Temporary vertical water supply method for high-rise building
By pre-embedding vertical water supply pipes during the construction of vertical steel bars in high-rise building structures, the problem of traditional water supply methods affecting construction results and increasing costs has been solved. Convenient and synchronous temporary vertical water supply has been achieved, reducing construction complexity and costs.
Patent Information
- Application Number
- CN202411494054.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-24
- Publication Date
- 2025-01-21
AI Technical Summary
The temporary vertical water supply method of traditional high-rise buildings will affect the construction effect and decoration effect of building exterior walls and pipeline wells, and occupy building space. The water pipe layout is complicated during the construction process, and the installation and demolition are cumbersome. Additional insulation and freezing are required in winter, which increases construction costs.
During the construction of the vertical steel bars of the structure, the vertical water supply pipes are pre-buried. After the formwork is removed, the pipe heads are cleaned and connected to the external water outlet to achieve normal water use and simplify the construction process.
The simultaneous implementation of temporary water pipelines and structures has been achieved, and the stents and later demolition and repair work of temporary water construction have been reduced. It provides convenient maintenance of water and work surface cleaning, avoiding winter anti -freezing problems, and reduced construction costs.
Smart Images

Figure CN119332770A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building construction, and in particular relates to a temporary vertical water supply method for a high-rise building. Background Art
[0002] Vertical water supply for floor construction has always been a difficult problem in project implementation, requiring timely and convenient installation and disassembly of vertical water supply, no impact on formal engineering construction, and as little finishing work as possible after disassembly. The traditional method of laying temporary water supply pipelines for high-rise or multi-story buildings is to install them along the outer wall or along the pipeline well to the roof, and use a variable frequency water pump for water supply. Although the above-mentioned traditional water supply method can solve the problem of temporary water supply on the upper floors of high-rise buildings, it will affect the construction effect inside the outer wall of the building and the decorative effect of the pipeline well. At the same time, it will also have an adverse effect on the use of the outer wall and the pipeline well, and occupy the building space. It is often displaced during the construction process. The water pipe layout requires a large number of brackets, and the installation, removal and repair are very troublesome. In winter, the water pipes need to be insulated and antifreeze treated, which consumes a lot of manpower and material resources, greatly increasing the construction cost. In order to solve the above technical problems, the present invention designs a new type of temporary vertical water supply method for high-rise buildings. Summary of the invention
[0003] In view of the deficiencies in the prior art, the present invention provides a temporary vertical water supply method for high-rise buildings. During the construction of the vertical reinforcement of the structure, the vertical water supply pipe is pre-buried. After the mold is removed, the internal pipe head of the structure is cleaned out and the external water outlet is prepared, so that normal water use can be achieved, which is convenient and quick.
[0004] The present invention achieves the above technical objectives through the following technical means.
[0005] A temporary vertical water supply method for a high-rise building includes the following steps: Step 1: Construction water design; Step 2: Assemble and install the pre-buried water pipes on the first floor; Step 3: The first floor concrete structure is sealed and poured. After the concrete pouring is completed and meets the requirements, the formwork is removed; Step 4: Clean the pre-buried water pipe head on the first floor, then connect the water inlet valve to the water source; Step 5: Assemble the pre-buried water pipes in the middle section; Step 6: Connect the upper and lower pre-buried water pipes; Step 7: The upper concrete structure is sealed and poured. After the concrete pouring is completed and meets the requirements, the formwork is removed; Step 8: Install the faucet; Step 9: Repeat steps 5 to 8, and construct the remaining layers of pre-buried water pipes upwards in sequence.
[0006] Furthermore, in step 2, the pre-buried water pipes on the first floor are pre-buried and installed together with the vertical steel bars of the concrete structure on the first floor, and are pre-buried and fixed by the vertical steel bars, and the upper part of the pre-buried water pipes on the first floor extends into the upper floor.
[0007] Furthermore, the pre-buried water pipes on the first floor include galvanized steel pipes connected by threads, end valves and end elbows are installed on the upper ends of the galvanized steel pipes, water pipe elbows are installed on the lower ends of the galvanized steel pipes, the mouths of the water pipe elbows are tightly sealed with water pipe plugs, and the water pipe elbows are used in conjunction with the "86" junction box for pre-buried, and before the template is installed, the "86" junction box is filled tightly with soft materials and sealed with tape, and the box mouth is close to the template.
[0008] Furthermore, in step 5, the embedded water pipe in the middle section includes a galvanized steel pipe connected by a thread, an end valve and an end elbow are installed at the upper end of the galvanized steel pipe, a water pipe tee is installed at the lower end of the galvanized steel pipe, the opening of the water pipe tee is tightly sealed with a water pipe plug, and the water pipe tee is used in conjunction with an "86" junction box for pre-embedded use, and before the upper template is installed, the "86" junction box is tightly filled with soft material and sealed with tape, and the box opening is close to the template.
[0009] Furthermore, the specific process of step 6 is as follows: Before installing the upper formwork, close the water inlet valve on the first floor, remove the end valve on the upper part of the pre-buried water pipe on the first floor, insert the top of the galvanized steel pipe of the pre-buried water pipe on the first floor into the "86" junction box of the middle section pre-buried water pipe and connect it to the water pipe tee, then carry out the pre-buried installation of the middle section pre-buried water pipe and ensure that the upper part of the middle section pre-buried water pipe extends into the upper layer.
[0010] Furthermore, the specific process of step 8 is as follows: Clean the filling material in the "86" junction box of the middle section pre-buried water pipe, close the bottom water inlet valve, remove the water pipe plug at the three-way opening of the middle section pre-buried water pipe, connect the short pipe and faucet, and then open the bottom water inlet valve to supply water upwards.
[0011] Furthermore, when water is not needed in the later stage of interior decoration of the building, the external short pipes on each floor are manually removed, grouting is performed in the water supply pipeline, and the decorative surface is partially repaired after the mortar is filled in the "86" junction box.
[0012] The present invention has the following beneficial effects: The present invention directly pre-buries and installs construction water pipelines in structural columns and walls, so that temporary water supply pipelines and structures are implemented synchronously, reducing the support for temporary water supply construction and the subsequent removal and repair work. It can ensure timely supply of water for concrete maintenance, facilitate the cleaning of the working surface, and provide water for fire prevention on the working surface.
[0013] The present invention is constructed once and can be used throughout the entire construction cycle; construction water is directly supplied to the working surface and workers can use it at any time, which improves the convenience of concrete maintenance; overcomes the anti-freezing problem of water pipes in winter; solves the problem of temporary water pipes occupying building space and often shifting during construction; the construction water can be used to directly flush the working surface and can replace compressed air for sawdust cleaning; water can be sprinkled on the hot work points on the working surface to prevent fire; and the heat-prevention and cooling effect for workers in high temperature seasons is obvious. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 This is a schematic diagram of the pre-buried water pipes on the first floor; Figure 2 This is a schematic diagram of the pre-buried water pipes in the middle section; Figure 3 This is a schematic diagram of the cross-connection of the pre-buried water pipe segment area; Figure 4 This is a schematic diagram of pre-buried water pipe segment areas; Figure 5 This is a schematic diagram of the pre-embedded water pipes on the first floor along with the vertical steel bars; Figure 6 This is a schematic diagram of the water inlet of the pre-buried water pipes after the first-floor concrete structure column (wall) is poured; Figure 7 Schematic diagram of the upper pipe connection before the upper column formwork is installed; Figure 8 This is the schematic diagram of the faucet installation after the upper template is removed; In the figure: 1- galvanized steel pipe; 2- end valve; 3- end elbow; 4- water pipe elbow; 5- water pipe plug; 6- "86" junction box; 7- template; 8- vertical steel bar; 9- water inlet valve; 10- water pipe tee; 11- faucet; 12- short pipe; 13- structural plate; 14- conversion valve; 15- flexible joint. DETAILED DESCRIPTION
[0015] The present invention is further described below in conjunction with the accompanying drawings and specific embodiments, but the protection scope of the present invention is not limited thereto.
[0016] The temporary vertical water supply method for high-rise buildings of the present invention comprises the following steps: Step 1: Construction water design; Use the high-pressure fire-fighting pipe network in the site to provide water for building construction, and determine the vertical segmented water supply layer according to the floor height; According to the single-story building area, determine the vertical water supply point on each floor, and the service radius of each water supply point is about 50 meters; The water supply point is designed in a public place that does not affect the structural safety and is easy to use and finish; The design of water points for high-rise and super-high-rise construction should also consider the convenience of conversion and pressurization; Step 2: Assemble and install the pre-buried water pipes on the first floor; Reference Figure 1 , 5 As shown, the pre-buried water pipes of the first floor are embedded together with the vertical steel bars 8, and are embedded and fixed with the help of the vertical steel bars 8, and the upper part of the pre-buried water pipes of the first floor is ensured to extend into the upper floor; wherein, the pre-buried water pipes of the first floor include galvanized steel pipes 1 (DN20) connected with threads, and the upper end of the galvanized steel pipe 1 is equipped with an end valve 2 and an end elbow 3, and the lower end of the galvanized steel pipe 1 is equipped with a water pipe elbow 4, and the mouth of the water pipe elbow 4 is tightly sealed with a water pipe plug 5, and the water pipe elbow 4 is used in conjunction with the "86" junction box 6 for pre-embedding, and before the column form is installed, the "86" junction box 6 is filled tightly with soft materials and sealed with tape, and the box mouth is required to be close to the template 7, as shown in FIG. Figure 5 shown.
[0017] Step 3: Seal the formwork of the first-floor concrete structure columns (walls), and then pour the first-floor concrete structure columns (walls). After the concrete pouring is completed and reaches the strength requirement, remove the formwork 7.
[0018] Step 4: Figure 6 As shown, clean the pre-buried water pipe head, then connect the external water inlet valve 9, connect the water source, open the corresponding valve to send water upward, and the concrete can be used for curing.
[0019] Step 5: Assemble the pre-buried water pipes in the middle section; like Figure 2 As shown, the embedded water pipe in the middle section includes a galvanized steel pipe 1 connected by a thread, an end valve 2 and an end elbow 3 are installed on the upper end of the galvanized steel pipe 1, a water pipe tee 10 is installed on the lower end of the galvanized steel pipe 1, the mouth of the water pipe tee 10 is tightly sealed with a water pipe plug 5, and the water pipe tee 10 is used in conjunction with an "86" junction box 6 for pre-embedded use, and before the upper column formwork is installed, the "86" junction box 6 is tightly filled with soft material and sealed with tape, and the box mouth is required to be close to the template 7.
[0020] Step 6: Upper level takeover; Before installing the upper column formwork, close the water inlet valve 9 of the first floor, remove the end valve 2 of the upper part of the pre-buried water pipe on the first floor, insert the top of the galvanized steel pipe 1 of the pre-buried water pipe on the first floor into the "86" junction box 6 of the middle section pre-buried water pipe and connect it with the water pipe tee 10, and then follow the same method to install the pre-buried water pipe in the middle section, and ensure that the upper part of the pre-buried water pipe in the middle section extends into the upper floor, as shown in the following figure. Figure 7 shown.
[0021] Step 7: Seal the upper concrete structure column (wall) formwork, then pour the upper concrete structure column (wall). After the concrete pouring is completed and reaches the strength requirement, remove the formwork 7.
[0022] Step 8: After removing the upper template 7, install the faucet 11; Clean the filling material in the junction box 6 of the middle section pre-buried water pipe "86", close the bottom water inlet valve 9, remove the water pipe plug 5 at the mouth of the water pipe tee 10 of the middle section pre-buried water pipe, connect the short pipe 12 and the faucet 11, and then open the bottom water inlet valve 9 to supply water upwards. Water can be used in the top and middle parts. Figure 8 shown.
[0023] Step 9: Repeat steps 5 to 8, constructing each layer of pre-buried water pipes upwards in sequence.
[0024] The above process is aimed at the situation of pre-embedding and water use in continuous areas. The present invention also provides a pre-embedding water use scheme for segmented areas, specifically as follows Figure 3 , 4 As shown, the principle is similar to the pre-buried water use in the continuous area and will not be repeated here; the segmented layer water source can be introduced by the fire riser to ensure the continuous supply of construction water. The segmented water supply method can ensure the management of construction water in each section, while ensuring the normal water pressure and water consumption of each section.
[0025] When water is not needed in the later stage of interior decoration of the building, the external short pipes 12 of each floor are manually removed, grouting is performed in the water supply pipeline, and the mortar in the "86" junction box 6 is filled and the decorative surface is partially repaired.
[0026] Preferably, the distance between the water pipe elbow 4, the water pipe plug 5 and the end valve 2 is 0.5 m from the ground of the structural plate 13.
[0027] When connecting the interfaces of the embedded water pipes of the present invention, sealing tape is used to fill the threads to ensure that the interfaces are tight and leak-free; the embedded water pipe tee 10 and the water pipe elbow 4 must be used in conjunction with the "86" junction box 6 for pre-embedding; before overmolding, the water pipe elbow 4 or the water pipe tee 10 in the "86" junction box 6 is tightly sealed with a water pipe plug 5, and the space in the "86" junction box 6 is filled with soft materials, and the mouth is close to the template 7. After concrete pouring and demolding, the soft materials in the box are cleaned, and the water pipe plug 5 is removed and the external short pipe 12 and the faucet 11 can be connected; before the project is completed, the faucet 11 and the short pipe 12 are removed, and the pipe is grouted, and the "86" junction box 6 is filled with mortar to complete the building decoration surface.
[0028] The embodiments are preferred implementations of the present invention, but the present invention is not limited to the above-mentioned implementations. Any obvious improvements, substitutions or modifications that can be made by those skilled in the art without departing from the essential content of the present invention belong to the protection scope of the present invention.
Claims
1. A temporary vertical water supply method for high-rise buildings, characterized in that: The process includes the following: Step 1: Construction water design; Step 2: Assemble and install the pre-buried water pipes on the first floor; Step 3: The first floor concrete structure is sealed and poured. After the concrete pouring is completed and meets the requirements, the formwork is removed (7); Step 4: Clean the pre-buried water pipe head on the first floor, then connect the water inlet valve (9) to the water source; Step 5: Assemble the pre-buried water pipes in the middle section; Step 6: Connect the upper and lower pre-buried water pipes; Step 7: The upper concrete structure is sealed and poured. After the concrete pouring is completed and meets the requirements, the formwork is removed (7); Step 8: Install the faucet (11); Step 9: Repeat steps 5 to 8, and construct the remaining layers of pre-buried water pipes upwards in sequence.
2. The temporary vertical water supply method for high-rise buildings according to claim 1, characterized in that: In step 2, the first-floor pre-buried water pipe is pre-buried and installed together with the vertical steel bars (8) of the first-floor concrete structure, and is pre-buried and fixed by the vertical steel bars (8), and the upper part of the first-floor pre-buried water pipe extends into the upper layer.
3. The temporary vertical water supply method for high-rise buildings according to claim 1, characterized in that: The first-floor pre-buried water pipe comprises a galvanized steel pipe (1) connected by a thread, an end valve (2) and an end elbow (3) are installed at the upper end of the galvanized steel pipe (1), a water pipe elbow (4) is installed at the lower end of the galvanized steel pipe (1), the mouth of the water pipe elbow (4) is blocked by a water pipe plug (5), and the water pipe elbow (4) is pre-buried in conjunction with an "86" junction box (6), and before the template (7) is installed, the "86" junction box (6) is filled with soft material and sealed with tape, and the box mouth is closely attached to the template (7).
4. The temporary vertical water supply method for high-rise buildings according to claim 3 is characterized in that: In the step 5, the intermediate section pre-buried water pipe comprises a galvanized steel pipe (1) connected by a thread, an end valve (2) and an end elbow (3) are installed at the upper end of the galvanized steel pipe (1), a water pipe tee (10) is installed at the lower end of the galvanized steel pipe (1), the mouth of the water pipe tee (10) is blocked with a water pipe plug (5), and the water pipe tee (10) is pre-buried in conjunction with the "86" junction box (6), and before the upper template (7) is installed, the "86" junction box (6) is filled with soft material and sealed with tape, and the box mouth is close to the template (7).
5. The temporary vertical water supply method for high-rise buildings according to claim 4, characterized in that: The specific process of step 6 is as follows: before installing the upper template (7), close the water inlet valve (9) of the first floor, remove the end valve (2) on the upper part of the pre-buried water pipe on the first floor, insert the top end of the galvanized steel pipe (1) of the pre-buried water pipe on the first floor into the "86" junction box (6) of the middle section pre-buried water pipe and connect it with the water pipe tee (10), then carry out the pre-buried installation of the middle section pre-buried water pipe, and ensure that the upper part of the middle section pre-buried water pipe extends into the upper floor.
6. The temporary vertical water supply method for high-rise buildings according to claim 4, characterized in that: The specific process of step 8 is as follows: clean the filling material in the junction box (6) of the intermediate section pre-buried water pipe "86", close the bottom water inlet valve (9), remove the water pipe plug (5) at the mouth of the water pipe tee (10) of the intermediate section pre-buried water pipe, connect the short pipe (12) and the faucet (11), and then open the bottom water inlet valve (9) to supply water upward.
7. The temporary vertical water supply method for high-rise buildings according to claim 4, characterized in that: When water is not needed in the later stage of interior decoration of a building, the external short pipes (12) of each floor are manually removed, grouting is performed in the water supply pipeline, and the mortar in the "86" junction box (6) is filled to partially repair the decorative surface.