A device and method for monitoring rebound deformation during the entire foundation pit excavation process

By designing a rebound deformation monitoring device for the entire foundation pit excavation process, and using a magnetic ring fixing device and an electronic warehouse combined with a precision level, the problem of the existing technology being unable to monitor the rebound deformation of the foundation pit soil layer throughout the entire process has been solved, achieving high-precision monitoring data collection and engineering safety assurance.

CN119121886BActive Publication Date: 2025-09-30陕西建工集团股份有限公司 +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202411519532.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-10-29
Publication Date
2025-09-30
Estimated Expiration
2044-10-29

AI Technical Summary

Technical Problem

The existing foundation pit rebound deformation monitoring method cannot realize the monitoring of the entire foundation pit excavation process, especially cannot simultaneously monitor the rebound deformation of the soil layers below and above the foundation pit bottom, resulting in incomplete monitoring data and insufficient accuracy.

Method used

A rebound deformation monitoring device for the entire foundation pit excavation process was designed, including layered rebound monitoring mechanisms above and below the foundation pit bottom. A magnetic ring fixing device and an electronic chamber combined with a precision level were used to achieve real-time monitoring of the rebound deformation of the foundation pit soil layer.

Benefits of technology

It realizes the monitoring of soil rebound deformation during the whole process of foundation pit excavation, improves the integrity and accuracy of monitoring data, provides engineering safety protection, and allows the reuse of magnetic ring measuring rods, reducing monitoring costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119121886B_ABST
    Figure CN119121886B_ABST
Patent Text Reader

Abstract

The present invention discloses a device and method for monitoring rebound deformation during the entire process of foundation pit excavation. The device includes a monitoring mechanism for layered rebound above the foundation pit bottom and a monitoring mechanism for layered rebound below the foundation pit bottom. The method includes the following steps: 1. installing a device for monitoring rebound deformation during the entire process of foundation pit excavation; 2. measuring the initial reference elevation value of the rebound mark and the initial reference elevation value of the magnetic ring; 3. excavating in layers and monitoring the rebound deformation after each layer is excavated. The present invention can simultaneously monitor the rebound deformation of soil layers below and above the foundation pit bottom, realizing the full-process rebound deformation of the soil during the foundation pit excavation process, effectively improving the integrity of monitoring data, improving monitoring accuracy, accurately measuring the rebound of foundation pit layers, and providing strong protection for engineering safety. After the foundation pit rebound stabilizes, the magnetic ring measuring rod components can be recycled and reused, reducing the cost of layered rebound monitoring, with high measurement accuracy, and applicable to various geological conditions.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of geotechnical engineering monitoring, and in particular relates to a device and method for monitoring rebound deformation during the entire foundation pit excavation process. Background Art

[0002] With increasing urban space constraints, the increasing number of projects such as super-high-rise construction and underground space development has led to a large number of deep foundation pit projects. When deep foundation pit excavation causes the soil's deadweight stress to decrease, the soil at the bottom of the pit unloads and rebounds. The magnitude of the pit rebound is a crucial indicator for determining pit deformation and stability, and is a prerequisite for accurately estimating future building settlement. Currently, pit rebound deformation is mostly estimated using methods such as the layered summation method, empirical formula method, and residual stress method. Because pit bottom rebound deformation is closely related to many factors, including the underlying soil properties, pit size, pit depth and width, pit bottom exposure time, retaining structure type, support stiffness, and construction quality, the base rebound deformation results obtained using these estimation methods often differ significantly from the measured values. Therefore, on-site monitoring is the most direct, accurate, and reliable method for determining the rebound deformation of each soil layer beneath the pit.

[0003] The current foundation pit rebound deformation monitoring first pre-buries rebound measuring marks in the foundation pit to be excavated, and conducts leveling measurements before and after the foundation pit excavation to measure the height difference changes of each measuring mark arranged on the bottom of the foundation pit, thereby obtaining the deformation of the rebound measuring mark. The main methods include: auxiliary rod method, steel ruler suspended hook method, and steel ruler with electromagnetic hammer (or electromagnetic probe) method. All three methods use leveling measurement, and the hole-making method and the method of burying the rebound measuring mark are basically the same. (1) Auxiliary rod method: It is generally more suitable for shallow foundation pits. When implementing, press the rebound measuring mark into the bottom of the hole, lift the protective casing about 10 cm to temporarily fix it, and lower the pre-prepared auxiliary measuring rod (about 30 cm longer than the hole depth, with a round bubble level installed on the top) to the bottom of the hole, stand it upright on the rebound mark, keep it vertical (bubble concentrated in the center), and then place a level ruler on the auxiliary measuring rod to measure the height; (2) Steel ruler hanging hook method: It is generally more suitable for medium-depth foundation pits. When implementing, the top of the rebound measuring mark is processed into a curved shape. Hook-shaped, the steel ruler head and the interface at the top of the rebound mark are connected with a hook. After the steel ruler is tightened on the ground with a tripod, pulley and weight, a level is used to observe the height difference between the reference point and the rebound mark. (3) Steel ruler with electromagnetic hammer (or electromagnetic probe) method: generally more suitable for deeper foundation pits. When it is implemented, a magnet block is set on the bottom of the weight in the hole so that it can be in close contact with the rebound mark head by the suction force of the magnet (the electromagnetic probe generates magnetic force after it is energized). The force exceeds the mass of the weight outside the hole. The weight is slowly lifted by hand to feel the contact. When the weight in the hole is in good contact with the rebound mark head, the weight is kept balanced and the steel ruler is kept vertical. The level is used to observe the height difference between the reference point and the rebound mark.

[0004] The above method still has the following shortcomings: (1) It can only monitor the final rebound deformation data of the foundation pit bottom after excavation, and cannot obtain the rebound deformation data of the foundation pit bottom during the excavation process; (2) It can only monitor the rebound deformation data of a certain depth at the same plane position, and cannot obtain the rebound deformation data of different depths at the same plane position. Therefore, a device and method for monitoring the rebound deformation of the entire foundation pit excavation process is urgently needed. Summary of the Invention

[0005] The technical problem to be solved by the present invention is to provide a rebound deformation monitoring device for the entire process of foundation pit excavation in response to the deficiencies in the above-mentioned existing technologies. The device has a novel and reasonable design and can simultaneously monitor the rebound deformation of the soil layers below and above the bottom of the foundation pit, thereby realizing the full-process rebound deformation of the soil during the foundation pit excavation process. It can effectively improve the integrity of the monitoring data, improve the monitoring accuracy, accurately measure the rebound of the foundation pit layers, and provide strong protection for the safety of the project. After the foundation pit rebound is stable, the magnetic ring measuring rod components can be recycled and reused, reducing the cost of layered rebound monitoring. The device has high measurement accuracy, is applicable to a variety of geological conditions, and is easy to promote and use.

[0006] In order to solve the above technical problems, the technical solution adopted by the present invention is: a rebound deformation monitoring device for the whole process of foundation pit excavation, characterized in that: it includes a monitoring mechanism for layered rebound above the bottom of the foundation pit and a monitoring mechanism for layered rebound below the bottom of the foundation pit; the layered rebound monitoring mechanism below the bottom of the foundation pit includes a plurality of hard plastic pipes centrally arranged in the borehole from bottom to top, two adjacent hard plastic pipes are connected by a hard plastic pipe joint, and a magnetic ring fixing device for fixing the magnetic ring is provided on the hard plastic pipe, and the magnetic ring fixing device includes an upper circular ring and a lower circular ring, and the magnetic ring is arranged at the bottom of the lower circular ring, and the inner diameter of the magnetic ring is smaller than the outer diameter of the hard plastic pipe joint, and the upper circular ring and the lower circular ring are fixed by multiple The rod is connected with multiple deformation mechanisms and multiple high-strength springs. The deformation mechanism includes a support leg hinged at one end on the upper circular ring and a support leg support rod hinged at one end on the lower circular ring. The other end of the support leg support rod is hinged to the middle of the support leg. A limit block groove for installing a limit block that is wide at the top and narrow at the bottom is opened on the outer wall of the upper circular ring. The limit block abuts against the fixed rod. A card slot for installing a steel card is provided on the outer wall of the upper circular ring at the limit block installation position. A lifting ring is provided on the top of the steel card. Multiple electronic compartments are arranged in sequence from bottom to top in the hard plastic tube. Two adjacent electronic compartments are connected by a measuring rod. The data cable of the electronic compartment extends out of the hard plastic tube and is connected to the demodulator on the original surface.

[0007] The monitoring mechanism for layered rebound above the bottom of the foundation pit includes a plurality of rebound marks arranged in the exploration wells beside the drill hole from bottom to top. A tripod is installed on the top of the exploration well, and a pulley group is provided on the tripod. A steel wire rope is wound around the pulley group at one end with a counterweight, and the other end is connected to a steel ruler extended into the exploration well and connected to the rebound mark. A reference point for installing an indium tile ruler and a precision level for measuring the elevation are set on the original surface.

[0008] The above-mentioned rebound deformation monitoring device for the entire foundation pit excavation process is characterized in that: a conical bottom plug is provided at the bottom of the hard plastic pipe, and cement mortar and a hard plastic pipe centering ring are sequentially provided at the bottom of the drill hole from bottom to top, and the bottom plug passes through the center position of the hard plastic pipe centering ring and extends into the cement mortar.

[0009] The above-mentioned rebound deformation monitoring device for the entire foundation pit excavation process is characterized in that the magnetic ring is connected to the lower circular ring through multiple J-shaped slots and screws.

[0010] The above-mentioned rebound deformation monitoring device for the entire foundation pit excavation process is characterized in that: the other end of the support leg is provided with a fixing claw that can be extended into the borehole wall; and a plurality of balls are provided on the outside of the limit block.

[0011] The above-mentioned rebound deformation monitoring device for the entire foundation pit excavation process is characterized in that the bottom of the electronic warehouse is connected to the measuring rod through a measuring rod centering positioning ring, and the measuring rod centering positioning ring includes a centering ring and a hollow threaded rod arranged at the center position of the centering ring.

[0012] The above-mentioned rebound deformation monitoring device for the entire foundation pit excavation process is characterized in that the two measuring rods are connected by an extension rod, and the extension rod and the measuring rod are connected by an extension bolt.

[0013] The above-mentioned rebound deformation monitoring device for the entire foundation pit excavation process is characterized in that the rebound mark includes a steel plate and a steel needle arranged at one end of the steel plate and inserted into the original soil, a circular ring is installed on the top of the steel plate, and a steel ruler is connected to the circular ring through a hook.

[0014] The above-mentioned rebound deformation monitoring device for the entire process of foundation pit excavation is characterized in that: the spacing between two adjacent rebound marks is 2m to 3m, the bottom of the exploration well is 10m to 15m lower than the bottom of the foundation pit, the exploration well is filled with backfill sand, and a white lime layer is laid in the backfill sand at a position 0.3m above the rebound mark, and the thickness of each white lime layer is 0.2m to 0.3m.

[0015] The above-mentioned rebound deformation monitoring device for the entire foundation pit excavation process is characterized in that: after the foundation pit is excavated, the tripod is moved to the upper side of the exploration well at the surface position after excavation, and a boom bracket for supporting the boom is set on the original surface. The extension length of the boom exceeds the slope line on the side of the foundation pit and is connected to another steel ruler through a wire rope, and a precision level is added to the surface after excavation.

[0016] At the same time, the present invention also discloses a method for monitoring rebound deformation during the entire foundation pit excavation process, which is characterized in that the method comprises the following steps:

[0017] Step 1: Installation of the rebound deformation monitoring device during the entire foundation pit excavation process. The process is as follows:

[0018] Step 101: Drilling holes at monitoring points using a dry drilling method;

[0019] Step 102: Place the magnetic ring on the bottom surface of the magnetic ring fixing device, pull up the upper ring until the top of the fixing rod reaches the bottom of the limit block slot, then place the limit block into the limit block slot, insert the steel card into the card slot, and tie thin ropes to the hanging rings. Tie each thin rope to a hanging rope and mark them accordingly.

[0020] Step 103: Splice the hard plastic pipes using hard plastic pipe joints. During the splicing process, the assembled magnetic ring and magnetic ring fixing device are placed on the outside of the hard plastic pipes. After the hard plastic pipe joints are used to lower the hard plastic pipes into the drilled holes, the lower end of the magnetic ring fixing device contacts the upper end of the hard plastic pipe joints.

[0021] Step 104: pour cement mortar with a thickness of 20cm to 30cm to the bottom of the drill hole, lower the assembled hard plastic pipe into the hole section by section, and gradually lower the lifting rope into the hole during the lowering process. Insert the bottom end of the hard plastic pipe into the cement mortar. The center ring of the hard plastic pipe ensures that the entire device is in the center without horizontal deviation. After the cement mortar solidifies, pull up the lifting rope layer by layer. In the initial state, a limit block is installed in the card slot. When the lifting rope drives the steel card to be completely pulled out, the high-strength spring begins to contract from the tensioned state. When the tension is provided and the contact surface between the limit block and the fixed rod is an inclined surface, the limit block will be squeezed out of the limit block groove by the fixed rod, and the upper ring will move to the lower ring due to the loss of restriction, and the support legs and the support leg support rods will be driven to extend outward, squeezing the fixed claws onto the side wall of the drill hole; during this movement, the position of the lower ring and the magnetic ring is fixed and always in the initial position without relative displacement. As the spring continues to contract, the support legs continue to open toward the hole wall until the support legs are firmly fixed to the hole wall. The entire device tends to be stable and reliably anchored to the hole wall;

[0022] Step 105: The electronic compartment, the measuring rod, and the measuring rod centering ring are connected section by section in sequence according to the designed positions and placed in a hard plastic tube. During the installation process, the data cable is led to the ground and connected to the demodulator.

[0023] Step 106: dig a pilot well next to the borehole, so that the sidewall of the pilot well is tangent to the sidewall of the borehole, and the bottom of the pilot well is 10m to 15m lower than the bottom of the foundation pit;

[0024] Step 107: Set a rebound mark measuring point every 2m to 3m from bottom to top. When installing the rebound mark, connect the lower end of the steel ruler to the rebound mark, pass the upper end around the pulley block and hang a counterweight. Adjust the steel ruler to keep it vertical. Use a precision level to monitor the initial reference elevation of all rebound marks. Then, backfill the exploration well in layers so that the density of the fill in the exploration well is basically consistent with the density of the surrounding original soil. When backfilling reaches 0.3m above the rebound mark elevation, set a white lime layer with a thickness of 0.2m to 0.3m to serve as a prompt layer during the foundation pit excavation process. Repeat the above steps when reaching the next measuring point until all rebound marks are installed and the fill in the exploration well is backfilled to the ground.

[0025] Step 2: Measure the initial reference elevation value of the rebound mark and the initial reference elevation value of the magnetic ring;

[0026] Step 3: Excavate in layers. The rebound deformation monitoring process after each layer of excavation is the same. The rebound deformation monitoring process after each layer of excavation is as follows:

[0027] Step 301, monitoring the rebound of each layer above the pit bottom: When the pit is excavated to 0.4m to 0.6m above the rebound mark of the corresponding layer, manually excavate downward along the original exploration well range to the circular ring position of the rebound mark, hook the lower end of the steel ruler on the circular ring of the rebound mark, pass the upper end around the pulley and hang a hammer, adjust the steel ruler to keep it vertical, use a precision level to monitor the current elevation of the rebound mark, and calculate the height of the rebound mark according to the formula , calculate the rebound deformation of the foundation soil below the rebound measuring point of the jth layer ,in, is the current elevation of the rebound measuring point on the jth layer, is the initial benchmark elevation value of the rebound measuring point of the jth layer;

[0028] Step 302, monitoring of layered rebound below the bottom of the foundation pit: Since the bottom plug of the pipe is reliably anchored to the cement mortar, the position of the electronic chamber and the measuring rod will not change. After the foundation pit is excavated, the soil layer rebounds and deforms. During the soil rebound process, the magnetic ring will be synchronously displaced, changing the length of the measuring rod passing through the magnetic ring. The measuring rod is equipped with a waveguide wire. During measurement, the electronic chamber sends a starting pulse, which is transmitted along the waveguide wire. When the pulse meets the magnetic ring, a magnetostrictive effect current pulse is generated. The demodulator measures the current pulse and calculates the time difference between the two pulses, which is the absolute position of the magnetic ring. According to the formula , calculate the rebound deformation of the foundation soil below the pit bottom at the i-th magnetic ring measuring point at time t ,in, is the current elevation value of the i-th magnetic ring measuring point of the foundation soil below the bottom of the foundation pit at time t, It is the initial benchmark elevation value of the i-th magnetic ring measuring point of the foundation soil below the bottom of the foundation pit at the initial moment.

[0029] Compared with the prior art, the present invention has the following advantages:

[0030] 1. The device used in the present invention has reliable anchoring and can simultaneously monitor the rebound deformation of the soil layers below and above the foundation pit bottom, realizing the full-process rebound deformation of the soil during the foundation pit excavation process, which can effectively improve the integrity of the monitoring data and improve the monitoring accuracy.

[0031] 2. The device used in the present invention can recycle and reuse the magnetostrictive settlement instrument measuring device after the foundation pit rebound stabilizes, thereby reducing the cost of layered rebound monitoring.

[0032] 3. The device used in the present invention can accurately measure the rebound of foundation pit layers, providing a strong guarantee for project safety. By real-time monitoring of the rebound deformation of the soil below the bottom of the foundation pit, the foundation pit rebound problem can be discovered in time, and corresponding measures can be taken to deal with it and prevent the problem from further expansion.

[0033] 4. The method adopted by the present invention has simple steps, convenient installation, high measurement accuracy, is applicable to various geological conditions, and is easy to promote and use.

[0034] To sum up, the design of the present invention is novel and reasonable. It can simultaneously monitor the rebound deformation of the soil layers below and above the bottom of the foundation pit, realize the full-process rebound deformation of the soil during the foundation pit excavation process, effectively improve the integrity of the monitoring data, improve the monitoring accuracy, accurately measure the rebound of the foundation pit layers, and provide strong protection for engineering safety. After the foundation pit rebound is stable, the magnetic ring measuring rod components can be recycled and reused, reducing the cost of layered rebound monitoring. The measurement accuracy is high, it is suitable for a variety of geological conditions, and is easy to promote and use.

[0035] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] Figure 1 This is a schematic diagram of the rebound mark height measurement in the exploration well according to the present invention;

[0037] Figure 2 This is a schematic diagram of measuring the rebound mark elevation during foundation pit excavation in the present invention;

[0038] Figure 3 It is a structural schematic diagram of the present invention;

[0039] Figure 4 This is a schematic diagram of the structure of the monitoring mechanism for layered rebound below the bottom of the foundation pit of the present invention;

[0040] Figure 5 This is a detailed schematic diagram of the bottom of the hard plastic pipe at location A of the present invention;

[0041] Figure 6 This is a schematic diagram of the magnetic ring fixing device of the present invention when it is not opened;

[0042] Figure 7 This is a detailed schematic diagram of point B when the magnetic ring fixing device of the present invention is not opened;

[0043] Figure 8 This is a schematic diagram of the magnetic ring fixing device of the present invention when it is opened;

[0044] Figure 9 Schematic diagram of the detail of point C when the magnetic ring fixing device of the present invention is opened;

[0045] Figure 10 This is a schematic diagram of the rebound of the present invention;

[0046] Figure 11 It is a schematic diagram of the center ring of the present invention.

[0047] Description of the accompanying drawings:

[0048] 1—original surface; 2—well bottom; 3—demodulator;

[0049] 4—lime layer; 5—backfill sand; 6—original soil;

[0050] 7—Rebound mark; 7-1—Ring; 7-2—Steel plate;

[0051] 7-3—Steel needle; 8—Data cable; 9—Electronic compartment;

[0052] 10—Measuring rod centering ring; 10-1—Hollow threaded rod; 10-2—Centering ring;

[0053] 11—Measuring rod; 12—Hard plastic pipe joint; 13—Extension bolt;

[0054] 14—Extension rod; 15—Magnetic ring fixing device; 15-1—Support leg;

[0055] 15-2—Support leg rod; 15-3—Fixed claw; 15-4—High-strength spring;

[0056] 15-5—Magnetic ring; 15-6—J-shaped slot; 15-7—Screw;

[0057] 15-8—upper ring; 15-9—steel card; 15-10—lifting ring;

[0058] 15-11—cage slot; 15-12—fixing rod; 15-13—lower ring;

[0059] 15-14—limit block; 15-15—ball bearing; 15-16—limit block slot;

[0060] 16—Hard plastic pipe; 16-1—Pipe bottom plug; 17—Hard plastic pipe centering ring;

[0061] 18—cement mortar; 19—pulley block; 20—tripod;

[0062] 21—precision level; 22—indium tile ruler; 23—reference point;

[0063] 24—Steel ruler; 25—Hook; 26—Exploration well;

[0064] 27—Hoist rod; 28—Slope line on the side of foundation pit; 29—Hoist rod bracket. DETAILED DESCRIPTION

[0065] like Figures 1 to 11 As shown, the present invention provides a rebound deformation monitoring device for the entire process of foundation pit excavation, including a monitoring mechanism for layered rebound above the foundation pit bottom and a monitoring mechanism for layered rebound below the foundation pit bottom; the layered rebound monitoring mechanism below the foundation pit bottom includes a plurality of hard plastic tubes 16 centrally arranged in a borehole from bottom to top, two adjacent hard plastic tubes 16 are connected by a hard plastic pipe joint 12, a magnetic ring fixing device 15 for fixing a magnetic ring 15-5 is sleeved on the hard plastic tube 16, the magnetic ring fixing device 15 includes an upper circular ring 15-8 and a lower circular ring 15-13, the magnetic ring 15-5 is arranged at the bottom of the lower circular ring 15-13, the inner diameter of the magnetic ring 15-5 is smaller than the outer diameter of the hard plastic pipe joint 12, the upper circular ring 15-8 and the lower circular ring 15-13 are connected by a plurality of fixing rods 15-12, a plurality of deformation mechanisms and a plurality of high-strength springs 15-4, the deformation mechanism The structure includes a support leg 15-1, one end of which is hinged on the upper circular ring 15-8, and a support leg rod 15-2, one end of which is hinged on the lower circular ring 15-13. The other end of the support leg rod 15-2 is hinged to the middle part of the support leg 15-1. The outer wall of the upper circular ring 15-8 is provided with a limit block groove 15-16 for installing a limit block 15-14 which is wide at the top and narrow at the bottom. The limit block 15-14 abuts against the fixed rod 15-12. The outer wall of the upper circular ring 15-8 is provided with a card slot 15-11 for installing a steel card 15-9 at the installation position of the limit block 15-14. A lifting ring 15-10 is provided on the top of the steel card 15-9. A plurality of electronic compartments 9 are arranged in sequence from bottom to top in the hard plastic tube 16. Two adjacent electronic compartments 9 are connected by a measuring rod 11. The data cable 8 of the electronic compartment 9 extends out of the hard plastic tube 16 and is connected to the demodulator 3 on the original surface 1.

[0066] The monitoring mechanism for the layered rebound above the bottom of the foundation pit includes a plurality of rebound marks 7 arranged in sequence from bottom to top in the exploration well 26 beside the borehole. A tripod 20 is installed on the top of the exploration well 26, and a pulley block 19 is provided on the tripod 20. A steel wire rope is wound around the pulley block 19. One end is provided with a counterweight, and the other end is connected to a steel ruler 24 that extends into the exploration well 26 and is connected to the rebound mark 7. A reference point 23 for installing an indium tile ruler 22 and a precision level 21 for measuring the elevation are provided on the original surface 1.

[0067] It should be noted that the magnetic ring is fixed to the soil through a magnetic ring fixing device and is sleeved on the outside of the hard plastic tube. When the soil rebounds, the magnetic ring will be driven to move upward, changing the relative position of the magnetic ring and the measuring rod, thereby measuring the soil rebound deformation. The J-shaped slot is connected to the lower circular ring by screws and is used to fix the magnetic ring at the bottom of the lower circular ring. The support leg is fixed to the outside of the upper circular ring by a hinge, and a fixing claw is provided at the outer end; the fixing claw is used to fix the magnetic ring fixing device in the soil; the support leg is hingedly connected to the bottom circular ring by a support rod; the high-strength spring is connected to the upper and lower magnetic rings by welding, and the high-strength spring is long under normal conditions. The length is shorter than the fixing rod; the fixing rod is connected to the lower circular ring by welding, and the upper part of the fixing rod is an inclined surface inclined to the outside of the circular ring; the upper circular ring has three circular holes that pass through the upper and lower parts for passing the fixing rod, and its weight can ensure that the fixing rod will not be bounced open when it pops out. The card slot is connected to the outside of the upper circular ring by welding, and there is a channel in the middle that is larger than the size of the limit block; the limit block is placed in the limit block groove, and the limit block groove is connected to the circular hole on the upper circular ring. One side of the limit block is an inclined surface that fits the top inclined surface of the fixing rod, and the other side is a ball groove for installing the ball; the upper part of the steel card is connected to a semicircular hanging ring and placed in the card slot.

[0068] The demodulator measures electronic pulse data. The pulsed electron chamber emits a signal along the waveguide wire. Upon encountering the magnetic ring, a magnetostrictive current pulse is generated. This signal is transmitted to the demodulator via a data cable, and the collected data is uploaded to a cloud platform for collecting and analyzing rebound deformation data deep below the foundation pit bottom. The waveguide wire is made of an iron-nickel alloy with a diameter of 0.5mm to 0.8mm. During measurement, the excitation module in the pulsed electron chamber applies a query pulse to both ends of the waveguide wire. This pulse generates a circumferential Ampere toroidal magnetic field around the waveguide wire at the speed of light. When this Ampere toroidal magnetic field couples with the bias permanent magnetic field of the vernier magnetic ring, a Widmanstätten effect torsional stress wave forms on the surface of the waveguide wire. The torsional wave propagates at the speed of sound from the generation point to the ends of the waveguide wire. The torsional wave reaching the ends is absorbed by the damping device, while the signal reaching the excitation end is received by the detection device. The control module in the electronic compartment calculates the time difference between the query pulse and the received signal, and then multiplies it by the propagation speed of the torsional stress wave in the waveguide material. It can then calculate the distance between the location where the torsional wave occurs and the measurement reference point, that is, the absolute distance between the magnetic ring and the measurement reference point at that moment, thereby achieving real-time and accurate measurement of the magnetic ring position. The electronic compartment can generate excitation pulses and process related electrical signals, and is connected to the demodulator to achieve long-distance transmission. The number of electronic compartments is consistent with the number of layers of rebound soil at the bottom of the foundation pit, and is arranged at the top of each layer of soil. When the soil layer rebounds and deforms, the fixed claw drives the magnetic ring fixing device to move, and a vertical relative displacement occurs between the magnetic ring and the measuring rod. The electronic compartment emits a wave signal, and the soil layer rebound amount is transmitted to the demodulator through the wave signal, thereby obtaining the rebound amount of each layer of soil below the bottom of the foundation pit; the measuring rod is made of stainless steel and is equipped with a waveguide wire inside. It is connected to the electronic warehouse, and the electronic warehouse transmits a wave signal that propagates at the speed of sound through the waveguide wire in the measuring rod; the extension rod is made of stainless steel, and is threadedly connected to the electronic warehouse and the measuring rod through an extension bolt, which is used to adjust the relative distance between the upper and lower electronic warehouses; the measuring rod centering ring includes a centering ring and a hollow threaded rod; the inner diameter of the central circular hole of the hollow threaded rod is the same as the outer diameter of the measuring rod and the extension rod, and is threadedly connected to the measuring rod and the extension rod through the central circular hole; the centering ring is fixed to the hollow threaded rod by threads, and the outer diameter of the centering ring is 2mm to 3mm smaller than the inner diameter of the hard plastic tube.

[0069] The inner diameter of the hard plastic tube is slightly larger than the center positioning ring of the measuring tube, and the outer diameter is slightly smaller than the inner diameters of the upper and lower rings in the magnetic ring fixing device. It is sleeved on the outside of the measuring rod, and a hard plastic tube plug is installed at the bottom. The hard plastic tube plug is connected to the hard plastic tube by adhesive. The conical circular hole inside the hard plastic tube plug is used for installing and centering the measuring device.

[0070] The cement mortar is poured at the bottom of the drill hole, the cement mortar grade is M10, and the lower end of the hard plastic pipe is inserted into the cement mortar as a relatively fixed point.

[0071] In this embodiment, a conical bottom plug 16-1 is provided at the bottom of the hard plastic tube 16, and cement mortar 18 and a hard plastic tube centering ring 17 are provided in sequence at the bottom of the drill hole from bottom to top. The bottom plug 16-1 passes through the center position of the hard plastic tube centering ring 17 and extends into the cement mortar 18.

[0072] In this embodiment, the magnetic ring 15-5 is connected to the lower circular ring 15-13 through multiple J-shaped slots 15-6 and screws 15-7.

[0073] In this embodiment, the other end of the support leg 15 - 1 is provided with a fixing claw 15 - 3 that can be extended into the drill hole wall; a plurality of balls 15 - 15 are provided on the outer side of the limit block 15 - 14.

[0074] It should be noted that when the magnetic ring fixing device 15 is not installed, the high-strength spring 15-4 in the device is in a stretched state. After the magnetic ring fixing device is hoisted to the specified position as a whole through the lifting ring 15-10, the steel card 15-9 is slowly pulled out from the card slot 15-11; in the initial state, a limit block 15-14 is installed in the card slot 15-11. When the steel card 15-9 is completely pulled out, the high-strength spring 15-4 begins to contract from the tensioned state. As the spring continues to contract, the support leg 15-1 continues to open toward the hole wall until the support leg 15-1 is firmly fixed to the hole wall. The entire device becomes stable and is reliably anchored to the hole wall.

[0075] In this embodiment, the bottom of the electronic compartment 9 is connected to the measuring rod 11 through the measuring rod centering positioning ring 10. The measuring rod centering positioning ring 10 includes a centering ring 10-2 and a hollow threaded rod 10-1 arranged at the center position of the centering ring 10-2.

[0076] In this embodiment, the two measuring rods 11 are connected by an extension rod 14 , and the extension rod 14 and the measuring rod 11 are connected by an extension bolt 13 .

[0077] In this embodiment, the rebound mark 7 includes a steel plate 7-2 and a steel needle 7-3 arranged at one end of the steel plate 7-2 and inserted into the original soil 6. A ring 7-1 is installed on the top of the steel plate 7-2, and a steel ruler 24 is connected to the ring 7-1 through a hook 25.

[0078] In this embodiment, the distance between two adjacent rebound marks 7 is 2m to 3m, the bottom of the exploration well 2 is 10m to 15m lower than the bottom of the foundation pit, the exploration well 26 is filled with backfill sand 5, and a white lime layer 4 is laid in the backfill sand 5 at a position 0.3m above the rebound mark 7, and the thickness of each layer of white lime layer 4 is 0.2m to 0.3m.

[0079] In this embodiment, after the foundation pit is excavated, the tripod 20 is moved to the upper side of the exploration well 26 at the surface position after excavation, and a boom bracket 29 for supporting the boom 27 is set on the original surface 1. The extension length of the boom 27 exceeds the slope line 28 of the side of the foundation pit and is connected to another steel ruler 24 through a wire rope, and a precision level 21 is added to the surface after excavation.

[0080] A method for monitoring rebound deformation during the entire foundation pit excavation process comprises the following steps:

[0081] Step 1: Installation of the rebound deformation monitoring device during the entire foundation pit excavation process. The process is as follows:

[0082] Step 101: Drilling holes at monitoring points using a dry drilling method;

[0083] Step 102: Place the magnetic ring 15-5 on the bottom surface of the magnetic ring fixing device 15, pull up the upper ring 15-8 until the top of the fixing rod 15-12 reaches the bottom of the limit block slot 15-16, then put the limit block 15-14 into the limit block slot 15-16, and then insert the steel card 15-9 into the card slot 15-11, and tie a string to the ring 15-10, tie each string to a hanging rope and mark it accordingly;

[0084] Step 103: Splice the hard plastic tube 16 with the hard plastic tube joint 12. During the splicing process, the assembled magnetic ring 15-5 and the magnetic ring fixing device 15 are placed on the outside of the hard plastic tube 16. After the hard plastic tube joint 12 is used to lower the hard plastic tube 16 into the drilled hole, the lower end of the magnetic ring fixing device 15 contacts the upper end of the hard plastic tube joint 12.

[0085] Step 104, pour cement mortar 18 with a thickness of 20cm to 30cm to the bottom of the drill hole, lower the assembled hard plastic tube 16 into the hole section by section, and gradually lower the lifting rope into the hole during the lowering process, insert the bottom end of the hard plastic tube 16 into the cement mortar 18, and the hard plastic tube centering ring 17 ensures that the entire device is in the center without horizontal deviation. After the cement mortar 18 solidifies, pull up the lifting rope layer by layer. In the initial state, the limit block 15-14 is installed in the card slot 15-11. When the lifting rope drives the steel card 15-9 to be completely pulled out, the high-strength spring 15-4 begins to contract from the tensioned state. Due to the tension provided by the high-strength spring 15-4 and the limit block 15-14 The contact surface with the fixing rod 15-12 is an inclined surface, and the limit block 15-14 will be squeezed out of the limit block groove 15-16 by the fixing rod 15-12. The upper ring 15-8 will move toward the lower ring 15-13 due to the loss of restriction, and the support leg 15-1 and the support leg support rod 15-2 will be driven to extend outward, squeezing the fixing claw 15-3 onto the side wall of the drill hole; during this movement, the lower ring 15-13 and the magnetic ring 15-5 are fixed in position and always in the initial position without relative displacement. As the spring continues to contract, the support leg 15-1 continues to open toward the hole wall until the support leg is firmly fixed to the hole wall. The entire device tends to be stable and reliably anchored to the hole wall.

[0086] Step 105: The electronic compartment 9, the measuring rod 11 and the measuring rod centering ring 10 are connected section by section in sequence according to the designed position and placed in the hard plastic tube 16. During the installation process, the data cable 8 is led to the ground and connected to the demodulator 3;

[0087] Step 106: excavate a pilot well 26 next to the borehole, so that the sidewall of the pilot well is tangent to the sidewall of the borehole, and the bottom of the pilot well is 10m to 15m lower than the bottom of the foundation pit;

[0088] Step 107: Set a rebound mark measuring point every 2m to 3m from bottom to top. When installing the rebound mark 7, connect the lower end of the steel ruler to the rebound mark, pass the upper end around the pulley block 19 and hang a counterweight, adjust the steel ruler 24 to keep it vertical, use the precision level 21 to monitor the initial reference elevation of all rebound marks, and then backfill the exploration well 26 in layers so that the density of the fill in the exploration well is basically consistent with the density of the surrounding original soil. When backfilling to 0.3m above the rebound mark elevation, set a white lime layer 4 with a thickness of 0.2m to 0.3m to serve as a prompt layer during the foundation pit excavation process. Repeat the above steps when reaching the next measuring point until all rebound marks 7 are installed and the fill in the exploration well is backfilled to the ground.

[0089] Step 2: Measure the initial reference elevation value of the rebound mark and the initial reference elevation value of the magnetic ring;

[0090] Step 3: Excavate in layers. The rebound deformation monitoring process after each layer of excavation is the same. The rebound deformation monitoring process after each layer of excavation is as follows:

[0091] Step 301, monitoring the rebound of each layer above the pit bottom: When the pit is excavated to 0.4m to 0.6m above the rebound mark of the corresponding layer, manually excavate downward along the original exploration well range to the position of the ring 7-1 of the rebound mark, hook the hook 25 at the lower end of the steel ruler 24 to the ring 7-1 on the rebound mark, pass the upper end around the pulley and hang a hammer, adjust the steel ruler to keep it vertical, use the precision level 21 to monitor the current elevation of the rebound mark, and calculate the value of the rebound mark according to the formula , calculate the rebound deformation of the foundation soil below the rebound measuring point of the jth layer ,in, is the current elevation of the rebound measuring point on the jth layer, is the initial benchmark elevation value of the rebound measuring point of the jth layer;

[0092] Step 302, monitoring the layered rebound below the bottom of the foundation pit: Since the bottom plug 16-1 of the pipe is reliably anchored to the cement mortar 18, the positions of the electronic chamber 9 and the measuring rod 11 will not change. After the foundation pit is excavated, the soil layer rebounds and deforms. During the soil layer rebound, the magnetic ring 15-5 will be synchronously displaced, changing the length of the measuring rod passing through the magnetic ring. The measuring rod 11 is equipped with a waveguide wire. During measurement, the electronic chamber 9 sends a starting pulse, which is transmitted along the waveguide wire. When the pulse meets the magnetic ring, a magnetostrictive effect current pulse is generated. The demodulator measures the current pulse and calculates the time difference between the two pulses, which is the absolute position of the magnetic ring. According to the formula , calculate the rebound deformation of the foundation soil below the pit bottom at the i-th magnetic ring measuring point at time t ,in, is the current elevation value of the i-th magnetic ring measuring point of the foundation soil below the bottom of the foundation pit at time t, It is the initial benchmark elevation value of the i-th magnetic ring measuring point of the foundation soil below the bottom of the foundation pit at the initial moment.

[0093] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any way. Any simple modification, change and equivalent structural change made to the above embodiment based on the technical essence of the present invention shall still fall within the scope of protection of the technical solution of the present invention.

Claims

1. A device for monitoring rebound deformation during the entire foundation pit excavation process, characterized by: The invention comprises a monitoring mechanism for layered rebound above the foundation pit bottom and a monitoring mechanism for layered rebound below the foundation pit bottom; the monitoring mechanism for layered rebound below the foundation pit bottom comprises a plurality of hard plastic pipes (16) centrally arranged in a borehole from bottom to top, two adjacent hard plastic pipes (16) are connected by a hard plastic pipe joint (12), a magnetic ring fixing device (15) for fixing a magnetic ring (15-5) is sleeved on the hard plastic pipe (16), and the magnetic ring fixing device (15) comprises an upper ring ( 15-8) and a lower circular ring (15-13), a magnetic ring (15-5) is arranged at the bottom of the lower circular ring (15-13), the inner diameter of the magnetic ring (15-5) is smaller than the outer diameter of the hard plastic pipe joint (12), the upper circular ring (15-8) and the lower circular ring (15-13) are connected by multiple fixing rods (15-12), multiple deformation mechanisms and multiple high-strength springs (15-4), the deformation mechanism includes a support leg with one end hinged on the upper circular ring (15-8) (15-1) and a support leg support rod (15-2) hinged at one end to the lower circular ring (15-13), the other end of the support leg support rod (15-2) is hinged to the middle of the support leg (15-1), the outer wall of the upper circular ring (15-8) is provided with a limit block groove (15-16) for installing a limit block (15-14) with a width at the top and a narrowness at the bottom, the limit block (15-14) is in contact with the fixing rod (15-12), and the outer wall of the upper circular ring (15-8) is located at the limit A card slot (15-11) for installing a steel card (15-9) is provided at the installation position of the block (15-14), and a lifting ring (15-10) is provided on the top of the steel card (15-9); a plurality of electronic compartments (9) are sequentially provided in the hard plastic tube (16) from bottom to top, two adjacent electronic compartments (9) are connected by a measuring rod (11), and a data cable (8) of the electronic compartment (9) extends out of the hard plastic tube (16) and is connected to a demodulator (3) on the original ground surface (1); The monitoring mechanism for the layered rebound above the bottom of the foundation pit includes a plurality of rebound marks (7) arranged in sequence from bottom to top in a pilot well (26) beside the borehole, a tripod (20) is installed on the top of the pilot well (26), a pulley block (19) is provided on the tripod (20), a steel wire rope is wound around the pulley block (19) and provided with a counterweight at one end, and a steel ruler (24) is connected to the other end thereof and extends into the pilot well (26) and is connected to the rebound mark (7), and a reference point (23) for installing an indium tile ruler (22) and a precision level (21) for measuring the elevation are provided on the original surface (1).

2. A device for monitoring rebound deformation during the entire foundation pit excavation process according to claim 1, characterized in that: A conical bottom plug (16-1) is provided at the bottom of the hard plastic pipe (16), and cement mortar (18) and a hard plastic pipe centering ring (17) are sequentially provided at the bottom of the drilled hole from bottom to top, and the bottom plug (16-1) passes through the center of the hard plastic pipe centering ring (17) and extends into the cement mortar (18).

3. The device for monitoring rebound deformation during the entire foundation pit excavation process according to claim 1, characterized in that: The magnetic ring (15-5) is connected to the lower circular ring (15-13) via a plurality of J-shaped slots (15-6) and screws (15-7).

4. The device for monitoring rebound deformation during the entire foundation pit excavation process according to claim 1, characterized in that: The other end of the support leg (15-1) is provided with a fixing claw (15-3) that can extend into the borehole wall; and a plurality of balls (15-15) are provided on the outside of the limiting block (15-14).

5. The device for monitoring rebound deformation during the entire foundation pit excavation process according to claim 2, characterized in that: The bottom of the electronic compartment (9) is connected to a measuring rod (11) via a measuring rod centering positioning ring (10), and the measuring rod centering positioning ring (10) comprises a centering ring (10-2) and a hollow threaded rod (10-1) arranged at the center of the centering ring (10-2).

6. The device for monitoring rebound deformation during the entire foundation pit excavation process according to claim 5, characterized in that: The two measuring rods (11) are connected via an extension rod (14), and the extension rod (14) and the measuring rod (11) are connected via an extension bolt (13).

7. The device for monitoring rebound deformation during the entire foundation pit excavation process according to claim 5, characterized in that: The rebound mark (7) comprises a steel plate (7-2) and a steel needle (7-3) arranged at one end of the steel plate (7-2) and inserted into the original soil (6); a circular ring (7-1) is installed on the top of the steel plate (7-2); and a steel ruler (24) is connected to the circular ring (7-1) via a hook (25).

8. The device for monitoring rebound deformation during the entire foundation pit excavation process according to claim 1, characterized in that: The distance between two adjacent rebound marks (7) is 2m to 3m, the bottom of the exploration well (2) is 10m to 15m lower than the bottom of the foundation pit, the exploration well (26) is filled with backfill sand (5), and a white lime layer (4) is laid in the backfill sand (5) at a position 0.3m above the rebound mark (7), and the thickness of each white lime layer (4) is 0.2m to 0.3m.

9. The device for monitoring rebound deformation during the entire foundation pit excavation process according to claim 1, characterized in that: After the foundation pit is excavated, the tripod (20) is moved to the upper side of the exploration well (26) at the surface position after the excavation, and a boom bracket (29) for supporting a boom (27) is set on the original surface (1). The extension length of the boom (27) exceeds the slope line (28) on the side of the foundation pit and is connected to another steel ruler (24) through a wire rope. A precision level (21) is also added to the surface after the excavation.

10. A method for monitoring rebound deformation during the entire excavation process of a foundation pit using the device according to claim 7, characterized in that: The method comprises the following steps: Step 1: Installation of the rebound deformation monitoring device during the entire foundation pit excavation process. The process is as follows: Step 101: Drilling holes at monitoring points using a dry drilling method; Step 102: Place the magnetic ring (15-5) on the bottom surface of the magnetic ring fixing device (15), pull up the upper ring (15-8) until the top of the fixing rod (15-12) reaches the bottom side of the limit block slot (15-16), then put the limit block (15-14) into the limit block slot (15-16), and then insert the steel card (15-9) into the card slot (15-11), and tie a string to the hanging ring (15-10), tie each string to a hanging rope and make corresponding marks; Step 103, the hard plastic pipe (16) is spliced ​​with the hard plastic pipe joint (12), and during the splicing process of the hard plastic pipe (16), the assembled magnetic ring (15-5) and the magnetic ring fixing device (15) are sleeved on the outside of the hard plastic pipe (16), and after the hard plastic pipe joint (12) is used to lower the hard plastic pipe (16) into the drilled hole, the lower end of the magnetic ring fixing device (15) contacts the upper end of the hard plastic pipe joint (12); Step 104, pouring cement mortar (18) with a thickness of 20cm to 30cm to the bottom of the drill hole, lowering the assembled hard plastic pipe (16) into the hole section by section, and gradually lowering the hanging rope into the hole during the lowering process, inserting the bottom end of the hard plastic pipe (16) into the cement mortar (18), and the hard plastic pipe centering ring (17) ensures that the entire device is in the center and does not shift horizontally. After the cement mortar (18) solidifies, the hanging rope is pulled up layer by layer. In the initial state, the card slot (15-11) is equipped with a limit block (15-14). When the hanging rope drives the steel card (15-9) to be completely pulled out, the high-strength spring (15-4) begins to contract from the tension state. Due to the tension provided by the high-strength spring (15-4) and the limit block (15-14) The contact surface with the fixing rod (15-12) is an inclined surface, and the limit block (15-14) is squeezed out of the limit block groove (15-16) by the fixing rod (15-12). The upper ring (15-8) moves toward the lower ring (15-13) due to the loss of restriction, and the support leg (15-1) and the support leg support rod (15-2) are driven to extend outward, squeezing the fixing claw (15-3) onto the side wall of the borehole; during this movement, the lower ring (15-13) and the magnetic ring (15-5) are fixed in position and always in the initial position, without any relative displacement; as the spring continues to shrink, the support leg (15-1) continues to open toward the hole wall until the support leg is firmly fixed to the hole wall, and the entire device tends to be stable and reliably anchored to the hole wall; Step 105, the electronic compartment (9), the measuring rod (11) and the measuring rod centering ring (10) are connected section by section in sequence according to the designed position and placed in the hard plastic tube (16). During the installation process, the data cable (8) is led to the ground and connected to the demodulator (3); Step 106: excavate a test well (26) next to the borehole, so that the sidewall of the test well is tangent to the sidewall of the borehole, and the bottom of the test well is 10m to 15m lower than the bottom of the foundation pit; Step 107, set a rebound mark measuring point every 2m to 3m from bottom to top. When installing the rebound mark (7), connect the lower end of the steel ruler to the rebound mark, pass the upper end around the pulley block (19) and hang a counterweight, adjust the steel ruler (24) to keep it vertical, use a precision level (21) to monitor the initial reference elevation value of all rebound marks, and then backfill the exploration well (26) in layers so that the density of the filling in the exploration well is basically consistent with the density of the surrounding original soil. When backfilling to 0.3m above the rebound mark elevation, set a white lime layer (4) with a thickness of 0.2m to 0.3m to serve as a prompt layer during the foundation pit excavation process. Repeat the above steps when reaching the next measuring point until all rebound marks (7) are installed and the filling in the exploration well is backfilled to the ground. Step 2: Measure the initial reference elevation value of the rebound mark and the initial reference elevation value of the magnetic ring; Step 3: Excavate in layers. The rebound deformation monitoring process after each layer of excavation is the same. The rebound deformation monitoring process after each layer of excavation is as follows: Step 301, monitoring of layered rebound above the pit bottom: When the pit is excavated to 0.4m to 0.6m above the rebound mark of the corresponding layer, manually excavate downward along the original exploration well range to the position of the circular ring (7-1) of the rebound mark, hook the lower end hook (25) of the steel ruler (24) on the circular ring (7-1) of the rebound mark, pass the upper end around the pulley and hang a hammer, adjust the steel ruler to keep it vertical, use the precision level (21) to monitor the current elevation of the rebound mark, according to the formula , calculate the rebound deformation of the foundation soil below the rebound measuring point of the jth layer ,in, is the current elevation of the rebound measuring point on the jth layer, is the initial benchmark elevation value of the rebound measuring point of the jth layer; Step 302, monitoring of layered rebound below the bottom of the foundation pit: Since the bottom plug (16-1) and the cement mortar (18) are reliably anchored, the positions of the electronic chamber (9) and the measuring rod (11) will not change. After the foundation pit is excavated, the soil layer rebounds and deforms. During the soil layer rebound process, the magnetic ring (15-5) will be driven to synchronously shift, changing the length of the measuring rod passing through the magnetic ring. The measuring rod (11) is equipped with a waveguide wire. During measurement, the electronic chamber (9) sends a starting pulse, which is transmitted along the waveguide wire. When the pulse meets the magnetic ring, a magnetostrictive effect current pulse is generated. The demodulator measures the current pulse and calculates the time difference between the two pulses, which is the absolute position of the magnetic ring. According to the formula , calculate the rebound deformation of the foundation soil below the pit bottom at the i-th magnetic ring measuring point at time t ,in, is the current elevation value of the i-th magnetic ring measuring point of the foundation soil below the bottom of the foundation pit at time t, It is the initial benchmark elevation value of the i-th magnetic ring measuring point of the foundation soil below the bottom of the foundation pit at the initial moment.

Citation Information

Patent Citations

  • Magnetic ring type testing device and method for foundation upheaval caused by foundation pit excavation

    CN106948388A

  • Soft basic deep water fill settlement monitoring device

    CN208254458U