A construction process and apparatus for installing urban renewal cover pipes

By adopting cover pipeline installation construction technology and 3D printing technology in urban renewal pipeline projects, the problems that affect urban traffic and engineering garbage disposal are solved, and construction safety and efficiency are improved, as well as resource conservation and road traffic recovery are achieved.

CN119221345BActive Publication Date: 2025-06-06JINAN URBAN CONSTRUCTION GROUP CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202411764117.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-12-04
Publication Date
2025-06-06
Estimated Expiration
2044-12-04

AI Technical Summary

Technical Problem

During the construction of existing urban renewal pipeline projects, the construction process affects urban transportation, and the engineering garbage disposal is difficult, and there is a lack of efficient construction technology to solve these problems.

Method used

Provide a construction process for the installation and construction of urban renewal cover plate pipelines, including sorting out project data, closing construction areas, installing screw piles and connecting beams, performing 3D printer installation and pipeline printing, and restoring road traffic functions, forming an overall trench support system and pipeline protection system.

Benefits of technology

Through the overall support system and 3D printing technology, the amount of trench excavation surface and earth excavation is reduced, the resource utilization of engineering garbage and the conservation of steel resources are achieved, construction safety and efficiency are improved, and road traffic functions are restored.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119221345B_ABST
    Figure CN119221345B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of urban renewal pipeline engineering construction, specifically a kind of urban renewal cover plate pipeline installation construction process and equipment, screw piles, groove baffles, connecting beams, and groove cover plates form a groove integral support system; the connecting beam is composed of a beam body and a printer longitudinal rod, and the beam bodies of adjacent connecting beams are sequentially connected to form a beam that is longitudinally long along the groove; a 3D printer is installed on the printer longitudinal rod, and is used to print pipelines, inspection wells, and pipeline supports in the pipeline groove; the groove cover plate includes a panel and a support grid, and the groove cover plate is installed on the connecting beam with the support grid facing downward, and the support grid is stuck between the connecting beams on both sides of the groove. This application solves the problem of mutual influence between pipeline engineering construction and urban traffic demand in the prior art.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of urban renewal pipeline engineering construction, and in particular to an urban renewal cover plate pipeline installation construction process and an apparatus. Background Art

[0002] In the existing urban renewal project pipeline construction, the current common construction technology is to cut slopes, open grooves and cover with steel plates for temporary passage. Due to the diversity of urban traffic conditions, pipeline construction and urban traffic demand affect each other: project construction affects urban traffic; project construction work surfaces and work time need to avoid urban traffic demand.

[0003] At the same time, the treatment of construction waste is one of the construction difficulties of urban renewal projects.

[0004] Therefore, the construction of urban renewal pipeline projects urgently needs a new urban renewal pipeline construction process to overcome the above problems. Summary of the invention

[0005] The purpose of the present invention is to provide a construction process and equipment for installing and constructing a cover plate pipeline for urban renewal, so as to solve the problems raised in the above-mentioned background technology.

[0006] To achieve the above object, the present invention provides the following technical solutions:

[0007] The present invention provides a construction process for installing a pipe for a cover plate for urban renewal, comprising:

[0008] S1: Organize the urban renewal pipeline project data according to the design drawings, determine the center, direction, length, depth, inspection well location, red line range and other specific information of the renewal pipeline, conduct on-site positioning and laying out, and make corresponding markings in the construction site;

[0009] S2: Close the pipeline engineering site along the construction red line, vertically cut the original pavement structure layer along the upper edge of the trench layout results, break the original pavement structure between the two upper edges of the trench and excavate it. The excavated part includes the original pavement and part of the roadbed. The thickness of the excavated structure layer is not less than 40cm. After excavating the road surface layer and part of the base layer, a concave construction groove is formed at the construction site;

[0010] S3: Locate the bottom edge of the pipeline trench along the bottom edge of the concave construction trench on both sides, mark it every 2 meters, and screw in the screw piles vertically along the marked points;

[0011] S4: Construction is carried out in the concave construction trench and the connecting beam is installed; the connecting beam is fixed to the top of the screw piles on both sides of the concave construction trench in turn to form two beams running along the longitudinal direction of the pipeline trench, which are used to form the overall trench support system in the later stage, and serve as the trench cover plate and the working track of the 3D printer;

[0012] S5: Dig the soil in the pipeline trench vertically along the screw piles on both sides of the concave construction trench, and remove the soil to the bottom of the pipeline trench;

[0013] S6: On both sides of the pipeline trench, install trench baffles along the smooth screws of the screw piles to form a vertical trench slope for overall protection;

[0014] S7: Level and compact the bottom of the groove, and lay the pipeline cushion along the bottom of the groove as a reference surface for 3D printing;

[0015] S8: Install 3D printers on the inner side of the connecting beams on both sides of the trench and install trench covers; screw piles, trench baffles, connecting beams, and trench covers form an overall trench support system; after the overall trench support system is established, temporarily lift the closure of the construction site and restore the road traffic function of the construction site;

[0016] S9: Connect the 3D printer to the concrete pump station through the feed pipe, and use the 3D printer to print the pipeline, inspection well, and pipeline support to complete the main pipeline project; during the operation, the roads in the construction area have normal traffic functions;

[0017] S10: After the entire pipeline is completed, the construction area is closed for the second time, and the following are removed in sequence: trench cover, 3D printer, trench baffle, connecting beam, screw pile; fluidized solidified soil is poured along the longitudinal direction of the trench to fill the gaps between the pipeline supports to form a pipeline protection system;

[0018] S11: Restore the roadbed and pavement structure layer, clean up the construction equipment, materials and debris in the site, lift the closure of the construction site, and restore the traffic function of the construction road.

[0019] The present invention provides an urban renewal cover plate pipeline installation construction tool, which is characterized in that: screw piles, groove baffles, connecting beams, and groove cover plates form an overall groove support system; the connecting beams are composed of a beam body and a printer longitudinal rod, and the beam bodies of adjacent connecting beams are sequentially connected to form a beam that is longitudinally long along the groove; a 3D printer is installed on the printer longitudinal rod, and is used to print pipelines, inspection wells, and pipeline supports in the pipeline groove; the groove cover plate includes a panel and a support grid, and the groove cover plate is installed on the connecting beam with the support grid facing downward, and the support grid is stuck between the connecting beams on both sides of the groove.

[0020] As a further solution of the present invention: the screw pile consists of a pile head, a screw rod, a smooth screw rod and a pile top.

[0021] As a further solution of the present invention: the groove cover plate also includes lateral anti-slip teeth arranged along the longitudinal direction of the groove cover plate and blunted corners at the four corners of the groove cover plate.

[0022] As a further solution of the present invention: the supporting grid is a grid load-bearing structure composed of planar connecting rods, oblique connecting rods and nodes, and the lateral anti-slip teeth are triangular saw teeth.

[0023] As a further solution of the present invention: the 3D printer consists of a printer head, a feed pipe, a printer vertical rod, a printer cross rod, a longitudinal rod pulley, and a pulley; the 3D printer is slidably connected to the printer longitudinal rod through the longitudinal rod pulley, the printer head is slidably connected to the printer vertical rod through the pulley, and the printer vertical rod is slidably connected to the printer cross rod through the pulley.

[0024] As a further solution of the present invention: it also includes a moving tool that enables the groove cover plate to slide on the top of the connecting beam, and the moving tool is composed of a bearing platform, an axle, and a first wheel.

[0025] As a further solution of the present invention: it also includes an opening tool for opening and closing the groove cover, and the opening tool is composed of an insertion rod, a pry bar, a handle, and a second wheel.

[0026] Compared with the prior art, the invention has the following beneficial effects: screw piles, connecting beams, groove baffles and groove covers constitute an integral support system for pipeline grooves, thereby improving the safety factor of engineering construction; since the integral groove support system does not require groove slope, and pipeline 3D printing reduces the space for manual operations, thereby reducing the groove width. The above two reasons reduce the groove excavation surface, thereby reducing the amount of earthwork excavation and the overall amount of engineering waste; the earthwork excavated by the process can be used for groove filling, thereby realizing the resource utilization of the excavated earthwork: the reduction in the width of the groove slope top reduces the width of the steel plate, thereby realizing the reduction of the steel plate width. The 3D printing technology of pipelines can save labor for pipeline installation and save social human resources, while avoiding underground operations of personnel and improving the safety factor of construction. The tools used in the process can be circulated and reused, which is conducive to saving social resources. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a schematic diagram of the overall trench support system of the present invention;

[0028] Figure 2 This is a schematic diagram of the installation of the 3D printer of the present invention;

[0029] Figure 3 It is a schematic diagram of the facade structure of the present invention;

[0030] Figure 4 It is a schematic diagram of the plane structure of the present invention;

[0031] Figure 5 It is a structural schematic diagram of the screw pile of the present invention;

[0032] Figure 6 It is a structural schematic diagram of the coupling beam of the present invention;

[0033] Figure 7 It is a structural schematic diagram of the groove cover plate of the present invention;

[0034] Figure 8 It is a schematic diagram of a basic unit of the support grid of the present invention;

[0035] Fig. 9 It is a schematic diagram of the structure of the 3D printer of the present invention;

[0036] Fig.10 This is a schematic diagram of opening and moving the groove cover of the present invention;

[0037] Fig.11 This is a schematic diagram of the structure of the mobile tool of the present invention;

[0038] Fig.12 It is a structural schematic diagram of the opening tool of the present invention.

[0039] Among them: 1 screw pile, 1.1 pile head, 1.2 screw rod, 1.3 smooth screw rod, 1.4 pile top, 2 connecting beam, 2.1 beam body, 2.2 printer longitudinal rod, 3 groove cover plate, 3.1 panel, 3.2 support grid, 3.21 node, 3.22 plane connecting rod, 3.23 oblique connecting rod, 3.3 lateral anti-skid teeth, 3.4 blunt angle, 4 groove baffle, 53D printer, 5.1 printer head, 5.2 feed pipe, 5.3 printer vertical rod, 5.4 printer horizontal rod, 5.5 longitudinal rod pulley, 5.6 pulley, 6 pipeline, 7 pipeline support, 8 moving tool, 8.1 foundation, 8.2 axle, 8.3 first wheel, 9 opening tool, 9.1 insertion rod, 9.2 pry bar, 9.3 handle, 9.4 second wheel. DETAILED DESCRIPTION

[0040] The present invention will be described in detail below with reference to the accompanying drawings and in conjunction with embodiments.

[0041] There are two grooves in the text below, the concave construction groove and the pipe groove located below it.

[0042] See also Figure 1-Figure 12 The present invention provides a construction process and apparatus for installing a pipe for a cover plate for urban renewal. The construction process comprises the following steps:

[0043] S1: Organize the urban renewal pipeline project data according to the design drawings, determine the center, direction, length, depth, inspection well location, red line range and other specific information of the renewal pipeline, conduct on-site positioning and laying out, and make corresponding markings in the construction site;

[0044] S2: Close the pipeline engineering site along the construction red line, vertically cut the original pavement structure layer along the upper edge of the trench layout results, break the original pavement structure between the two upper edges of the trench and dig it out. The excavated part includes the original pavement and part of the roadbed. The thickness of the excavated structure layer is not less than 40cm. After digging the road surface layer and part of the base layer, a concave construction groove is formed at the construction site. The width of the concave construction groove should meet the design requirements and be calculated as follows:

[0045]

[0046] Where B is the excavation width of the bottom of the pipeline trench;

[0047] D 0 ——Outer diameter of the pipe (mm);

[0048] b 1 ——The required width of the printing operation on one side of the pipe (mm);

[0049] b 2 ——Thickness of the support system on one side of the pipeline (mm);

[0050] The trench side slope is straight and not sloping.

[0051] S3: Locate the bottom edge of the pipeline trench along the bottom edge of the concave construction trench on both sides, mark it every 2 meters, and screw in the screw pile 1 vertically along the marked point;

[0052] The screw pile 1 is composed of a pile head 1.1, a screw rod 1.2, a smooth screw rod 1.3, and a pile top 1.4. The pile head 1.1 cuts the ground by pressing down and rotating at the same time, and the screw pile 1 is driven vertically downward into the soil as a whole, wherein the length of the screw rod 1.2 is not less than one third of the overall pile length, and the screw pile 1 is completely buried in the soil below the bottom surface of the pipeline trench.

[0053] The portion of the screw pile 1 above the bottom of the pipeline trench should be a smooth screw rod 1.3, the pile top 1.4 should be flush with the bottom of the concave construction trench, and the corresponding pile tops 1.4 on both sides of the concave construction trench should have the same height.

[0054] S4: Install the connecting beam 2 in the concave construction groove; the connecting beam 2 is sequentially fixed to the pile tops 1.4 of the screw piles 1 on both sides of the concave construction groove to form two beams extending along the longitudinal direction of the pipeline groove, which are used to form the overall groove support system in the later stage, and serve as the working track of the groove cover plate 3 and the 3D printer 5;

[0055] S5: Dig the soil in the pipeline trench vertically along the screw piles 1 on both sides of the concave construction trench, and remove the soil to the bottom of the pipeline trench; the trench soil is excavated in one go or in layers according to the depth. When excavating in layers, each layer is supported first, and then the lower soil is excavated. The support method refers to S6.

[0056] The trench wall of the excavated section should be smooth and the trench bottom should not be disturbed. When the bottom soil is miscellaneous fill or humus, it should be completely excavated and the trench bottom should be reinforced.

[0057] The excavated soil is selected for suitable soil quality and transported to the fluidized solidification soil field for the preparation of fluidized solidified soil. The soil quality should be excavated on site, the organic matter content should not be greater than 5%, and the coarse particle size should not be greater than 5cm. The fluidized solidified soil is mixed on site for use in S10. The preparation is divided into two steps: 1. Mix the mixing soil and water evenly; 2. Add the curing agent and mix.

[0058] S6: On both sides of the pipeline trench, groove baffles 4 are installed along the smooth screws 1.3 of the screw piles 1 to form a vertical groove slope for overall protection;

[0059] The groove baffle 4 is made of a material with a certain strength and not easy to deform, and the installation should be firm.

[0060] When the trench is too deep and needs to be excavated in layers, after the upper soil is excavated, the trench baffle 4 is installed first, and the lower soil can be excavated after the upper layer is fully supported. Excavation and support are carried out alternately, and the depth of each alternation is preferably 0.4m to 0.8m.

[0061] S7: Level and compact the bottom of the trench, and lay the pipeline cushion along the bottom of the trench as a reference surface for 3D printing; the bottom cushion should be C15 strength concrete, and deformation joints should be left according to design requirements, and the deformation joints should be consistent with the working interface of the 3D printer 5.

[0062] S8: Install 3D printer 5 on the inner side of connecting beam 2 on both sides of the trench, and install trench cover plate 3; screw pile 1, trench baffle 4, connecting beam 2, trench cover plate 3 form a trench overall support system; after the trench overall support system is established, temporarily lift the closure of the construction site and restore the road traffic function of the construction site;

[0063] S9: Connect the 3D printer 5 to the concrete pump station through the feed pipe 5.2, and use the 3D printer 5 to print the pipeline 6, the inspection well, and the pipeline support 7 with concrete in the pipeline trench to complete the main pipeline project; during the operation, the roads in the construction area have normal traffic functions;

[0064] S10: After the entire pipeline is completed, the construction area is closed for the second time, and the following are removed in sequence: trench cover 3, 3D printer 5, trench baffle 4, connecting beam 2, screw pile 1; fluidized solidified soil is poured along the longitudinal direction of the trench to fill the gaps between the pipeline supports 7, forming a pipeline protection system;

[0065] S11: Restore the roadbed and pavement structure layer, clean up the construction equipment, materials and debris in the site, lift the closure of the construction site, and restore the traffic function of the construction road.

[0066] The construction equipment structure is as follows:

[0067] The screw pile 1, the groove baffle 4, the connecting beam 2, and the groove cover 3 form an integral groove support system; the screw pile 1 is composed of a pile head 1.1, a screw rod 1.2, a smooth screw rod 1.3, and a pile top 1.4. The connecting beam 2 is composed of a beam body 2.1 and a printer longitudinal rod 2.2. The beam bodies 2.1 of adjacent connecting beams 2 are connected in sequence to form a beam that runs along the longitudinal direction of the groove; the 3D printer 5 is installed on the printer longitudinal rod 2.2, and is used to print pipelines 6, inspection wells, and pipeline supports 7 in the pipeline groove.

[0068] The groove cover plate 3 includes a panel 3.1 and a support grid 3.2; the panel 3.1 is a steel plate with a certain thickness. Preferably, a layer of USPC material is added on the top of the panel 3.1. After the USPC material and the steel are combined, noise is reduced, friction is increased, and anti-skid is prevented, so as to prevent pedestrians from falling due to the slip of the steel plate in winter. The groove cover plate 3 is installed on the connecting beam 2 with the support grid 3.2 facing downward, and the support grid 3.2 is stuck between the connecting beams 2 on both sides of the groove.

[0069] The groove cover plate 3 also includes lateral anti-skid teeth 3.3 arranged longitudinally along the groove cover plate 3 and blunt angles 3.4 at the four corners of the groove cover plate 3. The supporting grid 3.2 is a grid load-bearing structure composed of a plane connecting rod 3.22, an oblique connecting rod 3.23 and a node 3.21, and the lateral anti-skid teeth 3.3 are triangular saw teeth.

[0070] The 3D printer 5 is composed of a printer head 5.1, a feed pipe 5.2, a printer vertical rod 5.3, a printer cross rod 5.4, a longitudinal rod pulley 5.5, and a pulley 5.6; the 3D printer 5 is slidably connected to the printer longitudinal rod 2.2 via the longitudinal rod pulley 5.5, the printer head 5.1 is slidably connected to the printer vertical rod 5.3 via the pulley 5.6, and the printer vertical rod 5.3 is slidably connected to the printer cross rod 5.4 via the pulley 5.6. The above three-directional sliding realizes the spatial three-dimensional movement of the 3D printer 5.

[0071] The utility model also includes an opening tool 9 for opening and closing the groove cover plate 3, and the opening tool 9 is composed of an insertion rod 9.1, a pry bar 9.2, a handle 9.3, and a second wheel 9.4. The insertion rod 9.1 can be pressed against the panel 3.1 above the connecting beam 2, and the pry bar 9.2 can be pulled downward to raise the groove cover plate 3 by lever principle; the groove cover plate 3 can be lowered by releasing the pry bar 9.2, so as to realize opening and closing of the groove cover plate 3.

[0072] It also includes a moving tool 8 that enables the groove cover 3 to slide on the top of the connecting beam 2. The moving tool 8 is composed of a base 8.1, an axle 8.2, and a first wheel 8.3. The groove cover 3 can be raised or lowered on the top of the connecting beam 2 by an opening tool 9. After the groove cover 3 is raised, the moving tool 8 can be installed or removed. The moving tool 8 is installed at the four corners of the bottom surface of the groove cover 3, and the groove cover 3 is supported by the base 8.1; the first wheel 8.3 can move on the connecting beam 2.

[0073] The above describes in detail the preferred implementation of this patent, but this patent is not limited to the above implementation. Various changes can be made within the knowledge scope of ordinary technicians in this field without departing from the purpose of this patent.

Claims

1. A construction process for installing a cover plate pipeline for urban renewal, characterized in that: include: S1: Organize the urban renewal pipeline project data according to the design drawings, determine the center, direction, length, depth, inspection well location, and red line range of the renewal pipeline, conduct on-site positioning and laying out, and make corresponding markings in the construction site; S2: Close the pipeline engineering site along the construction red line, vertically cut the original pavement structure layer along the upper edge of the trench layout results, break the original pavement structure between the two upper edges of the trench and excavate it. The excavated part includes the original pavement and part of the roadbed. The thickness of the excavated structure layer is not less than 40cm. After excavating the road surface layer and part of the base layer, a concave construction groove is formed at the construction site; S3: Locate the bottom edge of the pipeline trench along the bottom edge of the concave construction trench on both sides, mark it every 2 meters, and screw in the screw piles vertically along the marked points; S4: Construction is carried out in the concave construction trench and the connecting beam is installed; the connecting beam is fixed to the top of the screw piles on both sides of the concave construction trench in turn to form two beams running along the longitudinal direction of the pipeline trench, which are used to form the overall trench support system in the later stage, and serve as the trench cover plate and the working track of the 3D printer; S5: Dig the soil in the pipeline trench vertically along the screw piles on both sides of the concave construction trench, and remove the soil to the bottom of the pipeline trench; S6: On both sides of the pipeline trench, install trench baffles along the smooth screws of the screw piles to form a vertical trench slope for overall protection; S7: Level and compact the bottom of the groove, and lay the pipeline cushion along the bottom of the groove as a reference surface for 3D printing; S8: Install 3D printers on the inner side of the connecting beams on both sides of the trench and install trench covers; screw piles, trench baffles, connecting beams, and trench covers form an overall trench support system; after the overall trench support system is established, temporarily lift the closure of the construction site and restore the road traffic function of the construction site; S9: Connect the 3D printer to the concrete pump station through the feed pipe, and use the 3D printer to print the pipeline, inspection well, and pipeline support to complete the main pipeline project; during the operation, the roads in the construction area have normal traffic functions; S10: After the entire pipeline is completed, the construction area is closed for the second time, and the following are removed in sequence: trench cover, 3D printer, trench baffle, connecting beam, screw pile; fluidized solidified soil is poured along the longitudinal direction of the trench to fill the gaps between the pipeline supports to form a pipeline protection system; S11: Restore the roadbed and pavement structure layer, clean up the construction equipment, materials and debris in the site, lift the closure of the construction site, and restore the traffic function of the construction road.

2. An urban renewal cover plate pipeline installation construction tool, characterized by: The screw piles, groove baffles, connecting beams and groove covers constitute an integral groove support system; the connecting beams consist of a beam body and a printer longitudinal rod, and the beam bodies of adjacent connecting beams are sequentially connected to form a beam that runs along the longitudinal direction of the groove; the 3D printer is installed on the printer longitudinal rod, and is used to print pipelines, inspection wells and pipeline supports in the pipeline groove; the groove cover includes a panel and a support grid, and the groove cover is installed on the connecting beam with the support grid facing downward, and the support grid is stuck between the connecting beams on both sides of the groove.

3. The urban renewal cover plate pipeline installation construction tool according to claim 2 is characterized by: The screw pile consists of a pile head, a screw rod, a smooth screw rod and a pile top.

4. The urban renewal cover plate pipeline installation construction tool according to claim 2 is characterized by: The groove cover plate also includes lateral anti-slip teeth arranged along the longitudinal direction of the groove cover plate and blunted corners at the four corners of the groove cover plate.

5. The urban renewal cover plate pipeline installation construction tool according to claim 4 is characterized by: The supporting grid is a grid load-bearing structure composed of planar connecting rods, oblique connecting rods and nodes, and the lateral anti-slip teeth are triangular saw teeth.

6. The urban renewal cover plate pipeline installation construction tool according to claim 2 is characterized by: The 3D printer consists of a printer head, a feed pipe, a printer vertical rod, a printer cross rod, a longitudinal rod pulley, and a pulley; the 3D printer is slidably connected to the printer longitudinal rod through the longitudinal rod pulley, the printer head is slidably connected to the printer vertical rod through the pulley, and the printer vertical rod is slidably connected to the printer cross rod through the pulley.

7. The urban renewal cover plate pipeline installation construction tool according to claim 2 is characterized by: It also includes a moving tool that enables the groove cover plate to slide on the top of the connecting beam, and the moving tool is composed of a bearing platform, an axle, and a first wheel.

8. The urban renewal cover plate pipeline installation construction tool according to claim 2 is characterized by: It also includes an opening tool for opening and closing the groove cover, and the opening tool consists of an insertion rod, a pry bar, a handle, and a second wheel.

Citation Information

Patent Citations

  • Municipal pipe network construction supporting integrated structure under unfavorable geological conditions and construction method

    CN114718116A

  • Cover excavation pipe gallery structure

    CN218757602U