) gap is difficult to achieve, resulting in conflicts in signal and resource use and affecting network operation efficiency.

Method used

Connections to multiple network cells are established through the first universal SIM (USIM) of the MUSIM user equipment, the timing of the MUSIM gap is determined and calculated, and the MUSIM gap request is generated and sent to configure and manage the MUSIM gap and ensure the effective utilization of network resources.

Benefits of technology

It realizes the efficiency and effectiveness of MUSIM operations in complex network scenarios, avoids signal and resource usage conflicts, and improves the efficiency and reliability of network operations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119014122A_ABST
    Figure CN119014122A_ABST
Patent Text Reader

Abstract

The present disclosure relates to a 5G or 6G communication system for supporting a higher data transmission rate. The present subject matter relates to methods and systems for implementing MUSIM gaps.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present disclosure relates to a method and system for implementing a Multiple User Identity Module (MUSIM) gap. Background Art

[0002] 5G mobile communication technology defines a wide frequency band, making high transmission rates and new services possible, and can be realized not only in "below 6 GHz" frequency bands such as 3.5 GHz, but also in "above 6 GHz" frequency bands called millimeter waves (mmWave) including 28 GHz and 39 GHz. In addition, it has been considered to implement 6G mobile communication technology (called super 5G system) in terahertz frequency bands (e.g., 95 GHz to 3 THz frequency bands) in order to achieve a transmission rate fifty times faster than 5G mobile communication technology and an ultra-low latency one-tenth of 5G mobile communication technology.

[0003] At the beginning of the development of 5G mobile communication technology, in order to support services and meet performance requirements related to enhanced Mobile BroadBand (eMBB), Ultra Reliable Low Latency Communications (URLLC) and massive Machine-Type Communications (mMTC), there is ongoing standardization on the following aspects: beamforming and massive MIMO for mitigating radio wave path loss in millimeter waves and increasing radio wave transmission distance, supporting parameter sets for dynamic operation of millimeter wave resources and time slot formats for efficient utilization (for example, operating multiple subcarrier spacings), initial access technology for supporting multi-beam transmission and broadband, definition and operation of BWP (BandWidth Part), new channel coding methods for large-scale data transmission such as LDPC (Low Density Parity Check) codes and polar codes for highly reliable transmission of control information, L2 preprocessing, and network slicing for providing dedicated networks customized for specific services.

[0004] Currently, in view of the services to be supported by 5G mobile communication technology, discussions are underway on improvements and performance enhancements of initial 5G mobile communication technology, and there is already physical layer standardization on technologies such as: V2X (Vehicle-to-everything) for assisting driving decisions of autonomous vehicles based on information about the location and status of the vehicle sent by the vehicle and for enhancing user convenience, NR-U (New Radio Unlicensed) for system operation designed to comply with various regulatory requirements within unlicensed bands, NR UE energy saving, non-terrestrial network (NTN) (which is UE (User Equipment) satellite direct communication for providing coverage in areas where communication with terrestrial networks is not possible), and positioning.

[0005] In addition, there is already ongoing standardization in the air interface architecture / protocol on technologies such as Industrial Internet of Things (IIoT) to support new services through interconnection and integration with other industries, IAB (Integrated Access and Backhaul) to provide nodes for network service area expansion by supporting wireless backhaul links and access links in an integrated manner, mobility enhancement including conditional switching and DAPS (Dual Active Protocol Stack) switching, and two-step random access (two-step RACH for NR) to simplify the random access process. Standardization is also ongoing on system architecture / services for 5G baseline architecture (e.g., service-based architecture or service-based interface) for combining Network Functions Virtualization (NFV) and Software-Defined Networking (SDN) technologies, as well as Mobile Edge Computing (MEC) for receiving UE location-based services.

[0006] With the commercialization of 5G mobile communication systems, the number of connected devices, which has been growing exponentially, will be connected to the communication network, and it is expected that the enhanced functions and performance of the 5G mobile communication system and the integrated operation of the connected devices will be necessary. To this end, new research related to extended reality (eXtended Reality, XR) is arranged to effectively support AR (Augmented Reality), VR (Virtual Reality), MR (Mixed Reality), etc., 5G performance improvement and complexity reduction by utilizing artificial intelligence (AI) and machine learning (ML), AI service support, meta-service support and drone communication.

[0007] In addition, such developments in 5G mobile communication systems will serve as a foundation for developing not only new waveforms for providing coverage in the terahertz band for 6G mobile communication technology, multi-antenna transmission technologies such as full Dimensional MIMO (FD-MIMO), array antennas, and massive antennas, metamaterial-based lenses and antennas for improving coverage of terahertz band signals, high-dimensional spatial multiplexing technology using OAM (Orbital Angular Momentum), and RIS (Reconfigurable Intelligent Surface), but also full-duplex technology for improving the frequency efficiency of 6G mobile communication technology and improving system networks, AI-based communication technology for achieving system optimization and internalizing end-to-end AI support functions using satellites and AI from the design stage, and next-generation distributed computing technology for implementing services at a complexity level that exceeds the limits of UE operating capabilities by utilizing ultra-high performance communication and computing resources.

[0008] Fifth generation (5G) or new radio (NR) mobile communications are gathering increasing momentum recently, with all global technical activities from industry and academia on various candidate technologies. Candidate enablers for 5G / NR mobile communications include massive antenna technology from traditional cellular bands up to high frequencies to provide beamforming gain and support increased capacity, new waveforms (e.g., new radio access technologies (RATs)) that flexibly accommodate various services / applications with different requirements, new multiple access schemes that support massive connectivity, etc. Summary of the invention

[0009] Technical issues

[0010] The operation of a MUSIM UE involves multiple USIMs (Universal SIMs, first universal SIM) sharing the same Radio Frequency (RF) circuitry to perform various activities and services on different networks. This means that multiple USIMs need to arbitrate and share common RF resources between them to perform various network activities and / or utilize network services. In order to perform network operations of USIM-B, USIM-A may require network gaps (interchangeably referred to as "MUSIM gaps") to avoid conflicts in signal and resource usage. The present disclosure provides a method and apparatus for deriving timing for requesting and configuring MUSIM gaps.

[0011] The technical subject matter pursued in the present disclosure may not be limited to the above-mentioned technical subject matter, and other technical subject matter not mentioned may be clearly understood by those skilled in the art to which the present disclosure belongs through the following description.

[0012] Solution to the problem

[0013] According to one embodiment of the present disclosure, a method for implementing a multi-user identity module (MUSIM) gap during carrier aggregation (CA) is disclosed. The method includes establishing, by a first universal SIM (USIM) of a MUSIM user equipment (UE), a connection with two or more component carriers (CC) provided by one or more cells of a first network. The one or more cells of the first network include at least one of a primary cell and a secondary cell. The method also includes determining, by the MUSIM UE, a requirement for a MUSIM gap in the first network to perform one or more network operations in a second USIM. In addition, the method includes calculating, by the MUSIM UE, a timing of the MUSIM gap relative to a timing configuration of a primary cell of the first network. In addition, the method includes generating, by the MUSIM UE, a MUSIM gap request for the MUSIM gap based on the timing for the MUSIM gap calculation. In addition, the method includes sending the generated MUSIM gap request to the first network.

[0014] According to another embodiment of the present disclosure, a method for implementing a MUSIM gap in a dual connection scenario at a MUSIM UE is disclosed. The method includes establishing, by a first universal SIM (USIM) of the MUSIM UE, a dual connection with at least one of a primary network node and a secondary network node. The method also includes receiving timing configuration information for calculating the timing of the MUSIM gap from the primary network node. In addition, the method includes determining, by the UE, a requirement for a MUSIM gap in a first USIM connection to perform one or more operations in a second USIM. In addition, the method includes calculating the timing of the required MUSIM gap based on at least one of the timing configuration information received from the primary network node and the timing configuration information based on a predefined selection process in the UE. In addition, the method includes generating a MUSIM gap request for the required MUSIM gap based on the calculated timing for the MUSIM gap. In addition, the method includes sending the generated MUSIM gap request to the primary network node.

[0015] According to another embodiment of the present disclosure, a method for implementing a multi-user identity module (MUSIM) gap in a dual-connection scenario in a base station is disclosed. The method includes establishing a dual connection with at least one of a primary network node and a secondary network node of a base station using a first universal SIM (USIM) of a MUSIM user equipment (UE). The method also includes receiving an indication that the MUSIM UE supports configuration of a MUSIM gap in at least one second USIM. In addition, the method includes sending timing configuration information for calculating the timing for the MUSIM gap to the MUSIM UE based on the received indication, the timing configuration information including an indication of a reference cell to be used for the timing configuration, a system frame number (SFN), and at least one of a subframe number. The reference cell is a primary cell of a master cell group (MCG), a primary cell of a secondary cell group (SCG), or one of cells in a frequency range 2 (FR2) in an MCG.

[0016] According to another embodiment of the present disclosure, a system for implementing a multi-user identity module (MUSIM) gap in a carrier aggregation scenario is disclosed. The system includes a memory and at least one processor communicatively coupled to the memory. At least one processor is configured to establish a connection with two or more component carriers (CCs) provided by one or more cells of a first network using a first universal SIM (USIM) of a MUSIM user equipment (UE). The one or more cells of the first network include at least one of a primary cell and a secondary cell. In addition, at least one processor is configured to determine a requirement for a MUSIM gap in the first network to perform one or more network operations in a second USIM. In addition, at least one processor is configured to calculate the timing of the MUSIM gap relative to the primary cell timing configuration of the first network. At least one processor is also configured to generate a MUSIM gap request for the MUSIM gap based on the calculated timing of the MUSIM gap. In addition, at least one processor is configured to send the generated MUSIM gap request to the first network.

[0017] According to another embodiment of the present disclosure, a system for implementing a multi-user identity module (MUSIM) gap in a dual-connection scenario at a MUSIM user equipment (UE) is disclosed. The system includes a memory and at least one processor communicatively coupled to the memory. The at least one processor is configured to establish a dual connection with at least one of a primary network node and a secondary network node using a first universal SIM (USIM) of the MUSIM UE. The at least one processor is also configured to receive timing configuration information for calculating the timing for the MUSIM gap from the primary network node. In addition, the at least one processor is configured to determine a requirement for a MUSIM gap in a first USIM connection to perform one or more operations in a second USIM. In addition, the at least one processor is configured to calculate the timing of the required MUSIM gap based on at least one of the timing configuration information received from the primary network node and the timing configuration information based on a predefined selection process in the UE. In addition, the at least one processor is configured to generate a MUSIM gap request for the required MUSIM gap based on the calculated timing for the MUSIM gap. In addition, the at least one processor is configured to send the generated MUSIM gap request to the primary network node.

[0018] According to another embodiment of the present disclosure, a system for implementing a multi-user identity module (MUSIM) gap in a dual-connection scenario in a base station. The system includes a memory and at least one processor communicatively coupled to the memory. At least one processor is configured to establish a dual connection with at least one of a primary network node and a secondary network node of the base station using a first universal SIM (USIM) of a MUSIM user equipment (UE). At least one processor is also configured to receive an indication that the MUSIM UE supports configuration of a MUSIM gap in at least one second USIM. At least one processor is also configured to send timing configuration information for calculating the timing for the MUSIM gap to the MUSIM UE based on the received indication. The timing configuration information includes at least one of an indication of a reference cell to be used for timing configuration, an SFN, and a subframe number. The reference cell is one of a primary cell of a primary cell group (MCG), a primary cell of a secondary cell group (SCG), or a frequency range 2 (FR2) cell in an MCG.

[0019] In order to further illustrate the advantages and features of the present invention, a more specific description of the present invention will be presented by reference to the specific embodiments of the present invention shown in the accompanying drawings. It should be understood that these drawings only depict typical embodiments of the present invention and therefore should not be considered to limit its scope. The present invention will be described and explained with additional features and details through the accompanying drawings.

[0020] Advantageous Effects of the Invention

[0021] The present disclosure provides an effective and efficient solution for implementing MUSIM gaps. Advantageous effects obtainable from the present disclosure may not be limited to the above-mentioned effects, and those skilled in the art to which the present disclosure pertains may clearly understand other effects not mentioned through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] These and other features, aspects and advantages of the present invention will be better understood when the following detailed description is read with reference to the accompanying drawings, in which like characters refer to like parts throughout the several views, and in which:

[0023] Figure 1 An exemplary environment of a Multi-Universal Subscriber Identity Module (MUSIM) User Equipment (UE) according to an embodiment of the present disclosure is shown;

[0024] Figure 2 An exemplary process flow depicting a method for implementing MUSIM gaps during carrier aggregation (CA) according to an embodiment of the present disclosure is shown;

[0025] Figure 3 An exemplary process flow depicting a method for implementing MUSIM gap in a dual connectivity scenario at a UE according to an embodiment of the present disclosure is shown;

[0026] Figure 4 An exemplary process flow depicting a method for implementing a MUSIM gap in a dual connectivity scenario at a base station according to an embodiment of the present disclosure is shown;

[0027] Figure 5 An operational flow diagram depicting a process for determining a timing for requesting a MUSIM gap in accordance with an embodiment of the present subject matter is shown;

[0028] Figure 6 An operational flow diagram depicting a process for deriving a system frame number (SFN) / subframe for a UE to request a MUSIM gap when dual connectivity is configured in accordance with an embodiment of the present subject matter is shown;

[0029] Figure 7 An operational flow diagram depicting a process for deriving a system frame number (SFN) / subframe for a UE to request a MUSIM gap when dual connectivity is configured according to another embodiment of the present subject matter is shown;

[0030] Figure 8 is a diagram showing a configuration of a UE in a wireless communication system according to an embodiment of the present disclosure; and

[0031] Fig. 9 is a diagram illustrating a configuration of a base station in a wireless communication system according to an embodiment of the present disclosure.

[0032] Furthermore, those skilled in the art will recognize that the elements in the illustrations are shown for simplicity and may not necessarily be drawn to scale. For example, the flow charts illustrate the methods in terms of the most salient steps involved to help improve understanding of the various aspects of the invention. Furthermore, with respect to the construction of the device, one or more components of the device may have been represented in the illustrations by conventional symbols, and the illustrations may show only those specific details relevant to understanding the embodiments of the invention so as not to obscure the illustrations with details that would be readily apparent to one of ordinary skill in the art having the benefit of the description herein. DETAILED DESCRIPTION

[0033] It should be understood at the outset that although illustrative implementations of embodiments of the present disclosure are shown below, the present invention may be implemented using any number of techniques, whether currently known or existing. The present disclosure should in no way be limited to the illustrative implementations, illustrations, and techniques shown below, including the exemplary designs and implementations shown and described herein, but may be modified within the scope of the appended claims and their full scope of equivalents.

[0034] The term "some", as used herein, is defined as "none, or one, or more than one, or all". Thus, the terms "none", "one", "more than one", "more than one but not all", or "all" will all fall under the definition of "some". The term "some embodiments" may refer to no embodiments, or to one embodiment, or to several embodiments, or to all embodiments. Thus, the term "some embodiments" is defined to mean "none, or to one embodiment, or to more than one embodiment, or to all embodiments".

[0035] The terms and structures used herein are used to describe, teach, and illustrate the embodiments and specific features and elements thereof, and are not intended to limit, restrict, or reduce the spirit and scope of the claims or their equivalents.

[0036] More specifically, any terms used herein, such as but not limited to "include", "comprises", "has", "composes" and grammatical variations thereof, unless otherwise stated, do not specify precise limitations or restrictions, and certainly do not exclude the possible addition of one or more features or elements. Furthermore, unless otherwise stated with the restrictive language "must include" or "need to include", it must not be considered to exclude the possible removal of one or more listed features and elements.

[0037] Regardless of whether a feature or element is limited to only one use, it can still be referred to as "one or more features" or "one or more elements" or "at least one feature" or "at least one element" in any way. In addition, the use of the term "one or more" or "at least one" feature or element does not exclude the absence of the feature or element, unless otherwise indicated by restrictive language such as "requires one or more..." or "requires one or more elements".

[0038] Unless otherwise defined, all terms used herein, especially any technical and / or scientific terms, may be considered to have the same meaning as commonly understood by one of ordinary skill in the art.

[0039] Embodiments of the present invention will be described in detail below with reference to the accompanying drawings.

[0040] Multi-Universal Subscriber Identity Module (USIM) User Equipment (UE) refers to a device that can support multiple USIMs simultaneously. In particular, a MUSIM UE can host more than one USIM to establish connections with two or more different networks. Such a device allows users to have different connection plans, different profiles, increased connectivity / reliability with support for multiple network connections.

[0041] However, in order to save costs, the operation of the MUSIM UE involves multiple USIMs sharing the same radio frequency (RF) circuitry in order to perform various activities and services on different networks. This means that multiple USIMs need to arbitrate and share common RF resources between them to perform various network activities and / or utilize network services. Examples of such network services include paging reception, system information block (SIB) acquisition, measurement, data or voice calls, Multimedia Broadcast Multicast Service (MBMS), emergency calls, access stratum (AS) signaling, non-access stratum (NAS) signaling, etc.

[0042] Prior to Release 17 in 3GPP, MUSIM UEs used arbitrary gaps to perform MUSIM operations without any control by the network. From Release 17 onwards, a USIM connected to a network node is configured to notify the connected network node about network switching required for MUSIM operation and gaps required for MUSIM operation. In addition, in Release 17, a MUSIM UE uses the RRCUE Assistance Information (UAI) procedure to request MUSIM gaps from a network node (gNB) or to notify the network node about network switching. In Release 17, only per-UE gaps are supported for MUSIM operation.

[0043] In Release 17, MUSIM UE uses the RRC UE Assistance Information (UAI) procedure to request a gap from the gNB or to notify the gNB about a leave. The network (gNB) uses otherConfig in the RRC message to configure the UE whether it can provide assistance information for MUSIM gap or MUSIM leave. Musim-GapAssistanceConfig in otherConfig is used to inform the UE whether it can provide MUSIM assistance information for providing gap information. In Release 17, only per-UE gaps are supported for MUSIM operation.

[0044] Below is an excerpt from the NR RRC specification on how to use otherConfig including musim-GapAssistanceConfig.

[0045]

[0046] Below is an excerpt from the NR RRC specification regarding the definition of otherConfig including musim-GapAssistanceConfig.

[0047]

[0048] The musim-GapAssistanceConfig transmitted by the gNB to the UE in this NR specification (initial version of the TS 38.331 specification) only contains the musim-GapProhibitTimer, which is the prohibition timer for MUSIM assistance information reporting without leaving RRC_CONNECTED for MUSIM purposes.

[0049] Once MUSIM is configured the UE (connected USIM) requests gaps for MUSIM purposes by sending UE assistance information as extracted below from 3gpp TS 38.331 specification.

[0050]

[0051]

[0052] The UE uses MUSIM assistance information for both periodic and aperiodic gaps. For periodic gaps, the assistance information includes the gap repetition period and the gap offset. For aperiodic gaps that are one-time gaps, the UE provides the starting SFN and subframe required for the gap.

[0053] The following excerpt includes the definition and description of the MUSIM gap information requested by a connected UE from the connected network in the UE assistance information.

[0054]

[0055]

[0056] Once the network receives the UE assistance information indicating the gap preference for MUSIM operation, it may configure the MUSIM gap for the UE.

[0057] An excerpt from the RRC specification is given below which indicates the UE behavior while receiving an RRC reconfiguration with gap configuration.

[0058]

[0059] An excerpt from the RRC specification including the definition of GapConfiguration is given below.

[0060]

[0061]

[0062] A further 3gpp specification excerpt including definitions of the various fields described above is given below.

[0063]

[0064] The MUSIM gap configuration for the UE includes musim-Start-SFN-AndSubframe for aperiodic gaps and musim-GapRepetitionAndOffset for periodic gaps. However, such a process cannot effectively and efficiently implement MUSIM operation in complex network scenarios such as carrier aggregation or dual connectivity. In order to overcome the above-mentioned problems in mobile communication networks, it is necessary to provide a technology that can perform MUSIM operation in an effective and efficient manner.

[0065] Figure 1 An exemplary environment 100 of a multi-universal subscriber identity module (MUSIM) user equipment (UE) 102 is shown according to an embodiment of the present disclosure. The MUSIM UE 102 may be configured to connect to one or more networks using two or more USIMs. In the illustrated embodiment, the MUSIM UE 102 (interchangeably referred to as "UE 102") includes two USIMs, namely USIM-A 104a and USIM-B 104b, to connect to one or more networks. However, embodiments are intended to include or otherwise encompass any number of USIMs configured at the UE 102. Examples of UE 102 may include, but are not limited to, a mobile phone, a laptop computer, a desktop computer, a personal computer (PC), a notebook computer, a tablet computer, or any other suitable communication device configured to support MUSIM operations.

[0066] UE 102 may include any suitable combination of hardware and software components that may be required to support MUSIM operation. For the sake of brevity, the description of such components is omitted. In an exemplary embodiment, USIM-A 104a may be connected to a network-A including multiple cells. Network-A may include a main node (MN) configured with a base station (gNB1-MN) and a secondary node (SN) configured with a base station (gNB1-SN). The MN of network-A may include a main cell group (MCG) and the SN of network-A may include a secondary cell group (SCG) configured to support network operation of the USIM installed at UE 102. In addition, the network nodes or cell groups shown are exemplary in nature, and the network may include any number of network nodes or cell groups. In addition, multiple network nodes or cell groups may enable the network to support complex network scenarios, such as carrier aggregation (CA) or dual connectivity. In an embodiment, USIM-B 104b may reside in network B configured with a base station (gNB2). However, USIM-B 104 b may remain in an idle state during network operations of USIM-A 104 a because each of USIM-B 104 b and USIM-A may utilize a single set of network components available at UE 102 .

[0067] In particular, the UE 102 may include a single set of network components such as, but not limited to, antennas, transceivers, modulator-demodulators, amplifiers, etc. The single set of network components provides a cheaper, simpler, and compact network structure at the UE 102. Therefore, in order to perform network operations of USIM-B, USIM-A may require a network gap (interchangeably referred to as a "MUSIM gap") to avoid conflicts in signal and resource usage. Therefore, the present disclosure provides an effective and efficient solution for implementing a MUSIM gap in different network scenarios such as, but not limited to, carrier aggregation and multi-radio dual connectivity scenarios.

[0068] In carrier aggregation (CA), two or more component carriers (CCs) of a network may be aggregated. Specifically, in CA, a UE 102 may receive or transmit simultaneously on one or more CCs depending on the capabilities of the UE. Both contiguous CCs and non-contiguous CCs may support CA. When CA is deployed, the frame timing and system frame number (SFN) required to define the MUSIM gap may be aligned on the cells that may be aggregated (synchronous CA), or the offset of multiple time slots between the primary cell and the secondary cell may be configured for aggregation (asynchronous CA). In an embodiment, a UE 102 in an inactive mode may store CA configuration information. In CA, the primary cell may be the cell used for initial access, and other cells may be referred to as secondary cells.

[0069] 3gpp specifies dual connectivity or technically more multi-radio dual connectivity in specifications such as TS 37.340. An overview of the details of dual connectivity is given below.

[0070] The New Generation-Radio Access Network (NG-RAN) supports Multi-Radio Dual Connectivity (MR-DC) operation, whereby a user equipment (UE) in a Radio Resource Control-Connected (RRC_CONNECTED) state can be configured to utilize radio resources provided by two different schedulers located in two different NG-RAN nodes connected via a non-ideal backhaul, one scheduler providing NR (New Radio) access and the other scheduler providing E-UTRA (Evolved UMTS Terrestrial Radio Access) or NR access. One node can act as a master / primary node (MN) and the other node can act as a slave node (SN). The MN and the SN are connected via a network interface, and at least the MN is connected to the core network. NG-RAN supports NG-RAN E-UTRA-NR dual connectivity (NGEN-DC), where the UE 102 can be connected to one ng-eNB (E-UTRA base station capable of connecting to a 5G core) acting as a MN and one gNB (5G base station) acting as a SN. NG-RAN also supports NR-E-UTRA dual connectivity (NE-DC). The primary cell of a primary or secondary cell group is called a SpCell. The SpCell of a primary cell group can be called a PCell, and the SpCell of a secondary cell group can be called a PSCell. In MR-DC, a group of service cells associated with a primary node, including an SpCell (PCell) and optionally one or more SCells, is called an MCG or a primary cell group. A group of service cells associated with a secondary node, including an SpCell (PSCell) and optionally one or more SCells, is called a secondary cell group (SCG) in MR-DC. In addition, the frame timing and SFN between the cells in the MCG and SCG may not be aligned.

[0071] The connected USIM (USIM-A) in a MUSIM UE can request gaps from the network it is connected to (NWK-A) for operations such as paging monitoring, serving and neighbor measurements, cell reselection operations, including reading system information of the target cell for idle / inactive UEs (USIM-B). USIM-A can be configured with dual connectivity or carrier aggregation, while USIM-B can store CA or DC configuration. USIM-A needs to provide the required timing to NWK-A while requesting MUSIM gaps, i.e., SFN and subframe for non-periodic gaps and offset for periodic gaps. We propose how USIM-A derives the timing for requesting MUSIM gaps for operations of USIM-B in a MUSIM UE.

[0072] Figure 2 An exemplary process flow depicting a method 200 for implementing MUSIM gaps during carrier aggregation (CA) according to an embodiment of the present disclosure is shown. The method 300 may be performed by a UE 102, a component of network A, and / or a component of network B, such as Figure 1 as shown in .

[0073] At step 202 , the method 200 may include establishing, by a first universal SIM (USIM-A) 104a of a MUSIM user equipment (UE) 102 , a connection with two or more component carriers (CCs) provided by one or more cells of a first network (Network-A).

[0074] Next, at step 204, the method 200 may include determining, by the MUSIM UE 102, a requirement for a MUSIM gap in the first network (network-A) to perform one or more network operations in the second USIM (USIM-B) 104b. In an embodiment, the UE 102 may determine the requirement for the MUSIM gap upon receiving an indication from the USIM-B 104b to perform one or more network operations. Such an indication may also indicate a requirement for one or more network resources of the UE 102, wherein the one or more network resources may be used by the USIM-A 104a for the network operation of the USIM-B 104b. Upon receiving the above indication, the UE 102 may determine the requirement for the MUSIM gap in order to perform the network operation of both USIMs (i.e., USIM-A 104a and USIM-B 104b). In another embodiment, the UE 102 may determine the requirement for the MUSIM gap based at least on determining that the USIM-A 104a has performed a network operation for a predefined period of time or that the USIM-A has not performed any network operation for a predefined period of time.

[0075] At step 206, the method 200 may include calculating, by the MUSIM UE 102, the timing of the MUSIM gap relative to the timing configuration of the primary cell of the first network (network A). The timing configuration of the primary cell of the first network may include information such as, but not limited to, a system frame number, a subframe number, etc. Specifically, the network may define the timing for the MUSIM gap in terms of SFN and subframe number. In addition, each of the primary cell and the secondary cell of the network may have a different timing configuration. Therefore, the timing configuration corresponding to the primary cell may include the current SFN and subframe number of the primary cell. In an embodiment, the UE 102 may determine the requirement for the MUSIM gap timing based on the indication received from the USIM-B 104b, and calculate and / or modify the MUSIM gap timing based on the timing information of the primary cell of Network-A.

[0076] At step 208, the method 200 may include generating, by the MUSIM UE 102, a MUSIM gap request for a MUSIM gap based on the calculated timing for the MUSIM gap. Since the timing requirement for the MUSIM gap is based on the timing configuration of the primary cell of network A, the primary cell may be able to handle the MUSIM gap in an effective and efficient manner. In an embodiment, the MUSIM gap corresponds to a periodic MUSIM gap or an aperiodic MUSIM gap. In addition, in the case of a periodic MUSIM gap, the generated MUSIM gap request may include information based on the calculated timing of the MUSIM gap, such as, but not limited to, a gap offset, a gap repetition, and a gap length. In the case of an aperiodic MUSIM gap, the generated MUSIM gap request may include information based on the calculated timing of the MUSIM gap, such as, but not limited to, a starting system frame number (SFN), a subframe, and a gap length.

[0077] At step 210, method 200 may include sending the generated MUSIM gap request to the first network (network A). In addition, method 200 may include receiving a MUSIM gap configuration based on the sent MUSIM gap request from the first network (network A) to configure the required MUSIM gap.

[0078] The embodiments are exemplary in nature, and according to various embodiments, such as Figure 2 The steps of the method 200 shown may occur in a variation of the sequence. The variation may include Figure 2 Additions and / or omissions of the steps shown in .

[0079] Figure 3An exemplary process flow depicting a method 300 for implementing MUSIM gap in a dual connectivity scenario at UE 102 according to an embodiment of the present disclosure is shown. The method 300 may be implemented using UE 102, components of network A, and / or components of network B, such as Figure 1 as shown in .

[0080] At step 302, the method 300 may include establishing, by a first universal SIM (USIM-A) 104a of the MUSIM UE 102, a dual connection with at least one of a primary network node and a secondary network node of network A. Next, at step 304, the method 300 may include receiving timing configuration information for calculating timing for MUSIM gaps from the primary network node. In an embodiment, the primary network node may determine that the connected UE 102 is a MUSIM UE that may require MUSIM operation, so if necessary, the primary network node may send the timing configuration to calculate the timing for the MUSIM gap. In an embodiment, the primary network node may determine that the UE 104 is a MUSIM UE based on receiving an indication from the UE 102 or based on receiving multiple connection and / or network service requests from the UE 102.

[0081] At step 306, the method 300 may include determining, by the UE 102, a requirement for a MUSIM gap in the connection of the first USIM (USIM-A) 104a for performing one or more operations in the second USIM (USIM-B) 104b. In an embodiment, the UE 102 may determine the requirement for the MUSIM gap when receiving an indication from the USIM-B 104b that one or more network operations are to be performed. Such an indication may also indicate a requirement for one or more network resources of the UE 102, wherein the one or more network resources may be used by the USIM-A 104a for the network operation of the USIM-B 104b. Upon receiving the above indication, the UE 102 may determine that there is a requirement for a MUSIM gap in order to perform network operations of both USIMs (i.e., USIM-A 104a and USIM-B 104b). In another embodiment, the UE 102 may determine the requirement for the MUSIM gap based at least on determining that the USIM-A 104a has performed a network operation for a predefined period of time or that the USIM-A has not performed any network operation for a predefined period of time.

[0082] At step 308, the method 300 may include calculating the timing for the required MUSIM gap based on at least one of the timing configuration information received from the master network node and the timing configuration information based on a predefined selection process in the UE. In an embodiment, the UE 102 may calculate the timing for the required MUSIM gap based on the timing configuration information from the master network node. In an embodiment, the timing configuration from the master network node may include information such as, but not limited to, an indication of a reference cell to be used for the timing configuration, an SFN, and a subframe number. In addition, the reference cell may be a master cell of a master cell group (MCG), a master cell of a slave cell group (SCG), or one of a frequency range 2 (FR2) cell in the MCG. In an embodiment, the predefined selection process that may be used by the UE 102 to receive the timing configuration for calculating the MUSIM gap may include selecting the master cell of the MCG as the reference cell when the MUSIM gap is applicable to at least one of the MCG, the SCG, the per-UE MUSIM gap, and the per-FR MUSIM gap for the FR of at least one serving cell in the MC. The predefined selection process may also include selecting a primary cell of the SCG when a MUSIMG gap is applicable to the SCG, at least one of a per-FR MUSIM gap for a FR configured in the SCG.

[0083] At step 310, the method 300 may include generating a MUSIM gap request for the required MUSIM gap based on the calculated timing for the MUSIM gap. In an exemplary embodiment, the UE 102 may generate the MUSIM gap request based on the calculated timing. In an embodiment, the MUSIM gap may correspond to a periodic MUSIM gap or an aperiodic MUSIM gap. In addition, in the case of a periodic MUSIM gap, the MUSIM gap request may include information such as, but not limited to, a gap offset calculated based on a reference cell and an indication of the reference cell. In the case of an aperiodic MUSIM gap, the MUSIM gap request may include information such as, but not limited to, a starting SFN and subframe calculated based on the reference cell, and an indication of the reference cell.

[0084] At step 312, method 300 may include sending the generated MUSIM gap request to the master network node. UE 102 may send the generated MUSIM gap request to the master network node and network A. Method 300 may also include receiving a MUSIM gap configuration based on the sent MUSIM gap request from the master network node to configure the MUSIM gap.

[0085] The embodiments are exemplary in nature, and according to various embodiments, such as Figure 3 The steps of the method 300 shown may occur in a variation of the sequence. The variation may include Figure 3Additions and / or omissions of the steps shown in .

[0086] Figure 4 An exemplary process flow depicting a method 400 for implementing MUSIM gap in a dual connectivity scenario at a base station (gNB1) according to an embodiment of the present disclosure is shown. The method 400 may be implemented using UE 102, components of network A, and / or components of network B, such as Figure 1 as shown in .

[0087] At step 402, the method 400 may include establishing a dual connection with at least one of a primary network node and a secondary network node of a base station using a first universal SIM (USIM-A) 104a of a MUSIM user equipment (UE) 102. Next, at step 404, the method 400 may include receiving an indication that the MUSIM UE 102 supports configuration of a MUSIM gap for at least one of a second USIM (USIM-B) 104b. Finally, at step 406, the method 400 may include sending timing configuration information for calculating the timing of the MUSIM gap to the MUSIM UE 102 based on the received indication. In an exemplary embodiment, the timing configuration may include information such as, but not limited to, an indication of a reference cell to be used for the timing configuration, a system frame number (SFN), and a subframe number.

[0088] The embodiments are exemplary in nature, and according to various embodiments, such as Figure 4 The steps of the method 400 shown may occur in a variation of the sequence. The variation may include Figure 4 Additions and / or omissions of the steps shown in .

[0089] Figure 5 An operational flow diagram depicting a process 500 for determining a timing for requesting a MUSIM gap for a MUSIM UE 102 in a carrier aggregation scenario according to an embodiment of the present subject matter is shown. The process 500 may be implemented using the UE 102, components of network A, and / or components of network B, such as Figure 1 shown.

[0090] In an embodiment, the MUSIM UE 102 may include two USIMs, namely, USIM-A 104 a in an RRC-CONNECTED state with network A and USIM-B 104 b in an RRC idle (RRC_IDLE) or RRC non-idle (RRC_INACTIVE) state with network B, as shown in step 502.

[0091] In addition, step 502 indicates that USIM-A 104a may be configured with a carrier aggregation request, which may include a starting SFN and subframe of an aperiodic MUSIM gap and a gap offset of a periodic MUSIM gap referenced to the SFN and subframe of a primary cell (PCell) of network A. The starting SFN and subframe in the request may be referred to as "musim-Start-SFN-AndSubframe". In addition, the gap offset in the request may be referred to as "musim-GapRepetitionAndOffset".

[0092] In addition, the above reference Figure 2 The illustrated embodiment can be as follows. For example,

[0093] The current SFN and subframe number of the primary cell (PCell) in USIM-A (PCell-A) can be 100 and 5,

[0094] The current SFN and subframe number of the secondary cell (SCell) in USIM-A (SCell-A) can be 98 and 3,

[0095] The current SFN and subframe number of the camped cell in USIM-B (PCell-B) may be 75 and 4, and

[0096] The current SFN and subframe number of the SCell stored in USIM-B (SCell-B) may be 78 and 3.

[0097] In addition, USIM-B requires a non-periodic gap of 3 subframes from the current time. Therefore, USIM-A can generate a MUSIM gap request with a "MUSIM-Start-SFN-AndSubframe" format of 100.8 to network A, that is, according to the timing configuration of the primary cell of network A.

[0098] Specifically, for the above embodiment, the following changes may be made to TS38.331:

[0099]

[0100]

[0101] In addition, at step 504, process 500 may include receiving, by USIM-A 104a, "MUSIMGapAssistanceConfig" information from Network-A. MusimGapAssistanceConfig may correspond to MUSIM timing configuration information that may be required to calculate MUSIM gaps, as discussed in methods 200-400. At step 506, RRC reconfiguration may be completed. At step 508, USIM-B 104b may determine that USIM-B 104b requires MUSIM gaps, for example, periodic gaps (each repetition period RP-b has an offset: xb and a gap length: gl-b) at USIM-B 104b for network operations (such as but not limited to paging monitoring, measurements, etc.) and non-periodic gap network operations (such as but not limited to cell reselection, etc.) at USIM-B 104b, which have a starting subframe SFN: x1-b, subframe: y1-b, and gap length: gl1-b. Next, at step 510, USIM-A 104a may convert the timing information of USIM-B 104b based on the timing configuration of PCell. Therefore, step 510 may correspond to step 206, such as Figure 2 As shown. Specifically, at step 510, process 500 may include converting offset: xb, SFN: x1-b, subframe: y1-b to offset: x-PcellA, SFN: x1-Pcell-A, subframe: y1-Pcell-A based on Pcell-A SFN and subframe timing. At step 512, USIM-A 104a may request a MUSIM gap in a MUSIMgapconfig request, wherein the MUSIMgapconfig request may include offset: x-PcellA, SFN: x1-Pcell-A, subframe: y1-Pcell-A as the required offset within the preferred gap configuration and startingSFNandsubframe, as calculated in the previous step. Step 512 may also correspond to steps 208-210 of method 200. At step 514, network A may send an RRC reconfiguration with a MUSIM gap configured based on the sent request. At step 516, the RRC reconfiguration is complete.

[0102] Figure 6 An operational flow chart depicting a process 600 for deriving a system frame number (SFN) / subframe for a UE to request a MUSIM gap when dual connectivity is configured according to an embodiment of the present subject matter is shown. Process 600 may be implemented using UE 102, components of network A, and / or components of network B, such as Figure 1 shown.

[0103] In an embodiment, when USIM-A is configured with dual connectivity, network A and / or associated network component(s) may inform USIM-A 104a about the cells that need to be used to determine the timing of the SFN and subframe (e.g., musim-Start-SFN-AndSubframe) for requesting aperiodic MUSIM gaps and the gap offset (e.g., offset within musim-GapRepetitionAndOffset) for periodic MUSIM gaps. In some embodiments, network A and / or associated network component(s) may request USIM-A 104b to use one of the PCell, PSCell, or FR2 cells in the MCG configured in USIM-A. In an exemplary embodiment, USIM-A 104a may request MUSIM-Start-SFN-AndSubframe for aperiodic MUSIM gaps and the gap offset for periodic MUSIM gaps according to the timing configuration of the cells configured by network A.

[0104] In addition, the above reference Figure 3-Figure 4 The illustrated embodiment can be as follows. For example,

[0105] The current SFN and subframe number of the primary cell (PCell) in USIM-A (PCell-A) can be 100 and 5,

[0106] The current SFN and subframe number of the PSCell in USIM-A (PSCell-A) can be 100 and 7,

[0107] The current SFN and subframe number of the secondary cell (SCell) in MCG USIM-A (SCellMCG-A) can be 98 and 3,

[0108] The current SFN and subframe number of the secondary cell (SCell) in SCG USIM-A (SCellSCG-A) can be 108 and 1,

[0109] The current SFN and subframe number of the camped cell in USIM-B (PCell-B) may be 75 and 4, and

[0110] The current SFN and subframe number of the SCell stored in USIM-B (SCell-B) may be 78 and 3.

[0111] In addition, network A may configure USIM-A 104a to request a MUSIM gap with reference to the PScell. Assume that USIM-B 104b may require an aperiodic gap with 3 subframes from the current time. Therefore, USIM-A 104a may generate a MUSIM gap request with musim-Start-SFN-AndSubframe in the format of 107,8 to network A.

[0112] In an embodiment, if USIM-A is configured to make requests for per-FR MUSIM gaps for FR2 gaps, network A and / or associated network components may configure UE 102 to use a specific FR2 cell as a reference for requesting the SFN and subframe for aperiodic MUSIM gaps or offsets for periodic MUSIM gaps. NWK-A may provide a cell identifier of a FR2 cell to use as a reference for MUSIM operation.

[0113] In an alternative embodiment, if Network A and / or associated network components do not configure the cell to request a SFN and subframe for aperiodic MUSIM gaps and an offset for periodic MUSIM gaps, USIM-A 104a may use the PCell for MUSIM gap requests.

[0114] Specifically, for the above embodiment, the following changes may be made to TS38.331:

[0115]

[0116] Although steps 602-616 are similar to steps 502-516, Figure 5 As explained, at step 604, network A may also send an indication of a reference cell, which will be used to calculate the timing requirements for the MUSIM gap. Furthermore, at step 610, USIM-A 104a may convert the MUSIM gap request made by USIM-B 104a based on the timing configuration of the cell indicated by the indication received at step 604. For the sake of brevity, the description of other steps has been omitted.

[0117] Figure 7 1 is an operational flow diagram depicting a process 700 for deriving a system frame number (SFN) / subframe for a UE to request a MUSIM gap when dual connectivity is configured according to another embodiment of the present subject matter. Process 700 may be implemented using UE 102, components of network A, and / or components of network B, such as Figure 1 shown.

[0118] In an embodiment, when the USIM-A 104a is configured with dual connectivity, the USIM-A 104a may select a reference cell based on a predefined selection process for determining the timing of the SFN and subframe (e.g., musim-Start-SFN-AndSubframe) for requesting an aperiodic MUSIM gap and the gap offset (e.g., the offset within musim-GapRepetitionAndOffset) for the periodic MUSIM gap. The USIM-A 104a may transmit the selected reference cell to the network along with the starting SFN and subframe of the aperiodic MUSIM gap and the offset of the periodic MUSIM gap in the MUSIM gap request, wherein the reference cell may be used to determine the timing for requesting the MUSIM gap. In particular, the USIM-A 104a may indicate that one of the PCell, PSCell, or FR2 cells in the MCG of the USIM-A corresponds to the reference cell for calculating the timing for the MUSIM gap.

[0119] In an embodiment, if the USIM-A 104a is configured to request per FR MUSIM gaps for FR2 gaps, the USIM-A 104a may decide to use a specific FR2 cell as a reference cell based on a predefined selection process for determining the timing of the starting SFN and subframe for requesting aperiodic MUSIM gaps or offsets of periodic MUSIM gaps. The USIM-A may provide a cell identifier of a FR2 cell to use as a reference for MUSIM operation. In this case, the USIM-A 104a may also indicate that the reference cell used is a FR2 cell in the MCG of the USIM-A 104a.

[0120] In an embodiment, if USIM-A 104a uses PCell to determine the timing for requesting the starting SFN and subframe of the aperiodic MUSIM gap and the offset of the periodic MUSIM gap, it may not inform Network A of the used cell.

[0121] In addition, the above reference Figure 3-Figure 4 The illustrated embodiment can be as follows. For example,

[0122] Current SFN / subframe of PCell in USIM-A (PCell-A): 100,5

[0123] Current SFN / subframe of PSCell in USIM-A (PSCell-A): 107,5

[0124] Current SFN / subframe of SCell in MCG USIM-A (SCellMCG-A): 98,3

[0125] Current SFN / subframe of SCell in SCG USIM-A (SCellSCG-A): 108,1

[0126] Current SFN / subframe of campedCell in USIM-B (PCell-B): 75,4

[0127] Current SFN / subframe of SCell stored in USIM-B (SCell-B): 78,3

[0128] USIM-A 104a may select PCell based on a predefined selection process to request a MUSIM gap. In this case, USIM-B 104b may request an aperiodic gap with 3 subframes from the current time. USIM-A 104a may request musim-Start-SFN-AndSubframe in the requested gap information to be 100,8 from network A and transmit the selection of PCell to the network.

[0129] Specifically, the example changes in TS38.331 may be changed as follows for the above embodiment:

[0130]

[0131]

[0132] In another embodiment, when USIM-A 104a is configured with dual connectivity, USIM-A 104a may request the starting SFN and subframe of the aperiodic MUSIM gap and the offset of the periodic MUSIM gap according to the SFN and subframe of the PCell in USIM-A 104a.

[0133] In another embodiment, the USIM-A 104a may request and / or the network A may configure the USIM-A 104a with a MUSIM gap applicable to one of the MCG or SCG. If the USIM-A 104a is configured with a MUSIM gap applicable to only one cell group, uplink or downlink data transmission may be achieved on the other cell group during the gap duration.

[0134] In an embodiment, the USIM-A 104a may request and / or the network A may configure the USIM-A 104a with a MUSIM gap as a per-FR gap. If the USIM-A 104a is configured with a per-FR MUSIM gap, data transfer may be limited to serving cells belonging to the same FR as the FR configured in the MUSIM gap during the MUSIM gap duration.

[0135] Although Figure 7 Steps 702-716 shown are similar to those according to Figure 6 602 - 616 as explained above, but at step 710 , instead of converting the MUSIM timing requirements based on the reference cell indicated by network A, the UE may convert the MUSIM timing requirements based on a cell selected using a predefined selection process, as also shown in step 308 of method 300 .

[0136] In an embodiment, the network A and / or the network B mentioned in the above description may correspond to any suitable network device that may be configured to implement the network A and / or the network B.

[0137] Figure 8 is a diagram illustrating a configuration of a user equipment (UE) 800 in a wireless communication system according to an embodiment of the present disclosure. Figure 8 The configuration of the UE 800 may be understood as a part of the configuration of the UE 800. In addition, according to another embodiment, the methods 200 and 300 disclosed above may be implemented in the UE 800. In an embodiment, the UE 800 corresponds to the UE 102. Hereinafter, it should be understood that the terms including "unit" or "module" at the end may indicate a unit for processing at least one function or operation and may be implemented in hardware, software, or a combination of hardware and software.

[0138] refer to Figure 8 , UE 800 may include at least one processor 802, a communication unit 804 (e.g., a communicator or communication interface), and a storage unit 806 (e.g., a storage device). As an example, UE 800 may be a user device such as a cellular phone or other device that communicates through multiple cellular networks (such as 3G, 4G, 5G or quasi-5G, 6G networks, or any future wireless communication networks). The communication unit 804 may perform functions for sending and receiving signals via a wireless channel.

[0139] As an example, the processor 802 can be a single processing unit or multiple units, all of which can include multiple computing units. The processor 802 can be implemented as one or more microprocessors, microcomputers, microcontrollers, digital signal processors, central processing units, state machines, logic circuits, and / or any device that manipulates signals based on operating instructions. In addition to other capabilities, the processor 802 is configured to obtain and execute computer-readable instructions and data stored in a memory. The processor 802 may include one or more processors. At this point, one or more processors 802 may be a general-purpose processor (such as a central processing unit (CPU), an application processor (AP), etc.), a graphics processing unit (such as a graphics processing unit (GPU), a visual processing unit (VPU)), and / or an AI-specific processor (such as a neural processing unit (NPU)). One or more processors 802 can control the processing of input data according to predefined operating rules or artificial intelligence (AI) models stored in non-volatile memory and volatile memory (i.e., memory unit 806). Predefined operating rules or artificial intelligence models are provided by training or learning.

[0140] The memory 806 may include any non-transitory computer-readable medium known in the art, including, for example, volatile memory (such as static random access memory (SRAM) and dynamic random access memory (DRAM)) and / or non-volatile memory (such as read-only memory (ROM), erasable programmable ROM, flash memory, hard disk, optical disk, and magnetic tape).

[0141] Fig. 9 is a diagram showing a configuration of a base station 900 in a wireless communication system according to an embodiment of the present disclosure. Fig. 9 The configuration may be understood as a part of the configuration of network-A and network-B and / or associated components (particularly base stations). In addition, according to another embodiment, the method 400 disclosed above may be implemented in a base station 900. In an embodiment, the base station 900 corresponds to any one of gNB-MN, gNB-SN, etc. Hereinafter, it should be understood that the terminology including "unit" or "module" at the end may indicate a unit for processing at least one function or operation and may be implemented in hardware, software, or a combination of hardware and software.

[0142] Components 902-906 are similar to components 802-806, so the description of components 902-906 is omitted for the sake of brevity.

[0143] In view of the above embodiments, it is apparent that the present disclosure enables implementation of MUSIM gaps in an effective and efficient manner and provides efficient utilization of network resources at the UE.

[0144] Some example embodiments disclosed herein may be implemented using processing circuitry.For example, some example embodiments disclosed herein may be implemented using at least one software program running on at least one hardware device and performing network management functions to control elements.

[0145] Although specific language has been used to describe the present disclosure, no limitations are intended thereby. It will be apparent to those skilled in the art that various working modifications may be made to the methods described in order to implement the inventive concepts taught herein.

[0146] The accompanying drawings and the foregoing description give examples of embodiments. Those skilled in the art will recognize that one or more of the elements described may be well combined into a single functional element. Alternatively, certain elements may be divided into multiple functional elements. Elements from one embodiment may be added to another embodiment. For example, the order of the processes described herein may be changed and are not limited to the manner described herein.

[0147] Furthermore, the actions of any flow chart need not be implemented in the order shown; nor do all actions necessarily need to be performed. Moreover, those actions that are not dependent on other actions may be performed in parallel with other actions. The scope of the embodiments is by no means limited by these specific examples. Many variations are possible, such as differences in structure, size, and use of materials, whether or not explicitly given in the specification. The scope of the embodiments is at least as wide as that given by the appended claims.

[0148] Benefits, other advantages, and solutions to problems have been described above with respect to specific embodiments. However, the benefits, advantages, solutions to problems, and any component (or components) that may cause any benefit, advantage, or solution to occur or become more apparent should not be construed as a critical, required, or essential feature or component of any or all of the claims.

Claims

1. A method performed by a terminal in a wireless communication system, the method include: receiving a first message from a base station, wherein the first message includes information for determining a subframe and a system frame number (SFN) associated with a multiple user identity module (MUSIM) gap; Determining a subframe and SFN of a primary cell (PCell) based on the information for determining a subframe and SFN associated with the MUSIM gap; A second message including information about the MUSIM gap preferred by the terminal is transmitted to the base station, wherein the information about the MUSIM gap preferred by the terminal includes information associated with the determined SFN and the determined subframe.

2. The method according to claim 1, in, In the case where the MUSIM gap is periodic, information for determining a subframe and SFN associated with the MUSIM gap includes information on a gap repetition period and information on a gap offset.

3. The method according to claim 1, in, In the case where the MUSIM gap is aperiodic, the information used to determine the subframe and SFN associated with the MUSIM gap includes information about the gap start position.

4. The method according to claim 1, in, In the case where the MUSIM gap is periodic, the information about the MUSIM gap preferred by the terminal includes at least one value of information about a gap offset preferred by the terminal, information about a gap repetition period, and a length of the MUSIM gap; and Wherein, in the case where the MUSIM gap is non-periodic, the information about the MUSIM gap preferred by the terminal includes at least one value of the length of the MUSIM gap preferred by the terminal.

5. A method performed by a base station in a wireless communication system, the method include: Sending a first message to a terminal, wherein the first message includes information for determining a subframe and a system frame number (SFN) associated with a multi-user identity module (MUSIM) gap; receiving, from the terminal, a second message including information about a MUSIM gap preferred by the terminal; The information about the MUSIM gap preferred by the terminal includes information associated with a subframe and SFN of a primary cell (PCell); and The SFN and the subframe are determined based on information used to determine the subframe and SFN associated with the MUSIM gap.

6. The method according to claim 5, in, In the case where the MUSIM gap is periodic, information for determining a subframe and SFN associated with the MUSIM gap includes information on a gap repetition period and information on a gap offset.

7. The method according to claim 5, in, In the case where the MUSIM gap is aperiodic, the information used to determine the subframe and SFN associated with the MUSIM gap includes information about the gap start position.

8. The method according to claim 5, in, In the case where the MUSIM gap is periodic, the information about the MUSIM gap preferred by the terminal includes at least one value of information about a gap offset preferred by the terminal, information about a gap repetition period, and a length of the MUSIM gap; and Wherein, in the case where the MUSIM gap is non-periodic, the information about the MUSIM gap preferred by the terminal includes at least one value of the length of the MUSIM gap preferred by the terminal.

9. A terminal in a wireless communication system, the terminal include: Transceiver; and At least one processor coupled to the transceiver and configured to: receiving a first message from a base station, wherein the first message includes information for determining a subframe and a system frame number (SFN) associated with a multi-user identity module (MUSIM) gap, determining a subframe and SFN of a primary cell (PCell) based on information for determining a subframe and SFN associated with a MUSIM gap, A second message including information about the MUSIM gap preferred by the terminal is transmitted to the base station, wherein the information about the MUSIM gap preferred by the terminal includes information associated with the determined SFN and the determined subframe.

10. The terminal according to claim 9, in, In the case where the MUSIM gap is periodic, information for determining a subframe and SFN associated with the MUSIM gap includes information on a gap repetition period and information on a gap offset.

11. The method according to claim 9, in, In the case where the MUSIM gap is aperiodic, the information used to determine the subframe and SFN associated with the MUSIM gap includes information about the gap start position.

12. The method according to claim 9, in, In the case where the MUSIM gap is periodic, the information about the MUSIM gap preferred by the terminal includes at least one value of information about a gap offset preferred by the terminal, information about a gap repetition period, and a length of the MUSIM gap, and Wherein, in the case where the MUSIM gap is non-periodic, the information about the MUSIM gap preferred by the terminal includes at least one value of the length of the MUSIM gap preferred by the terminal.

13. A base station in a wireless communication system, the base station include: Transceiver; and At least one controller coupled to the transceiver and configured to: sending a first message to a terminal, wherein the first message includes information for determining a subframe and a system frame number (SFN) associated with a multi-user identity module (MUSIM) gap, receiving, from the terminal, a second message including information about a MUSIM gap preferred by the terminal, The information about the MUSIM gap preferred by the terminal includes information associated with a subframe and SFN of a primary cell (PCell), and The SFN and the subframe are determined based on information used to determine the subframe and SFN associated with the MUSIM gap.

14. The method according to claim 13, in, In the case where the MUSIM gap is periodic, the information for determining the subframe and SFN associated with the MUSIM gap includes information about the gap repetition period and information about the gap offset, Wherein, in the case that the MUSIM gap is non-periodic, the information used to determine the SFN and subframe related to the MUSIM gap includes information about the starting position of the gap.

15. The method according to claim 13, in, In the case where the MUSIM gap is periodic, the information about the MUSIM gap preferred by the terminal includes at least one value of information about a gap offset preferred by the terminal, information about a gap repetition period, and a length of the MUSIM gap, and In the case where the MUSIM gap is non-periodic, the information about the MUSIM gap preferred by the terminal includes at least one value of the length of the MUSIM gap preferred by the terminal.