Rapid forming pouring type bus duct and pouring method thereof

By heating at the bottom of the cast busbar gun mold and cooling on the side wall, combined with the top scraping structure, the problem of insufficient epoxy resin filling is solved, and the casting effect and molding efficiency are improved.

CN119543019APending Publication Date: 2025-02-28ZHENJIANG GARDERMOEN INTELLIGENT POWER TECH CO LTD

Patent Information

Application Number
CN202411646557.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-18
Publication Date
2025-02-28

AI Technical Summary

Technical Problem

The existing pouring bus troughs have insufficient filling problems during the epoxy resin pouring process, resulting in molding defects and increased molding time.

Method used

By setting a heating structure at the bottom of the cast bus trough mold, the epoxy resin fluid is kept in the fluid state, and a cooling structure is set on the side wall to quickly cool the epoxy resin fluid, while a scraping structure is set on the top of the mold to ensure the integrity of the epoxy resin fluid.

Benefits of technology

The casting effect of epoxy resin is improved, ensuring that the epoxy resin fully fills the mold, reducing molding defects and shortening molding time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119543019A_ABST
    Figure CN119543019A_ABST
Patent Text Reader

Abstract

The invention discloses a rapid forming pouring type bus duct and a pouring method thereof, the rapid forming pouring type bus duct comprises a bus duct body, the bus duct body comprises a plurality of conductive copper bars distributed at equal intervals, the middle positions of the plurality of conductive copper bars are sleeved with a copper bar stabilizing frame, and epoxy resin layers are poured on the outer walls of the copper bar stabilizing frame and the plurality of conductive copper bars. According to the pouring type bus duct mold, the heating structure is arranged at the bottom of the pouring type bus duct mold, so that poured epoxy resin fluid can be in a fluid state, the situation that the epoxy resin fluid is insufficiently filled in the mold is prevented, and the pouring effect of epoxy resin is improved; according to the pouring mold, the epoxy resin fluid can be rapidly cooled after being filled, the forming efficiency of the pouring type bus duct is improved, meanwhile, a slicking structure is arranged at the top of the pouring mold, rapid slicking treatment can be conveniently conducted on the epoxy resin fluid after pouring, and the integrity of the epoxy resin fluid after pouring forming is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of application of cast-type bus duct, in particular to a rapid prototyping cast-type bus duct and a casting method thereof. Background Art

[0002] Cast-in-place bus duct is a system used for power transmission and distribution, usually made of copper or aluminum. Its main feature is that it forms a complete structure by embedding the conductor into the insulating material, thus providing good electrical performance and mechanical strength.

[0003] When pouring epoxy resin, the existing cast-type bus duct generally requires multiple people to assemble the casting mold, and when installing multiple conductive copper bars, multiple people need to cooperate with each other to neatly adjust and fix the conductive copper bars, thereby increasing the cost of labor input. At the same time, when pouring epoxy resin fluid, the top of the mold is generally open, and it needs to be poured manually step by step. After a period of time, the epoxy resin fluid at the initial position of the bottom of the mold will solidify and cannot blend with each other, thereby causing the epoxy resin fluid to be unable to fully fill the mold, resulting in some defects, affecting the integrity of the cast-type bus duct, and in the later stage of molding, it is generally left to stand and cool naturally, which increases the molding time of the bus duct. Therefore, the present invention proposes a rapid molding cast-type bus duct and a casting method thereof. Summary of the invention

[0004] The technical problem to be solved by the present invention is to provide a rapid prototyping cast-type bus duct and a casting method thereof. A heating structure is provided at the bottom of the cast-type bus duct mold so that the injected epoxy resin fluid can be in a fluid state, thereby preventing the epoxy resin fluid from being insufficiently filled inside the mold and improving the casting effect of the epoxy resin. A cooling structure is correspondingly provided on the side wall of the mold so that the filled epoxy resin fluid can quickly dissipate heat and cool, thereby improving the molding efficiency of the cast-type bus duct. At the same time, a scraping structure is provided on the top of the casting mold so that the cast epoxy resin fluid can be quickly scraped and leveled to ensure the integrity of the epoxy resin fluid after casting.

[0005] In order to solve the above technical problems, a technical solution adopted by the present invention is: to provide a rapid prototyping casting type bus duct, including a bus duct body, the bus duct body comprises a plurality of equally spaced conductive copper bars, a copper bar stabilizing frame is sleeved at the middle position of the plurality of conductive copper bars, and an epoxy resin layer is cast on the outer wall of the copper bar stabilizing frame and the plurality of conductive copper bars; A rapid prototyping mold, which is snap-connected to the outer wall of a plurality of conductive copper bars and is used for positioning and casting the plurality of conductive copper bars; The rapid prototyping mold comprises The heating positioning frame at the bottom is used to heat the epoxy resin fluid poured into the rapid prototyping mold to keep it in a fluid state; A matching scraping frame, which is snap-connected to the top of the heating positioning frame and is used to scrape the top of the epoxy resin fluid after it is poured in; Two cooling side plates, the two cooling side plates are symmetrically hingedly connected to the side walls of the heating positioning frame, and are used to limit the injected epoxy resin fluid and quickly cool and form it; Two mold reinforcement components, the two mold reinforcement components are symmetrically connected to the top of the matching scraper frame near the end surface, and are used to stably fit the two cooling side plates to the side walls of the matching scraper frame; Two copper bar adjustment components are symmetrically bolted to the bottom of the heating positioning frame and close to the end surface, and are used to align the end surfaces of multiple conductive copper bars placed in the rapid prototyping mold.

[0006] The present invention is further configured as follows: a U-shaped protective frame is fixedly connected to the bottom of the heating positioning frame, and the end face of the protective frame extends to the bottom of the two copper bar adjustment components, positioning grooves are symmetrically provided at the top position of the end face of the heating positioning frame, and positioning blocks are symmetrically fixedly connected to the bottom position of the end face of the matching scraping frame, and the heating positioning frame and the matching scraping frame are mutually engaged and connected through the arranged positioning grooves and positioning blocks.

[0007] Through the above technical solution, it is convenient to use the bottom protective frame to protect the bottom of the entire mold and protect the copper bar adjustment assembly. The positioning block and the positioning groove can make the installed heating positioning frame and the matching scraping frame quickly positioned and fixed, thereby improving assembly efficiency.

[0008] The present invention is further configured as follows: a graphite plate is bolted to the inner bottom of the heating positioning frame, a wire groove is provided in the middle of the front wall of the graphite plate, and a plurality of heating rods are evenly inserted into the interior of the graphite plate through the guide groove, and a heat conducting plate is fitted on the top of the graphite plate.

[0009] Through the above technical solution, the multiple heating rods arranged inside the heating positioning frame are started, and the heat can be continuously transferred to the heat conducting plate through the external graphite plate. The heat conducting plate is used to heat the injected epoxy resin, so that the epoxy resin is always in a fluid state, preventing the epoxy resin from solidifying due to a long injection time and causing insufficient filling.

[0010] The present invention is further configured as follows: casting grooves are symmetrically opened near the middle of the top of the matching scraping frame, the inner walls of the two casting grooves are symmetrically fixedly connected with guide rods, and the outer walls of the two groups of sliding rods are slidably connected with the scraping frame.

[0011] Through the above technical scheme, it is convenient to use the casting trough to pour epoxy resin into the mold, and use the scraping frame to slide back and forth on the guide rod to scrape the top of the epoxy resin fluid.

[0012] The present invention is further configured as follows: the scraping frame includes a push rod sliding on the guide rod, the push rod is slidably connected to the guide rod through a sliding groove opened near the end surface, a hand push column is threadedly connected at the top center of the push rod, the bottom of the push rod is fixedly connected to a scraper, and the side wall of the scraper is evenly provided with multiple leakage grooves.

[0013] Through the above technical scheme, when the scraping frame is pushed, it can drive the push rod to push back and forth on the guide rod through the hand push column, so that the scraper at the bottom scrapes the epoxy resin fluid inside the casting trough, and under the action of multiple internal leakage grooves, the epoxy resin fluid can overflow during the scraping process, thereby facilitating multiple reciprocating scraping operations.

[0014] The present invention is further configured as follows: the inner wall of the cooling side plate is bolted to a grid plate, the side wall of the grid plate is evenly fixedly connected to a plurality of brackets, the side portions of the plurality of brackets are clamped and connected to S-shaped cooling pipes, and the side wall of the cooling side plate is bolted to a cover plate.

[0015] Through the above technical solution, coolant is introduced into the cooling pipe inside the cooling side plate. In the process of the coolant passing through the cooling pipe, the heat transferred to the side wall of the cooling side plate by the epoxy resin fluid is absorbed and carried, and the epoxy resin fluid is quickly cooled.

[0016] The present invention is further configured as follows: the mold reinforcement assembly includes a reinforcement rod A and a reinforcement rod B that are matched and connected, and the mold reinforcement assembly can be detachably installed inside an auxiliary groove opened on the top of a matching scraping frame, and is correspondingly engaged and connected to the inside of a drawing groove opened on the top of two cooling side plates through the opposite ends of the reinforcement rod A and the reinforcement rod B.

[0017] The above technical solution facilitates the installation and fixation of the mold reinforcement assembly, and the reinforcement rods A and B can be used to tightly tighten and fix the cooling side plates on both sides.

[0018] The present invention is further configured as follows: the reinforcement rod B is inserted into the insertion groove opened on the end face of the reinforcement rod A through the insertion block fixedly arranged on its end face, and the end face of the reinforcement rod B is fixedly connected with a tensioning belt, and the tensioning belt passes around the positioning shaft fixedly connected to the end face of the reinforcement rod A, and the tensioning belt is tightly sleeved on the positioning column fixedly connected to the top of the reinforcement rod B near the middle position near the end face.

[0019] Through the above technical solution, the insertion block on the end face of the reinforcement rod B is inserted into the insertion groove of the reinforcement rod A for sliding, and the tensioning belt is used to pull the reinforcement rod B for further tightening, and the tensioning belt is fixed on the positioning, so that the reinforcement rod A and the reinforcement rod B can drive the cooling side plates connected by the end faces to fit tightly against the heating positioning frame and the cooperating scraping frame to ensure the sealing of the mold.

[0020] The present invention is further configured as follows: the copper bar adjustment assembly comprises an angle bracket bolted to the bottom of the heating positioning bracket, the side wall of the angle bracket is symmetrically fixedly connected with a slide bar away from the middle position, the outer walls of the two slide bars are sequentially installed with a slider, a spring and an adjustment nut, the side wall of the slider is symmetrically bolted with a bent rod, the top positions of the two bent rods are fixedly connected with an adjustment column, and the outer wall of the adjustment column is tightly pressed against the end face of the conductive copper bar; The slider is slidably connected to the two slide rods, there are two adjusting nuts, which are respectively threadedly connected to the two slide rods near the end surfaces, and the end surfaces of the spring are respectively pressed against the slider and the adjusting nut.

[0021] Through the above technical scheme, the squeezing effect of the installed conductive copper busbar on the adjusting column is utilized, so that the bent rod drives the slider to squeeze the spring, and under the action of the restoring elasticity of the spring, the slider drives the adjusting column on the bent rod to mechanically press the conductive copper busbar, so that the installed conductive copper busbar can maintain an aligned state, and the compression force of the spring can be adjusted by using the adjusting nut according to different needs.

[0022] On the other hand, a method for casting a rapid prototyping cast-type bus duct is provided, comprising the following steps: S1. First, sleeve the copper bar stabilizing frame onto the outer walls of multiple conductive copper bars, and place the copper bar stabilizing frame in the middle of the multiple conductive copper bars; S2, then install multiple conductive copper bars inside the heating positioning frame, and at the same time, press the end surface of the conductive copper bar against the copper bar adjustment assembly, so that the conductive copper bar squeezes the two adjustment columns, and uses the restoring elasticity of the compressed spring to make the slider reset and slide on the slide rod, so that the connected curved rod drives the adjustment column to squeeze and adjust the multiple conductive copper bars, so that the end surfaces of the multiple conductive copper bars are flush with the upper end surface of the heating positioning frame; S3, then the matching scraping frame is correspondingly engaged with the plurality of conductive copper bars, and the positioning blocks provided at the bottom are used to engage with the positioning grooves provided at the top of the heating positioning frame, and then the two cooling side plates are rotated by means of hinges to form a mold cavity with the heating positioning frame; S4, then the two mold reinforcement components are clamped in the drawing groove through the movably connected reinforcement rod A and reinforcement rod B, and are installed in the auxiliary groove set on the top of the scraping frame, and then the tension belt on the reinforcement rod B is pulled, so that the insertion block on the end face of the reinforcement rod B slides in the insertion groove, so that the cooling side plates on both sides can fit tightly on the side walls of the heating positioning frame and the matching scraping frame, and at the same time, the tension belt is passed around the positioning shaft and sleeved on the positioning to ensure the cooling side plates are tightly fitted; S5, then pouring epoxy resin into the interior of the entire accelerated molding mold through two pouring troughs, and at the same time starting multiple heating rods arranged inside the heating positioning frame, and continuously transferring heat to the heat conducting plate through the external graphite plate, and using the heat conducting plate to heat the poured epoxy resin, so that the epoxy resin is always in a fluid state, to prevent the epoxy resin from solidifying due to a long pouring time and causing insufficient filling; S6. When the top layer of the epoxy resin fluid is at the bottom of the casting trough, the multiple heating rods at the bottom are turned off, and at the same time, coolant is introduced into the cooling pipe inside the cooling side plate. When the coolant passes through the cooling pipe, the heat transferred from the epoxy resin fluid to the side wall of the cooling side plate is absorbed and carried, and the epoxy resin fluid is quickly cooled; S7. Finally, use the hand push column on the scraping frame to drive the push rod to push back and forth on the guide rod, so that the scraper at the bottom scrapes the epoxy resin fluid inside the casting trough to complete the entire casting operation, and form a cast bus duct after standing and cooling for a period of time.

[0023] The beneficial effects of the present invention are as follows: 1. The rapid prototyping casting type bus duct and casting method thereof proposed by the present invention provide a heating structure at the bottom of the casting type bus duct mold, so that the injected epoxy resin fluid can be in a fluid state, thereby preventing the epoxy resin fluid from being insufficiently filled inside the mold and improving the casting effect of the epoxy resin; 2. The rapid prototyping casting type bus duct and casting method thereof proposed by the present invention provide a cooling structure corresponding to the side wall of the mold, so that the epoxy resin fluid after filling can quickly dissipate heat and cool, thereby improving the molding efficiency of the casting type bus duct; 3. The rapid prototyping cast-type bus duct and casting method thereof proposed by the present invention provides a leveling structure on the top of the casting mold, which facilitates the rapid leveling of the epoxy resin fluid after casting, thereby ensuring the integrity of the epoxy resin fluid after casting. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 A structural diagram of a rapid prototyping casting type bus duct and a casting method thereof according to the present invention; Figure 2An exploded diagram of a rapid prototyping casting type bus duct and a casting method thereof according to the present invention; Figure 3 A forming state diagram of a rapid prototyping casting type bus duct and a casting method thereof according to the present invention; Figure 4 It is an assembly structure diagram of a rapid prototyping casting type bus duct and a casting method thereof of the present invention; Figure 5 It is a structural diagram of a rapid prototyping casting type bus duct and a rapid prototyping mold in a casting method thereof of the present invention; Figure 6 This is a structural diagram of a heating and positioning frame in a rapid prototyping casting type bus duct and a casting method thereof of the present invention; Figure 7 An exploded view of a heating and positioning frame in a rapid prototyping casting type bus duct and a casting method thereof according to the present invention; Figure 8 This is a structural diagram of a quick-prototype casting type bus duct and a casting method thereof in combination with a scraping frame according to the present invention; Fig. 9 It is a structural diagram of a rapid prototyping casting type bus duct and a scraping frame in a casting method thereof of the present invention; Fig.10 An exploded view of a cooling side plate in a rapid prototyping casting type bus duct and a casting method thereof according to the present invention; Fig.11 An exploded view of a mold reinforcement component in a rapid prototyping casting type bus duct and a casting method thereof of the present invention; Fig.12 The present invention provides a structural diagram of a copper bar adjusting component in a rapid prototyping casting type bus duct and a casting method thereof.

[0025] In the figure: 1. bus duct body; 11. conductive copper bar; 12. copper bar stabilizing frame; 13. epoxy resin layer; 2. Rapid prototyping mold; 21. Heating positioning frame; 211. Protective frame; 212. Positioning groove; 213. Graphite plate; 214. Heating rod; 215. Heat conducting plate; 22, cooperating scraping frame; 221, auxiliary trough; 222, positioning block; 223, casting trough; 224, guide rod; 225, scraping frame; 2251, push rod; 2252, slide trough; 2253, hand push column; 2254, scraper; 2255, drain trough; 23. Cooling side plate; 231. Grooving; 232. Grid plate; 233. Bracket; 234. Cooling pipe; 235. Cover plate; 24. Mold reinforcement assembly; 241. Reinforcement rod A; 2411. Insertion slot; 2412. Positioning shaft; 242. Reinforcement rod B; 2421. Insertion block; 2422. Tensioning belt; 2423. Positioning column; 25. Copper busbar adjustment assembly; 251. Angle bracket; 252. Sliding rod; 253. Sliding block; 254. Spring; 255. Adjusting nut; 256. Bending rod; 257. Adjusting column. DETAILED DESCRIPTION

[0026] The preferred embodiments of the present invention are described in detail below in conjunction with the accompanying drawings so that the advantages and features of the present invention can be more easily understood by those skilled in the art, thereby making a clearer and more definite definition of the protection scope of the present invention.

[0027] like Figure 1-Figure 4 As shown, a rapid prototyping cast-type bus duct comprises a bus duct body 1, wherein the bus duct body 1 comprises a plurality of equally spaced conductive copper bars 11 for ensuring normal power supply to the entire bus duct body 1, a rapid prototyping mold 2 is arranged outside the conductive copper bars 11 for rapidly casting and molding the cast-type bus duct, a copper bar stabilizing frame 12 is sleeved at the middle positions of the plurality of conductive copper bars 11 for positioning and fixing the middle positions of the long conductive copper bars 11 to prevent the conductive copper bars 11 from bending during casting and installation, an epoxy resin layer 13 is cast on the outer walls of the copper bar stabilizing frame 12 and the plurality of conductive copper bars 11 for completely wrapping the plurality of conductive copper bars 11 and the copper bar stabilizing frame 12, thereby ensuring the insulation of the entire cast-type bus duct and providing certain protection to the conductive copper bars 11 inside.

[0028] like Figure 5-Figure 7As shown, the rapid prototyping mold 2 is snap-connected to the outer wall of a plurality of conductive copper bars 11, and the rapid prototyping mold 2 includes a heating positioning frame 21 at the bottom, which is used to heat the epoxy resin fluid poured into the rapid prototyping mold 2 to make it in a fluid state, and a U-shaped protective frame 211 is fixedly connected to the bottom of the heating positioning frame 21, and the end face of the protective frame 211 extends to the bottom of the two copper bar adjustment components 25, and the top position of the end face of the heating positioning frame 21 is symmetrically provided with positioning grooves 212, and the bottom position of the end face of the matching scraping frame 22 is symmetrically fixedly connected with positioning blocks 222, and the heating positioning frame 21 and the matching scraping frame 22 are snap-connected to each other through the provided positioning grooves 212 and positioning blocks 222, so that the bottom of the entire mold can be protected by the bottom protective frame 211, and the copper bar adjustment component 25 can be protected, and the positioning blocks 222 and the positioning grooves 212 can be used to install the heating positioning frame 21 and the matching scraping frame 22. The scraping frame 22 is combined for rapid positioning and fixing to improve assembly efficiency. The inner bottom bolt of the heating positioning frame 21 is connected with a graphite plate 213. The high thermal conductivity of the graphite plate 213 is used to improve heat transfer. A wire groove is provided in the middle of the front wall of the graphite plate 213 to facilitate the installation of the wiring harness after the multiple heating rods 214 are electrically connected to avoid the disorder of the wiring harness. Multiple heating rods 214 are evenly inserted into the inside of the graphite plate 213 through the guide groove to provide heat to the inside of the mold. A heat conducting plate 215 is provided on the top of the graphite plate 213. The multiple heating rods 214 provided inside the heating positioning frame 21 are started, and the heat can be continuously transferred to the heat conducting plate 215 through the external graphite plate 213. The poured epoxy resin is heated by the heat conducting plate 215, so that the epoxy resin is always in a fluid state to prevent the epoxy resin from solidifying due to a long pouring time and causing insufficient filling.

[0029] like Figure 5 , Figure 8 and Fig. 9As shown, the scraping frame 22 is snap-connected to the top of the heating positioning frame 21, and is used to scrape the top of the epoxy resin fluid after being poured. A casting groove 223 is symmetrically opened near the middle of the top of the scraping frame 22. The inner walls of the two casting grooves 223 are symmetrically fixedly connected with guide rods 224. The outer walls of the two sets of sliding rods 224 are slidably connected with scraping frames 225, which is convenient for pouring epoxy resin into the mold using the casting grooves 223, and the scraping frame 225 is used to slide back and forth on the guide rods 224 to scrape the top of the epoxy resin fluid. The scraping frame 225 includes a push rod 2251 sliding on the guide rod 224. The push rod 2251 passes through its end surface The slide groove 2252 opened at the position is slidably connected to the guide rod 224, and a hand push column 2253 is threadedly connected to the top center of the push rod 2251. The bottom of the push rod 2251 is fixedly connected to a scraper 2254, and a plurality of leakage grooves 2255 are evenly opened on the side wall of the scraper 2254, so that when the scraping frame 225 is pushed, it can drive the push rod 2251 to push back and forth on the guide rod 224 through the hand push column 2253, so that the scraper 2254 at the bottom can scrape and level the epoxy resin fluid inside the casting groove 223, and under the action of the multiple leakage grooves 2255 inside, the epoxy resin fluid can overflow during the scraping process, thereby facilitating multiple reciprocating scraping operations.

[0030] like Figure 5 and Fig.10 As shown, the two cooling side panels 23 are symmetrically hinged to the side walls of the heating positioning frame 21, which are used to limit the injected epoxy resin fluid and quickly cool and form it. The inner wall of the cooling side panel 23 is bolted with a grid plate 232, and the side wall of the grid plate 232 is evenly fixedly connected with a plurality of brackets 233, which is convenient for reasonable installation and fixation of the internal cooling pipe 234 and convenient for later disassembly and maintenance. The side parts of the plurality of brackets 233 are clamped and connected with S-shaped cooling pipes 234, and the side wall of the cooling side panel 23 is bolted with a cover plate 235, which is used to protect the internal cooling pipe 234 to prevent damage to the cooling pipe 234 during use. Coolant is passed into the cooling pipe 234 inside the cooling side panel 23. In the process of the coolant passing through the cooling pipe 234, the heat transferred to the side wall of the cooling side panel 23 by the epoxy resin fluid is absorbed and carried, and the epoxy resin fluid is quickly cooled.

[0031] like Figure 5 and Fig.11As shown, two mold reinforcement components 24 are symmetrically snap-fitted and connected at the top of the matching scraper frame 22 near the end surface, and are used to stably fit the two cooling side plates 23 to the side walls of the matching scraper frame 22. The mold reinforcement component 24 includes a matching reinforcement rod A241 and a reinforcement rod B242. The mold reinforcement component 24 is detachably installed in the auxiliary groove 221 opened at the top of the matching scraper frame 22, and the opposite ends of the reinforcement rod A241 and the reinforcement rod B242 are correspondingly snap-fitted and connected to the inside of the drawing groove 231 opened at the top of the two cooling side plates 23, so as to facilitate the installation and fixation of the mold reinforcement component 24, and the reinforcement rod A241 and the reinforcement rod B242 can be used to tightly tighten and fix the cooling side plates 23 on both sides, and the reinforcement rod B242 is inserted into the reinforcement rod A241 through the insertion block 2421 fixedly arranged on its end surface. Inside the insertion groove 2411 opened on the end face, the end face of the reinforcement rod B242 is fixedly connected with a tensioning belt 2422, and the tensioning belt 2422 passes around the positioning shaft 2412 fixedly connected to the end face of the reinforcement rod A241, and the tensioning belt 2422 is tightly sleeved on the positioning column 2423 fixedly connected to the top of the reinforcement rod B242 near the middle position near the end face, and the insertion block 2421 on the end face of the reinforcement rod B242 is inserted into the insertion groove 2411 of the reinforcement rod A241 for sliding, and the tensioning belt 2422 is used to pull the reinforcement rod B242 to further tighten, and the tensioning belt 2422 is fixed on the positioning post 2423, so that the reinforcement rod A241 and the reinforcement rod B242 can drive the cooling side plate 23 connected by the end face clamping to fit tightly against the heating positioning frame 21 and the cooperating scraping frame 22 to ensure the sealing of the mold.

[0032] like Figure 5 and Fig.12As shown, two copper bar adjustment components 25 are symmetrically bolted to the bottom of the heating positioning frame 21 and close to the end surface position, which are used to align the end surfaces of multiple conductive copper bars 11 placed in the rapid prototyping mold 2. The copper bar adjustment component 25 includes an angle frame 251 bolted to the bottom of the heating positioning frame 21, which is convenient for installing and fixing the entire copper bar adjustment component 25. The side wall of the angle frame 251 is symmetrically fixedly connected with a slide bar 252 away from the middle position. The outer walls of the two slide bars 252 are successively installed with sliders 253, springs 254 and adjustment nuts 255. The side wall of the slider 253 is symmetrically bolted with a bent rod 256. The top position of the two bent rods 256 is fixedly connected with an adjustment column 257, and the outer wall of the adjustment column 257 is tightly pressed against the conductive copper bar 1 1, the slider 253 is slidably connected to the two slide bars 252, there are two adjusting nuts 255, which are respectively threadedly connected to the two slide bars 252 near the end faces, and the end faces of the spring 254 are respectively pressed against the slider 253 and the adjusting nut 255. The installed conductive copper bus 11 has an extrusion effect on the adjusting column 257, so that the bent rod 256 drives the slider 253 to squeeze the spring 254, and under the action of the restoring elasticity of the spring 254, the slider 253 drives the adjusting column 257 on the bent rod 256 to mechanically press the conductive copper bus 11, so that the installed conductive copper bus 11 can maintain an aligned state, and the compression force of the spring 254 can be adjusted by the adjusting nut 255 according to different needs.

[0033] like Figure 1-Figure 12 As shown, a method for casting a rapid prototyping casting type bus duct comprises the following steps; S1, firstly, sleeve the copper bar stabilizing frame 12 on the outer wall of the plurality of conductive copper bars 11, and place the copper bar stabilizing frame 12 in the middle of the plurality of conductive copper bars 11; S2, then install multiple conductive copper bars 11 inside the heating positioning frame 21, and at the same time, press the end surface of the conductive copper bar 11 against the copper bar adjustment component 25, so that the conductive copper bar 11 squeezes the two adjustment columns 257, and uses the restoring elasticity of the compressed spring 254 to make the slider 253 reset and slide on the slide rod 252, so that the connected curved rod 256 drives the adjustment column 257 to squeeze and adjust the multiple conductive copper bars 11, so that the end surfaces of the multiple conductive copper bars 11 are flush with the upper end surface of the heating positioning frame 21; S3, then the matching scraping frame 22 is correspondingly engaged with the plurality of conductive copper bars 11, and the positioning block 222 provided at the bottom is engaged with the positioning groove 212 provided at the top of the heating positioning frame 21, and then the two cooling side plates 23 are rotated by means of hinges to form a mold cavity with the heating positioning frame 21; S4, then the two mold reinforcement components 24 are engaged in the drawing groove 231 through the movably connected reinforcement rod A241 and reinforcement rod B242, and are installed in the auxiliary groove 221 set on the top of the scraping frame 22, and then the tension belt 2422 on the reinforcement rod B242 is pulled, so that the insertion block 2421 on the end face of the reinforcement rod B242 slides in the insertion groove 2411, so that the cooling side plates 23 on both sides can fit tightly against the side walls of the heating positioning frame 21 and the matching scraping frame 22, and at the same time, the tension belt 2422 is passed around the positioning shaft 2412 and sleeved on the positioning block 2423 to ensure the cooling side plates 23 fit tightly; S5, then pouring epoxy resin into the entire accelerated molding mold 2 through the two pouring troughs 223, while starting the multiple heating rods 214 arranged inside the heating positioning frame 21, and continuously transferring heat to the heat conducting plate 215 through the external graphite plate 213, and using the heat conducting plate 215 to heat the poured epoxy resin, so that the epoxy resin is always in a fluid state, to prevent the epoxy resin from solidifying due to a long pouring time and causing insufficient filling; S6. When the top layer of the epoxy resin fluid is at the bottom of the casting trough 223, the multiple heating rods 214 at the bottom are turned off, and at the same time, coolant is introduced into the cooling pipe 234 inside the cooling side plate 23. When the coolant passes through the cooling pipe 234, the heat transferred to the side wall of the cooling side plate 23 by the epoxy resin fluid is absorbed and carried, thereby rapidly cooling the epoxy resin fluid. S7. Finally, the push rod 2251 is pushed back and forth on the guide rod 224 by the hand push column 2253 on the scraping frame 225, so that the scraper 2254 at the bottom scrapes the epoxy resin fluid inside the casting trough 223, completing the entire casting operation, and forming a cast bus duct after standing and cooling for a period of time.

[0034] The above descriptions are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A rapid prototyping casting type bus duct, characterized in that: include A bus duct body (1), the bus duct body (1) comprising a plurality of equally spaced conductive copper bars (11), a copper bar stabilizing frame (12) being sleeved at the middle of the plurality of conductive copper bars (11), and an epoxy resin layer (13) being cast on the outer walls of the copper bar stabilizing frame (12) and the plurality of conductive copper bars (11); A rapid prototyping mold (2), the rapid prototyping mold (2) being snap-fitted and connected to the outer wall of the plurality of conductive copper bars (11) and used for positioning and casting the plurality of conductive copper bars (11); The rapid prototyping mold (2) comprises A heating positioning frame (21) located at the bottom is used to heat the epoxy resin fluid poured into the rapid prototyping mold (2) to keep it in a fluid state; A matching scraping frame (22), the matching scraping frame (22) is snap-connected to the top of the heating positioning frame (21) and is used to scrape the top of the epoxy resin fluid after it is poured in; Two cooling side plates (23), the two cooling side plates (23) are symmetrically hingedly connected to the side walls of the heating positioning frame (21), and are used to limit the position of the injected epoxy resin fluid and to quickly cool and shape it; Two mold reinforcement components (24), the two mold reinforcement components (24) are symmetrically snap-fitted to the top of the matching scraper frame (22) near the end surface, and are used to stably fit the two cooling side plates (23) to the side walls of the matching scraper frame (22); Two copper bar adjustment assemblies (25) are symmetrically bolted to the bottom of the heating positioning frame (21) and close to the end surface, and are used to align the end surfaces of a plurality of conductive copper bars (11) placed inside the rapid prototyping mold (2).

2. The rapid prototyping casting type bus duct according to claim 1, characterized in that: A U-shaped protective frame (211) is fixedly connected to the bottom of the heating positioning frame (21), and the end surface of the protective frame (211) extends to the bottom of the two copper bar adjustment components (25). Positioning grooves (212) are symmetrically provided at the top of the end surface of the heating positioning frame (21), and positioning blocks (222) are symmetrically fixedly connected to the bottom of the end surface of the matching scraping frame (22). The heating positioning frame (21) and the matching scraping frame (22) are connected to each other in a mutually engaging manner through the provided positioning grooves (212) and positioning blocks (222).

3. The rapid prototyping casting type bus duct according to claim 2, characterized in that: A graphite plate (213) is bolted to the inner bottom of the heating positioning frame (21), a guide groove is provided in the middle of the front wall of the graphite plate (213), and a plurality of heating rods (214) are evenly inserted into the graphite plate (213) through the guide groove, and a heat conducting plate (215) is fitted on the top of the graphite plate (213).

4. The rapid prototyping casting type bus duct according to claim 2, characterized in that: A casting groove (223) is symmetrically provided near the middle of the top of the matching scraping frame (22), the inner side walls of the two casting grooves (223) are symmetrically fixedly connected with guide rods (224), and the outer walls of the two sets of sliding rods (224) are slidably connected with the scraping frame (225).

5. The rapid prototyping casting type bus duct according to claim 4, characterized in that: The scraping frame (225) comprises a push rod (2251) sliding on the guide rod (224); the push rod (2251) is slidably connected to the guide rod (224) via a slide groove (2252) provided near the end surface thereof; a hand push column (2253) is threadedly connected at the center of the top of the push rod (2251); a scraper (2254) is fixedly connected to the bottom of the push rod (2251); and a plurality of drain grooves (2255) are evenly provided on the side wall of the scraper (2254).

6. The rapid prototyping casting type bus duct according to claim 1, characterized in that: The inner wall of the cooling side plate (23) is bolted to a grid plate (232), the side wall of the grid plate (232) is evenly fixedly connected to a plurality of brackets (233), the side portions of the plurality of brackets (233) are clamped and connected to S-shaped cooling pipes (234), and the side wall of the cooling side plate (23) is bolted to a cover plate (235).

7. The rapid prototyping casting type bus duct according to claim 1, characterized in that: The mold reinforcement component (24) comprises a reinforcement rod A (241) and a reinforcement rod B (242) that are matched and connected. The mold reinforcement component (24) is detachably mounted inside an auxiliary groove (221) opened at the top of the matching scraper frame (22), and is correspondingly engaged and connected to the inside of a draw groove (231) opened at the top of two cooling side plates (23) through the opposite ends of the reinforcement rod A (241) and the reinforcement rod B (242).

8. The rapid prototyping casting type bus duct according to claim 7, characterized in that: The reinforcing rod B (242) is inserted into an insertion groove (2411) provided on the end face of the reinforcing rod A (241) via an insertion block (2421) fixedly arranged on the end face of the reinforcing rod B (242); a tensioning belt (2422) is fixedly connected to the end face of the reinforcing rod B (242); the tensioning belt (2422) passes around a positioning shaft (2412) fixedly connected to the end face of the reinforcing rod A (241); and the tensioning belt (2422) is tightly sleeved near the end face onto a positioning column (2423) fixedly connected to the top of the reinforcing rod B (242) near the middle.

9. The rapid prototyping casting type bus duct according to claim 1, characterized in that: The copper busbar adjustment assembly (25) comprises an angle frame (251) bolted to the bottom of the heating positioning frame (21); a sliding rod (252) is symmetrically fixedly connected to the side wall of the angle frame (251) away from the middle position; a slider (253), a spring (254) and an adjustment nut (255) are sequentially installed on the outer walls of the two sliding rods (252); a bent rod (256) is symmetrically bolted to the side wall of the slider (253); an adjustment column (257) is fixedly connected to the top position of the two bent rods (256); and the outer wall of the adjustment column (257) is pressed against the end surface of the conductive copper busbar (11); The slider (253) is slidably connected to the two slide bars (252), there are two adjusting nuts (255), which are respectively threadedly connected to the two slide bars (252) near the end surfaces, and the end surfaces of the spring (254) are respectively pressed against the slider (253) and the adjusting nut (255).

10. A method for casting a rapid prototyping casting type bus duct according to any one of claims 1 to 9, characterized in that: The steps include: S1. First, a copper bar stabilizing frame (12) is sleeved onto the outer walls of a plurality of conductive copper bars (11), and the copper bar stabilizing frame (12) is placed in the middle of the plurality of conductive copper bars (11); S2, then installing the plurality of conductive copper bars (11) inside the heating positioning frame (21), and simultaneously pressing the end faces of the conductive copper bars (11) against the copper bar adjustment assembly (25), so that the conductive copper bars (11) press the two adjustment columns (257), and utilizing the restoring elasticity of the compressed spring (254) to cause the slider (253) to slide back on the slide bar (252), thereby causing the connected curved rod (256) to drive the adjustment column (257) to press and adjust the plurality of conductive copper bars (11), so that the end faces of the plurality of conductive copper bars (11) are flush with the upper end faces of the heating positioning frame (21); S3, then the matching scraping frame (22) is correspondingly engaged with the plurality of conductive copper bars (11), and the positioning blocks (222) provided at the bottom are engaged with the positioning grooves (212) provided at the top of the heating positioning frame (21) for positioning, and then the two cooling side plates (23) are rotated by means of hinges to form a mold cavity with the heating positioning frame (21); S4, then the two mold reinforcement components (24) are engaged in the drawing groove (231) through the movably connected reinforcement rod A (241) and the reinforcement rod B (242), and are installed in the auxiliary groove (221) set on the top of the scraping frame (22), and then the tensioning belt (2422) on the reinforcement rod B (242) is pulled so that the insertion block (2421) on the end face of the reinforcement rod B (242) slides in the insertion groove (2411), so that the cooling side plates (23) on both sides can fit tightly against the side walls of the heating positioning frame (21) and the matching scraping frame (22), and at the same time, the tensioning belt (2422) is passed around the positioning shaft (2412) and sleeved on the positioning block (2423) to ensure that the cooling side plates (23) fit tightly; S5, then, epoxy resin is poured into the interior of the entire accelerated molding mold (2) through the two pouring troughs (223), and at the same time, a plurality of heating rods (214) arranged inside the heating positioning frame (21) are started, and heat is continuously transferred to the heat conducting plate (215) through the external graphite plate (213), and the poured epoxy resin is heated by the heat conducting plate (215), so that the epoxy resin is always in a fluid state; S6. When the top layer of the epoxy resin fluid is at the bottom of the casting trough (223), the plurality of heating rods (214) at the bottom are turned off, and at the same time, cooling liquid is introduced into the cooling pipe (234) inside the cooling side plate (23). When the cooling liquid passes through the cooling pipe (234), the heat transferred from the epoxy resin fluid to the side wall of the cooling side plate (23) is absorbed and carried, thereby rapidly cooling the epoxy resin fluid; S7. Finally, the push rod (2251) is driven to push back and forth on the guide rod (224) by the hand push column (2253) on the scraping frame (225), so that the scraper (2254) at the bottom scrapes the epoxy resin fluid inside the casting trough (223) to complete the entire casting operation, and after standing and cooling for a period of time, a cast bus duct is formed.

Citation Information

Patent Citations

  • A bus slot convenient for mounting and a preparation method thereof

    CN108988256A

  • High-strength anti-shock bus duct and production process thereof

    CN109082080A

  • Manufacturing method for special paraffin for 3D printing machine

    CN109203320A

  • Pressure forming mold for bus groove joint separation plates

    CN109514789A

  • Concrete pouring mold

    CN209817422U

Cited By

  • Common-differential mode inductor integrating pouring and hot injection

    CN121709391A