Power industry distribution network business expansion project construction quotation generation system and method
By designing an automated quotation generation system in the distribution network expansion project of the power industry, using historical data and real-time market information, the dynamic adjustment, manual dependence, standardization and information integration of quotation preparation in the existing technology has been solved, and more accurate , more efficient construction quotations improve cost control and user experience.
Patent Information
- Application Number
- CN202411199192.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-29
- Publication Date
- 2024-11-26
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing methods for preparing construction quotations for distribution network expansion projects in the power industry lack dynamic adjustment mechanism, rely on manual operations, insufficient standardization, weak information integration capabilities, lack of intelligent decision-making support, insufficient risk management, poor user experience, and poor confidentiality. It is not possible to reflect changes in market material prices and labor costs in real time.
A system for the expansion project of distribution network industry in the power industry was designed, including a human-computer interaction unit and a quotation order generation system. It uses the historical distribution network industry in the power industry to expand construction quotations, construction material quotations and standard materials, combined with real-time market information , automatically generate the final quotation, and generate more accurate construction quotations through a comprehensive bill of quantities database and real-time market information update mechanism.
It realizes more accurate and efficient construction quotation preparation, reduces budget overspending and cost waste, improves cost control and management levels, ensures the confidentiality and user experience of quotations, and reduces human errors and operational complexity.
Smart Images

Figure CN119027197A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of expansion and matching of distribution network in the electric power industry. Background Art
[0002] In the power industry's distribution network expansion and supporting projects, in order to facilitate management, it is necessary to use a project quotation preparation method to facilitate supporting operations.
[0003] However, the existing quotation compilation method for distribution network expansion project based on bill of quantities has the following deficiencies and shortcomings: 1. Lack of dynamic adjustment mechanism: Traditional quotation compilation method is often fixed and cannot reflect market material price fluctuations and labor cost changes in real time, resulting in a disconnect between quotation and actual cost; 2. Dependence on manual operation: A large amount of reliance on manual data collection, processing and calculation is prone to human errors, low efficiency, and difficulty in coping with complex and changing engineering environments; 3. Insufficient standardization: Existing methods lack unified standards for the compilation and analysis of bill of quantities. Technical and economic personnel of different construction companies may have different understandings and practices, affecting the timeliness and accuracy of quotations; 4. Weak information integration capabilities: Information from multiple different professions and links is difficult to integrate. 5. Lack of intelligent decision support: Existing methods fail to make full use of modern information technology, such as artificial intelligence and big data analysis, to assist in making more accurate and scientific decisions; 6. Inadequate risk management: In terms of risk assessment and management, existing methods often only consider fixed risk premiums, without personalized assessments based on the unique risks of specific projects; 7. Poor user experience: When customers and construction companies use traditional quotation systems, the interface may not be friendly enough, the operation is cumbersome, and it is not conducive to rapid understanding and application; 8. Security and confidentiality issues: During data transmission and storage, the existing system may not be able to fully guarantee the security and confidentiality of information, so a new compilation method needs to be proposed. Summary of the invention
[0004] The present invention aims to solve the problems that the existing methods for generating construction reports for distribution network expansion projects in the power industry rely on manual labor, have poor confidentiality, or cannot take into account real-time market material price fluctuations and labor cost changes. A method for generating construction quotations for distribution network expansion projects in the power industry is now provided.
[0005] The present invention provides a construction quotation generation system for a power industry distribution network expansion project, comprising: the system comprises a human-computer interaction unit and a quotation sheet generation system;
[0006] The human-computer interaction unit also provides a port for importing or entering the bill of quantities to be quoted and the maximum bid limit price, and the human-computer interaction unit transmits the bill of quantities to be quoted and the maximum bid limit price to the quotation sheet generation system;
[0007] The quotation generation system extracts different construction lists from the bill of quantities to be quoted; uses the historical distribution network expansion project construction quotations of the power industry and the construction material quotas and standard materials of the power industry to determine the material quotas and standard materials in the different construction lists; then determines the material prices and labor costs in the bill of quantities to be quoted based on the price information of the materials provided by Party A in the bill of quantities to be quoted and the market prices of the materials and labor provided by Party B at the current construction site, obtains an initial quotation based on the standard material prices and labor costs in the construction list, compares the initial quotation with the highest bid limit, and when the total price of the initial quotation is higher than the highest bid limit, adjusts the quota coefficient in the initial quotation until the total price of the initial quotation is lower than the highest bid limit, obtains a final quotation, and outputs the final quotation to the human-computer interaction unit for display.
[0008] Furthermore, in the present invention, the human-computer interaction unit is also used to set terrain parameters, earthwork parameters, construction site transportation costs, distribution costs and special project fees according to the project implementation site; the set parameters and costs are transmitted to the quotation generation system, and the quotation generation system applies the historical distribution network expansion project construction quotation of the power industry, and adds the costs corresponding to the terrain parameters and earthwork parameters, construction site transportation costs, distribution costs and special project fees to the initial quotation.
[0009] Furthermore, in the present invention, the historical distribution network expansion project construction quotations of the electric power industry are obtained through a prefabricated list library, which is a list of historical distribution network expansion project construction quotations and electric power industry construction quotas and standard materials at the construction site of the electric power industry in the past N years.
[0010] Furthermore, in the present invention, the different construction lists include: a building list, an installation list and a demolition list.
[0011] Furthermore, the present invention also includes an audit modification module, which is used to provide an audit modification port for auditors.
[0012] A method for generating a construction quotation for a power industry distribution network expansion project, the method comprising:
[0013] Using the historical construction quotations of power industry distribution network expansion projects and the power industry construction material quotas and standard material standards, the quotas and standard materials of the construction list are determined;
[0014] Determine the material price and labor cost in the bill of quantities to be quoted based on the price information of the materials provided by Party A in the bill of quantities to be quoted and the market price of the materials and labor provided by Party B at the current construction site;
[0015] Obtain an initial quotation based on the standard material prices and labor costs in the construction list;
[0016] The initial quotation is compared with the maximum bid limit. When the total price of the initial quotation is higher than the maximum bid limit, the quota coefficient in the initial quotation is adjusted until the total price of the initial quotation is lower than the maximum bid limit, and the final quotation is obtained.
[0017] Furthermore, the present invention also includes setting the terrain parameters, earthwork parameters, site transportation parameters, distribution distance, special project fees and area type in the bill of quantities to be quoted according to the location of the construction site of the project to be quoted; applying the historical distribution network expansion project construction quotation of the power industry, and adding the different fees corresponding to the terrain parameters and earthwork parameters, site transportation fees, distribution fees and special project fees to the initial quotation.
[0018] By constructing a comprehensive bill of quantities database and a real-time market information update mechanism, the present invention can more accurately reflect the actual cost of materials, equipment and labor, thereby generating a more accurate construction quotation. Effectively reducing budget overruns and cost waste, not only brings significant progress in technology and operation, but also the automatic quotation generation effectively guarantees confidentiality, which is of great significance for improving the cost control and management level of distribution network expansion projects. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 The present invention provides a block diagram of the principle of a construction quotation generation system for a power industry distribution network expansion project. DETAILED DESCRIPTION
[0020] The following will be combined with the accompanying drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work belong to the scope of protection of the present invention. It should be noted that the embodiments of the present invention and the features in the embodiments can be combined with each other without conflict.
[0021] Specific implementation method 1: refer to Figure 1 Specifically describing this embodiment, a construction quotation generation system for a power industry distribution network expansion project described in this embodiment includes: the system includes a human-computer interaction unit and a quotation sheet generation system;
[0022] The human-computer interaction unit is used to provide information entry and quotation display for operators, and transmit the entered information to the quotation generation system;
[0023] The human-computer interaction unit also provides a port for importing or entering the bill of quantities to be quoted and the maximum bid limit price, and the human-computer interaction unit transmits the bill of quantities to be quoted and the maximum bid limit price to the quotation sheet generation system;
[0024] The quotation generation system extracts different construction lists from the bill of quantities to be quoted; uses the historical distribution network expansion project construction quotations of the power industry and the construction material quotas and standard materials of the power industry to determine the material quotas and standard materials in the different construction lists; then determines the material prices and labor costs in the bill of quantities to be quoted based on the price information of the materials provided by Party A in the bill of quantities to be quoted and the market prices of the materials and labor provided by Party B at the current construction site, obtains an initial quotation based on the standard material prices and labor costs in the construction list, compares the initial quotation with the highest bid limit, and when the total price of the initial quotation is higher than the highest bid limit, adjusts the quota coefficient in the initial quotation until the total price of the initial quotation is lower than the highest bid limit, obtains a final quotation, and outputs the final quotation to the human-computer interaction unit for display.
[0025] Furthermore, in the present invention, the human-computer interaction unit is also used to set terrain parameters, earthwork parameters, construction site transportation costs, distribution costs and special project costs according to the project implementation site; apply terrain parameters and earthwork parameters;
[0026] The set parameters and costs are transmitted to the quotation generation system, and the quotation generation system applies the historical distribution network expansion project construction quotation of the power industry, and adds the costs corresponding to the terrain parameters and earthwork parameters, site transportation costs, distribution costs and special project costs into the cost list.
[0027] Furthermore, in the present invention, the historical distribution network expansion project construction quotations of the electric power industry are obtained through a prefabricated list library, which is a list of historical distribution network expansion project construction quotations and electric power industry construction quotas and standard materials at the construction site of the electric power industry in the past N years.
[0028] Furthermore, in the present invention, the different construction lists include: a building list, an installation list and a demolition list.
[0029] Furthermore, the present invention also includes an audit modification module, which is used to provide an audit modification port for auditors.
[0030] Specific implementation method 2: A method for generating a construction quotation for a power industry distribution network expansion project described in this implementation method includes:
[0031] Using the historical construction quotations of power industry distribution network expansion projects and the quotas and standard material standards of power industry construction materials, the quotas and standard materials of the construction list are determined;
[0032] Determine the material price and labor cost in the bill of quantities to be quoted based on the price information of the materials provided by Party A in the bill of quantities to be quoted and the market price of the materials and labor provided by Party B at the current construction site;
[0033] Obtain an initial quotation based on the standard material prices and labor costs in the construction list;
[0034] The initial quotation is compared with the maximum bid limit. When the total price of the initial quotation is higher than the maximum bid limit, the quota coefficient in the initial quotation is adjusted until the total price of the initial quotation is lower than the maximum bid limit, and the final quotation is obtained.
[0035] Furthermore, the present invention also includes setting the terrain parameters, earthwork parameters, site transportation parameters, distribution distance, special project fees and area type in the bill of quantities to be quoted according to the location of the construction site of the project to be quoted; applying the historical distribution network expansion project construction quotation of the power industry, and adding the fees corresponding to the terrain parameters and earthwork parameters, site transportation fees, distribution fees and special project fees to the cost list.
[0036] The construction material quotas and standard material standards for the power industry in the present invention are determined through the "Regulations on the Preparation and Calculation of Budgets for Construction of Distribution Network Projects of 20kV and Below (2022 Edition)" and relevant regulations on the budget quotas for construction of distribution network projects of 20kv and below.
[0037] The threshold list library is a collection of all list items that meet local engineering requirements extracted from the "dl / t 5766-2018 20kv and below distribution network project bill of quantities calculation specification" and "dl / t 5765-2018 20kv and below distribution network project bill of quantities pricing specification" for the management of historical business expansion and supporting projects. The prefabricated list library includes the list name, project characteristics, associated quotas, associated materials and associated projects. When in use, you can just search for the required items and the corresponding costs.
[0038] The system and method of the present invention are more accurate, efficient, reliable and user-friendly methods for compiling construction quotations for distribution network expansion projects, so as to meet the needs of the rapid development of the power industry and provide users with a better service experience. By building a comprehensive bill of quantities database and a real-time market information update mechanism, the method can more accurately reflect the actual costs of materials, equipment and labor, thereby generating more accurate construction quotations. This improvement in accuracy helps to reduce budget overruns and cost waste. Enhanced transparency: The technical solution makes the quotation process transparent through a clear algorithm model and detailed output report function, which is conducive to the understanding and acceptance of the cost structure by all parties involved in the project, and reduces disputes that may arise due to opaque quotations. Improved efficiency: The traditional quotation preparation process is often time-consuming and cumbersome, while the technical solution greatly shortens the quotation preparation time and improves work efficiency through automated system design, so that the engineering team can quickly respond to bidding requirements or customer needs. Optimized decision support: The intelligent algorithm model not only provides basic quotation calculations, but also provides cost forecasts and risk assessments based on historical data and market trends, providing more scientific decision support for the project management team. Strong adaptability: As market conditions change, the technical solution can flexibly adjust quotation parameters to ensure the real-time and market adaptability of quotations, which is essential for maintaining competitiveness in a dynamically changing market environment. Standardizing industry standards: The implementation of this technical solution helps promote the standardization process within the industry, and through a unified quotation preparation method, it improves the professional level and service quality of the entire industry. Reduce human errors: Systematized quotation preparation reduces the number of manual operations, reduces quotation deviations caused by human errors or subjective judgments, and ensures the objectivity and fairness of quotations.
[0039] The present invention aims to provide a more accurate, efficient, reliable and user-friendly method for compiling construction quotation for distribution network expansion projects, so as to meet the needs of the rapid development of the power industry and provide users with a better service experience. The specific process of using the system of the present invention to generate a cost sheet and carry out practical application is as follows:
[0040] S1. Preparation: Establish or update the bill of quantities database to ensure that all possible engineering items, processes, materials and equipment are included;
[0041] Collect real-time market information, such as material prices, labor wages, etc.;
[0042] Update the bill of quantities database with collected market information to ensure quotations reflect current market conditions;
[0043] S2. Input engineering requirements: Build a system interface, form input and output units, and perform interactive operations; users input specific bill of quantities requirements through the system interface, and automatically extract corresponding items and processes;
[0044] S3. Calculate preliminary quotation: The system calculates preliminary construction quotation based on project requirements and market information; considers different project characteristics and historical data to optimize the accuracy of cost forecast;
[0045] S4. Adjustment and optimization: Users can adjust the preliminary quotation, such as modifying material specifications, adding or removing specific processes, etc. The system recalculates the quotation based on the adjustment and provides the adjusted cost analysis;
[0046] S5. Generate quotation report: The system outputs a detailed quotation report, including the bill of quantities, sub-item costs, other project costs, etc.; ensure the clarity of the report, and the project party participates in and reviews it to understand and build it;
[0047] S6. Review and confirmation: The project leader or relevant professionals review the quotation report to ensure that all information is accurate; after confirming the quotation report, it will be used for bidding, contract signing or other business activities;
[0048] S7. Follow-up tracking and maintenance: According to the actual project situation, the algorithm model and bill of quantities database are regularly updated to improve the accuracy of future quotations.
[0049] In summary, compared with the existing technology, the method of compiling construction quotation for distribution network expansion projects based on the bill of quantities has not only brought significant progress in technology and operation, but also demonstrated its unique advantages in industry management and market adaptability. It is of great significance to improve the cost control and management level of distribution network expansion projects.
[0050] Although the present invention is described herein with reference to specific embodiments, it should be understood that these embodiments are merely examples of the principles and applications of the present invention. It should therefore be understood that many modifications may be made to the exemplary embodiments and that other arrangements may be devised without departing from the spirit and scope of the present invention as defined by the appended claims. It should be understood that the various dependent claims and features described herein may be combined in a manner different from that described in the original claims. It should also be understood that the features described in conjunction with a single embodiment may be used in other described embodiments.
Claims
1. A construction quotation generation system for power industry distribution network expansion projects, characterized in that: include: The system includes a human-computer interaction unit and a quotation generation system; The human-computer interaction unit is used to provide information entry and quotation display for operators, and transmit the entered information to the quotation generation system; The human-computer interaction unit also provides a port for importing or entering the bill of quantities to be quoted and the maximum bid limit price, and the human-computer interaction unit transmits the bill of quantities to be quoted and the maximum bid limit price to the quotation sheet generation system; The quotation generation system extracts different construction lists from the bill of quantities to be quoted; uses the historical distribution network expansion project construction quotations of the power industry and the construction material quotas and standard materials of the power industry to determine the material quotas and standard materials in the different construction lists; then determines the material prices and labor costs in the bill of quantities to be quoted based on the price information of the materials provided by Party A in the bill of quantities to be quoted and the market prices of the materials and labor provided by Party B at the current construction site, obtains an initial quotation based on the standard material prices and labor costs in the construction list, compares the initial quotation with the highest bid limit, and when the total price of the initial quotation is higher than the highest bid limit, adjusts the quota coefficient in the initial quotation until the total price of the initial quotation is lower than the highest bid limit, obtains a final quotation, and outputs the final quotation to the human-computer interaction unit for display.
2. A construction quotation generation system for power industry distribution network expansion projects according to claim 1, characterized in that: The human-computer interaction unit is also used to set terrain parameters, earthwork parameters, construction site transportation costs, distribution costs and special project costs according to the project implementation site; apply terrain parameters and earthwork parameters; The set parameters and costs are transmitted to the quotation generation system, and the quotation generation system applies the historical distribution network expansion project construction quotations of the power industry, and adds the different costs corresponding to the terrain parameters and earthwork parameters, construction site transportation costs, distribution costs and special project fees into the initial quotation.
3. A construction quotation generation system for power industry distribution network expansion projects according to claim 1, characterized in that: The historical construction quotations of the distribution network expansion projects in the electric power industry are obtained through a prefabricated list library, which is a list of historical construction quotations of the distribution network expansion projects in the construction site of the electric power industry in the past N years and the construction quotas and standard materials of the electric power industry.
4. A construction quotation generation system for power industry distribution network expansion projects according to claim 1, 2 or 3, characterized in that: The different construction checklists include: a building checklist, an installation checklist and a demolition checklist.
5. A construction quotation generation system for power industry distribution network expansion projects according to claim 4, characterized in that: It also includes an audit modification module, which is used to provide an audit modification port for auditors.
6. A method for generating a construction quotation for a power industry distribution network expansion project, characterized in that: The method includes: Using the historical construction quotations of power industry distribution network expansion projects and the power industry construction material quotas and standard material standards, the quotas and standard materials of the construction list are determined; Determine the material price and labor cost in the bill of quantities to be quoted based on the price information of the materials provided by Party A in the bill of quantities to be quoted and the market price of the materials and labor provided by Party B at the current construction site; Obtain an initial quotation based on the standard material prices and labor costs in the construction list; The initial quotation is compared with the maximum bid limit. When the total price of the initial quotation is higher than the maximum bid limit, the quota coefficient in the initial quotation is adjusted until the total price of the initial quotation is lower than the maximum bid limit, and the final quotation is obtained.
7. A method for generating construction quotation for power industry distribution network expansion project according to claim 6, characterized in that: It also includes setting the terrain parameters, earthwork parameters, site transportation parameters, distribution distance, special project fees and area type in the bill of quantities to be quoted according to the location of the construction site of the project to be quoted; applying the historical distribution network expansion project construction quotation of the power industry, and adding the different fees corresponding to the terrain parameters and earthwork parameters, site transportation fees, distribution fees and special project fees to the initial quotation.
Citation Information
Patent Citations
Distribution network batch cost compilation method
CN107767077A
Power transmission and transformation project cost calculation system and cost calculation method based on three-dimensional model
CN112036953A
Cited By
Method and device for generating quotation sheet based on large language model
CN119311698A
Control method of distribution network business expansion supporting project management and control system based on bill of quantity
CN119599609A
Low-voltage power supply scheme generation method for power industry business expansion supporting project
CN119671783A