Large-span daylighting roof construction method
By using gantry crane steel frame assembly and hanging basket installation technology on the roof, the problem of irregular lighting roof construction is solved, and efficient construction does not occupy vertical transportation tools and indoor space is achieved. It is suitable for the construction and maintenance of various lighting roofs.
Patent Information
- Application Number
- CN202411475933.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-22
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2044-10-22
Smart Images

Figure CN119021483A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of large-span skylight roof construction, and in particular to a large-span skylight roof construction method. Background Art
[0002] The existing large-span skylight installation method uses a high-altitude bulk method, that is, a scaffold is set up indoors, and the construction workers stand on the scaffold to lift the components of the skylight steel frame, and then assemble the skylight steel frame. This method is simple, but it requires a temporary (scaffold) to be set up indoors, which seriously affects the interior decoration of the scaffolding location and has low work efficiency.
[0003] A cable net platform is tied around the structure, and a safety net is laid under the cable net. The cable net tie points need to be calculated for structural force. Wooden springboards are laid all over the cable net as an operating platform for construction workers, and main materials cannot be stacked. The tower crane is used as the main vertical transportation equipment, and the steel structure is made into a truss-shaped unit. A temporary movable frame is set up on the cable net platform as an auxiliary operating platform to assemble the steel structure as a whole. This method requires pre-embedded casings in the surrounding beams so that the cable net can pass through and be fixed. It has high requirements for the surrounding beams, and the deformation coefficient of the cable net platform needs to be monitored at any time. It is highly professional and occupies the tower crane for a long time, affecting the construction of other projects.
[0004] Chinese patent document CN1670322A discloses a "matrix top-pushing installation method for large-span and large-depth space steel structures". An assembly frame is set on the outside of the skylight span, a slideway is arranged, and the main truss is assembled on the flat frame. The main truss is lifted to the frame by a crane for assembly. After assembly, the main truss and the column are pushed and translated along the slideway by a hydraulic jack and a reaction frame for one column distance, and then assembled and pushed again, and repeated until completion. This method is more suitable for regular rectangular skylights, but not for irregular skylights. Summary of the invention
[0005] In order to overcome the technical defect that the existing large-span skylight construction method is suitable for regular rectangular skylights but not for irregular skylights, the present invention provides a large-span skylight construction method.
[0006] The present invention provides a large-span skylight construction method, comprising the following steps: Step 1: Use a truck crane or tower crane to transport the gantry crane steel frame assembly materials vertically to the roof, use the roof as a construction site, and assemble the gantry crane steel frame into shape; Step 2: Set up a safety net under the skylight opening; arrange two parallel gantry crane tracks in the length direction of the roof skylight, use a car crane or tower crane to make the assembled gantry crane steel frame stand up and install it in place on the gantry crane track, and the construction measures platform is set up; Step 3: Use a gantry crane to install an annular steel support along the opening of the skylight roof, connect the annular steel support to the roof embedded parts, and the annular steel support is located between the two gantry crane tracks; Step 4: Use a gantry crane to hoist the main steel keel in the middle of the skylight roof. The middle main steel keel is spliced on the roof and put into place as a whole using two electric hoists installed on the gantry crane. Step 5: The gantry crane lifting the main keel of the steel structure slides along the gantry crane track under the traction of the electric zippers on both sides to ensure that the gantry crane moves in parallel and synchronously; Step 6: After the gantry crane is moved into place, the main keel of the steel structure spans across the skylight opening and its two ends are welded to the annular steel support. The lifting rope on the main keel of the steel structure can be removed only after ensuring that the connection between the main keel of the steel structure and the annular steel support is stable; Step 7. Repeat steps 4 to 6. After the two adjacent steel structure column keels are installed and fixed, a hanging basket is set on the gantry crane. One electric crane lifts the steel structure secondary keel, and the other electric crane lifts the hanging basket. Workers operate in the hanging basket to install the steel structure secondary keel between the two steel structure main keels. After the steel structure secondary keel between the two steel structure main keels is installed, the remaining steel structure main keels and steel structure secondary keels are installed, and the steel structure main keel and steel structure secondary keel are installed symmetrically from the middle to both sides respectively. Step 8: Weld the curtain wall adapters above the main steel structure keel and the secondary steel structure keel. After this step is completed, the deformation of the steel structure is fully reviewed, and the relevant data is fed back to the design department and the processing plant in a timely manner to make fine adjustments to the processing of the curtain wall keel and glass in a timely manner; Step 9: Use the hanging basket on the gantry crane to position and install the curtain wall keel. The hanging basket can be lifted freely within the range of the curtain wall grid; Step 10: Use the hanging basket and glass panel lifting platform to install the glass panel; the glass panel is installed symmetrically at two points to ensure balanced loading at both ends of the steel structure and avoid deformation or instability of the steel structure due to eccentric loading; Step 11. After the installation of the fixed glass panel is completed, the opening fan is installed. This step needs to be coordinated with the electric opening and weak current fire linkage construction units. After the installation of the opening fan is completed, the opening test should be carried out in time, and the opening hardware and related circuits should be adjusted in time.
[0007] Compared with the prior art, the technical solution provided by the present invention has the following technical characteristics: the invention is suitable for large-span skylights, especially irregular skylights, and does not occupy vertical transportation tools such as tower cranes; and the use of this construction technology does not occupy indoor space and does not affect indoor decoration, especially when indoors are in business, it can be used for skylight maintenance; this construction method can be carried out before the construction of the roofing project, or after the completion of the roofing project, and can be carried out in parallel with other sub-projects to save construction time. BRIEF DESCRIPTION OF THE DRAWINGS
[0008] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the invention and, together with the description, serve to explain the principles of the invention.
[0009] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0010] Figure 1 This is a schematic diagram of the operation of installing the main keel of the steel structure in a large-span skylight construction method described in an embodiment of the present invention; Figure 2 It is a schematic diagram of the operation of installing a secondary keel of a steel structure in a large-span skylight construction method described in an embodiment of the present invention; Figure 3 It is a detailed structural schematic diagram of a hanging basket in a large-span skylight construction method described in a certain embodiment of the present invention; Figure 4 It is a schematic diagram of the structure after the installation of the main steel structure keel and the secondary steel structure keel in a large-span skylight roof construction method described in a certain embodiment of the present invention.
[0011] In the picture: 1. Roof; 2. Gantry crane track; 3. Gantry crane; 4. Base pulley; 5. Electric crane; 6. Lifting rope; 7. Main keel of steel structure; 8. Annular steel support; 9. Skylight roof opening; 10. Secondary keel of steel structure; 11. Hanging basket; 12. Workers; 13. Moving pulley. DETAILED DESCRIPTION
[0012] In order to more clearly understand the above-mentioned objectives, features and advantages of the present invention, the scheme of the present invention will be further described below. It should be noted that the embodiments of the present invention and the features in the embodiments can be combined with each other without conflict.
[0013] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein; it is obvious that the embodiments in the specification are only part of the embodiments of the present invention, rather than all of the embodiments.
[0014] The specific embodiments of the present invention are described in detail below with reference to the accompanying drawings.
[0015] In one embodiment, Figure 1 As shown, a large-span skylight construction method is disclosed, comprising the following steps: Step 1: Use a truck crane or a tower crane to transport the gantry crane 3 steel frame assembly materials vertically to the roof 1 on the ground, use the roof 1 as a construction site, and assemble the gantry crane 3 steel frame into shape; Step 2: Set up a safety net below the skylight opening 9; arrange two parallel gantry crane tracks 2 in the length direction of the skylight on the roof 1, use a car crane or a tower crane to make the welded gantry crane 3 stand up and install it in place on the gantry crane track 2, and the construction measures platform is set up; Step 3: Use a gantry crane to install an annular steel support 8 along the skylight top opening 9, connect the annular steel support 8 to the embedded parts of the roof 1, and the annular steel support 8 is located between the two gantry crane tracks 2; Step 4: Use the gantry crane 3 to hoist the steel structure main keel 7 in the middle of the skylight roof. The middle steel structure main keel 7 is spliced and formed on the roof 1, and the two electric hoists 5 set on the gantry crane 3 are used to put the whole into place; Step 5: The gantry crane 3 lifting the main keel 7 of the steel structure slides along the gantry crane track 2 under the traction of the electric zippers on both sides to ensure that the gantry crane 3 moves in parallel and synchronously; Step 6: After the gantry crane 3 is moved into place, the main keel 7 of the steel structure spans the skylight opening 9 and its two ends are welded to the annular steel support 8. The suspension rope 6 on the main keel 7 of the steel structure can be removed only after ensuring that the connection between the main keel 7 of the steel structure and the annular steel support 8 is stable; Step 7, repeating steps 4 to 6, after two adjacent steel structure column keels are installed and fixed, a hanging basket 11 is set on the gantry crane 3, one electric crane 5 lifts the steel structure secondary keel 10, and the other electric crane 5 lifts the hanging basket 11, and the worker 12 operates in the hanging basket 11 to install the steel structure secondary keel 10 between the two steel structure main keels 7; after the steel structure secondary keel 10 between the two steel structure main keels 7 is installed, the remaining steel structure main keels 7 and steel structure secondary keels 10 are installed, wherein the steel structure main keel 7 and the steel structure secondary keel 10 are installed symmetrically from the middle to both sides respectively; Step 8: Weld the curtain wall adapters above the steel structure main keel 7 and the steel structure secondary keel 10. After this step is completed, the deformation of the steel structure is fully reviewed, and the relevant data is fed back to the design department and the processing plant in a timely manner to fine-tune the processing of the curtain wall keel and glass in a timely manner; Step 9: Use the hanging basket 11 on the gantry crane 3 to position and install the curtain wall keel, and the hanging basket 11 can be freely lifted within the range of the curtain wall grid; Step 10: Use the hanging basket 11 and the glass panel lifting platform to install the glass panel; the glass panel is installed symmetrically at two points to ensure balanced loading at both ends of the steel structure and avoid deformation or instability of the steel structure caused by eccentric loading; Step 11. After the installation of the fixed glass panel is completed, the opening fan is installed. This step needs to be coordinated with the electric opening and weak current fire linkage construction units. After the installation of the opening fan is completed, the opening test should be carried out in time, and the opening hardware and related circuits should be adjusted in time.
[0016] The above is only a specific implementation of the present invention, which enables those skilled in the art to understand or implement the present invention. Although detailed descriptions are given with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions recorded in the aforementioned embodiments, or replace some or all of the technical features therein by equivalents; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments, and they should all be covered by the protection scope of the claims.
Claims
1. A large-span skylight construction method, characterized in that: The steps include: Step 1: Use a truck crane or a tower crane to vertically transport the gantry crane (3) steel frame assembly materials to the roof (1) on the ground, and use the roof (1) as a construction site to assemble the gantry crane (3) steel frame into shape; Step 2: Set up a safety net below the skylight opening (9); arrange two parallel gantry crane tracks (2) in the length direction of the skylight of the roof (1); use a truck crane or a tower crane to make the assembled gantry crane (3) stand up and install it in place on the gantry crane track (2) through the base pulley (4); and the construction measures platform is set up; Step 3: Using a gantry crane (3) to install an annular steel support (8) along the skylight opening (9), connecting the annular steel support (8) to the embedded parts of the roof (1), the annular steel support (8) being located between the two gantry crane tracks (2); Step 4: Use a gantry crane (3) to hoist the steel structure main keel (7) in the middle of the skylight roof. The middle steel structure main keel (7) is spliced and formed on the roof (1). The two electric hoists (5) provided on the gantry crane (3) are used to put the whole into place. The electric hoists (5) are connected to the hoisting rope (6) via a movable pulley (13); Step 5: The gantry crane (3) lifting the main keel (7) of the steel structure slides along the gantry crane track (2) under the traction of the electric zippers on both sides to ensure that the gantry crane (3) moves in parallel and synchronously; Step 6: After the gantry crane (3) is moved into position, the main keel (7) of the steel structure is placed across the skylight opening (9) and its two ends are welded to the annular steel support (8). The suspension rope (6) on the main keel (7) of the steel structure can be removed only after ensuring that the connection between the main keel (7) of the steel structure and the annular steel support (8) is stable. Step 7, repeating steps 4 to 6, after two adjacent steel structure column keels are installed and fixed, a hanging basket (11) is arranged on the gantry crane (3), one electric crane (5) lifts the steel structure secondary keel (10), and the other electric crane (5) lifts the hanging basket (11), and the worker (12) operates in the hanging basket (11) to install the steel structure secondary keel (10) between the two steel structure main keels (7); after the steel structure secondary keel (10) between the two steel structure main keels (7) is installed, the remaining steel structure main keels (7) and steel structure secondary keels (10) are installed, wherein the steel structure main keel (7) and the steel structure secondary keel (10) are installed symmetrically from the middle to both sides respectively; Step 8: Weld the curtain wall adapters above the steel structure main keel (7) and the steel structure secondary keel (10). After this step is completed, the deformation of the steel structure is fully reviewed, and the relevant data is fed back to the design department and the processing plant in a timely manner to make fine adjustments to the processing of the curtain wall keel and glass in a timely manner; Step 9: Use the hanging basket (11) on the gantry crane (3) to position and install the curtain wall keel, and the hanging basket (11) can be freely lifted within the range of the curtain wall grid; Step 10: Use the hanging basket (11) and the glass panel lifting platform to install the glass panel; the glass panel is installed symmetrically at two points to ensure balanced loading at both ends of the steel structure and avoid deformation or instability of the steel structure caused by eccentric loading; Step 11. After the installation of the fixed glass panel is completed, the opening fan is installed. This step needs to be coordinated with the electric opening and weak current fire linkage construction units. After the installation of the opening fan is completed, the opening test should be carried out in time, and the opening hardware and related circuits should be adjusted in time.
Citation Information
Patent Citations
Large-span daylighting roof glass curtain installing constructing method
CN109577656A
Construction method for roof combined hoisting system of daylighting roof
CN111021740A
Roof daylighting roof steel frame installation method
CN117090393A
Large-span double-curved-surface daylighting building roof structure and construction method thereof
CN118461824A
Method for erecting large roof by direct hanging
JP1999107534A