By designing a system of data acquisition, analysis and control modules in power plants, the complex and cost problems of safety production management in the existing technology are solved, and comprehensive supervision and rapid response to equipment, environment and personnel safety are achieved, and the improvement of the Production level safe.

CN119294798AInactive Publication Date: 2025-01-10HUADIAN FU XIN ENERGY CORP ANN SAND HYDROELECTRIC POWER FACTO +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202411146043.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-20
Publication Date
2025-01-10
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The deployment and maintenance of existing power plants' safe production mobile management and control systems are complex, costly, and lack a comprehensive analysis of equipment safety, working environment and personnel safety training, which makes it difficult to effectively manage safety hazards.

Method used

A system including power plant safety production data acquisition, data analysis, judgment and management module is designed. By collecting and analyzing equipment operation, working environment and personnel training data, a safety management index is generated. If the set limit value is exceeded, an abnormality will be generated. Information and equipment and personnel safety control.

Benefits of technology

It has achieved comprehensive supervision of the safety production of power plants, improved the level of safety management, reduced the possibility of accidents, ensured the safety of equipment, environment and personnel, and improved safety management efficiency and response speed.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119294798A_ABST
    Figure CN119294798A_ABST
Patent Text Reader

Abstract

The invention relates to a power plant safety production mobile management and control system, which comprises the following modules: a power plant safety production data acquisition module, a power plant safety production data analysis module, a power plant safety production judgment module and a power plant safety management and control module. The invention further relates to a power plant safety production mobile management and control method. Power plant equipment working data, power plant working environment data and power plant staff safety training data are collected, power plant equipment safety, power plant working environment and power plant staff safety training are analyzed, and then a power plant equipment operation abnormity index, a power plant working environment abnormity index and a power plant staff safety training index are obtained; the comprehensive supervision and management of safety production are realized, the safety production level is improved, the possibility of accidents is reduced, and the equipment safety, the working environment safety and the staff safety are guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power plants, and in particular to a mobile control system and method for safe production of power plants. Background Art

[0002] As society pays more and more attention to safety issues, all walks of life are strengthening safety production management. As an important energy production unit, the safety production of power plants is related to national energy supply and social stability, so it is necessary to introduce advanced technical means to improve the level of safety management.

[0003] For example, publication number CN116128283A discloses a mobile control system and method for power plant production safety, which includes a business management layer: including an operation process safety control subsystem, a personnel behavior visualization subsystem, a personnel access control subsystem and a mobile inspection management subsystem; the operation process safety control subsystem is used for online error prevention management, intelligent pressure plate management, temporary ground wire management and maintenance isolation management; the personnel behavior visualization subsystem is used for personnel positioning management, power plant three-dimensional modeling, personnel trajectory query and virtual electronic fence; the personnel access control subsystem is used for intelligent access control management, intelligent lock control management, risk intelligent warning and outsider management; the mobile inspection management subsystem is used for inspection task compilation, inspection data collection, inspection data statistics and inspection data query; it can promote the construction of inherent safety and intelligent control with the characteristics of the power generation industry.

[0004] The above-mentioned mobile control system and method for safe production of power plants are relatively complex to deploy and maintain, and require a large amount of manpower, material and financial resources, resulting in high costs.

[0005] In addition, the system lacks analysis and judgment of the safety of power plant equipment, the working environment of the power plant, and the safety training of power plant personnel, resulting in the inability to conduct comprehensive mobile control of the power plant's production safety, which may lead to safety hazards in the power plant's production process. Summary of the invention

[0006] In view of the deficiencies in the prior art, the present invention provides a mobile control system and method for safe production in a power plant, which solves the problems of the above-mentioned background technology.

[0007] To achieve the above objectives, the present invention is implemented through the following technical solutions:

[0008] A power plant production safety mobile management and control system, comprising the following modules: a power plant production safety data acquisition module, a power plant production safety data analysis module, a power plant production safety judgment module, and a power plant safety management and control module;

[0009] The power plant production safety data acquisition module is used to collect power plant operation monitoring data and perform preprocessing to obtain power plant production safety data;

[0010] The power plant production safety data analysis module is used to analyze the health status and use risks of power plant equipment based on the power plant production safety data, obtain the power plant equipment operation abnormality index, analyze the safety characteristics of the power plant working environment, obtain the power plant working environment abnormality index, analyze the coverage of power plant personnel safety training and personnel safety training effect evaluation, obtain the power plant personnel safety training index, and comprehensively process the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index to obtain the power plant safety management and control index;

[0011] The power plant production safety judgment module is used to compare the power plant safety control index with the set power plant safety control index limit value, if the power plant safety control index is greater than the power plant safety control index limit value, generate power plant safety abnormality information, and send the power plant safety abnormality information to the power plant safety control module;

[0012] The power plant safety management and control module is used to receive the power plant safety anomaly information sent by the power plant safety production judgment module, and send the power plant safety anomaly information to the administrator, and manage the power plant equipment and personnel safety respectively through the administrator's operation.

[0013] Furthermore, the power plant safety production data includes power plant equipment working data, power plant working environment data, and power plant employee safety training data;

[0014] The power plant equipment operation data includes the normal operation time of the power plant equipment, the total operation time of the power plant equipment, the average load of the power plant equipment, the rated load of the power plant equipment, the number of failures of the power plant equipment, the average maintenance interval time of the power plant equipment, and the average maintenance time of the power plant equipment;

[0015] The power plant working environment data includes the average temperature value of the power plant working area, the set safe temperature value of the power plant working area, the temperature range fluctuation value of the power plant working area, the average noise intensity value of the power plant working area, and the safe noise standard value of the power plant working area;

[0016] The power plant employee safety training data includes the power plant employee attendance rate, the power plant employee participation rate, and the power plant employee test pass rate.

[0017] Furthermore, based on the working data of the power plant equipment, the health status and use risk of the power plant equipment are analyzed, and the specific process of obtaining the abnormal operation index of the power plant equipment is as follows:

[0018] Compare the normal operation time of the power plant working equipment with the total operation time of the power plant working equipment to obtain the operation availability rate of the power plant working equipment; compare the average load of the power plant working equipment with the rated load of the power plant working equipment to obtain the load rate of the power plant working equipment;

[0019] The power plant working equipment operation availability rate and the power plant working equipment load rate are processed comprehensively to obtain the power plant working equipment health status index;

[0020] The number of failures of the power plant working equipment is compared with the total operating time of the power plant working equipment to obtain the failure rate of the power plant working equipment, and the average maintenance interval time of the power plant working equipment is compared with the average maintenance time of the power plant working equipment to obtain the maintenance utilization rate of the power plant working equipment;

[0021] The power plant working equipment failure rate and the power plant working equipment maintenance utilization rate are processed comprehensively to obtain the power plant working equipment use risk index;

[0022] The power plant equipment operation abnormality index is obtained by comprehensively calculating the power plant equipment health status index and the power plant equipment use risk index.

[0023] Furthermore, based on the power plant working environment data, the safety characteristics of the power plant working environment are analyzed, and the specific process of obtaining the power plant working environment abnormality index is as follows:

[0024] The average temperature value of the power plant working area is calculated by absolute value with the set safe temperature value of the power plant working area, and compared with the fluctuation value of the temperature range of the power plant working area to obtain the abnormal temperature index of the power plant working area;

[0025] The average noise intensity value of the power plant working area is calculated by difference with the safety noise standard value of the power plant working area, and compared with the safety noise standard value of the power plant working area to obtain the power plant working noise abnormality index;

[0026] The power plant working temperature abnormality index and the power plant working noise abnormality index are comprehensively processed to obtain the power plant working environment abnormality index.

[0027] Furthermore, based on the power plant employee safety training data, the power plant personnel safety training coverage and the personnel safety training effectiveness evaluation are analyzed, and the specific process of obtaining the power plant personnel safety training index is as follows: each safety training is numbered 1, 2, 3..., i,...n in sequence, and the power plant employee attendance rate, power plant employee participation rate and power plant employee test pass rate are comprehensively calculated and processed to obtain the power plant personnel safety training index.

[0028] Furthermore, the specific formula of the power plant personnel safety training index is as follows:

[0029]

[0030] Where ω represents the power plant personnel safety training index, FJ i represents the attendance rate of power plant employees at the i-th safety training, KP i represents the participation rate of power plant employees in the i-th safety training, BH i represents the pass rate of the power plant employees in the i-th safety training test, i represents the number of safety training, and n represents the total number of safety training numbers.

[0031] Furthermore, the specific process of comprehensively processing the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index to obtain the power plant safety control index is as follows:

[0032] By using the analytic hierarchy process, weights are assigned to the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index, and the weight factors of the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index are obtained;

[0033] The power plant safety management index is obtained by comprehensively calculating the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index and the weight factor of the power plant equipment operation abnormality index, the weight factor of the power plant working environment abnormality index and the weight factor of the power plant personnel safety training index.

[0034] Furthermore, the specific formula of the power plant safety control index is as follows:

[0035]

[0036] In the formula, Gv represents the power plant safety control index, τ represents the power plant equipment operation abnormality index, represents the abnormal working environment index of the power plant, ω represents the safety training index of the power plant personnel, α1 represents the weight factor of the abnormal operation index of the power plant equipment, α2 represents the weight factor of the abnormal working environment index of the power plant, and α3 represents the weight factor of the safety training index of the power plant personnel.

[0037] Furthermore, the specific process of generating power plant safety abnormality information is as follows:

[0038] The power plant safety control index is compared with the set limit value of the power plant safety control index. When the power plant safety control index exceeds the set limit value of the power plant safety control index, the abnormal conditions of the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index are analyzed to generate corresponding safety abnormality information.

[0039] A mobile control method for safe production of a power plant comprises the following steps:

[0040] S1. Collect power plant operation monitoring data and pre-process it to obtain power plant safety production data;

[0041] S2. Based on the power plant's production safety data, analyze the health status and use risks of the power plant's equipment, obtain the power plant's equipment operation abnormality index, analyze the safety characteristics of the power plant's working environment, obtain the power plant's working environment abnormality index, analyze the coverage of the power plant's personnel safety training and the evaluation of the personnel safety training effect, and obtain the power plant's personnel safety training index;

[0042] S3. Comprehensively process the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index to obtain the power plant safety control index;

[0043] S4. Compare the power plant safety control index with the set limit value of the power plant safety control index. If the power plant safety control index is greater than the limit value of the power plant safety control index, generate power plant safety abnormality information, and send the power plant safety abnormality information to the administrator. Through the administrator's operation, the power plant equipment and personnel safety are controlled respectively.

[0044] The present invention has the following beneficial effects:

[0045] (1) The present invention collects power plant equipment operating data, power plant working environment data, and power plant employee safety training data, analyzes the power plant equipment safety, power plant working environment, and power plant personnel safety training, and then obtains the power plant equipment operation abnormality index, power plant working environment abnormality index, and power plant personnel safety training index, to achieve comprehensive supervision and management of production safety, improve the level of production safety, reduce the possibility of accidents, and ensure equipment safety, work environment safety, and employee safety.

[0046] (2) The present invention also generates power plant safety anomaly information by acquiring and comparing the power plant safety control index with the set limit value of the power plant safety control index, and manages the power plant equipment and personnel safety respectively through administrator operation, which can help the power plant to achieve timely monitoring, rapid response and effective control of production safety, thereby improving safety management efficiency, reducing safety risks, and ensuring the safety of equipment and personnel.

[0047] Of course, any product implementing the present invention does not necessarily need to achieve all of the advantages described above at the same time. BRIEF DESCRIPTION OF THE DRAWINGS

[0048] Figure 1 The present invention is a flow chart of a mobile control system for safe production in a power plant.

[0049] Figure 2 The present invention is a flow chart of a method for mobile control of power plant production safety. DETAILED DESCRIPTION

[0050] The embodiment of the present application uses a mobile control system and method for power plant production safety to achieve analysis and judgment on power plant equipment safety, power plant working environment and power plant personnel safety training, comprehensively conduct mobile control of power plant production safety, and solve the problem of safety hazards in the production process of the power plant.

[0051] The overall idea of ​​this application is as follows:

[0052] Collect power plant operation monitoring data and pre-process it to obtain power plant safety production data.

[0053] Based on the power plant's production safety data, the health status and usage risks of the power plant's equipment are analyzed to obtain the power plant equipment operation abnormality index. The safety characteristics of the power plant's working environment are analyzed to obtain the power plant's working environment abnormality index. The coverage of power plant personnel safety training and the evaluation of personnel safety training effectiveness are analyzed to obtain the power plant personnel safety training index.

[0054] The power plant safety management index is obtained by comprehensively processing the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index.

[0055] The power plant safety control index is compared with the set limit value of the power plant safety control index. If the power plant safety control index is greater than the limit value of the power plant safety control index, power plant safety abnormality information is generated.

[0056] The power plant safety anomaly information is sent to the administrator, and the power plant equipment and personnel safety are managed and controlled through the administrator's operations.

[0057] See also Figure 1 , a mobile control system for power plant production safety, including the following modules: a power plant production safety data acquisition module, a power plant production safety data analysis module, a power plant production safety judgment module, and a power plant safety control module;

[0058] The power plant safety production data acquisition module is used to collect power plant operation monitoring data and perform preprocessing to obtain power plant safety production data; the power plant safety production data analysis module is used to analyze the health status and use risks of power plant equipment based on power plant safety production data, obtain the power plant equipment operation abnormality index, analyze the safety characteristics of the power plant working environment, obtain the power plant working environment abnormality index, analyze the coverage of power plant personnel safety training and personnel safety training effect evaluation, obtain the power plant personnel safety training index, and comprehensively process the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index to obtain the power plant safety management and control index;

[0059] The power plant production safety judgment module is used to compare the power plant safety control index with the set power plant safety control index limit value. If the power plant safety control index is greater than the power plant safety control index limit value, the power plant safety abnormality information is generated and sent to the power plant safety control module;

[0060] The power plant safety management and control module is used to receive the power plant safety anomaly information sent by the power plant safety production judgment module, and send the power plant safety anomaly information to the administrator, so as to manage and control the power plant equipment and personnel safety respectively through the administrator's operation.

[0061] In this implementation scheme, the power plant production safety data acquisition module is responsible for collecting various production safety-related data from the power plant's monitoring equipment and preprocessing these data for subsequent analysis and use; the power plant production safety judgment module compares the power plant's safety control index with the pre-set safety control index limit value based on the analyzed data. If the power plant's safety control index exceeds the limit value, it will generate power plant safety anomaly information for further processing. The power plant safety control module receives the safety anomaly information from the production safety judgment module and sends it to the administrator, who can use this module to control the equipment and personnel safety of the power plant and take appropriate measures to deal with safety anomalies.

[0062] Specifically, the power plant safety production data includes power plant equipment working data, power plant working environment data, and power plant employee safety training data;

[0063] The power plant equipment operation data include the normal operation time of the power plant equipment, the total operation time of the power plant equipment, the average load of the power plant equipment, the rated load of the power plant equipment, the number of failures of the power plant equipment, the average maintenance interval time of the power plant equipment, and the average maintenance time of the power plant equipment;

[0064] The power plant working environment data includes the average temperature value of the power plant working area, the set safe temperature value of the power plant working area, the temperature range fluctuation value of the power plant working area, the average noise intensity value of the power plant working area, and the safe noise standard value of the power plant working area;

[0065] Power plant employee safety training data includes power plant employee attendance rate, power plant employee participation rate, and power plant employee test pass rate.

[0066] It should be noted that the normal operation time of the working equipment of a power plant refers to the period of time during which the working equipment operates normally under the specified operating conditions, which can be obtained through the operation records of the monitoring equipment of the working equipment;

[0067] The total operating time of the working equipment of the power plant refers to the total operating time of the working equipment in a specific period, including normal operation time and shutdown maintenance time, which is obtained through the equipment operation log;

[0068] The average load of working equipment in a power plant refers to the average load level of working equipment during operation, which is obtained through monitoring equipment of working equipment;

[0069] The rated load of the working equipment of a power plant refers to the maximum load capacity specified when the working equipment is designed or manufactured, which can be obtained from the equipment manual.

[0070] The number of failures of working equipment in a power plant refers to the number of failures that occur during the operation of the working equipment, which is obtained through equipment maintenance records.

[0071] The mean maintenance interval of power plant working equipment refers to the average time interval between failure or maintenance of working equipment after continuous operation for a period of time.

[0072] The average maintenance time of working equipment in a power plant refers to the average repair time when the working equipment is under maintenance.

[0073] The average temperature value of the power plant working area refers to the average temperature value in the power plant working area, which is obtained by arranging temperature sensors in the working area and monitoring in real time. The average noise intensity value of the power plant working area refers to the average noise intensity value in the power plant working area, which can be obtained by arranging noise sensors in the working area and monitoring in real time. The safe temperature value of the power plant working area refers to the maximum allowable temperature in the power plant working area. The temperature range fluctuation value of the power plant working area indicates the range of temperature changes in the working area within a certain period of time. The safe noise standard value of the power plant working area indicates the maximum noise level allowed in the working area.

[0074] The attendance rate of power plant employees refers to the proportion of employees who work according to the shift schedule. The participation rate of power plant employees refers to the proportion of employees who participate in safety training activities. The pass rate of power plant employees' tests refers to the proportion of employees who pass the test after the safety training.

[0075] Specifically, based on the working data of power plant equipment, the health status and use risk of power plant equipment are analyzed, and the specific process of obtaining the abnormal operation index of power plant equipment is as follows: the normal operation time of power plant equipment is compared with the total operation time of power plant equipment to obtain the operation availability of power plant equipment; the average load of power plant equipment is compared with the rated load of power plant equipment to obtain the load rate of power plant equipment; the operation availability of power plant equipment and the load rate of power plant equipment are comprehensively processed to obtain the health status index of power plant equipment;

[0076] The number of failures of the power plant working equipment is compared with the total operating time of the power plant working equipment to obtain the failure rate of the power plant working equipment; the average maintenance interval time of the power plant working equipment is compared with the average maintenance time of the power plant working equipment to obtain the maintenance utilization rate of the power plant working equipment; the failure rate of the power plant working equipment and the maintenance utilization rate of the power plant working equipment are comprehensively processed to obtain the use risk index of the power plant working equipment;

[0077] The power plant equipment operation abnormality index is obtained by comprehensively calculating the power plant equipment health status index and the power plant equipment use risk index.

[0078] In this implementation scheme, in addition to regular evaluation and inspection of the equipment operation status by experts, the power plant equipment operation abnormality index can be obtained through expert experience and knowledge. The power plant equipment operation abnormality index can also be calculated through the following calculation formula. The calculation formula of the power plant equipment operation abnormality index is as follows:

[0079]

[0080] In the formula, Rd represents the health status index of the power plant equipment, which is used to evaluate the health status of the power plant equipment; Cs represents the risk index of the power plant equipment, which is used to measure the risk level of the power plant equipment; τ represents the abnormal operation index of the power plant equipment, which is used to evaluate the abnormal operation level of the power plant equipment; Qf represents the normal operation time of the power plant equipment, QZ represents the total operation time of the power plant equipment, Pxh represents the average load of the power plant equipment, Ped represents the rated load of the power plant equipment, Wv represents the number of failures of the power plant equipment, Fk represents the average maintenance interval of the power plant equipment, and Dn represents the power plant equipment. The average maintenance time, β1 represents the weight factor of the power plant equipment health index, and β2 represents the weight factor of the power plant equipment use risk index. The weight factor is obtained by comparing the hierarchical analysis method. The example is as follows: set the target layer and the criterion layer, the target layer: evaluate the power plant equipment operation abnormality index, the criterion layer: the power plant equipment health index, the power plant equipment use risk index; construct a pairwise comparison matrix through the weight factor of the power plant equipment health index and the weight factor of the power plant equipment use risk index, and compare the two indicators in pairs according to the expert evaluation, give their relative importance values, and normalize the pairwise comparison matrix. Sum each row of the normalized matrix, and then take the average value to get the weight vector.

[0081] Specifically, based on the power plant working environment data, the safety characteristics of the power plant working environment are analyzed, and the specific process of obtaining the power plant working environment abnormality index is as follows:

[0082] The average temperature value of the power plant working area is calculated by absolute value with the set safe temperature value of the power plant working area, and compared with the fluctuation value of the temperature range of the power plant working area to obtain the abnormal temperature index of the power plant working area;

[0083] The average noise intensity value of the power plant working area is calculated by difference with the safety noise standard value of the power plant working area, and compared with the safety noise standard value of the power plant working area to obtain the power plant working noise abnormality index;

[0084] The power plant working temperature abnormality index and the power plant working noise abnormality index are comprehensively processed to obtain the power plant working environment abnormality index.

[0085] In this implementation scheme, in addition to obtaining the power plant working environment abnormality index by experts performing regular evaluation and inspection on the equipment operation status, the power plant working environment abnormality index can also be calculated by the following calculation formula. The specific formula of the power plant working environment abnormality index is as follows:

[0086]

[0087] In the formula, It represents the abnormal index of the working environment of the power plant, which is used to evaluate the abnormal degree of the working environment of the power plant. Ks represents the average temperature value of the working area of ​​the power plant, T A represents the safe temperature value of the working area of ​​the power plant, ΔWd represents the temperature fluctuation value of the working area of ​​the power plant, γ represents the abnormal temperature index of the power plant, which is used to measure the abnormal degree of the working temperature of the power plant, and N a Indicates the average noise intensity value in the working area of ​​the power plant, N s It represents the standard value of the safety noise in the working area of ​​the power plant, δ represents the abnormal index of the working noise of the power plant, which is used to evaluate the abnormal degree of the working noise of the power plant, ε1 represents the weight factor of the abnormal index of the working temperature of the power plant, and ε2 represents the weight factor of the abnormal index of the working noise of the power plant. The weight factor is obtained by comparing the analytic hierarchy process.

[0088] Specifically, based on the power plant employee safety training data, the power plant personnel safety training coverage and the personnel safety training effectiveness evaluation are analyzed, and the specific process of obtaining the power plant personnel safety training index is as follows: each safety training is numbered 1, 2, 3..., i,...n in sequence, and the power plant employee attendance rate, power plant employee participation rate and power plant employee test pass rate are comprehensively calculated and processed to obtain the power plant personnel safety training index.

[0089] In this implementation scheme, the attendance of employees at each safety training is recorded, and the attendance rate can be calculated by the ratio of the number of employees who attended to the total number of employees who should attend. The higher the attendance rate, the higher the participation in the training. The participation of employees in the training activities in each safety training is recorded, and the participation rate can be calculated by the ratio of the number of employees who participated in the training activities to the total number of employees. The participation rate reflects the degree of importance that employees attach to safety training. Each safety training is assessed or tested, the test scores of the employees are recorded, and the test pass rate is calculated, that is, the ratio of the number of employees who passed the test to the total number of employees who participated in the test. The test pass rate reflects the degree of mastery of safety knowledge by employees. The data such as attendance rate, participation rate and test pass rate are comprehensively calculated and processed, and the weighted average method or other algorithms can be used to obtain the power plant personnel safety training index.

[0090] Specifically, in addition to obtaining the power plant personnel safety training index by experts through regular evaluation and inspection of the equipment operation status, the power plant personnel safety training index can also be calculated through the following calculation formula. The specific formula of the power plant personnel safety training index is as follows:

[0091] Where ω represents the power plant personnel safety training index, which is used to evaluate the safety training level of power plant personnel, and FJ irepresents the attendance rate of power plant employees at the i-th safety training, KP i represents the participation rate of power plant employees in the i-th safety training, BH i represents the pass rate of the power plant employees in the i-th safety training test, i represents the number of safety training, and n is the total number of safety training numbers.

[0092] In this implementation scheme, by calculating the safety training index, the effect of each safety training can be objectively evaluated. A higher safety training index means that employees have a higher level of mastery of safety knowledge and the training effect is better. The safety training index not only includes the attendance rate and participation rate of employees, but also takes other parameters into consideration. By monitoring the changes in the safety training index, changes in employee participation can be discovered in a timely manner, and timely measures can be taken to promote employees to actively participate in safety training. By analyzing the safety training index, problems and deficiencies in the training process can be discovered. Managers can adjust and improve the content and methods of training according to changes in the safety training index to improve the training effect. By regularly calculating and publishing the safety training index, employees' safety awareness and sense of responsibility can be enhanced. A higher safety training index can motivate employees to actively participate in safety training, thereby improving the safety management level of the entire power plant.

[0093] Specifically, the specific process of comprehensively processing the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index to obtain the power plant safety control index is as follows:

[0094] The power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index are assigned weights through the hierarchical analysis method to obtain the weight factors of the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index; the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index are comprehensively processed with the weight factors of the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index to obtain the power plant safety management and control index.

[0095] In this implementation plan, a comprehensive evaluation index is obtained by comprehensively considering factors such as abnormal operation of power plant equipment, abnormal working environment and personnel safety training, which is used to evaluate the safety management level and safety risks of power plants. By decomposing complex decision-making problems into a hierarchical structure, and then determining the importance and weights of factors at each level through expert judgment and data analysis, a comprehensive evaluation result is finally obtained. In the comprehensive calculation process, weighted calculation can be performed according to the weight factor of each factor to obtain the power plant safety management index.

[0096] Specifically, in addition to regular evaluation and inspection of the equipment operation status by experts to obtain the power plant safety control index, the specific formula of the power plant safety control index is as follows:

[0097]

[0098] In the formula, Gv represents the power plant safety control index, τ represents the power plant equipment operation abnormality index, represents the abnormal working environment index of the power plant, ω represents the safety training index of the power plant personnel, α1 represents the weight factor of the abnormal operation index of the power plant equipment, α2 represents the weight factor of the abnormal working environment index of the power plant, and α3 represents the weight factor of the safety training index of the power plant personnel.

[0099] In this implementation scheme, when calculating the power plant safety control index, each index and weight factor are weighted, and exponential operation is used. This processing method may be to better reflect the relationship between each index and weight factor, and their comprehensive impact on the power plant safety control index. The three indexes of abnormal operation of power plant equipment, abnormal working environment and personnel safety training are comprehensively considered, and some special processing is performed when calculating the power plant safety control index to better reflect the impact of various aspects on safety control.

[0100] Specifically, the specific process of generating power plant safety abnormality information is as follows: compare the power plant safety management and control index with the set limit value of the power plant safety management and control index. When the power plant safety management and control index exceeds the set limit value of the power plant safety management and control index, analyze the abnormal conditions of the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index to generate corresponding safety abnormality information.

[0101] In this implementation scheme, the power plant production safety mobile management and control system can monitor the power plant's safety management and control index in real time. Once the index is found to exceed the set limit value, the system can analyze the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index, and immediately generate corresponding safety abnormality information, and issue an early warning to help managers discover potential safety risks in a timely manner. For example: when the power plant safety management and control index exceeds the set power plant safety management and control index limit value, if the power plant personnel safety training index is found to be abnormal, the employee's abnormal information will be displayed, and the power plant employee's safety training attendance rate, participation rate, and test pass rate will be obtained, and they will be transferred to other positions or retrained.

[0102] See also Figure 2, a mobile control method for power plant production safety, comprising the following steps: S1. Collecting power plant operation monitoring data and preprocessing to obtain power plant production safety data; S2. Based on the power plant production safety data, analyzing the health status and use risk of power plant equipment, obtaining the power plant equipment operation abnormality index, analyzing the safety characteristics of the power plant working environment, obtaining the power plant working environment abnormality index, analyzing the power plant personnel safety training coverage and personnel safety training effect evaluation, and obtaining the power plant personnel safety training index; S3. Comprehensively processing the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index to obtain the power plant safety control index; S4. Comparing the power plant safety control index with the set limit value of the power plant safety control index, if the power plant safety control index is greater than the limit value of the power plant safety control index, generating power plant safety abnormality information, and sending the power plant safety abnormality information to the administrator, and controlling the power plant equipment and personnel safety respectively through the administrator's operation.

[0103] In this implementation plan, the health status of power plant equipment, the safety characteristics of the working environment, and the coverage and effectiveness of personnel safety training are comprehensively considered. Through comprehensive analysis and processing of these indicators, the safety control index of the power plant is obtained. This comprehensive processing method of multi-dimensional indicators can more comprehensively evaluate the safety status of the power plant and provide more accurate data support for safety management.

[0104] In summary, this application has at least the following effects:

[0105] A mobile control system and method for power plant production safety collects power plant equipment working data, power plant working environment data, and power plant employee safety training data to analyze power plant equipment safety, power plant working environment, and power plant personnel safety training, obtains power plant equipment operation abnormality index, power plant working environment abnormality index, and power plant personnel safety training index, realizes comprehensive supervision and management of production safety, improves production safety level, reduces the possibility of accidents, ensures equipment safety, working environment safety, and employee safety, generates power plant safety abnormality information by comparing the power plant safety control index with a set limit value of the power plant safety control index, and helps power plants realize timely monitoring, rapid response, and effective control of production safety, thereby improving safety management efficiency, reducing safety risks, and ensuring the safety of equipment and personnel.

[0106] Those skilled in the art will appreciate that embodiments of the present invention may be provided as methods, systems, or computer program products. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.

[0107] The present invention is described with reference to flowcharts and / or block diagrams of systems, devices (systems), and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0108] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0109] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0110] Although the preferred embodiments of the present invention have been described, those skilled in the art may make other changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications that fall within the scope of the present invention.

[0111] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.

Claims

1. A mobile control system for safe production in a power plant, characterized in that: It includes the following modules: power plant production safety data acquisition module, power plant production safety data analysis module, power plant production safety judgment module, power plant safety management and control module; The power plant production safety data acquisition module is used to collect power plant operation monitoring data and perform preprocessing to obtain power plant production safety data; The power plant production safety data analysis module is used to analyze the health status and use risks of power plant equipment based on the power plant production safety data, obtain the power plant equipment operation abnormality index, analyze the safety characteristics of the power plant working environment, obtain the power plant working environment abnormality index, analyze the coverage of power plant personnel safety training and personnel safety training effect evaluation, obtain the power plant personnel safety training index, and comprehensively process the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index to obtain the power plant safety management and control index; The power plant production safety judgment module is used to compare the power plant safety control index with the set power plant safety control index limit value, if the power plant safety control index is greater than the power plant safety control index limit value, generate power plant safety abnormality information, and send the power plant safety abnormality information to the power plant safety control module; The power plant safety management and control module is used to receive the power plant safety anomaly information sent by the power plant safety production judgment module, and send the power plant safety anomaly information to the administrator, and manage the power plant equipment and personnel safety respectively through the administrator's operation.

2. A mobile control system for safe production of power plants according to claim 1, characterized in that: The power plant safety production data includes power plant equipment working data, power plant working environment data, and power plant employee safety training data; The power plant equipment operation data includes the normal operation time of the power plant equipment, the total operation time of the power plant equipment, the average load of the power plant equipment, the rated load of the power plant equipment, the number of failures of the power plant equipment, the average maintenance interval time of the power plant equipment, and the average maintenance time of the power plant equipment; The power plant working environment data includes the average temperature value of the power plant working area, the set safe temperature value of the power plant working area, the temperature range fluctuation value of the power plant working area, the average noise intensity value of the power plant working area, and the safe noise standard value of the power plant working area; The power plant employee safety training data includes the power plant employee attendance rate, the power plant employee participation rate, and the power plant employee test pass rate.

3. A mobile control system for safe production of power plants according to claim 2, characterized in that: Based on the working data of power plant equipment, the health status and use risk of power plant equipment are analyzed, and the specific process of obtaining the abnormal operation index of power plant equipment is as follows: Compare the normal operation time of the power plant working equipment with the total operation time of the power plant working equipment to obtain the operation availability rate of the power plant working equipment; compare the average load of the power plant working equipment with the rated load of the power plant working equipment to obtain the load rate of the power plant working equipment; The power plant working equipment operation availability rate and the power plant working equipment load rate are processed comprehensively to obtain the power plant working equipment health status index; The number of failures of the power plant working equipment is compared with the total operating time of the power plant working equipment to obtain the failure rate of the power plant working equipment, and the average maintenance interval time of the power plant working equipment is compared with the average maintenance time of the power plant working equipment to obtain the maintenance utilization rate of the power plant working equipment; The power plant working equipment failure rate and the power plant working equipment maintenance utilization rate are processed comprehensively to obtain the power plant working equipment use risk index; The power plant equipment operation abnormality index is obtained by comprehensively calculating the power plant equipment health status index and the power plant equipment use risk index.

4. A mobile control system for safe production of power plants according to claim 3, characterized in that: Based on the working environment data of the power plant, the safety characteristics of the working environment of the power plant are analyzed, and the specific process of obtaining the abnormal index of the working environment of the power plant is as follows: The average temperature value of the power plant working area is calculated by absolute value with the set safe temperature value of the power plant working area, and compared with the fluctuation value of the temperature range of the power plant working area to obtain the abnormal temperature index of the power plant working area; The average noise intensity value of the power plant working area is calculated by difference with the safety noise standard value of the power plant working area, and compared with the safety noise standard value of the power plant working area to obtain the power plant working noise abnormality index; The power plant working temperature abnormality index and the power plant working noise abnormality index are comprehensively processed to obtain the power plant working environment abnormality index.

5. A mobile control system for safe production of power plants according to claim 4, characterized in that: Based on the power plant employee safety training data, the power plant personnel safety training coverage and personnel safety training effect evaluation are analyzed. The specific process of obtaining the power plant personnel safety training index is as follows: Each safety training is numbered 1, 2, 3..., i,... n in sequence, and the attendance rate, participation rate and test pass rate of power plant employees are comprehensively calculated to obtain the power plant personnel safety training index; The specific formula of the power plant personnel safety training index is as follows: Where ω represents the power plant personnel safety training index, FJ i represents the attendance rate of power plant employees at the i-th safety training, KP i represents the participation rate of power plant employees in the i-th safety training, BH i represents the pass rate of the power plant employees in the i-th safety training test, i represents the number of safety training, and n represents the total number of safety training numbers.

6. A mobile control system for safe production of power plants according to claim 5, characterized in that: The specific process of comprehensively processing the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index to obtain the power plant safety control index is as follows: By using the analytic hierarchy process, weights are assigned to the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index, and the weight factors of the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index are obtained; The power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index are comprehensively calculated and processed with the weight factor of the power plant equipment operation abnormality index, the weight factor of the power plant working environment abnormality index and the weight factor of the power plant personnel safety training index to obtain the power plant safety control index; The specific formula of the power plant safety control index is as follows: In the formula, Gv represents the power plant safety control index, τ represents the power plant equipment operation abnormality index, represents the abnormal working environment index of the power plant, ω represents the safety training index of the power plant personnel, α1 represents the weight factor of the abnormal operation index of the power plant equipment, α2 represents the weight factor of the abnormal working environment index of the power plant, and α3 represents the weight factor of the safety training index of the power plant personnel.

7. A mobile control system for safe production of power plants according to claim 6, characterized in that: The specific process of generating power plant safety abnormality information is as follows: The power plant safety control index is compared with the set limit value of the power plant safety control index. When the power plant safety control index exceeds the set limit value of the power plant safety control index, the abnormal conditions of the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index are analyzed to generate corresponding safety abnormality information.

8. A power plant production safety mobile control method, applied to a power plant production safety mobile control system according to any one of claims 1 to 7, characterized in that: The following steps are involved: S1. Collect power plant operation monitoring data and pre-process it to obtain power plant safety production data; S2. Based on the power plant's production safety data, analyze the health status and use risks of the power plant's equipment, obtain the power plant's equipment operation abnormality index, analyze the safety characteristics of the power plant's working environment, obtain the power plant's working environment abnormality index, analyze the coverage of the power plant's personnel safety training and the evaluation of the personnel safety training effect, and obtain the power plant's personnel safety training index; S3. Comprehensively process the power plant equipment operation abnormality index, the power plant working environment abnormality index and the power plant personnel safety training index to obtain the power plant safety control index; S4. Compare the power plant safety control index with the set limit value of the power plant safety control index. If the power plant safety control index is greater than the limit value of the power plant safety control index, generate power plant safety abnormality information, and send the power plant safety abnormality information to the administrator. Through the administrator's operation, the power plant equipment and personnel safety are controlled respectively.

Citation Information

Patent Citations

  • Power plant safety production mobile management and control system and method

    CN116128283A