Intelligent control system and control method of pit digging device
By designing the intelligent control system, real -time collection and analysis of digging data, generating and modifying the excavation strategy, dynamic adjustment of excavation speed and equipment power, solving the problems of low efficiency, poor safety and environmental adaptability in the traditional potholes mining process. High -efficiency and safe potholes digging homework.
Patent Information
- Application Number
- CN202411909315.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-24
- Publication Date
- 2025-01-24
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The traditional pit excavation process has problems such as low efficiency, poor safety, weak environmental adaptability, and relying on manual experience in decision-making, and information silos limit the effective use of data.
An intelligent control system for pothole excavation equipment is designed, including an excavation data collection module, a cloud data server, an excavation control module, an environmental control device, a data processing module and a communication module. The system collects and analyzes excavation data in real time, generates and corrects excavation strategies, and dynamically adjusts excavation speed and equipment power to achieve environmental adaptive control.
It has significantly improved the operating efficiency and security of potholes, reduced manual intervention and accident risks, supports remote monitoring and equipment maintenance, reduced maintenance costs and improved equipment utilization.
Smart Images

Figure CN119356100A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of equipment control, and in particular to an intelligent control system and a control method for a pit excavation device. Background Art
[0002] In the fields of modern infrastructure construction, mineral resource mining and underground space development, pit excavation is a vital operation. The traditional pit excavation process often relies on manual operation and simple mechanical equipment control, which has problems such as low efficiency, poor safety and weak environmental adaptability. With the advancement of science and technology, especially the rapid development of information technology, Internet of Things technology, big data analysis and artificial intelligence technology, the realization of intelligent and automated pit excavation process has become an urgent need of the industry.
[0003] The main challenges faced by traditional pit excavation operations include: The contradiction between excavation efficiency and safety: In order to increase the excavation speed, it is often necessary to increase the power of the equipment, but this may lead to a deterioration of the working environment (such as increased dust concentration, increased temperature, etc.), threatening the health and safety of the workers.
[0004] Poor environmental adaptability: Excavation operations under different geological conditions have different requirements for equipment parameters and environmental control measures. Traditional methods are difficult to adjust in real time to adapt to changing environmental conditions.
[0005] Decision-making relies on human experience: The formulation of excavation strategies relies heavily on the experience and intuition of operators, lacks scientific basis and data support, and is difficult to achieve optimal control.
[0006] Information islands: Data collection, processing and application during the excavation process are often carried out in isolation, failing to form an effective data closed loop, which limits the application of data mining and intelligent decision-making. Summary of the invention
[0007] The purpose of the present invention is to overcome the shortcomings of the prior art and provide an intelligent control system for a pit excavation device, including an excavation data acquisition module, a cloud data server, an excavation control module, an environmental control device, a data processing module, and a communication module; The excavation data acquisition module, excavation control module, environmental control device and communication module are respectively connected to the data processing module in communication; the cloud data server is connected to the communication module in communication; The cloud data server is used to generate a tunneling strategy based on the tunneling target location and to modify the tunneling strategy based on the tunneling data; The excavation data collection module is used to collect excavation data during the excavation process; The environmental control device is used to control the excavation environment according to the excavation data; The excavation control module is used to control the excavation equipment according to the excavation strategy.
[0008] Preferably, the cloud data server is used to generate a tunneling strategy according to the tunneling target position, including: The cloud data server obtains the power control parameters of the excavation equipment according to the set target excavation speed and the excavation equipment parameters; and obtains the estimated concentration of the environmental monitoring target according to the excavation speed, and obtains the equipment operating parameters of the environmental control device; the power control parameters of the excavation equipment, the equipment operating parameters of the environmental control device and the target excavation parameters constitute the excavation strategy.
[0009] Preferably, the excavation data acquisition module is used to collect excavation data of the excavation process, wherein the excavation data includes excavation speed and environmental parameters; The excavation speed is the moving speed of the excavation equipment per unit time, and the speed difference with the target excavation speed is obtained according to the excavation speed; the environmental parameters are the concentration data of the preset environmental monitoring target and the change of the concentration data.
[0010] Preferably, the excavation strategy correction according to the excavation data includes: If the concentration of the environmental monitoring target is less than the concentration threshold, and the difference between the excavation speed and the target excavation speed is less than the set difference threshold, the excavation strategy continues to be executed; otherwise, the equipment operating parameters of the environmental control device are adjusted according to the concentration of the environmental monitoring target to obtain a revised excavation strategy, or the excavation speed is adjusted according to the concentration of the environmental monitoring target to obtain a revised excavation strategy.
[0011] Preferably, the device operating parameters of the environmental control device are adjusted according to the concentration of the environmental monitoring target to obtain a revised excavation strategy, or the excavation speed is adjusted according to the concentration of the environmental monitoring target to obtain a revised excavation strategy, including: If the concentration of the environmental monitoring target is greater than the concentration threshold, and the difference between the excavation speed and the target excavation speed is less than the set difference threshold, the excavation speed of the excavation equipment is adjusted according to the concentration change per unit time of the environmental monitoring target to obtain the adjusted excavation speed, and the excavation speed of the excavation strategy is adjusted to the adjusted excavation speed to obtain the revised excavation strategy; If the concentration of the environmental monitoring target is greater than the concentration threshold, and the difference between the excavation speed and the target excavation speed is greater than the set difference threshold, the equipment operating parameters of the environmental control device are adjusted according to the concentration change per unit time of the environmental monitoring target to obtain the adjusted equipment operating parameters, the equipment operating parameters of the excavation strategy are adjusted to the adjusted equipment operating parameters, and the excavation speed of the excavation strategy is adjusted to the current excavation speed to obtain the revised excavation strategy.
[0012] Preferably, the excavation speed of the excavation equipment is adjusted according to the concentration change per unit time of the environmental monitoring target to obtain the adjusted excavation speed, including: According to the change in concentration per unit time, the increase per unit time of the environmental monitoring target is obtained. According to the increase per unit time of the environmental monitoring target discharged by the environmental control device, the required discharge time is obtained. According to the discharge time and the excavation speed, the excavation length is obtained. The adjusted excavation speed is: The unit excavation length is the length of excavation per unit time according to the excavation speed.
[0013] Preferably, the device operating parameters of the environmental control device are adjusted according to the concentration change per unit time of the environmental monitoring target to obtain the adjusted device operating parameters, including: According to the change in concentration per unit time, the increase in the environmental monitoring target per unit time is obtained. According to the power required by the environmental control device to discharge the increase in the environmental monitoring target per unit time, the power in the equipment operating parameters of the environmental control device in the excavation strategy is corrected to the sum of the original power and the required power.
[0014] An intelligent control method for a pit excavation device is applied to an intelligent control system of the pit excavation device.
[0015] The beneficial effect of the present invention is that the system can dynamically adjust the excavation speed and equipment power according to the concentration changes of the environmental monitoring target. In particular, when encountering emergencies (such as a sudden increase in gas concentration), the system can respond quickly, reduce the excavation speed or suspend operations, and at the same time enhance ventilation to ensure personnel safety.
[0016] Through big data analysis technology, the system can mine the data value in the excavation process, identify operational efficiency bottlenecks, predict potential risks, provide managers with a scientific basis, and help optimize decision-making.
[0017] The present invention significantly improves the operating efficiency and safety of pit excavation through intelligent control, reduces human intervention, and reduces the risk of accidents.
[0018] With the help of cloud data servers and communication modules, the system supports remote monitoring of tunneling operation status and timely detection and resolution of problems. At the same time, remote maintenance and fault diagnosis of equipment have become more convenient, reducing maintenance costs and improving equipment utilization. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a schematic diagram of the principle of an intelligent control system of a pit excavation device; Figure 2This is a schematic diagram of the principle of the tunneling data acquisition module. DETAILED DESCRIPTION
[0020] The technical solution of the present invention is further described in detail below in conjunction with the accompanying drawings, but the protection scope of the present invention is not limited to the following.
[0021] The features and performance of the present invention are further described in detail below in conjunction with the embodiments.
[0022] like Figure 1 As shown, an intelligent control system for a pit excavation device includes an excavation data acquisition module, a cloud data server, an excavation control module, an environmental control device, a data processing module, and a communication module; The excavation data acquisition module, excavation control module, environmental control device and communication module are respectively connected to the data processing module in communication; the cloud data server is connected to the communication module in communication; The cloud data server is used to generate a tunneling strategy based on the tunneling target location and to modify the tunneling strategy based on the tunneling data; The excavation data collection module is used to collect excavation data during the excavation process; like Figure 2 As shown, the excavation data acquisition module includes an environmental data acquisition device and an excavation data acquisition device; the environmental data acquisition device and the excavation data acquisition device are respectively connected to the data processing module.
[0023] The environment control device is used for controlling the excavation environment according to the excavation data; the environment control device comprises a ventilation device and a drainage device; the ventilation device and the drainage device are respectively connected to the data processing module.
[0024] The excavation control module is used to control the excavation equipment according to the excavation strategy.
[0025] The cloud data server is used to generate a tunneling strategy according to the tunneling target location, including: The cloud data server obtains the power control parameters of the excavation equipment according to the set target excavation speed and the excavation equipment parameters; and obtains the estimated concentration of the environmental monitoring target according to the excavation speed, and obtains the equipment operating parameters of the environmental control device; the power control parameters of the excavation equipment, the equipment operating parameters of the environmental control device and the target excavation parameters constitute the excavation strategy.
[0026] The excavation data acquisition module is used to collect excavation data of the excavation process, wherein the excavation data includes excavation speed and environmental parameters; The excavation speed is the moving speed of the excavation equipment per unit time, and the speed difference with the target excavation speed is obtained according to the excavation speed; the environmental parameters are the concentration data of the preset environmental monitoring target and the change of the concentration data.
[0027] The said modification of the excavation strategy according to the excavation data comprises: If the concentration of the environmental monitoring target is less than the concentration threshold, and the difference between the excavation speed and the target excavation speed is less than the set difference threshold, the excavation strategy continues to be executed; otherwise, the equipment operating parameters of the environmental control device are adjusted according to the concentration of the environmental monitoring target to obtain a revised excavation strategy, or the excavation speed is adjusted according to the concentration of the environmental monitoring target to obtain a revised excavation strategy.
[0028] The method of adjusting the equipment operating parameters of the environmental control device according to the concentration of the environmental monitoring target to obtain a revised excavation strategy, or adjusting the excavation speed according to the concentration of the environmental monitoring target to obtain a revised excavation strategy, includes: If the concentration of the environmental monitoring target is greater than the concentration threshold, and the difference between the excavation speed and the target excavation speed is less than the set difference threshold, the excavation speed of the excavation equipment is adjusted according to the concentration change per unit time of the environmental monitoring target to obtain the adjusted excavation speed, and the excavation speed of the excavation strategy is adjusted to the adjusted excavation speed to obtain the revised excavation strategy; If the concentration of the environmental monitoring target is greater than the concentration threshold, and the difference between the excavation speed and the target excavation speed is greater than the set difference threshold, the equipment operating parameters of the environmental control device are adjusted according to the concentration change per unit time of the environmental monitoring target to obtain the adjusted equipment operating parameters, the equipment operating parameters of the excavation strategy are adjusted to the adjusted equipment operating parameters, and the excavation speed of the excavation strategy is adjusted to the current excavation speed to obtain the revised excavation strategy.
[0029] The method of adjusting the excavation speed of the excavation equipment according to the concentration change per unit time of the environmental monitoring target to obtain the adjusted excavation speed includes: According to the change in concentration per unit time, the increase per unit time of the environmental monitoring target is obtained. According to the increase per unit time of the environmental monitoring target discharged by the environmental control device, the required discharge time is obtained. According to the discharge time and the excavation speed, the excavation length is obtained. The adjusted excavation speed is: The unit excavation length is the length of excavation per unit time according to the excavation speed.
[0030] The device operating parameters of the environmental control device are adjusted according to the concentration change per unit time of the environmental monitoring target to obtain the adjusted device operating parameters, including: According to the change in concentration per unit time, the increase in the environmental monitoring target per unit time is obtained. According to the power required by the environmental control device to discharge the increase in the environmental monitoring target per unit time, the power in the equipment operating parameters of the environmental control device in the excavation strategy is corrected to the sum of the original power and the required power.
[0031] The intelligent control system of a pit excavation device described in the present invention mainly includes the following core modules: Excavation data acquisition module: This module is responsible for collecting key data in the excavation process in real time, including but not limited to excavation speed, environmental parameters (such as dust concentration, gas concentration, temperature, humidity, etc.). These data are acquired through high-precision sensors and directly transmitted to the data processing module for analysis. In particular, the excavation data acquisition device is subdivided into environmental data acquisition devices and excavation data acquisition devices to ensure the comprehensiveness and accuracy of data collection.
[0032] Cloud data server: As the "brain" of the system, the cloud data server receives data from the excavation site, and uses big data analysis and machine learning algorithms to intelligently generate initial excavation strategies based on geological information of the excavation target location, historical excavation data, etc. At the same time, the server can also dynamically adjust the excavation strategy based on real-time feedback of excavation data to ensure the efficiency and safety of excavation operations.
[0033] Excavation control module: Based on the excavation strategy provided by the cloud data server, the excavation control module accurately controls the operating status of the excavation equipment, including excavation speed, power distribution, etc., to ensure that the excavation operation is carried out according to the optimal strategy.
[0034] Environmental control device: In response to environmental problems that may be encountered during excavation, such as excessive dust and water accumulation, environmental control devices (including ventilation devices, drainage devices, etc.) are automatically adjusted according to the analysis results of the data processing module to maintain a good working environment. These devices are closely connected with the data processing module to achieve real-time monitoring and intelligent control of environmental parameters.
[0035] Data processing module: As the information processing center of the system, the data processing module is responsible for receiving, integrating and analyzing data from various modules, providing decision-making basis for the cloud data server, and directly controlling the operation of the tunneling control module and environmental control device.
[0036] Communication module: ensures efficient and stable communication between all components of the system, and enables seamless data transmission whether it is a tunneling site deep underground or a remote cloud server.
[0037] How it works Intelligent generation and modification of tunneling strategies Initial strategy generation: The cloud data server calculates the optimal excavation equipment power control parameters and environmental control device operating parameters through an algorithm model based on the geological characteristics of the excavation target location, equipment performance parameters and the preset excavation target speed, and forms an initial excavation strategy.
[0038] Dynamic correction: During the excavation process, the excavation data acquisition module continuously collects data and uploads it to the cloud. The server automatically determines whether the excavation strategy needs to be adjusted based on the comparison of real-time data (especially the concentration data of environmental monitoring targets and excavation speed) with the preset threshold. For example, when the dust concentration exceeds the safety threshold or the excavation speed deviates too much from the target, the system will adjust the power of the ventilation device, excavation speed, etc. accordingly to ensure safe and efficient operation.
[0039] Environmental Adaptive Control Intelligent ventilation and drainage adjustment: The environmental control device automatically adjusts the ventilation volume and drainage efficiency according to the analysis results of the data processing module, effectively responding to the challenges brought by environmental changes during the excavation process. For example, the ventilation volume is increased when the dust concentration rises, or the drainage is strengthened when the groundwater level rises, to ensure the comfort and safety of the working environment.
[0040] Intelligent adjustment of excavation speed and equipment power The system can dynamically adjust the excavation speed and equipment power according to the concentration changes of the environmental monitoring target, achieving a balance between excavation efficiency and environmental protection. In particular, when encountering emergencies (such as a sudden increase in gas concentration), the system can respond quickly, reduce the excavation speed or suspend operations, while enhancing ventilation to ensure personnel safety.
[0041] Example 1: Application of intelligent control system in coal mine excavation In a large coal mine project, the intelligent control system of the pit excavation device described in the present invention is deployed. The system collects key data in the excavation process in real time through the excavation data acquisition module, including environmental parameters such as excavation speed, gas concentration, dust concentration, and the operating status information of the excavation equipment. These data are immediately transmitted to the data processing module for analysis and processing.
[0042] Tunneling strategy generation and modification: Generation of initial excavation strategy: The cloud data server generates an initial excavation strategy based on the excavation target position of the coal mine, the set target excavation speed, and the specific parameters of the excavation equipment (such as power, efficiency, etc.), including the power control parameters of the excavation equipment and the operating parameters of the environmental control devices (such as ventilation devices).
[0043] Strategy modification during excavation: As excavation progresses, the excavation data acquisition module continues to collect data. When the system detects that the gas concentration exceeds the preset threshold, and the difference between the excavation speed and the target excavation speed is less than the set difference threshold, it indicates that there are safety hazards in the current excavation environment but the excavation efficiency is acceptable. At this time, the system automatically adjusts the power of the ventilation device according to the change in gas concentration per unit time to speed up gas discharge and ensure safety. If the gas concentration continues to rise and the excavation speed drops significantly, the system will further adjust the excavation speed, reduce the excavation intensity, and increase ventilation until the environmental parameters return to a safe range.
[0044] Specific implementation: When the gas concentration suddenly rises to 1.5% (assumed to be the concentration threshold) and the excavation speed is only slightly lower than the target speed, the system calculates the increase in gas concentration per unit time and adjusts the power of the ventilation device to the maximum accordingly, while keeping the excavation speed unchanged to quickly reduce the gas concentration.
[0045] If the gas concentration continues to rise to 2% and the excavation speed slows down significantly, the system will automatically reduce the excavation speed by 20% and further optimize the operating parameters of the ventilation device to ensure that the excavation operation is carried out in a safe environment.
[0046] Example 2: Application of intelligent control system in underground tunnel excavation In a complex underground tunnel excavation project, the intelligent control system of the present invention also plays an important role. The system not only monitors the excavation speed, but also pays close attention to key environmental parameters such as groundwater level and air quality (such as oxygen content and harmful gas concentration).
[0047] Dynamic adjustment of excavation strategy: Initial strategy formulation: The cloud data server generates an initial excavation strategy including excavation speed, equipment power control and drainage device operating parameters based on the tunnel design drawings, geological conditions and the performance of the excavation equipment.
[0048] Strategy revision and optimization: Abnormal environmental parameter handling: During the excavation process, if the system detects an abnormal rise in the groundwater level, threatening the safety of excavation, and the excavation speed is not much different from the target speed, the system will immediately start the drainage device and adjust its drainage capacity according to the water level rise rate to ensure that the excavation area remains dry.
Claims
1. An intelligent control system for a pit excavation device, characterized in that: It includes excavation data acquisition module, cloud data server, excavation control module, environmental control device, data processing module and communication module; The excavation data acquisition module, excavation control module, environmental control device and communication module are respectively connected to the data processing module in communication; the cloud data server is connected to the communication module in communication; The cloud data server is used to generate excavation strategies according to the excavation target location; and modifying the excavation strategy based on excavation data; The excavation data collection module is used to collect excavation data during the excavation process; The environmental control device is used to control the excavation environment according to the excavation data; The excavation control module is used to control the excavation of the excavation equipment according to the excavation strategy.
2. The intelligent control system of a pit excavation device according to claim 1, characterized in that: The cloud data server is used to generate a tunneling strategy according to the tunneling target location, including: The cloud data server obtains the power control parameters of the excavation equipment according to the set target excavation speed and the excavation equipment parameters; and obtains the estimated concentration of the environmental monitoring target according to the excavation speed, and obtains the equipment operating parameters of the environmental control device; the power control parameters of the excavation equipment, the equipment operating parameters of the environmental control device and the target excavation parameters constitute the excavation strategy.
3. The intelligent control system of a pit excavation device according to claim 2, characterized in that: The excavation data acquisition module is used to collect excavation data of the excavation process, wherein the excavation data includes excavation speed and environmental parameters; The excavation speed is the moving speed of the excavation equipment per unit time, and the speed difference with the target excavation speed is obtained according to the excavation speed; the environmental parameters are the concentration data of the preset environmental monitoring target and the change of the concentration data.
4. The intelligent control system of a pit excavation device according to claim 3, characterized in that: The said modification of the excavation strategy according to the excavation data comprises: If the concentration of the environmental monitoring target is less than the concentration threshold, and the difference between the excavation speed and the target excavation speed is less than the set difference threshold, the excavation strategy continues to be executed; otherwise, the equipment operating parameters of the environmental control device are adjusted according to the concentration of the environmental monitoring target to obtain a revised excavation strategy, or the excavation speed is adjusted according to the concentration of the environmental monitoring target to obtain a revised excavation strategy.
5. The intelligent control system of a pit excavation device according to claim 4, characterized in that: The method of adjusting the equipment operating parameters of the environmental control device according to the concentration of the environmental monitoring target to obtain a revised excavation strategy, or adjusting the excavation speed according to the concentration of the environmental monitoring target to obtain a revised excavation strategy, includes: If the concentration of the environmental monitoring target is greater than the concentration threshold, and the difference between the excavation speed and the target excavation speed is less than the set difference threshold, the excavation speed of the excavation equipment is adjusted according to the concentration change per unit time of the environmental monitoring target to obtain the adjusted excavation speed, and the excavation speed of the excavation strategy is adjusted to the adjusted excavation speed to obtain the revised excavation strategy; If the concentration of the environmental monitoring target is greater than the concentration threshold, and the difference between the excavation speed and the target excavation speed is greater than the set difference threshold, the equipment operating parameters of the environmental control device are adjusted according to the concentration change per unit time of the environmental monitoring target to obtain the adjusted equipment operating parameters, the equipment operating parameters of the excavation strategy are adjusted to the adjusted equipment operating parameters, and the excavation speed of the excavation strategy is adjusted to the current excavation speed to obtain the revised excavation strategy.
6. The intelligent control system of a pit excavation device according to claim 5, characterized in that: The method of adjusting the excavation speed of the excavation equipment according to the concentration change per unit time of the environmental monitoring target to obtain the adjusted excavation speed includes: According to the change in concentration per unit time, the increase per unit time of the environmental monitoring target is obtained. According to the increase per unit time of the environmental monitoring target discharged by the environmental control device, the required discharge time is obtained. According to the discharge time and the excavation speed, the excavation length is obtained. The adjusted excavation speed is: The unit excavation length is the length of excavation per unit time according to the excavation speed.
7. The intelligent control system of a pit excavation device according to claim 5, characterized in that: The device operating parameters of the environmental control device are adjusted according to the concentration change per unit time of the environmental monitoring target to obtain the adjusted device operating parameters, including: According to the concentration change per unit time, the increase per unit time of the environmental monitoring target is obtained. According to the power required by the environmental control device to discharge the increase per unit time of the environmental monitoring target, the power in the equipment operating parameters of the environmental control device in the excavation strategy is corrected to the sum of the original power and the required power.
8. An intelligent control method for a pit excavation device, characterized in that: An intelligent control system for a pit excavation device as described in any one of claims 1-7.
Citation Information
Patent Citations
Multi-source data safety acquisition system of tunneling device
CN115097758A
Heading machine intelligent management and control system and method based on big data
CN116187831A
Digital twinning system of coal mine rapid digging and anchoring complete equipment
CN116877108A
Control method, system and device of heading machine, heading machine and engineering machinery
CN117345341A
Face shovel type excavator and operation control system thereof
CN118345892A