Integrated port management system based on artificial intelligence

Through the comprehensive port management system based on artificial intelligence, the combined matching technology of ship data acquisition and main control terminals is solved, the problem of flexible management and allocation in port berth coordination is achieved, efficient matching and dispatch of berths is achieved, and port operation efficiency is improved.

CN119067353APending Publication Date: 2024-12-03苏州诀智科技有限公司
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202411020591.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-29
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

It is difficult to achieve flexible management and timely allocation of existing technologies in port berth coordination, and it is impossible to effectively improve overall operational efficiency.

Method used

Adopt an integrated port management system based on artificial intelligence to obtain the information of the berth and berth through the ship data acquisition end. The main control end performs one-to-one combination matching, and optimizes and analyzes based on the remaining value and the total unloading length to achieve flexible matching and scheduling of berths. .

Benefits of technology

It realizes flexible matching and scheduling of berths, improves port operation efficiency, can optimize berth use in different periods and scenarios, adapts to changes in ship size, and simplifies the scheduling process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119067353A_ABST
    Figure CN119067353A_ABST
Patent Text Reader

Abstract

The invention discloses a port comprehensive management system based on artificial intelligence, and relates to the technical field of port comprehensive management, a ship data acquisition end is used for acquiring ships appearing in a set position within a set time period, marking the ships as undetermined objects, synchronously acquiring standard information representing the sizes of the undetermined objects, and sending the standard information to a server; transmitting a to-be-determined object group consisting of a plurality of to-be-determined objects and standard information thereof to the main control end; meanwhile, the remaining berths of the ship berths of the port and the corresponding berth adaptive values are synchronized, and whether the to-be-determined object can be parked in the corresponding remaining berths or not can be determined through matching of the berth adaptive values and the standard information; then the main control end is used for carrying out one-to-one combination matching on all the to-be-determined objects and the remaining berths to obtain a plurality of object matching combinations, then a selected object combination is determined according to the remaining value of each object matching combination, first-wave berth matching can be carried out according to time periods and time division scenes, and no berths exist in the subsequent process; and flexible scheduling can be realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of port integrated management, and in particular is an artificial intelligence-based port integrated management system. Background Art

[0002] Port berth coordination is mainly achieved through multi-terminal berth coordination allocation strategies, one-way channel multi-objective ship scheduling optimization models and other methods. Under limited port resources, in order to effectively coordinate port berths and improve overall operational efficiency, it is necessary to comprehensively consider multiple factors and adopt scientific scheduling strategies;

[0003] The patent with publication number CN114861956A discloses a smart port integrated management system for improving the intelligence of ports and the efficiency of logistics. The smart port integrated management system includes: a port scheduling module, a security monitoring module, a data exchange module, a collaborative operation module, an intelligent gate module, a mobile transport terminal and a client; the port scheduling module is used to: receive a warehouse reservation request sent by the client, and parse the warehouse reservation request to obtain warehouse parameters and use date; and match the target container corresponding to the warehouse reservation request according to the warehouse parameters and use date, and match the mobile transport terminal corresponding to the target container; and extract the target container from the external container warehouse of the port through the mobile transport terminal according to the container transportation plan and transport the target container to the smart port; and dispatch the target ship according to the ship scheduling strategy, and load the target container with cargo according to the target ship and cargo loading plan.

[0004] However, the above patent does not involve much in the flexible management and deployment of berths, and cannot flexibly manage berths and coordinate in time; based on this, a solution is provided. Summary of the invention

[0005] The present invention aims to solve at least one of the technical problems existing in the prior art; to this end, the present invention proposes an artificial intelligence-based integrated port management system, comprising:

[0006] The ship data acquisition terminal is used to acquire ships that appear within the set position within the set time period, mark the ships as pending objects, synchronously acquire standard information indicating the size of the pending objects, and transmit a pending object group consisting of several pending objects and their standard information to the main control terminal; at the same time, the remaining berths of the ship berths of the port and their corresponding berth adaptation values ​​are synchronized. The berth adaptation value is used to express the specific adapted size of the pending object. The matching of the berth adaptation value and the standard information can determine whether the pending object can be parked in the corresponding remaining berth;

[0007] The main control end performs one-to-one matching of all pending objects with the remaining berths to obtain several object matching combinations, and then determines the selected object combination according to the residual value of each object matching combination. The residual value is the tonnage difference between the tonnage of the largest ship that the remaining berths can accommodate and the tonnage of the matching pending object;

[0008] The master control end is used to drive the operation end for scheduling according to the selected object combination.

[0009] Furthermore, the ship data acquisition terminal includes a first detection unit and a countdown unit;

[0010] The first detection unit is used to detect all ships arriving at the set position. The specific method of detecting ships is as follows:

[0011] When the first ship is detected to enter the set position, a countdown signal is transmitted to the countdown unit, and the countdown unit starts to count down;

[0012] Continuously detect ships that enter the set position. For the convenience of description below, they are marked as pending objects here. Synchronously obtain standard information of the pending objects. The standard information is used to indicate the size of the ship and to reflect the size of the berth it is suitable for. A pending object group consisting of several pending objects and their corresponding standard information is obtained.

[0013] When the countdown ends, a detection segment ends until the next detection segment begins. The next detection segment also starts from the detection of the next pending object;

[0014] The first detection unit is used to transmit the pending object group to the main control unit of the main control end.

[0015] Furthermore, the setting position determination method is to mark the center position of the port berth as the center of the circle and set the distance as the radius of the circle.

[0016] Furthermore, it also includes a remaining acquisition unit, which is used to synchronize the usage information of the ship berths of the port, the usage information includes the remaining berths and their corresponding berth adaptation values, the remaining berths refer to the berths where the ships are available to berth, and the berth adaptation values ​​of the remaining berths are used to express the size of the specific adapted pending object;

[0017] The remaining acquisition unit is used to transmit the usage information to the main control unit.

[0018] Furthermore, the main control unit is used to perform a balanced analysis on the pending object group and the usage information, so as to determine the selected object combination. The specific method of the balanced analysis is as follows:

[0019] Step 1: Obtain any pending object in the pending object group and its standard information;

[0020] Step 2: Obtain usage information, obtain all remaining berths that can accommodate pending objects based on the usage information, and then obtain all remaining berths that can accommodate the pending objects;

[0021] Step 3: Each pending object corresponds to a number of remaining berths that can be matched with it. Each pending object is matched with the remaining berths to obtain a number of matching combinations, which are marked as object matching combinations. Each object matching combination ensures that each pending object has a remaining berth;

[0022] Step 4: Get the remaining value of each object matching combination. The remaining value is specifically defined as:

[0023] The maximum tonnage that can be parked on the pending object corresponding to the remaining berth is obtained, and the tonnage of the current pending object is subtracted from the tonnage to obtain the tonnage difference, and the value obtained by removing the dimension from the tonnage difference is marked as the remaining value;

[0024] Step 5: Then, the sum of the remaining values ​​of each object matching combination is obtained, and the object matching combination with the smallest sum of the remaining values ​​is marked as the selected object combination; each selected object combination includes a number of pending objects and their corresponding remaining berths.

[0025] Furthermore, the main control end also includes an auxiliary analysis unit, which is used to obtain the unloading place of the pending object.

[0026] And re-balance analysis is carried out in combination with the unloading site, the specific method is as follows:

[0027] Get the remaining berths in any object matching combination, and then get the distance from the corresponding pending object to the unloading place;

[0028] Get the distance from each remaining berth to the unloading site corresponding to the pending object, add up all the distances, and mark the obtained value as the total unloading length of the corresponding object matching combination;

[0029] The remaining value of each object matching combination is marked as Yi, i=1, ..., n, and the total unloading length of the object matching combination is marked as Ci, i=1, ..., n;

[0030] Then the selected value Zi is calculated according to the formula. The specific calculation formula is:

[0031] Zi=0.44*Yi+0.56*Ci;

[0032] In the formula, 0.44 and 0.56 are the preset weights;

[0033] Mark the object matching combination with the smallest selection value as the selected matching combination.

[0034] Furthermore, the unloading place is a transfer point where the cargo on board needs to be unloaded after the ship enters the berth, or it is a temporary storage place for cargo that needs to be shipped away.

[0035] Furthermore, when the main control unit is performing a balance analysis, if it is analyzed that any pending object has no corresponding remaining berths that can be allocated, but there are vacant remaining berths, a temporary allocation analysis will be automatically performed. The specific method of the temporary allocation analysis is:

[0036] First, the pending objects that are not assigned to the remaining berths are marked as objects to be filled;

[0037] Afterwards, the remaining berths that can accommodate the objects to be filled and the pending objects to be parked on the remaining berths are obtained, and the remaining berths that meet the requirements are marked as berths to be adjusted;

[0038] Selecting from the berths to be adjusted that can accommodate the object to be filled, and the pending object in the berths to be adjusted can be docked in the remaining vacant berths, and the remaining vacant berths refer to the remaining berths that are not assigned with the pending object;

[0039] All the berths to be adjusted that meet the requirements are obtained, and the pending objects in the berths to be adjusted are also re-marked as objects to be adjusted, and the remaining value of the objects to be adjusted in the berths to be adjusted is obtained. At the same time, the total unloading length of the objects to be filled when they are docked at the berths to be adjusted is also obtained, and the pending value of the berths to be adjusted is calculated using the formula, which is:

[0040] Value to be adjusted = 0.42*total unloading length + 0.58*remaining value;

[0041] The values ​​to be adjusted of all the berths to be adjusted are calculated in the above manner, and the berth with the smallest value to be adjusted is marked as the adjusted berth.

[0042] Compared with the prior art, the present invention has the following beneficial effects:

[0043] The present invention uses a ship data acquisition terminal to acquire ships that appear within a set position within a set time period, mark the ships as pending objects, synchronously acquire standard information indicating the size of the pending objects, and transmit a pending object group consisting of a number of pending objects and their standard information to a main control terminal; at the same time, the remaining berths of the ship berths of the port and their corresponding berth adaptation values ​​are synchronized, the berth adaptation value is used to express the specific adapted size of the pending object, and the matching of the berth adaptation value and the standard information can determine whether the pending object can be parked in the corresponding remaining berth;

[0044] Then, the main control end is used to perform one-to-one combination matching of all pending objects and the remaining berths to obtain several object matching combinations, and then the selected object combination is determined according to the remaining value of each object matching combination. The first wave of berth matching can be performed according to time periods and scenes. If there are no berths later, or when a small boat enters a large berth, it can be flexibly scheduled. The present invention is simple, effective, and easy to use. BRIEF DESCRIPTION OF THE DRAWINGS

[0045] Figure 1 is a system block diagram of the present invention;

[0046] Figure 2 It is a system block diagram of the present invention. DETAILED DESCRIPTION

[0047] The technical solution of the present invention will be clearly and completely described below in conjunction with the embodiments. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0048] See also Figure 1-Figure 2 ,This application provides an artificial intelligence-based integrated port management system, including;

[0049] Ship data acquisition terminal, main control terminal, and operation terminal;

[0050] Among them, the ship data acquisition end includes a first detection unit, a countdown unit, and a remaining acquisition unit;

[0051] The first detection unit is used to detect all ships arriving at the port at a set position, where the set position is the position of the circle with the center of the port berth marked as the center and the set distance as the radius; the specific method of detecting ships is:

[0052] When the first ship is detected to enter the set position, a countdown signal is transmitted to the countdown unit, and the countdown unit starts to count down;

[0053] Continuously detect ships that enter the set position. For the convenience of description below, they are marked as pending objects here. Synchronously obtain standard information of the pending objects. The standard information is used to indicate the size of the ship and to reflect the size of the berth it is suitable for. A pending object group consisting of several pending objects and their corresponding standard information is obtained.

[0054] When the countdown ends, a detection segment ends until the next detection segment begins. The next detection segment also starts from the detection of the next pending object;

[0055] The first detection unit is used to transmit the pending object group to the main control unit, and the main control unit receives the data transmitted by the first detection unit to the pending object group;

[0056] The remaining acquisition unit is used to synchronize the usage information of the ship berths in the port. The usage information includes the remaining berths and their corresponding berth adaptation values. The remaining berths refer to the berths where the ships are available to berth. The berth adaptation values ​​of the remaining berths are used to express the size of the specific adaptation object to be determined, which is generally measured by the shoreline length of the berth, the number of ships, tonnage and other factors;

[0057] The remaining acquisition unit is used to transmit the usage information to the main control unit, and the main control unit receives the usage information transmitted by the remaining acquisition unit;

[0058] The main control unit is used to perform a balance analysis on the pending object group and the usage information. The specific method of the balance analysis is as follows:

[0059] Step 1: Obtain any pending object in the pending object group and its standard information;

[0060] Step 2: Obtain usage information, obtain all remaining berths that can accommodate pending objects based on the usage information, and then obtain all remaining berths that can accommodate the pending objects;

[0061] Step 3: Each pending object corresponds to a number of remaining berths that can be matched with it. Each pending object is matched with the remaining berths to obtain a number of matching combinations, which are marked as object matching combinations. Each object matching combination ensures that each pending object has a remaining berth;

[0062] Step 4: Get the remaining value of each object matching combination. The remaining value is specifically defined as:

[0063] If a larger tonnage can be parked on the pending object corresponding to the remaining berth, the tonnage difference will be automatically obtained. The tonnage difference is the maximum tonnage that can be parked minus the current tonnage. The result is marked as tonnage difference, and the value obtained after removing the dimension from the tonnage difference is marked as the remaining value;

[0064] Step 5: Then, the sum of the remaining values ​​of each object matching combination is obtained, and the object matching combination with the smallest sum of the remaining values ​​is marked as the selected object combination; each selected object combination includes a number of pending objects and their corresponding remaining berths.

[0065] The main control unit is used to transmit the selected object combination to the execution unit of the operation end for the user to execute.

[0066] As a second embodiment of the present application, the present application further includes an auxiliary analysis unit, which is used to obtain the unloading place of the pending object. The unloading place is where the cargo on board needs to be unloaded to the transfer point after the ship enters the berth, and it can also be a temporary storage place for cargo that needs to be shipped away; and re-balance analysis is performed in combination with the unloading place, and the specific method is as follows:

[0067] Get the remaining berths in any object matching combination, and then get the distance from the corresponding pending object to the unloading place;

[0068] Get the distance from each remaining berth to the unloading site corresponding to the pending object, add up all the distances, and mark the obtained value as the total unloading length of the corresponding object matching combination;

[0069] The remaining value of each object matching combination is marked as Yi, i=1, ..., n, and the total unloading length of the object matching combination is marked as Ci, i=1, ..., n;

[0070] Then the selected value Zi is calculated according to the formula. The specific calculation formula is:

[0071] Zi=0.44*Yi+0.56*Ci;

[0072] In the formula, 0.44 and 0.56 are preset weights used to highlight the different importance of different factors;

[0073] Mark the object matching combination with the smallest selection value as the selected matching combination;

[0074] As the third embodiment of the present application, this embodiment is implemented on the basis of the second embodiment, and the difference is that when the main control unit in this embodiment performs the balancing analysis, if it is analyzed that any pending object has no corresponding remaining berths that can be allocated, but there are vacant remaining berths, a temporary allocation analysis will be automatically performed. The specific method of the temporary allocation analysis is:

[0075] First, the pending objects that are not assigned to the remaining berths are marked as objects to be filled;

[0076] Afterwards, the remaining berths that can accommodate the objects to be filled and the pending objects to be parked on the remaining berths are obtained, and the remaining berths that meet the requirements are marked as berths to be adjusted;

[0077] Selecting from the berths to be adjusted that can accommodate the object to be filled, and the pending object in the berths to be adjusted can be docked in the remaining vacant berths, and the remaining vacant berths refer to the remaining berths that are not assigned with the pending object;

[0078] All the berths to be adjusted that meet the requirements are obtained, and the pending objects in the berths to be adjusted are also re-marked as objects to be adjusted, and the remaining value of the objects to be adjusted in the berths to be adjusted is obtained. At the same time, the total unloading length of the objects to be filled when they are docked at the berths to be adjusted is also obtained, and the pending value of the berths to be adjusted is calculated using the formula, which is:

[0079] Value to be adjusted = 0.42*total unloading length + 0.58*remaining value;

[0080] The values ​​to be adjusted of all the berths to be adjusted are calculated in the above manner, and the berth with the smallest value to be adjusted is marked as the adjusted berth.

[0081] Some of the data in the above formula are calculated by removing the dimensions and taking their numerical values. The formula is a formula that is closest to the actual situation obtained by software simulation of a large amount of collected data; the preset parameters and preset thresholds in the formula are set by technical personnel in this field according to actual conditions or obtained through simulation of a large amount of data.

[0082] The above embodiments are only used to illustrate the technical method of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical method of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical method of the present invention.

Claims

1. An integrated port management system based on artificial intelligence, characterized in that: include: The ship data acquisition terminal is used to acquire ships that appear within the set position within the set time period, mark the ships as pending objects, synchronously acquire standard information indicating the size of the pending objects, and transmit a pending object group consisting of several pending objects and their standard information to the main control terminal, while synchronizing the remaining berths of the ship berths of the port and their corresponding berth adaptation values. The berth adaptation value is used to express the specific adapted size of the pending object. The matching of the berth adaptation value and the standard information can determine whether the pending object can be parked in the corresponding remaining berth; The main control end performs one-to-one matching of all pending objects with the remaining berths to obtain several object matching combinations, and then determines the selected object combination according to the residual value of each object matching combination. The residual value is the tonnage difference between the tonnage of the largest ship that the remaining berths can accommodate and the tonnage of the matching pending object; The master control end is used to drive the operation end for scheduling according to the selected object combination.

2. According to claim 1, the integrated port management system based on artificial intelligence is characterized in that: The ship data acquisition terminal includes a first detection unit and a countdown unit; The first detection unit is used to detect all ships arriving at the set position. The specific method of detecting ships is as follows: When the first ship is detected to enter the set position, a countdown signal is transmitted to the countdown unit, and the countdown unit starts to count down; Continuously detect ships that enter the set position, mark the corresponding ships as pending objects, and simultaneously obtain standard information of the pending objects. The standard information is used to indicate the size of the ship and to reflect the size of the berth that the ship is suitable for, and obtain a pending object group consisting of several pending objects and their corresponding standard information; When the countdown ends, a detection segment ends until the next detection segment begins. The next detection segment also starts from the detection of the next pending object; The first detection unit is used to transmit the pending object group to the main control unit of the main control end.

3. According to claim 2, the integrated port management system based on artificial intelligence is characterized in that: The setting position is determined by marking the center of the port berth as the center of the circle and setting the distance as the radius of the circle.

4. According to claim 2, the integrated port management system based on artificial intelligence is characterized in that: It also includes a remaining acquisition unit, which is used to synchronize the usage information of the ship berths of the port, the usage information includes the remaining berths and their corresponding berth adaptation values, the remaining berths refer to the berths where the ships are available to berth, and the berth adaptation values ​​of the remaining berths are used to express the size of the specific adaptation to be determined object; The remaining acquisition unit is used to transmit the usage information to the main control unit.

5. According to claim 2, the integrated port management system based on artificial intelligence is characterized in that: The main control unit is used to perform a balanced analysis on the pending object group and usage information to determine the selected object combination. The specific method of the balanced analysis is as follows: Step 1: Obtain any pending object in the pending object group and its standard information; Step 2: Obtain usage information, obtain all remaining berths that can accommodate pending objects based on the usage information, and then obtain all remaining berths that can accommodate the pending objects; Step 3: Each pending object corresponds to a number of remaining berths that can be matched with it. Each pending object is matched with the remaining berths to obtain a number of matching combinations, which are marked as object matching combinations. Each object matching combination ensures that each pending object has a remaining berth; Step 4: Get the remaining value of each object matching combination. The remaining value is specifically defined as: The maximum tonnage that can be parked on the pending object corresponding to the remaining berth is obtained, and the tonnage of the current pending object is subtracted from the tonnage to obtain the tonnage difference, and the value obtained by removing the dimension from the tonnage difference is marked as the remaining value; Step 5: Then, the sum of the remaining values ​​of each object matching combination is obtained, and the object matching combination with the smallest sum of the remaining values ​​is marked as the selected object combination; each selected object combination includes a number of pending objects and their corresponding remaining berths.

6. According to claim 5, the integrated port management system based on artificial intelligence is characterized in that: The main control end also includes an auxiliary analysis unit, which is used to obtain the unloading place of the pending object. And re-balance analysis is carried out in combination with the unloading site, the specific method is as follows: Get the remaining berths in any object matching combination, and then get the distance from the corresponding pending object to the unloading place; Get the distance from each remaining berth to the unloading site corresponding to the pending object, add up all the distances, and mark the obtained value as the total unloading length of the corresponding object matching combination; The remaining value of each object matching combination is marked as Yi, i=1, ..., n, and the total unloading length of the object matching combination is marked as Ci, i=1, ..., n; Then the selected value Zi is calculated according to the formula. The specific calculation formula is: Zi=0.44*Yi+0.56*Ci; In the formula, 0.44 and 0.56 are the preset weights; Mark the object matching combination with the smallest selection value as the selected matching combination.

7. The artificial intelligence-based integrated port management system according to claim 6 is characterized in that: The unloading place is the transfer point where the cargo on board needs to be unloaded after the ship enters the berth, or it is a temporary storage place for cargo that needs to be shipped away.

8. The artificial intelligence-based integrated port management system according to claim 6 is characterized in that: When the main control unit is performing a balance analysis, if it is analyzed that any pending object has no corresponding remaining berths that can be allocated, and if there are vacant remaining berths, it will automatically perform a temporary allocation analysis. The specific method of temporary allocation analysis is as follows: First, the pending objects that are not assigned to the remaining berths are marked as objects to be filled; Afterwards, the remaining berths that can accommodate the objects to be filled and the pending objects to be parked on the remaining berths are obtained, and the remaining berths that meet the requirements are marked as berths to be adjusted; Selecting from the berths to be adjusted that can accommodate the object to be filled, and the pending object in the berths to be adjusted can be docked in the remaining vacant berths, and the remaining vacant berths refer to the remaining berths that are not assigned with the pending object; All the berths to be adjusted that meet the requirements are obtained, and the pending objects in the berths to be adjusted are also re-marked as objects to be adjusted, and the remaining value of the objects to be adjusted in the berths to be adjusted is obtained. At the same time, the total unloading length of the objects to be filled when they are docked at the berths to be adjusted is also obtained, and the pending value of the berths to be adjusted is calculated using the formula, which is: Value to be adjusted = 0.42*total unloading length + 0.58*remaining value; The values ​​to be adjusted of all the berths to be adjusted are calculated, and the berth with the smallest value to be adjusted is marked as the adjusted berth.

Citation Information

Patent Citations

  • Intelligent port comprehensive management system

    CN114861956A

  • Parking management method and management system thereof

    CN106652506A

  • Automatic parking method and device, electronic equipment and computer readable storage medium

    CN112214021A

  • Park logistics vehicle scheduling management system based on artificial intelligence

    CN117933672A

  • Multi-objective optimization port channel and berth cooperative scheduling method

    CN118036821A