Construction project management method and equipment based on BIM modeling and storage medium
By adopting BIM modeling technology in construction project management, analyzing construction equipment and material data, predicting conflict time and area, the problem of inability to effectively predict construction project conflicts in the existing technology is solved, and construction efficiency is improved.
Patent Information
- Application Number
- CN202411556819.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-04
- Publication Date
- 2025-02-07
AI Technical Summary
The existing construction project management methods cannot effectively predict the time and location of the conflict in the construction project, resulting in the construction project interfering with the normal construction process due to land occupation conflicts and affecting the overall construction efficiency.
Using the construction project management method based on BIM modeling, the construction site model is established in the spatial coordinate system, the construction equipment and material data are analyzed, the construction restriction space and conflict space are obtained, and the construction process is analyzed based on the planning timeline, and the conflict time is predicted. Construction adjustment.
Effectively predict and adjust the conflict areas of construction projects, prevent conflicts from interfering with normal construction processes, and improve overall construction efficiency.
Smart Images

Figure CN119398709A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of construction management, and in particular to a construction project management method, equipment and storage medium based on BIM modeling. Background Art
[0002] Construction project management refers to the management of the entire process of planning, organizing, arranging, directing, managing, supervising, controlling and coordinating construction projects by construction units in the process of completing the undertaken engineering construction projects, using systematic viewpoints and theories as well as modern scientific and technological means; construction project management mainly includes: construction preparation stage, construction stage, completion acceptance stage, and quality assurance and after-sales service stage.
[0003] Existing methods for construction project management usually monitor the construction site and the construction process by using modules such as construction progress tracking, construction personnel tracking, construction material tracking, construction site environment detection, and construction site safety monitoring, and perform real-time control based on the data obtained from the supervision. Although this improved method can monitor the construction project in real time, when there are many construction projects being executed at the same time on the construction site, resulting in conflicts in the space occupied by the construction projects, this improved method can only monitor after the conflict occurs, and cannot effectively predict the time and location of the conflict, resulting in the construction project interfering with the normal construction process due to the conflict in occupying space, thereby affecting the overall construction efficiency. For example, in the public number Patent application CN117649317A discloses a construction project platform management method and system. The solution is to monitor the construction progress, the amount of construction materials and the construction personnel in real time, and at the same time realize a green construction environment, thereby ensuring the smooth and orderly operation of the project construction. Other improvements in construction project management are usually improvements in construction coordination and construction personnel management. This improvement method still cannot effectively predict the time and location of conflicts in construction projects, resulting in the construction project being disturbed by the conflict of land occupation, thereby affecting the overall construction efficiency. In view of this, it is necessary to improve the existing methods for construction project management. Summary of the invention
[0004] The present invention aims to solve one of the technical problems in the prior art to at least a certain extent. By proposing a construction project management method, equipment and storage medium based on BIM modeling, the present invention is used to solve the problem that the existing methods for construction project management cannot effectively predict the time and location of conflicts in construction projects, resulting in the construction projects being disturbed by land conflicts and affecting the overall construction efficiency.
[0005] To achieve the above objectives, in a first aspect, the present application provides a construction project management method based on BIM modeling, comprising the following steps:
[0006] Based on the construction planning data, BIM modeling is used to place the construction site in the spatial coordinate system, and the construction planning data is analyzed. Based on the analysis results, the construction equipment and materials corresponding to all construction projects are obtained;
[0007] Obtain the construction restriction space corresponding to each construction project in the spatial coordinate system based on the construction equipment and construction materials, analyze the construction restriction space, and obtain the construction conflict space based on the analysis results;
[0008] A planning timeline is established based on the construction planning data, and the progress of each construction project is analyzed in the spatial coordinate system based on the planning timeline; the construction conflict space is analyzed, and the conflict time is obtained based on the analysis results and construction adjustments are made.
[0009] Furthermore, based on the construction planning data, BIM modeling is used to place the construction site in a spatial coordinate system, and the construction planning data is analyzed. Based on the analysis results, the construction equipment and construction materials corresponding to all construction projects are obtained, including:
[0010] Obtain the location of the construction site in the map; establish a spatial coordinate system, recorded as the construction analysis coordinate system, where the units of the X-axis, Y-axis and Z-axis of the construction analysis coordinate system are all meters; obtain the size data of each construction equipment in the construction site in the map based on the construction planning data, and use BIM modeling to establish a model corresponding to the construction site in the construction analysis coordinate system, recorded as the construction model, where the construction planning data is used to record the size data of all construction equipment during construction in the construction site, the construction time data of the construction project, the data of the construction equipment used in the construction project, and the quantity and location data of the construction materials;
[0011] Record the number of construction equipment as R, and the number of construction projects as T; create a table of R+1 rows × T+1 columns and record it as the project analysis table; among which, the top row of the project analysis table is filled with all construction projects from left to right except the leftmost cell, and the leftmost column of the project analysis table is filled with all construction equipment from top to bottom except the top cell.
[0012] Furthermore, obtaining construction equipment and construction materials corresponding to all construction projects based on the analysis results also includes:
[0013] For any construction project in the project analysis table, the time required to complete the construction project is recorded as t, and all the construction equipment used to complete the construction project are recorded as project equipment XB1 to project equipment XB j ; Establish a time axis with a length of t, recorded as the construction time axis;
[0014] For any project device XB j1 , set the start time of the construction project as the starting point of the construction timeline, and set the project equipment XB j1 The time used is marked in the construction timeline, and the marked time node and time period are recorded as project equipment XB j1 The time of use will be j1 The time of use is filled in the XB in the construction analysis form j1 —T1 grid, where XB j1 —T1 is project equipment XB j1 The cell where the row is located and the column where the construction project is located intersects, j1 is a positive integer less than or equal to j and greater than or equal to 1; analyze all project equipment XB of the construction equipment, and fill in the corresponding usage time in the corresponding cell;
[0015] Get the usage time of project equipment XB of all construction projects and fill in the corresponding cells.
[0016] Furthermore, obtaining the construction restricted space corresponding to each construction project in the spatial coordinate system based on the construction equipment and construction materials includes:
[0017] For any construction project and project equipment XB1 to project equipment XB used to complete the construction project j ; For any project device XB j1 , set the project device XB j1 The position in the construction analysis coordinate system is recorded as the equipment position SW j1 ; When the construction project is completed, the project equipment XB j1 The construction materials used are recorded as equipment materials SC, and the positions of all equipment materials in the construction analysis coordinate system are recorded as material positions CW; for any material position CW, the material position CW is marked to the equipment position SW in the construction analysis coordinate system based on the construction planning data j1 The shortest path is recorded as the material transportation path;
[0018] Get the material transportation paths corresponding to all equipment materials SC, and store all material locations SC, all material transportation paths and equipment locations SW j1 Recorded as project equipment XB j1 Equipment restricted area; record the equipment restricted area of all project equipment XB as the construction restricted space of the construction project;
[0019] Get the construction restricted spaces for all construction projects.
[0020] Further, the construction restriction space is analyzed, and the construction conflict space is obtained based on the analysis result, including: for any two construction projects α1 and α2, the construction restriction space β1 and the construction restriction space β2 of the construction project α1 and the construction project α2 are simultaneously placed in the construction analysis coordinate system;
[0021] When the construction restriction space β1 and the construction project β2 do not have an intersection, the construction project α1 and the construction project α2 are recorded as non-intersecting projects; when the construction restriction space β1 and the construction restriction space β2 have an intersection and only the material position SC exists in the intersection area, the construction project α1 and the construction project α2 are recorded as non-intersecting projects, wherein the construction conflict space of the non-intersecting projects is recorded as non-existent;
[0022] When the construction restriction space β1 and the construction restriction space β2 intersect, there is a material transportation path in the intersection area, and there is no equipment location SW in the intersection area, the construction project α1 and the construction project α2 are recorded as path intersection projects, and the material transportation path in the intersection area is recorded as the construction conflict space;
[0023] When the construction restriction space β1 and the construction restriction space β2 intersect, there is an equipment location SW in the intersection area, and there is no transportation material path in the intersection area, the construction project α1 and the construction project α2 are recorded as equipment intersection projects, and the equipment location SW in the intersection area is recorded as the construction conflict space;
[0024] When the construction restriction space β1 and the construction restriction space β2 intersect and there are equipment positions SW and material transportation paths in the intersection area, the construction project α1 and the construction project α2 are recorded as full intersection projects, and the equipment positions SW and material transportation paths in the intersection area are recorded as construction conflict space;
[0025] Each construction project is analyzed with all other construction projects, and the corresponding construction conflict space is obtained.
[0026] Furthermore, a planning timeline is established based on the construction planning data, and the progress of each construction project is analyzed in the spatial coordinate system based on the planning timeline; the construction conflict space is analyzed, and the conflict time is obtained based on the analysis results and construction adjustments are made, including:
[0027] For any construction plan in the construction planning data, a planning time axis is established, wherein the starting point of the planning time axis is the time when construction starts in the construction plan, and the end point of the planning time axis is the time when construction ends in the construction plan;
[0028] All construction projects used for construction planning are recorded as planning projects GX1 to GX n; The construction time of all planning projects GX in the construction plan is marked as planning period GS1 to planning period GS in the planning timeline. n ;
[0029] For any planning project GX n1 , will be combined with the planning period GS n1 The planning project corresponding to the planning period GS with an intersection is recorded as planning project GX n1 The items to be screened and analyzed; when the items to be screened and analyzed are the same as the planned items GX n1 If there are no overlapping projects, no adjustment will be made to the construction. n1 If not all of them are non-intersecting projects, they will be combined with the planned project GX n1 The analysis items to be screened that are not non-intersecting items are recorded as conflict analysis items.
[0030] Furthermore, analyzing the construction conflict space, obtaining the conflict time based on the analysis result and making construction adjustments also include:
[0031] For any conflict analysis project, the planning period GS of the conflict analysis project is recorded as the conflict period; when the conflict analysis project and the planning project are path intersection projects, the planning project GX n1 The time for transporting materials to the construction conflict space is in the planning period GS n1 In the conflict analysis project, the time for transporting materials to the construction conflict space is recorded as the conflict path time in the conflict period; when the project path time and the conflict path time overlap, the project path time is recorded as the conflict time; when the project path time and the conflict path time do not overlap, no conflict time is set;
[0032] When the conflict analysis project and the planning project are equipment intersection projects, the project equipment XB corresponding to the equipment position SW recorded as the construction conflict space is recorded as the equipment to be screened; based on the planning project GX n1 The usage time of the equipment to be screened is in the planning period GS n1 The use time of the equipment to be screened based on the conflict analysis project is recorded as the conflict equipment time in the conflict period. When the project equipment time and the conflict equipment time overlap, the overlapping time node or time period is recorded as the conflict time, and the conflict time is set; when the project equipment time and the conflict equipment time do not overlap, the conflict time is not set;
[0033] When the conflict analysis project and the planning project are full intersection projects, the conflict time is obtained based on the analysis method when the conflict analysis project and the planning project are path intersection projects and when the conflict analysis project and the planning project are path intersection projects.
[0034] Furthermore, analyzing the construction conflict space, obtaining the conflict time based on the analysis result and making construction adjustments also include:
[0035] When the conflicting time is obtained, the planning project GX n1 The process at the conflict time and the process of the conflict analysis project at the conflict time are recorded as the planning conflict process and the analysis conflict process; for any conflicting process in the planning conflict process and the analysis conflict process, the other processes of the planning project GX where the conflicting process is located are recorded as the to-be-associated processes DG1 to the to-be-associated processes DG g , for any process DG to be associated g1 , when the equipment material SC or project equipment XB used in the conflicting process is associated with the process to be associated DG g1 If the equipment material SC or project equipment XB in the same, the process DG to be associated g1 Recorded as a weakly associated process of the conflicting process; when the equipment material SC and project equipment XB used in the conflicting process are g1 If the equipment material SC and project equipment XB are the same, the process to be associated DG g1 Recorded as a strongly associated process of the conflicting process;
[0036] The number of processes recorded as strongly associated in all the processes to be associated DG is recorded as the strong association value; the number of processes recorded as weakly associated in all the processes to be associated DG is recorded as the weak association value; when the strong association value of the planning conflict process is equal to the strong association value of the conflict analysis process, both the planning conflict process and the conflict analysis process are recorded as processes to be adjusted; when the strong association value of the planning conflict process is not equal to the strong association value of the conflict analysis process, the conflict process with the smallest sum of the strong association value and the weak association value in the planning conflict process and the conflict analysis process is recorded as the process to be adjusted;
[0037] Report the progress to be adjusted for construction adjustment; based on the GX of the planned project n1 The analytical method is used for all planning projects GX n1 Conduct analysis and make construction adjustments after obtaining the conflicting time.
[0038] In a second aspect, the present application provides an electronic device, including a processor and a memory, wherein the memory stores computer-readable instructions, and when the computer-readable instructions are executed by the processor, the steps in the above method are performed.
[0039] In a third aspect, the present application provides a storage medium having a computer program stored thereon, and when the computer program is executed by a processor, the steps in the above method are performed.
[0040] Beneficial effects of the present invention: The present application first uses BIM modeling based on construction planning data to place the construction site in a spatial coordinate system, analyzes the construction planning data, and obtains construction equipment and construction materials corresponding to all construction projects based on the analysis results; then obtains the construction restriction space corresponding to each construction project in the spatial coordinate system based on the construction equipment and construction materials, analyzes the construction restriction space, and obtains the construction conflict space based on the analysis results. The advantage of this is that by obtaining the construction equipment and construction materials corresponding to the construction project and obtaining the construction conflict space, it is possible to effectively obtain the areas where there are potential conflicts when each construction project is constructed simultaneously with all other construction projects, which is helpful for analyzing the areas where there are potential conflicts when analyzing the progress of the construction project later, thereby effectively predicting and adjusting the areas where conflicts occur in the construction project, and preventing the problem of conflicts in the construction project interfering with the normal construction process;
[0041] The present application also establishes a planning timeline based on the construction planning data, and analyzes the progress of each construction project in the spatial coordinate system based on the planning timeline; analyzes the construction conflict space, obtains the conflict time based on the analysis results, and makes construction adjustments. The advantage of this is that by analyzing the progress of the construction project based on the planning timeline, the conflict time when the conflict of the construction project occurs can be obtained, so that the construction can be adjusted based on the conflict time, which helps to prevent the normal construction progress from being disturbed by the land conflict, thereby affecting the overall construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0042] Figure 1 is a flow chart of the steps of the method of the present invention;
[0043] Figure 2 It is a schematic diagram of the construction timeline of the present invention;
[0044] Figure 3 It is a schematic diagram of obtaining the construction restricted space of the present invention;
[0045] Figure 4 It is a schematic structural diagram of the electronic device of the present invention. DETAILED DESCRIPTION
[0046] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0047] Example 1, first aspect, please refer to Figure 1As shown, this application provides a construction project management method based on BIM modeling, including the following steps:
[0048] Step S1, placing the construction site in a spatial coordinate system using BIM modeling based on the construction planning data, analyzing the construction planning data, and obtaining construction equipment and construction materials corresponding to all construction projects based on the analysis results;
[0049] Step S1 includes: step S101, obtaining the position of the construction site in the map; establishing a spatial coordinate system, recorded as the construction analysis coordinate system, wherein the units of the X-axis, Y-axis and Z-axis of the construction analysis coordinate system are all meters; obtaining the size data of each construction equipment in the construction site in the map based on the construction planning data, and using BIM modeling to establish a model corresponding to the construction site in the construction analysis coordinate system, recorded as the construction model, wherein the construction planning data is used to record the size data of all construction equipment during construction in the construction site, the construction time data of the construction project, the data of the construction equipment used in the construction project, and the quantity and location data of the construction materials;
[0050] In the specific implementation process, by using BIM modeling to establish a model corresponding to the construction site in the construction analysis coordinate system, it is helpful to analyze the construction model in the subsequent analysis, so as to more conveniently obtain accurate site data; for example, in a data analysis, the two construction projects in the construction planning data used in this embodiment are mixing mud and sand and building steel bars, and the construction equipment for mixing mud and sand includes a mud and sand transport truck, a cement transport truck and a concrete mixer. The construction time for mixing mud and sand is from 14:00 to 15:00, and the construction materials are 100 kg of soil and 100 kg of sand respectively; the construction equipment for building steel bars includes a steel bar transport truck, a cement transport truck, a steel bar straightening machine and a steel bar cutting machine. The construction time for building steel bars is from 14:20 to 15:40, and the construction materials are 100 kg of steel bars;
[0051] Step S102, record the number of construction equipment as R, record the number of construction projects as T; create a table of R+1 rows×T+1 columns, and record it as a project analysis table; wherein, the top row of the project analysis table is filled with all construction projects from left to right except the leftmost cell, and the leftmost column of the project analysis table is filled with all construction equipment from top to bottom except the top cell;
[0052] In the specific implementation process, the project analysis table obtained based on the construction planning data of this embodiment is shown in Table 1: Project Analysis Table;
[0053] Table 1: Project analysis table
[0054]
[0055]
[0056] Please refer to the time axis corresponding to the mixing of mud and the construction of steel bars obtained through analysis. Figure 2 As shown, the time axis corresponding to DD1 is the construction time axis of mixing mud and sand, and XB0 is the time when the mud and sand transport truck is used at 14:02, XB1 is the time when the cement transport truck is used at 14:10 and 14:30, and XB2 is the time when the concrete mixer is used at 14:15 and 14:40; the time axis corresponding to DD2 is the construction time axis of building steel bars, and XB1 is the time when the cement transport truck is used at 14:30, XB3 is the time when the steel bar transport truck is used at 14:22, XB4 is the time when the steel bar straightening machine is used at 14:40, and XB5 is the time when the steel bar cutting machine is used at 15:15;
[0057] Step S103: for any construction project in the project analysis table, the time required to complete the construction project is recorded as t, and all the construction equipment used to complete the construction project are recorded as project equipment XB1 to project equipment XB j ; Establish a time axis with a length of t, recorded as the construction time axis;
[0058] Step S104: for any project device XB j1 , set the start time of the construction project as the starting point of the construction timeline, and set the project equipment XB j1 The time used is marked in the construction timeline, and the marked time node and time period are recorded as project equipment XB j1 The time of use will be j1 The time of use is filled in the XB in the construction analysis form j1 —T1 grid, where XB j1 —T1 is project equipment XB j1 The cell where the row is located and the column where the construction project is located intersects, j1 is a positive integer less than or equal to j and greater than or equal to 1; analyze all project equipment XB of the construction equipment, and fill in the corresponding usage time in the corresponding cell;
[0059] Step S105, obtaining the usage time of the project equipment XB of all construction projects and filling in the corresponding cells.
[0060] Step S2, based on the construction equipment and construction materials, obtain the construction restriction space corresponding to each construction project in the spatial coordinate system, analyze the construction restriction space, and obtain the construction conflict space based on the analysis result; Step S2 includes: Step S201, for any construction project and the project equipment XB1 to project equipment XB used to complete the construction project j ; For any project device XB j1, set the project device XB j1 The position in the construction analysis coordinate system is recorded as the equipment position SW j1 ; When the construction project is completed, the project equipment XB j1 The construction materials used are recorded as equipment materials SC, and the positions of all equipment materials in the construction analysis coordinate system are recorded as material positions CW; for any material position CW, the material position CW is marked to the equipment position SW in the construction analysis coordinate system based on the construction planning data j1 The shortest path is recorded as the material transportation path;
[0061] In the specific implementation process, obtaining the material transportation path will help to obtain the conflicting paths between construction projects in the subsequent analysis, so that in the actual construction, analysis can be performed based on the conflicting paths and construction adjustments can be made to prevent conflicts in material transportation paths during the actual construction, which will affect the overall construction progress.
[0062] Step S202, obtain the material transportation paths corresponding to all equipment materials SC, and store all material positions SC, all material transportation paths and equipment positions SW j1 Recorded as project equipment XB j1 Equipment restricted area; record the equipment restricted area of all project equipment XB as the construction restricted space of the construction project;
[0063] Step S203, obtaining the construction restricted space of all construction projects;
[0064] Step S204, for any two construction projects α1 and α2, the construction restriction space β1 and the construction restriction space β2 of the construction project α1 and the construction project α2 are simultaneously placed in the construction analysis coordinate system;
[0065] Step S205, when the construction restriction space β1 and the construction project β2 do not have an intersection, the construction project α1 and the construction project α2 are recorded as non-intersecting projects; when the construction restriction space β1 and the construction restriction space β2 have an intersection and only the material position SC exists in the intersection area, the construction project α1 and the construction project α2 are recorded as non-intersecting projects, wherein the construction conflict space of the non-intersecting projects is recorded as non-existent;
[0066] In the specific implementation process, for example, the construction restricted spaces corresponding to the mixing of mud and sand and the construction of steel bars in the construction project of this embodiment are respectively as follows: Figure 3As shown in TT1 and TT2 in, SW1 is the location of the cement truck, SW2 is the location of the silt truck and the concrete mixer, SW3 is the location of the steel bar straightening machine and the steel bar cutting machine, SW4 is the location of the steel bar truck, and the path between SW1 and SW3 is the path of the cement truck in the process of building the steel bar, the path between SW1 and SW2 is the path of the silt truck in the process of mixing silt, and the path between SW3 and SW4 is the path of the steel bar truck in the process of building the steel bar; through analysis, it can be obtained that the area where WW1 and SW1 are located is the intersection of the construction space TT1 and the construction space TT2, then mixing silt and building steel bars are recorded as full intersection projects, and the location SW1 of the cement truck and the path WW1 are recorded as construction conflict space;
[0067] Step S206, when the construction restricted space β1 and the construction restricted space β2 intersect, a material transportation path exists in the intersection area, and there is no equipment position SW in the intersection area, the construction project α1 and the construction project α2 are recorded as path intersection projects, and the material transportation path in the intersection area is recorded as a construction conflict space;
[0068] Step S207, when the construction restricted space β1 and the construction restricted space β2 intersect, there is a device position SW in the intersection area, and there is no transportation material path in the intersection area, the construction project α1 and the construction project α2 are recorded as equipment intersection projects, and the device position SW in the intersection area is recorded as a construction conflict space;
[0069] Step S208, when the construction restricted space β1 and the construction restricted space β2 intersect and there are equipment positions SW and material transportation paths in the intersection area, the construction project α1 and the construction project α2 are recorded as full intersection projects, and the equipment positions SW and material transportation paths in the intersection area are recorded as construction conflict space;
[0070] Step S209: Analyze each construction project with all other construction projects, and obtain corresponding construction conflict spaces.
[0071] Step S3, establishing a planning timeline based on the construction planning data, and analyzing the progress of each construction project in the spatial coordinate system based on the planning timeline; analyzing the construction conflict space, obtaining the conflict time based on the analysis results and making construction adjustments; Step S3 includes:
[0072] Step S301, for any construction plan in the construction planning data, a planning time axis is established, wherein the starting point of the planning time axis is the time when construction starts in the construction plan, and the end point of the planning time axis is the time when construction ends in the construction plan;
[0073] Step S302: record all construction projects used for construction planning as planning projects GX1 to GX n ; The construction time of all planning projects GX in the construction plan is marked as planning period GS1 to planning period GS in the planning timeline. n ;
[0074] Step S303: for any planning project GX n1 , will be combined with the planning period GS n1 The planning project corresponding to the planning period GS with an intersection is recorded as planning project GX n1 The items to be screened and analyzed; when the items to be screened and analyzed are the same as the planned items GX n1 If there are no overlapping projects, no adjustment will be made to the construction. n1 If not all of them are non-intersecting projects, they will be combined with the planned project GX n1 The analysis items to be screened that are not non-intersection items are recorded as conflict analysis items;
[0075] Step S304: for any conflict analysis item, record the planning period GS of the conflict analysis item as the conflict period; when the conflict analysis item and the planning item are path intersection items, record the planning item GX n1 The time for transporting materials to the construction conflict space is in the planning period GS n1 In the conflict analysis project, the time for transporting materials to the construction conflict space is recorded as the conflict path time in the conflict period; when the project path time and the conflict path time overlap, the project path time is recorded as the conflict time; when the project path time and the conflict path time do not overlap, no conflict time is set;
[0076] In the specific implementation process, in the analysis of this embodiment, mixing mud and building steel bars are conflict analysis projects and are full intersection projects. For the planning project mixing mud and building steel bars, Figure 2The construction time axis DD2 of the steel bar construction is recorded as the conflict period; through analysis, it can be obtained that for the construction conflict space WW1: the time when the silt transport truck drives to WW1 in the silt mixing is 14:10, and the time when the steel bar transport truck drives to WW1 in the steel bar construction is 14:25, then the project path time and the conflict path time do not overlap, and no conflict time is set; for the construction conflict space SW1: the cement transport truck is used at 14:10 and 14:30 in the silt mixing, and the cement transport truck is used at 14:30 in the steel bar construction. At 14:30, the same cement transport truck is used by two construction projects at the same time, that is, the project equipment time and the conflict equipment time overlap. In order to ensure that both construction projects can be implemented smoothly, 14:30 should be recorded as the conflict time, and the conflict time should be reported to the staff, so as to adjust the time when the cement transport truck is used in the two construction projects to prevent the conflict of the use of cement transport trucks from interfering with the normal construction process, thereby affecting the overall construction efficiency;
[0077] Step S305: When the conflict analysis project and the planning project are equipment intersection projects, the project equipment XB corresponding to the equipment position SW recorded as the construction conflict space is recorded as the equipment to be screened; based on the planning project GX n1 The usage time of the equipment to be screened is in the planning period GS n1 The use time of the equipment to be screened based on the conflict analysis project is recorded as the conflict equipment time in the conflict period. When the project equipment time and the conflict equipment time overlap, the overlapping time node or time period is recorded as the conflict time, and the conflict time is set; when the project equipment time and the conflict equipment time do not overlap, the conflict time is not set;
[0078] Step S306, when the conflict analysis item and the planning item are full intersection items, based on the analysis method when the conflict analysis item and the planning item are path intersection items and when the conflict analysis item and the planning item are path intersection items, obtaining the conflict time;
[0079] Step S307: when the conflicting time is obtained, the planning project GX n1 The process at the conflict time and the process of the conflict analysis project at the conflict time are recorded as the planning conflict process and the analysis conflict process; for any conflicting process in the planning conflict process and the analysis conflict process, the other processes of the planning project GX where the conflicting process is located are recorded as the to-be-associated processes DG1 to the to-be-associated processes DG g , for any process DG to be associated g1 , when the equipment material SC or project equipment XB used in the conflicting process is associated with the process to be associated DG g1 If the equipment material SC or project equipment XB in the same, the process DG to be associatedg1 Recorded as a weakly associated process of the conflicting process; when the equipment material SC and project equipment XB used in the conflicting process are g1 If the equipment material SC and project equipment XB are the same, the process to be associated DG g1 Recorded as a strongly associated process of the conflicting process;
[0080] In the specific implementation process, for example, in a data processing, the planning conflict process and the analysis conflict process are mixing mud and building steel bars, and the conflict time is 14:30; the process of mixing mud at 14:30 is transporting cement, and all the processes DG to be associated with mixing mud are transporting mud and mixing mud, among which, the equipment materials SC and project equipment XB used for transporting cement are cement and cement transport truck, the equipment materials SC and project equipment XB used for transporting mud are mud and mud transport truck, and the equipment materials SC and project equipment XB used for mixing mud are concrete mixer, mud and cement; then mixing mud can be recorded as a weakly associated process of the conflicting process transporting cement; by obtaining the weakly associated process and the strongly associated process of the conflicting process, the correlation between the conflicting process and other processes can be obtained. For the conflicting process with weak correlation with other processes, the process can be adjusted relatively easily to prevent the adjustment of the process from affecting other processes in the project;
[0081] The number of processes recorded as strongly associated in all processes to be associated DG is recorded as the strong association value; the number of processes recorded as weakly associated in all processes to be associated DG is recorded as the weak association value; when the strong association value of the planning conflict process is equal to the strong association value of the analysis conflict process, both the planning conflict process and the analysis conflict process are recorded as processes to be adjusted; when the strong association value of the planning conflict process is not equal to the strong association value of the analysis conflict process, the conflict process with the smallest sum of the strong association value and the weak association value in the planning conflict process and the analysis conflict process is recorded as the process to be adjusted; in the specific implementation process, for example, in a data processing, the strong association value corresponding to the mixing of mud and sand is 1 and the weak association value is 1, and the strong association value corresponding to the construction of steel bars is 1 and the weak association value is 2, then through analysis, it can be obtained that the conflict process corresponding to the mixing of mud and sand is recorded as the process to be adjusted;
[0082] Report the progress to be adjusted for construction adjustment; based on the GX of the planned project n1 The analytical method is used for all planning projects GX n1 Conduct analysis and make construction adjustments after obtaining the conflicting time.
[0083] Example 2, please refer to Figure 4 As shown, Figure 4The structural schematic diagram of an electronic device is illustrated, and the electronic device may include: a processor, a communication interface, a memory and a communication bus, wherein the processor, the communication interface and the memory complete mutual communication through the communication bus. The memory stores computer-readable instructions, and the processor may call the instructions in the memory. When the computer-readable instructions are executed by the processor, the steps in the construction project management method based on BIM modeling are executed to realize the following functions: first, the construction site is placed in the spatial coordinate system using BIM modeling based on the construction planning data, and the construction planning data is analyzed, and the construction equipment and construction materials corresponding to all construction projects are obtained based on the analysis results; then, the construction restriction space corresponding to each construction project is obtained in the spatial coordinate system based on the construction equipment and construction materials, and the construction restriction space is analyzed, and the construction conflict space is obtained based on the analysis results; finally, a planning timeline is established based on the construction planning data, and the progress of each construction project is analyzed in the spatial coordinate system based on the planning timeline; the construction conflict space is analyzed, and the conflict time is obtained based on the analysis results and construction adjustments are made.
[0084] In addition, the logic instructions in the above-mentioned memory can be implemented in the form of software functional units and can be stored in a computer-readable storage medium when sold or used as an independent product. Based on this understanding, the technical solution of the present application can be essentially or partly embodied in the form of a software product that contributes to the prior art, and the computer software product is stored in a storage medium, including several instructions to enable a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present application. The aforementioned storage medium includes: various media that can store program codes, such as a USB flash drive, a mobile hard disk, a read-only memory (ROM), a random access memory (RAM), a disk or an optical disk.
[0085] Embodiment 3. The present application also provides a computer program product, which includes a computer program stored on a computer-readable storage medium, and the computer program includes program instructions. When the program instructions are executed by a computer, the computer can execute the construction project management method based on BIM modeling provided by the above methods, and the method includes: first, based on the construction planning data, the construction site is placed in a spatial coordinate system using BIM modeling, and the construction planning data is analyzed, and the construction equipment and construction materials corresponding to all construction projects are obtained based on the analysis results; then, based on the construction equipment and construction materials, the construction restriction space corresponding to each construction project is obtained in the spatial coordinate system, and the construction restriction space is analyzed, and the construction conflict space is obtained based on the analysis results; finally, a planning timeline is established based on the construction planning data, and the progress of each construction project is analyzed in the spatial coordinate system based on the planning timeline; the construction conflict space is analyzed, and the conflict time is obtained based on the analysis results and construction adjustments are made.
[0086] Embodiment 4, the present application also provides a computer-readable storage medium, the present application provides a storage medium, on which a computer program is stored. When the computer program is executed by a processor, the steps in the construction project management method based on BIM modeling are executed to achieve the following functions: first, the construction site is placed in a spatial coordinate system based on the construction planning data using BIM modeling, and the construction planning data is analyzed, and the construction equipment and construction materials corresponding to all construction projects are obtained based on the analysis results; then, the construction restriction space corresponding to each construction project is obtained in the spatial coordinate system based on the construction equipment and construction materials, and the construction restriction space is analyzed, and the construction conflict space is obtained based on the analysis results; finally, a planning timeline is established based on the construction planning data, and the progress of each construction project is analyzed in the spatial coordinate system based on the planning timeline; the construction conflict space is analyzed, and the conflict time is obtained based on the analysis results and construction adjustments are made.
[0087] Through the description of the above implementation methods, the embodiments of the present invention can be provided as methods, systems or computer program products. Based on such an understanding, the above technical solutions can be essentially or partly contributed to the prior art in the form of software products, which can be stored in a computer-readable storage medium, such as ROM / RAM, a magnetic disk, an optical disk, etc., and include several instructions for enabling a computer device (which can be a personal computer, a server, or a network device, etc.) to execute the methods described in each embodiment or some parts of the embodiments.
[0088] In the embodiments provided in the present application, it should be understood that the disclosed system or method can be implemented in other ways. The embodiments described above are merely schematic. For example, the division of modules or units is only a logical function division. There may be other division methods in actual implementation. For example, multiple modules or units can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some communication interfaces, and the indirect coupling or communication connection of systems, modules and units can be electrical, mechanical or other forms.
[0089] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit it. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application.
Claims
1. The construction project management method based on BIM modeling is characterized by: The steps include: Based on the construction planning data, BIM modeling is used to place the construction site in the spatial coordinate system, and the construction planning data is analyzed. Based on the analysis results, the construction equipment and materials corresponding to all construction projects are obtained; Obtain the construction restriction space corresponding to each construction project in the spatial coordinate system based on the construction equipment and construction materials, analyze the construction restriction space, and obtain the construction conflict space based on the analysis results; A planning timeline is established based on the construction planning data, and the progress of each construction project is analyzed in the spatial coordinate system based on the planning timeline; the construction conflict space is analyzed, and the conflict time is obtained based on the analysis results and construction adjustments are made.
2. The construction project management method based on BIM modeling according to claim 1 is characterized in that: Based on the construction planning data, BIM modeling is used to place the construction site in the spatial coordinate system, and the construction planning data is analyzed. Based on the analysis results, the construction equipment and construction materials corresponding to all construction projects are obtained, including: Obtain the location of the construction site in the map; establish a spatial coordinate system, recorded as the construction analysis coordinate system, where the units of the X-axis, Y-axis and Z-axis of the construction analysis coordinate system are all meters; obtain the size data of each construction equipment in the construction site in the map based on the construction planning data, and use BIM modeling to establish a model corresponding to the construction site in the construction analysis coordinate system, recorded as the construction model, where the construction planning data is used to record the size data of all construction equipment during construction in the construction site, the construction time data of the construction project, the data of the construction equipment used in the construction project, and the quantity and location data of the construction materials; Record the number of construction equipment as R, and the number of construction projects as T; create a table of R+1 rows × T+1 columns and record it as the project analysis table; among which, the top row of the project analysis table is filled with all construction projects from left to right except the leftmost cell, and the leftmost column of the project analysis table is filled with all construction equipment from top to bottom except the top cell.
3. The construction project management method based on BIM modeling according to claim 2 is characterized in that: Based on the analysis results, the construction equipment and materials corresponding to all construction projects are obtained, including: For any construction project in the project analysis table, the time required to complete the construction project is recorded as t, and all the construction equipment used to complete the construction project are recorded as project equipment XB1 to project equipment XB j ; Establish a time axis with a length of t, recorded as the construction time axis; For any project device XB j1 , set the start time of the construction project as the starting point of the construction timeline, and set the project equipment XB j1 The time used is marked in the construction timeline, and the marked time node and time period are recorded as project equipment XB j1 The time of use will be j1 The time of use is filled in the XB in the construction analysis form j1 —T1 grid, where XB j1 —T1 is project equipment XB j1 The cell where the row is located and the column where the construction project is located intersects, j1 is a positive integer less than or equal to j and greater than or equal to 1; analyze all project equipment XB of the construction equipment, and fill in the corresponding usage time in the corresponding cell; Get the usage time of project equipment XB of all construction projects and fill in the corresponding cells.
4. The construction project management method based on BIM modeling according to claim 3 is characterized in that: Based on construction equipment and construction materials, the construction restriction space corresponding to each construction project is obtained in the spatial coordinate system, including: For any construction project and project equipment XB1 to project equipment XB used to complete the construction project j ; For any project device XB j1 , set the project device XB j1 The position in the construction analysis coordinate system is recorded as the equipment position SW j1 ; When the construction project is completed, the project equipment XB j1 The construction materials used are recorded as equipment materials SC, and the positions of all equipment materials in the construction analysis coordinate system are recorded as material positions CW; for any material position CW, the material position CW is marked to the equipment position SW in the construction analysis coordinate system based on the construction planning data j1 The shortest path is recorded as the material transportation path; Get the material transportation paths corresponding to all equipment materials SC, and store all material locations SC, all material transportation paths and equipment locations SW j1 Recorded as project equipment XB j1 Equipment restricted area; record the equipment restricted area of all project equipment XB as the construction restricted space of the construction project; Get the construction restricted spaces for all construction projects.
5. The construction project management method based on BIM modeling according to claim 4 is characterized in that: Analyze the construction restriction space, and obtain the construction conflict space based on the analysis result, including: for any two construction projects α1 and α2, simultaneously place the construction restriction space β1 and the construction restriction space β2 of the construction project α1 and the construction project α2 in the construction analysis coordinate system; When the construction restriction space β1 and the construction project β2 do not have an intersection, the construction project α1 and the construction project α2 are recorded as non-intersecting projects; when the construction restriction space β1 and the construction restriction space β2 have an intersection and only the material position SC exists in the intersection area, the construction project α1 and the construction project α2 are recorded as non-intersecting projects, wherein the construction conflict space of the non-intersecting projects is recorded as non-existent; When the construction restriction space β1 and the construction restriction space β2 intersect, there is a material transportation path in the intersection area, and there is no equipment location SW in the intersection area, the construction project α1 and the construction project α2 are recorded as path intersection projects, and the material transportation path in the intersection area is recorded as the construction conflict space; When the construction restriction space β1 and the construction restriction space β2 intersect, there is an equipment location SW in the intersection area, and there is no transportation material path in the intersection area, the construction project α1 and the construction project α2 are recorded as equipment intersection projects, and the equipment location SW in the intersection area is recorded as the construction conflict space; When the construction restriction space β1 and the construction restriction space β2 intersect and there are equipment positions SW and material transportation paths in the intersection area, the construction project α1 and the construction project α2 are recorded as full intersection projects, and the equipment positions SW and material transportation paths in the intersection area are recorded as construction conflict space; Each construction project is analyzed with all other construction projects, and the corresponding construction conflict space is obtained.
6. The construction project management method based on BIM modeling according to claim 5 is characterized in that: Establish a planning timeline based on the construction planning data, and analyze the progress of each construction project in the spatial coordinate system based on the planning timeline; analyze the construction conflict space, obtain the conflict time based on the analysis results and make construction adjustments, including: For any construction plan in the construction planning data, a planning time axis is established, wherein the starting point of the planning time axis is the time when construction starts in the construction plan, and the end point of the planning time axis is the time when construction ends in the construction plan; All construction projects used for construction planning are recorded as planning projects GX1 to GX n ; The construction time of all planning projects GX in the construction plan is marked as planning period GS1 to planning period GS in the planning timeline. n ; For any planning project GX n1 , will be combined with the planning period GS n1 The planning project corresponding to the planning period GS with an intersection is recorded as planning project GX n1 of analysis items to be screened; when the analysis items to be screened are the same as the planned items GX n1 If there are no overlapping projects, no adjustment will be made to the construction. n1 If not all of them are non-intersecting projects, they will be combined with the planned project GX n1 The analysis items to be screened that are not non-intersection items are recorded as conflict analysis items.
7. The construction project management method based on BIM modeling according to claim 6 is characterized in that: Analyze the construction conflict space, obtain the conflict time based on the analysis results and make construction adjustments, including: For any conflict analysis project, the planning period GS of the conflict analysis project is recorded as the conflict period; when the conflict analysis project and the planning project are path intersection projects, the planning project GX n1 The time for transporting materials to the construction conflict space is in the planning period GS n1 In the conflict analysis project, the time for transporting materials to the construction conflict space is recorded as the conflict path time in the conflict period; when the project path time and the conflict path time overlap, the project path time is recorded as the conflict time; when the project path time and the conflict path time do not overlap, no conflict time is set; When the conflict analysis project and the planning project are equipment intersection projects, the project equipment XB corresponding to the equipment position SW recorded as the construction conflict space is recorded as the equipment to be screened; based on the planning project GX n1 The usage time of the equipment to be screened is in the planning period GS n1 The use time of the equipment to be screened based on the conflict analysis project is recorded as the conflict equipment time in the conflict period. When the project equipment time and the conflict equipment time overlap, the overlapping time node or time period is recorded as the conflict time, and the conflict time is set; when the project equipment time and the conflict equipment time do not overlap, the conflict time is not set; When the conflict analysis project and the planning project are full intersection projects, the conflict time is obtained based on the analysis method when the conflict analysis project and the planning project are path intersection projects and when the conflict analysis project and the planning project are path intersection projects.
8. The construction project management method based on BIM modeling according to claim 7 is characterized in that: Analyze the construction conflict space, obtain the conflict time based on the analysis results and make construction adjustments, including: When the conflicting time is obtained, the planning project GX n1 The process at the conflict time and the process of the conflict analysis project at the conflict time are recorded as the planning conflict process and the analysis conflict process; for any conflicting process in the planning conflict process and the analysis conflict process, the other processes of the planning project GX where the conflicting process is located are recorded as the to-be-associated processes DG1 to the to-be-associated processes DG g , for any process DG to be associated g1 , when the equipment material SC or project equipment XB used in the conflicting process is associated with the process to be associated DG g1 If the equipment material SC or project equipment XB in the same, the process DG to be associated g1 Recorded as a weakly associated process of the conflicting process; when the equipment material SC and project equipment XB used in the conflicting process are g1 If the equipment material SC and project equipment XB are the same, the process to be associated DG g1 Recorded as a strongly associated process of the conflicting process; The number of processes recorded as strongly associated in all the processes to be associated DG is recorded as the strong association value; the number of processes recorded as weakly associated in all the processes to be associated DG is recorded as the weak association value; when the strong association value of the planning conflict process is equal to the strong association value of the conflict analysis process, both the planning conflict process and the conflict analysis process are recorded as processes to be adjusted; when the strong association value of the planning conflict process is not equal to the strong association value of the conflict analysis process, the conflict process with the smallest sum of the strong association value and the weak association value in the planning conflict process and the conflict analysis process is recorded as the process to be adjusted; Report the progress to be adjusted for construction adjustment; based on the GX of the planned project n1 The analytical method is used for all planning projects GX n1 Conduct analysis and make construction adjustments after obtaining the conflicting time.
9. An electronic device, characterized in that: The method comprises a processor and a memory, wherein the memory stores computer-readable instructions. When the computer-readable instructions are executed by the processor, the steps in the method according to any one of claims 1 to 8 are executed.
10. A storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 8 are executed.
Citation Information
Patent Citations
Construction project platform management method and system
CN117649317A
Cited By
Construction project progress management method and system based on BIM
CN119990721A
Construction optimization method and system based on BIM model
CN120197910A
Fabricated office building construction management method and system
CN120430754A
Building engineering management method and system based on BIM
CN121766638A