Early warning system for heating defect of large power transformer

By using leakage current acquisition equipment and back-end monitoring center systems in large power transformers, the leakage current of the core and clamps is monitored and analyzed, and the alarm and current limiting functions are provided, which solves the heating and insulation oil caused by multi-point grounding of the core. The performance degradation problem improves the safety of the power grid and the reliability of the power supply.

CN119070474AInactive Publication Date: 2024-12-03HUANGSHI POWER SUPPLY CO
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202411066631.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-05
Publication Date
2024-12-03
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The prior art is difficult to effectively monitor and early warning of heating defects in large power transformers, resulting in increased losses caused by multi-point grounding of the iron core, overheating and degradation of insulating oil performance, affecting the safe and stable operation of the power grid.

Method used

An early warning system including leakage current acquisition equipment, serial port networking server, router and backend monitoring center is designed. The leakage current of the iron core and clamp are monitored and analyzed through leakage current sensors, providing data processing, fault analysis and alarm functions, and Provide historical data queries and trend analysis in the monitoring center.

Benefits of technology

It realizes early detection and current limit of the grounding current of the iron core and clamps, prevents accidents, improves the safety and power supply reliability of the power grid, and reduces unnecessary maintenance and economic losses.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119070474A_ABST
    Figure CN119070474A_ABST
Patent Text Reader

Abstract

The invention provides an early warning system for a heating defect of a large power transformer. The system comprises a leakage current acquisition device, a serial port networking server, a router and a background monitoring center. The leakage current acquisition equipment, the serial port networking server, the router and the background monitoring center are in communication connection in sequence; wherein the leakage current acquisition equipment is used for monitoring leakage current of an iron core and a clamp, and performing data processing, fault analysis, display and uploading on the leakage current; the serial port networking server and the router are used for transmitting the leakage current and the fault analysis result to the system server; and the background monitoring center is used for receiving the data uploaded by the leakage current acquisition equipment and providing alarming, historical data query, trend analysis and report printing functions. The grounding current of the iron core or the clamp can be monitored, and the early fault hidden danger of the main transformer can be found.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of heating monitoring of power transformers, and in particular to an early warning system for heating defects of large power transformers. Background Art

[0002] Transformer is one of the most important and expensive power equipment in the power system. With the increase of grid voltage level and transmission capacity, transformer failure will have a serious impact on the safe and stable operation of the grid.

[0003] When the transformer is running, there is an alternating magnetic field around the core. Under the action of the magnetic field, the charged winding of the core is coupled by the parasitic capacitance, and a suspended potential is generated to the ground. If the suspended potential is too high, it will break through the insulation layer between the components of the transformer, causing partial discharge, causing damage to the transformer, and threatening the personal safety of on-site personnel. In order to eliminate the influence of the suspended potential, the transformer core is generally grounded through the shell to make it equal to the earth potential, but only one point of grounding is allowed. If two or more points are grounded at the same time, a current loop will be formed between the core and the earth, generating a circulating current, and the maximum current can reach tens of amperes. The hazards caused by multi-point grounding of the core are mainly: 1) Increased core loss, local overheating of the core, and even burnout; 2) The temperature rise caused by overheating will cause the transformer oil to decompose, and the generated gas will dissolve in the oil, which may cause the performance of the insulating oil to deteriorate; the gas in the oil continues to increase and precipitate, which may cause the gas relay to operate and the transformer to trip. Therefore, early detection and treatment of core grounding problems are of great significance to the safe operation of the system.

[0004] For a long time, the normal operation maintenance of transformers in power systems mainly adopts two methods: post-maintenance and preventive maintenance. However, preventive maintenance requires power outages for maintenance, which affects the reliability of power supply; some of the equipment replaced during regular maintenance is unnecessary, which reduces the economic efficiency. Therefore, conventional detection methods are not compatible with the development trend of modern condition maintenance. In order to ensure the reliability and economy of power supply in the power system, online monitoring and fault diagnosis of power equipment came into being. Summary of the invention

[0005] In order to solve the technical problems existing in the above-mentioned background technology, the present invention provides an early warning system for heating defects of large power transformers, the system comprising a leakage current acquisition device, a serial port networking server, a router and a background monitoring center; the leakage current acquisition device, the serial port networking server, the router and the background monitoring center are sequentially connected in communication; wherein,

[0006] The leakage current acquisition device is used to monitor the leakage current of the iron core and the clamp, and to perform data processing, fault analysis, display and upload of the leakage current;

[0007] The serial port networking server and the router are used to transmit the leakage current and fault analysis results to the system server;

[0008] The background monitoring center is used to receive the data uploaded by the leakage current acquisition device and provide alarm, historical data query, trend analysis, and report printing functions.

[0009] Preferably, the leakage current collection equipment includes a leakage current sensor, a data collection cabinet, and a collection cabinet display instrument; the leakage current sensor is installed on the ground bus of the transformer core and the clamp to detect the leakage current of the core and the clamp; the data collection cabinet converts the analog signal collected by the leakage current sensor into a digital signal and displays it on the collection cabinet display instrument, and transmits the leakage current and fault analysis results to the serial port network server and the router.

[0010] Preferably, the serial port networking server provides a TCP / UDP socket working mode including a first server and a client, and each serial port networking server has two RS-485 ports, so that each serial port device occupies a serial port separately to avoid mutual interference in data transmission.

[0011] Preferably, the background monitoring center is composed of a second server and management software; wherein the management software receives all data collected by the leakage current collection device and provides alarm, historical data query, trend analysis, and report printing functions.

[0012] Preferably, the leakage current sensor adopts an active zero-flux design principle.

[0013] Preferably, the leakage current sensor is connected to the data acquisition cabinet via a shielded double-stripe wire.

[0014] Preferably, the data acquisition cabinet uses TI chips to receive, process, analyze faults, display and upload sensor data.

[0015] Preferably, the data acquisition cabinet further comprises a current limiting system, which limits excessive grounding current when monitoring the grounding current of the core or the clamp.

[0016] This application has the function of limiting the excessive grounding current while monitoring the grounding current of the core or the clamp, which can discover the early fault hazards of the main transformer and play an important role in preventing accidents. At the same time, the current limiting system can slow down the development of accident hazards and buy time for maintenance. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.

[0018] Figure 1 It is a structural schematic diagram of an early warning system for heating defects of a large power transformer disclosed in an embodiment of the present invention;

[0019] Figure 2 It is a structural schematic diagram of a leakage current acquisition device disclosed in an embodiment of the present invention;

[0020] Figure 3 It is a schematic diagram of the structure of the serial port networking server disclosed in an embodiment of the present invention;

[0021] Figure 4 It is a structural diagram of the background monitoring center disclosed in the embodiment of the present invention. DETAILED DESCRIPTION

[0022] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0023] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0024] In the description of the present invention, it should be noted that if the terms "upper", "lower", "inside", "outside", etc. appear to indicate an orientation or position relationship, they are based on the orientation or position relationship shown in the accompanying drawings, or are the orientation or position relationship in which the product of the invention is usually placed when used. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0025] In addition, the terms “first”, “second”, etc., if used, are merely used to distinguish between the descriptions and should not be understood as indicating or implying relative importance.

[0026] See also Figure 1 The embodiment of the present invention discloses an early warning system for heating defects of large power transformers, the system comprising a leakage current acquisition device, a serial port networking server, a router and a background monitoring center; the leakage current acquisition device, the serial port networking server, the router and the background monitoring center are sequentially connected in communication; wherein,

[0027] The leakage current acquisition device is used to monitor the leakage current of the iron core and the clamp, and to perform data processing, fault analysis, display and upload of the leakage current;

[0028] The serial port networking server and the router are used to transmit the leakage current and fault analysis results to the system server;

[0029] The background monitoring center is used to receive the data uploaded by the leakage current acquisition device and provide multiple functions such as alarm, historical data query, trend analysis, report printing, etc.

[0030] Preferably, see Figure 2 The leakage current collection device includes a leakage current sensor, a data collection cabinet, and a collection cabinet display instrument; the leakage current sensor is installed on the ground bar of the transformer core and the clamp to detect the leakage current of the core and the clamp; the data collection cabinet converts the analog signal collected by the leakage current sensor into a digital signal and displays it on the collection cabinet display instrument, and transmits the leakage current and fault analysis results to the serial port networking server and the router.

[0031] Among them, the leakage current sensor adopts the fixing method of clamping copper busbar without destroying any structure of the original system, and the use of metal mold greatly reduces the influence of external magnetic field on the leakage current collection accuracy.

[0032] Preferably, see Figure 3 The serial port networking server provides a TCP / UDP socket working mode including a first server and a client. Each serial port networking server has two RS-485 ports, so that each serial port device occupies a serial port separately to avoid mutual interference in data transmission.

[0033] Preferably, see Figure 4 The background monitoring center is composed of a second server and management software; wherein the management software receives all data collected by the leakage current acquisition device and provides multiple functions such as alarm, historical data query, trend analysis, report printing, etc.

[0034] Preferably, the leakage current sensor adopts an active zero-flux design principle.

[0035] Preferably, the data acquisition cabinet further comprises a current limiting system, which limits excessive grounding current when monitoring the grounding current of the core or the clamp.

[0036] The system of the present invention not only monitors the grounding current of the core or the clamp, but also has the function of limiting the excessive grounding current. The current limiting system can slow down the development of potential accidents and gain time for maintenance.

[0037] Due to the temperature drift defect of traditional sensors, if they are not calibrated after a normal period of use, an error of the same order as the actual leakage current will be generated, which reduces the measurement accuracy and is not conducive to long-term measurement in a strong electromagnetic environment. The leakage current sensor adopts the active zero flux design principle, which can not only meet the collection of mA-level current signals, but also has strong anti-interference ability and can suppress temperature drift. Based on the above considerations, the leakage current sensor used in the present invention adopts the principle of zero flux compensation and is manufactured by a German professional small signal sensor manufacturer. Its accuracy can reach the microampere level and has extremely strong anti-interference ability.

[0038] Preferably, the leakage current sensor is connected to the data acquisition cabinet via a shielded double-stripe wire.

[0039] One end of the shielded double-stripe wire for data transmission is connected to the data acquisition cabinet, and the other end is connected to the sensor body. The shielded double-stripe wire for data transmission has strong anti-interference ability and can transmit up to 2km, covering the entire substation.

[0040] Preferably, the data acquisition cabinet uses TI chips to receive, process, analyze faults, display and upload sensor data.

[0041] TI chips refer to semiconductor products produced by Texas Instruments (TI), such as the C2000, C5000, and C6000 series for high-speed digital signal processing.

[0042] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed by the present invention should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. An early warning system for heating defects in large power transformers, Features: The system includes a leakage current acquisition device, a serial port networking server, a router and a background monitoring center; the leakage current acquisition device, the serial port networking server, the router and the background monitoring center are sequentially connected in communication; wherein, The leakage current acquisition device is used to monitor the leakage current of the iron core and the clamp, and to perform data processing, fault analysis, display and upload of the leakage current; The serial port networking server and the router are used to transmit the leakage current and fault analysis results to the system server; The background monitoring center is used to receive the data uploaded by the leakage current acquisition device and provide alarm, historical data query, trend analysis, and report printing functions.

2. According to claim 1, an early warning system for heating defects of large power transformers, Features: The leakage current collection equipment includes a leakage current sensor, a data collection cabinet, and a collection cabinet display instrument; the leakage current sensor is installed on the ground bar of the transformer core and the clamp to detect the leakage current of the core and the clamp; the data collection cabinet converts the analog signal collected by the leakage current sensor into a digital signal and displays it on the collection cabinet display instrument, and transmits the leakage current and fault analysis results to the serial port networking server and the router.

3. According to claim 2, an early warning system for heating defects of large power transformers, Features: The serial port networking server provides a TCP / UDP socket working mode including a first server and a client. Each serial port networking server has two RS-485 ports, so that each serial port device occupies a serial port separately to avoid mutual interference in data transmission.

4. According to claim 3, an early warning system for heating defects of large power transformers, Features: The background monitoring center is composed of a second server and management software; wherein the management software receives all data collected by the leakage current collection device and provides alarm, historical data query, trend analysis, and report printing functions.

5. An early warning system for heating defects of large power transformers according to claim 4, Features: The leakage current sensor adopts an active zero-flux design principle.

6. The early warning system for heating defects of a large power transformer according to claim 2, Features: The leakage current sensor is connected to the data acquisition cabinet via a shielded double-stripe wire.

7. The early warning system for heating defects of a large power transformer according to claim 6, Features: The data acquisition cabinet uses TI chips to receive, process, analyze, display and upload sensor data.

8. The early warning system for heating defects of a large power transformer according to claim 7, Features: The data acquisition cabinet adopts TI chip to receive sensor data, process data, and analyze faults. The data acquisition cabinet also includes a current limiting system, which limits the excessive grounding current when monitoring the grounding current of the iron core or the clamp.

Citation Information

Patent Citations

  • Device and method for monitoring leakage current of transformer

    CN117214521A

  • Online monitoring system for iron core grounding current

    CN203479895U

  • On-line monitoring device for grounding current of transformer core

    CN203606415U