By installing overlapping ribs and prestressed steel wires embedded in the prefabricated and cast-in-place layer in the prestressed overlapping floor slab, ensuring that the overlapping ribs bear loads throughout the floor slab, solving the problem of idle and waste of some materials on the overlapping ribs. , improves material utilization and arch resistance.

CN119083645AInactive Publication Date: 2024-12-06SHANGHAI XINGBANG CONSTR TECH CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411209198.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-30
Publication Date
2024-12-06
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Some of the materials on the laminated ribs of the existing prestressed superposition floor slabs are idle and wasted and not fully utilized, resulting in low material utilization.

Method used

A prestressed overlapping floor slab was designed. By setting up multiple prestressed steel wires and multiple overlapping ribs between the concrete prefabricated layer and the cast-in-place layer, the overlapping ribs include the truss upper chord rod and the curved structure, and the lower part of the curved structure is embedded. It is provided in the prefabricated layer and the upper part is embedded in the cast-in-place layer to ensure that it bears loads throughout the floor slab.

Benefits of technology

It effectively improves the material utilization rate of the laminated ribs, avoids idle waste, and enhances the anti-arching performance of the floor slabs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083645A_ABST
    Figure CN119083645A_ABST
Patent Text Reader

Abstract

The invention provides a prestressed composite floor slab. The prestressed composite floor slab comprises a concrete prefabricated layer, a concrete cast-in-place layer, a plurality of prestressed steel wires and a plurality of first composite ribs. And the prestressed steel wires are arranged at intervals and are embedded in the concrete prefabricated layer. The first laminated ribs are arranged at intervals, each first laminated rib comprises a first truss upper chord member and a first bending structure, the first truss upper chord members are connected with the top ends of the first bending structures, and the lower portions of the first bending structures are embedded in the concrete prefabricated layer. The upper portion of each first bending structure is embedded in the concrete cast-in-place layer, each first truss upper chord is embedded in the concrete cast-in-place layer, and the concrete cast-in-place layer is connected with the concrete prefabricated layer. The prestressed composite floor slab solves the problems that composite ribs of an existing prestressed composite floor slab are not fully utilized, and materials on the upper portions of the composite ribs are left unused and wasted.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of building construction, and in particular to a prestressed composite floor slab. Background Art

[0002] Prestressed composite slab is a kind of slab that combines precast concrete slab and cast-in-place concrete slab. By applying prestress to the steel bars, compressive stress is generated in the concrete before it bears the load, thereby improving the bearing capacity and crack resistance of the prestressed composite slab.

[0003] The precast concrete slab is provided with overlapping reinforcement, and the lower part of the overlapping reinforcement is embedded in the precast concrete slab to provide rigidity to the precast concrete slab during the demoulding and hoisting process of the precast concrete slab to prevent the precast concrete slab from cracking. The upper part of the overlapping reinforcement does not bear the load in the subsequent pouring of the cast-in-place concrete slab, resulting in the upper part of the overlapping reinforcement being idle and wasted. Therefore, the overlapping reinforcement of the existing prestressed composite slab is not fully utilized, and there is a problem that part of the material on the overlapping reinforcement is idle and wasted. Summary of the invention

[0004] The purpose of the present application is to provide a prestressed composite floor slab that improves the utilization rate of composite reinforcement materials, including a precast concrete layer, a cast-in-place concrete layer, a plurality of prestressed steel wires and a plurality of first composite reinforcements. Each of the prestressed steel wires is arranged at intervals from each other, and each of the prestressed steel wires is buried in the precast concrete layer. Each of the first composite reinforcements is arranged at intervals from each other, and each of the first composite reinforcements includes a first truss upper chord and a first curved structure, the first truss upper chord is connected to the top of the first curved structure, and the lower part of each of the first curved structures is embedded in the precast concrete layer. The upper part of each of the first curved structures is embedded in the cast-in-place concrete layer, and each of the first truss upper chords is embedded in the cast-in-place concrete layer, and the cast-in-place concrete layer and the precast concrete layer are connected.

[0005] Optionally, the first bending structure includes multiple first bending units, the top ends of each of the first bending units are connected in sequence, the first truss upper chord is connected to the top end of each of the first bending units, the upper part of each of the first bending units is embedded in the cast-in-place concrete layer, and the lower part of each of the first bending units is embedded in the precast concrete layer.

[0006] Optionally, the first curved structure is in the shape of a curved rod, and a plane passing through a central axis of the first curved structure on the first laminated reinforcement and a central axis of the first truss upper chord is perpendicular to the precast concrete layer.

[0007] Optionally, the prestressed composite floor slab further includes structural steel bars, wherein the first composite bars are arranged parallel to each other and aligned, the structural steel bars are passed through the bottom of the first bending units at the same position of the first composite bars, and the structural steel bars are connected to the first bending units at the same position of the first composite bars.

[0008] Optionally, the prestressed composite floor also includes a plurality of second composite bars, which are arranged spaced apart from each other, the arrangement direction of the first composite bars is different from the arrangement direction of the second composite bars, the second composite bars are connected to the first composite bars, the upper part of each second composite bar is embedded in the cast-in-place concrete layer, and the lower part of each second composite bar is embedded in the precast concrete layer.

[0009] Optionally, an arrangement direction of the first stacking ribs and an arrangement direction of the second stacking ribs are perpendicular to each other, and each of the first stacking ribs are parallel to each other and aligned.

[0010] Optionally, each of the second composite reinforcements includes a second truss upper chord and a second curved structure, the second truss upper chord is connected to the top of the second curved structure, the upper part of the second curved structure is embedded in the cast-in-place concrete layer, the lower part of the second curved structure is embedded in the prefabricated concrete layer, the second truss upper chord is embedded in the cast-in-place concrete layer, and the second truss upper chord is connected to the first composite reinforcement.

[0011] Optionally, the second bending structure includes multiple second bending units, the top ends of each second bending unit are connected in sequence, the second truss upper chord is connected to the top end of each second bending unit, the upper part of each second bending unit is embedded in the cast-in-place concrete layer, and the lower part of each second bending unit is embedded in the precast concrete layer.

[0012] Optionally, the second curved structure is in the shape of a curved rod, and a plane passing through a central axis of the second curved structure on the second laminated reinforcement and a central axis of the second truss upper chord is perpendicular to the precast concrete layer.

[0013] Optionally, each of the first stacking bars are parallel and aligned with each other, the second truss upper chord is passed through the top of the first bending unit at the same position of each of the first stacking bars, and the second truss upper chord is connected to the top of the first bending unit at the same position of each of the first stacking bars.

[0014] The beneficial effects of the present application are as follows: by setting a precast concrete layer, a cast-in-place concrete layer, a plurality of prestressed steel wires and a plurality of first superimposed bars. The prestressed steel wires are arranged at intervals from each other, and the prestressed steel wires are buried in the precast concrete layer. The first superimposed bars are arranged at intervals from each other, and the first superimposed bars include a first truss upper chord and a first curved structure, the first truss upper chord is connected to the top of the first curved structure, and the lower part of each first curved structure is embedded in the precast concrete layer. The upper part of each first curved structure is embedded in the cast-in-place concrete layer, and the first truss upper chord is embedded in the cast-in-place concrete layer, and the cast-in-place concrete layer and the precast concrete layer are connected.

[0015] Since the lower part of each first curved structure is embedded in the prefabricated concrete layer, the upper part of each first curved structure is embedded in the cast-in-place concrete layer, and the upper chord of each first truss is embedded in the cast-in-place concrete layer, all parts of the upper chord of the first truss and the first curved structure can bear the load in the prestressed composite floor slab, so that the upper chord of the first truss can be used as the upper steel bar of the cast-in-place concrete layer, and the upper chord of the first truss and the first curved structure can be utilized, thereby improving the material utilization rate of the first composite reinforcement and avoiding the idle waste of the upper chord of the first truss.

[0016] The above description is only an overview of the technical solution of the present application. In order to more clearly understand the technical means of the present application and implement it according to the contents of the specification, the present application is described in detail below with reference to the preferred embodiments of the present application and the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a front view, a partial cross-sectional view and an enlarged partial cross-sectional view of a prestressed composite floor slab in one embodiment of the present application;

[0018] Figure 2 is a three-dimensional diagram of a prestressed composite floor slab in one embodiment of the present application (the cast-in-place concrete layer is omitted, each first composite reinforcement is marked in purple, and each second composite reinforcement is marked in red);

[0019] Figure 3 It is a top view of a prestressed composite floor slab in one embodiment of the present application (the cast-in-place concrete layer and the second composite reinforcement are omitted);

[0020] Figure 4 It is a front view and a partial enlarged view of a first laminated rib in one embodiment of the present application;

[0021] Figure 5 It is a three-dimensional diagram of a prestressed composite floor slab in one embodiment of the present application (the cast-in-place concrete layer and the precast concrete layer are omitted, each first composite reinforcement is marked in purple, each second composite reinforcement is marked in red, and each structural reinforcement is marked in green);

[0022] Figure 6 It is a front view and a partially enlarged view of the second laminated rib in one embodiment of the present application.

[0023] Wherein, the reference numerals are:

[0024] 1 Precast concrete layer

[0025] 2 Cast-in-place concrete layer

[0026] 3 Prestressed steel wire

[0027] 4. The first laminated reinforcement

[0028] 40 First truss upper chord

[0029] 41 First bending structure

[0030] 410 First bending unit

[0031] 4100 First Truss Web

[0032] 4101 Second truss web

[0033] 5 Structural reinforcement

[0034] 6 Second laminated reinforcement

[0035] 60 Second truss upper chord

[0036] 61 Second bending structure

[0037] 610 Second bending unit

[0038] 6100 Third Truss Web

[0039] 6101 Fourth truss web DETAILED DESCRIPTION

[0040] The following is an explanation of the implementation of the present application by means of specific embodiments. People familiar with the technology can easily understand other advantages and effects of the present application from the contents disclosed in this specification.

[0041] It should be noted that, in the absence of conflict, the embodiments in the present application and the features in the embodiments can be combined with each other. The present application will be described in detail below with reference to the drawings and in combination with the embodiments. In order to enable those skilled in the art to better understand the present application scheme, the technical scheme in the embodiments of the present application will be clearly and completely described below in combination with the drawings in the embodiments of the present application. Obviously, the described embodiments are only embodiments of a part of the present application, not all embodiments. Based on the embodiments of the present application, all other embodiments obtained by ordinary technicians in the field without making creative work should fall within the scope of protection of the present application.

[0042] It should be noted that the terms "first", "second", etc. in the specification and claims of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0043] It should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, or it can be the internal connection of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0044] For the convenience of explanation, a rectangular coordinate system O-XYZ is set in some drawings. The X-axis of the coordinate system is parallel to the length direction of the first laminated reinforcement 4, the Y-axis of the coordinate system is parallel to the length direction of the second laminated reinforcement 6, and the Z-axis of the coordinate system is parallel to the thickness direction of the precast concrete layer 1 and the cast-in-place concrete layer 2. The positive direction of the X-axis, the positive direction of the Y-axis, and the positive direction of the Z-axis remain the same in each drawing with a coordinate system.

[0045] Please also refer to Figures 1 to 3 In this embodiment, a prestressed composite floor slab is provided, including a precast concrete layer 1, a cast-in-place concrete layer 2, a plurality of prestressed steel wires 3, and a plurality of first composite bars 4. The prestressed steel wires 3 are arranged at intervals from each other, and the prestressed steel wires 3 are buried in the precast concrete layer 1. The first composite bars 4 are arranged at intervals from each other, and the first composite bars 4 include a first truss upper chord 40 and a first curved structure 41, the first truss upper chord 40 and the top of the first curved structure 41 are connected, and the lower part of each first curved structure 41 is embedded in the precast concrete layer 1. The upper part of each first curved structure 41 is embedded in the cast-in-place concrete layer 2, and the first truss upper chord 40 is embedded in the cast-in-place concrete layer 2, and the cast-in-place concrete layer 2 and the precast concrete layer 1 are connected.

[0046] like Figure 1As shown, since the lower part of each first curved structure 41 is embedded in the precast concrete layer 1, the upper part of each first curved structure 41 is embedded in the cast-in-place concrete layer 2, and each first truss upper chord 40 is embedded in the cast-in-place concrete layer 2, the first truss upper chord 40 and the first curved structure 41 can bear the load in the prestressed composite floor, so that the first truss upper chord 40 can be used as the upper steel bar of the cast-in-place concrete layer 2, and all parts of the first truss upper chord 40 and the first curved structure 41 can be used, which improves the material utilization rate of the first composite reinforcement 4 and avoids the idle waste of the first truss upper chord 40. At the same time, the use of the first composite reinforcement 4 with the first curved structure 41 can also prevent the prestressed composite floor from arching.

[0047] Please also refer to Figure 1 and Figure 2 The precast concrete layer 1 can be cast with concrete in advance at the construction site, and the lower parts of each prestressed steel wire 3 and each first laminated bar 4 can be covered by the concrete of the cast precast concrete layer 1. After the casting of the precast concrete layer 1 is completed, it can be hoisted to the building together with the first laminated bar 4 and the second laminated bar 6 by a crane. After the precast concrete layer 1 is hoisted into place, the layer formed by pouring concrete on the precast concrete layer 1 on site is the cast-in-place concrete layer 2. The length directions of each first laminated bar 4 can be parallel to each other. The prestressed steel wires 3 can be parallel to each other and parallel to the X-axis. The top of the first truss upper chord 40 and the first curved structure 41 can be connected by wire tying or welding.

[0048] Please also refer to Figure 1 and Figure 4 Optionally, the first bending structure 41 includes a plurality of first bending units 410, the top ends of the first bending units 410 are connected in sequence, the first truss upper chord 40 is connected to the top ends of the first bending units 410, the upper portion of each first bending unit 410 is embedded in the concrete cast-in-place layer 2, and the lower portion of each first bending unit 410 is embedded in the concrete precast layer 1. The first bending units 410 can be connected by welding or integral molding. The shapes and sizes of the first bending units 410 can be the same. The first bending units 410 can be V-shaped. The first truss upper chord 40 and the top ends of the first bending units 410 can be connected by wire bundling or welding.

[0049] Please also refer to Figure 1 and Figure 4, each first bending unit 410 can be formed by a first truss web 4100 and a second truss web 4101. The bottom end of the first truss web 4100 and the bottom end of the second truss web 4101 of the same first bending unit 410 can be connected by welding or integral molding. The top of the first truss web 4100 and the top of the second truss web 4101 of the adjacent first bending units 410 can be connected by welding or integral molding. The first truss upper chord 40 and the top of each first truss web 4100 and the top of each second truss web 4101 can be connected by welding or wire binding. The upper part of each first truss web 4100 and the upper part of each second truss web 4101 can be embedded in the concrete cast-in-place layer 2, and the lower part of each first truss web 4100 and the lower part of each second truss web 4101 can be embedded in the concrete precast layer 1.

[0050] Please also refer to Figure 1 and Figure 4 Optionally, the first curved structure 41 is in the shape of a curved rod, and the plane passing through the central axis of the first curved structure 41 on the first superimposed reinforcement 4 and the central axis of the first truss upper chord 40 is perpendicular to the precast concrete layer 1. In this way, when multiple first superimposed reinforcements 4 are arranged, adjacent first superimposed reinforcements 4 can be arranged more densely without interfering with each other, and more rows of first superimposed reinforcements 4 can be arranged to increase the stiffness of the precast concrete layer 1 and the cast-in-place concrete layer 2. For each first superimposed reinforcement 4, the plane passing through the central axis of the first curved structure 41 on the first superimposed reinforcement 4 and the central axis of the first truss upper chord 40 can be parallel to the XOZ plane. The first curved structure 41 can be in the shape of a wavy rod.

[0051] Please also refer to Figure 1 , Figure 4 and Figure 5 Optionally, the prestressed composite floor slab further includes structural reinforcement 5, each first composite reinforcement 4 is parallel and aligned with each other, the structural reinforcement 5 is passed through the bottom of the first bending unit 410 at the same position of each first composite reinforcement 4, and the structural reinforcement 5 is connected to the first bending unit 410 at the same position of each first composite reinforcement 4. The structural reinforcement 5 is passed through the bottom of the first bending unit 410 at the same position of each first composite reinforcement 4, and the first bending unit 410 at the same position of each first composite reinforcement 4 can be used to locate the structural reinforcement 5, so as to facilitate the connection between the structural reinforcement 5 and the first bending unit 410. The structural reinforcement 5 can be embedded in the precast concrete layer 1.

[0052] Please also refer to Figure 4 and Figure 5For example, when the first composite reinforcements 4 are aligned and arranged parallel to each other, the rightmost structural reinforcement 5 can be passed through the bottom of each second first curved unit 410 from the right side of each first curved structure 41 (each first first curved unit 410 from the right side of each first curved structure 41 only shows the first truss web 4100).

[0053] Please also refer to Figure 1 and Figure 2 Optionally, the prestressed composite floor further comprises a plurality of second composite bars 6, the plurality of second composite bars 6 are arranged at intervals from each other, the arrangement direction of the first composite bars 4 is different from the arrangement direction of the second composite bars 6, the second composite bars 6 are connected to the first composite bars 4, the upper part of each second composite bar 6 is embedded in the cast-in-place concrete layer 2, and the lower part of each second composite bar 6 is embedded in the precast concrete layer 1. The arrangement direction of the first composite bars 4 is different from the arrangement direction of the second composite bars 6, so that the first composite bars 4 and the second composite bars 6 can prevent the prestressed composite floor from arching in different directions (for example, in the direction parallel to the X-axis and the direction parallel to the Y-axis). The length directions of each second composite bar 6 can be parallel to each other.

[0054] like Figure 2 As shown, the arrangement direction of the first laminated ribs 4 may be parallel to the Y axis, and the arrangement direction of the second laminated ribs 6 may be parallel to the X axis. The second laminated ribs 6 and the first laminated ribs 4 may be connected by wire bundling or welding.

[0055] Please also refer to Figure 4 and Figure 5 Optionally, the arrangement direction of the first stacking ribs 4 and the arrangement direction of the second stacking ribs 6 are perpendicular to each other, and the first stacking ribs 4 are parallel to each other and aligned. This arrangement can facilitate the second stacking ribs 6 in each row to pass through the first bending units 410 at the same position of each first stacking rib 4. Because the first stacking ribs 4 are parallel to each other and aligned, the first bending units 410 at the same position of each first stacking rib 4 are aligned. At this time, the arrangement direction of the first stacking ribs 4 and the arrangement direction of the second stacking ribs 6 are perpendicular, so the second stacking ribs 6 can just pass through the first bending units 410 at the same position of each first stacking rib 4.

[0056] Please also refer to Figure 1 and Figure 6 Optionally, each second composite reinforcement 6 includes a second truss upper chord 60 and a second curved structure 61, the second truss upper chord 60 and the second curved structure 61 are connected at the top, the upper part of the second curved structure 61 is embedded in the cast-in-place concrete layer 2, the lower part of the second curved structure 61 is embedded in the precast concrete layer 1, the second truss upper chord 60 is embedded in the cast-in-place concrete layer 2, and the second truss upper chord 60 is connected to the first composite reinforcement 4.

[0057] Please also refer to Figure 1 and Figure 6 Since the lower part of each second curved structure 61 is embedded in the precast concrete layer 1, the upper part of each second curved structure 61 is embedded in the cast-in-place concrete layer 2, and each second truss upper chord 60 is embedded in the cast-in-place concrete layer 2, the second truss upper chord 60 and the second curved structure 61 can bear the load in the prestressed composite floor slab, so that the second truss upper chord 60 can also be used as the upper reinforcement of the cast-in-place concrete layer 2. All parts of the second truss upper chord 60 and the second curved structure 61 can be used, which improves the material utilization rate of the second composite reinforcement 6 and avoids the idle waste of the second truss upper chord 60.

[0058] Please also refer to Figure 1 , Figure 4 and Figure 6 , the top of the second truss upper chord 60 and the second curved structure 61 can be connected by wire tying or welding. The second truss upper chord 60 and the first laminated bar 4 can be connected by wire tying or welding. The upper part of the first curved structure 41, the upper part of the second curved structure 61, the first truss upper chord 40 and the second truss upper chord 60 can be embedded in the concrete cast-in-place layer 2, and the lower part of the first curved structure 41 and the lower part of the second curved structure 61 can be embedded in the precast concrete layer 1, so that the first laminated bar 4 and the second laminated bar 6 can be buried in the precast concrete layer 1 and the cast-in-place concrete layer 2, and then the concrete can be used to prevent the first laminated bar 4 and the second laminated bar 6 from rusting. The prestressed steel wire 3 and each first laminated bar 4 are arranged at intervals. The prestressed steel wire 3 and each second laminated bar 6 are arranged at intervals. The material of the first laminated bar 4 and the second laminated bar 6 can be steel.

[0059] Please also refer to Figure 1 , Figure 4 and Figure 6 Optionally, the second bending structure 61 includes a plurality of second bending units 610, the top ends of the second bending units 610 are connected in sequence, the second truss upper chord 60 is connected to the top ends of the second bending units 610, the upper portion of each second bending unit 610 is embedded in the concrete cast-in-place layer 2, and the lower portion of each second bending unit 610 is embedded in the concrete precast layer 1. The second bending units 610 can be connected by welding or integral molding. The shapes and sizes of the second bending units 610 can be the same. The second bending unit 610 can be V-shaped. The shape and size of the second bending unit 610 can be the same as the shape and size of the first bending unit 410. The second truss upper chord 60 and the top ends of the second bending units 610 can be connected by wire bundling or welding.

[0060] Please also refer to Figure 1 and Figure 6, each second bending unit 610 can be formed by a third truss web 6100 and a fourth truss web 6101. The bottom end of the third truss web 6100 and the bottom end of the fourth truss web 6101 of the same second bending unit 610 can be connected by welding or integral molding. The top of the third truss web 6100 and the top of the fourth truss web 6101 of the adjacent second bending units 610 can be connected by welding or integral molding. The second truss upper chord 60 and the top of each third truss web 6100 and the top of each fourth truss web 6101 can be connected by welding or wire binding. The upper part of each third truss web 6100 and the upper part of each fourth truss web 6101 are embedded in the concrete cast-in-place layer 2, and the lower part of each third truss web 6100 and the lower part of each third truss web 6100 are embedded in the concrete precast layer 1.

[0061] Please also refer to Figure 1 and Figure 6 Optionally, the second curved structure 61 is in the shape of a curved rod, and the plane passing through the central axis of the second curved structure 61 on the second laminated bar 6 and the central axis of the second truss upper chord 60 is perpendicular to the precast concrete layer 1. In this way, when multiple second laminated bars 6 are arranged, adjacent second laminated bars 6 can be arranged more densely without interfering with each other, and more rows of second laminated bars 6 can be arranged to increase the rigidity of the precast concrete layer 1 and the cast-in-place concrete layer 2. For each second laminated bar 6, the plane passing through the central axis of the second curved structure 61 on the second laminated bar 6 and the central axis of the second truss upper chord 60 can be parallel to the YOZ plane. The second curved structure 61 can be in the shape of a wavy rod.

[0062] Please also refer to Figure 4 , Figure 5 and Figure 6 Optionally, each first laminated rib 4 is parallel to each other and aligned, and the second truss upper chord 60 is passed through the top of the first bending unit 410 at the same position of each first laminated rib 4, and the second truss upper chord 60 is connected to the top of the first bending unit 410 at the same position of each first laminated rib 4. In this way, the first bending unit 410 can be used to position the second truss upper chord 60, so that the second truss upper chord 60 and the first bending unit 410 are conveniently connected.

[0063] Please also refer to Figure 4 , Figure 5 and Figure 6, since the top ends of adjacent first bending units 410 can be connected to form a bending portion, the second truss upper chord 60 can be positioned by the bending portion. The second truss upper chord 60 and the top ends of the first bending units 410 at the same position of each first laminated rib 4 can be connected by wire tying or welding. When the first laminated ribs 4 are aligned and arranged parallel to each other, the rightmost second truss upper chord 60 can be passed through the lower part of the connection (i.e., the bending portion) of each second first bending unit 410 from the right side of each first bending structure 41 and the corresponding third first bending unit 410 (only the first truss web 4100 is shown for each first first bending unit 410 from the right side of each first bending structure 41).

[0064] The above is a detailed introduction to the prestressed composite floor provided by the embodiment of the present application. For those skilled in the art, according to the idea of ​​the embodiment of the present application, there will be some changes in the specific implementation method and application scope. In summary, the content of this specification should not be understood as a limitation to the present application, and all equivalent modifications or changes made according to the spirit and technical ideas of the present application should still be covered by the claims of the present application.

Claims

1. A prestressed composite floor slab, characterized in that: include: Precast concrete layer; A plurality of prestressed steel wires, each of which is arranged apart from each other and each of which is buried in the precast concrete layer; A plurality of first laminated bars, each of which is arranged apart from each other, each of which comprises a first truss upper chord and a first curved structure, the first truss upper chord is connected to the top of the first curved structure, and the bottom of each of the first curved structures is embedded in the precast concrete layer; as well as A cast-in-place concrete layer, the upper portion of each of the first curved structures is embedded in the cast-in-place concrete layer, each of the first truss upper chords is embedded in the cast-in-place concrete layer, and the cast-in-place concrete layer is connected to the prefabricated concrete layer.

2. The prestressed composite floor slab according to claim 1, characterized in that: The first bending structure includes multiple first bending units, the top ends of each of the first bending units are connected in sequence, the first truss upper chord is connected to the top end of each of the first bending units, the upper part of each of the first bending units is embedded in the cast-in-place concrete layer, and the lower part of each of the first bending units is embedded in the precast concrete layer.

3. The prestressed composite floor slab according to claim 2, characterized in that: The first curved structure is in the shape of a curved rod, and a plane passing through the central axis of the first curved structure on the first overlapped reinforcement and the central axis of the first truss upper chord is perpendicular to the precast concrete layer.

4. The prestressed composite floor slab according to claim 2, characterized in that: It also includes structural steel bars, wherein the first composite bars are arranged parallel to each other and aligned, the structural steel bars are passed through the bottom of the first bending units at the same position of the first composite bars, and the structural steel bars are connected to the first bending units at the same position of the first composite bars.

5. The prestressed composite floor slab according to claim 2, characterized in that: It also includes a plurality of second overlapping bars, which are arranged at intervals from each other, the arrangement direction of the first overlapping bars is different from the arrangement direction of the second overlapping bars, the second overlapping bars are connected to the first overlapping bars, the upper part of each of the second overlapping bars is embedded in the cast-in-place concrete layer, and the lower part of each of the second overlapping bars is embedded in the precast concrete layer.

6. The prestressed composite floor slab according to claim 5, characterized in that: The arrangement direction of the first overlapping ribs and the arrangement direction of the second overlapping ribs are perpendicular to each other, and the first overlapping ribs are parallel to each other and aligned.

7. The prestressed composite floor slab according to claim 5, characterized in that: Each of the second composite reinforcements includes a second truss upper chord and a second curved structure, the second truss upper chord is connected to the top of the second curved structure, the upper part of the second curved structure is embedded in the cast-in-place concrete layer, the lower part of the second curved structure is embedded in the prefabricated concrete layer, the second truss upper chord is embedded in the cast-in-place concrete layer, and the second truss upper chord is connected to the first composite reinforcement.

8. The prestressed composite floor slab according to claim 7, characterized in that: The second curved structure includes a plurality of second curved units, the top ends of the respective second curved units are connected in sequence, the second truss upper chord is connected to the top ends of the respective second curved units, the upper portion of the respective second curved units is embedded in the cast-in-place concrete layer, and the lower portion of the respective second curved units is embedded in the precast concrete layer.

9. The prestressed composite floor slab according to claim 7, characterized in that: The second curved structure is in the shape of a curved rod, and a plane passing through the central axis of the second curved structure on the second overlapped reinforcement and the central axis of the second truss upper chord is perpendicular to the precast concrete layer.

10. The prestressed composite floor slab according to claim 7, characterized in that: The first stacking bars are parallel and aligned with each other, the second truss upper chord is passed through the top of the first bending unit at the same position of the first stacking bars, and the second truss upper chord is connected to the top of the first bending unit at the same position of the first stacking bars.

Citation Information

Patent Citations

  • Prefabricated concrete bottom plate integrated with truss steel bars and prestressed steel wire meshes

    CN114059699A

  • Production process of concrete composite floor slab with bidirectional steel bar trusses

    CN115519666A

  • Steel bar truss prestressed concrete superimposed sheet

    CN201013040Y

  • Large-width prestressed steel bar truss composite floor slab

    CN220565524U

  • A manufacturing process for the truss half precast prestressed concrete panel

    KR1020090040040A