A concrete pouring device for high-pile wharf engineering

By designing a concrete pouring device for high pile dock engineering including hanging pipe plates, input pipes, pouring pipes, swing frames and pipe limiting rings, the problem of long dismantling of conveying pipelines in different locations is solved, and the uniform placement of concrete and the improvement of construction efficiency is achieved.

CN119177659BActive Publication Date: 2025-02-28CCCC FIRST HARBOR ENGINEERING CO LTD +1
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411693094.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-11-25
Publication Date
2025-02-28
Estimated Expiration
2044-11-25

AI Technical Summary

Technical Problem

When the existing concrete pouring device for high piles at different locations, it takes time to dismantle the conveying pipeline, which affects the construction efficiency.

Method used

A concrete pouring device including a suspended pipe plate, an input pipe, a pouring pipe, a swing rack and a pipe limiting ring is designed. The cast structure is lifted through the hanging plate and the hanging line seat, and the circular movement of the cast pipe is achieved using the driving gear and pipe limiting ring to ensure uniform placement of concrete. At the same time, the bending groove rod and arc-side foot board are used to quickly position the high pile mold to prevent the influence of wind.

Benefits of technology

The uniform placement of concrete is achieved, concrete bubbles are reduced, casting effect is improved, and materials are prevented from being blocked through rapid positioning and vibration, improving construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure FT_1
    Figure FT_1
  • Figure FT_2
    Figure FT_2
  • Figure FT_3
    Figure FT_3
Patent Text Reader

Abstract

The present invention relates to the technical field of engineering construction, and discloses a concrete pouring device for a high-pile wharf project, comprising a pipe hanging plate, an input pipe is arranged below the pipe hanging plate, one end of the input pipe is fixedly connected with a spherical joint, the end of the spherical joint away from the input pipe is movably connected with a bent pipe, and the bottom end of the bent pipe is fixedly connected with a casting pipe; a pipe hanging ring is fixedly connected with a pipe hanging ring on the rear side of the pipe hanging plate, a hanging plate is fixedly connected with a hanging tray on the front side of the pipe hanging plate, and four hanging wire seats are fixedly connected with the outer edge of the hanging tray; a steel cable is movably connected with the inner side of each hanging wire seat, a casting structure is arranged at the bottom end of the steel cable, and the casting structure comprises a swing frame. The present invention can prevent the material in the casting pipe from being blocked and affecting the material discharge rate, and avoid the material from adhering to the inner wall of the casting pipe and affecting the subsequent material conveying efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of engineering construction, in particular to a high-pile wharf engineering concrete pouring device. Background Art

[0002] The impact of wind on the pouring construction of high-pile wharf projects cannot be ignored. Reasonable construction plans, effective safety measures and timely weather monitoring can reduce the adverse effects of wind, thereby ensuring construction quality and safety. During the entire construction process, the construction team should strengthen the monitoring and evaluation of wind forces to ensure that pouring operations are carried out in a safe environment.

[0003] The patent with publication number CN216892216U discloses a long-distance concrete high-pile wharf engineering construction pouring device, including a mounting plate, and the side wall of the mounting plate is fixedly connected to two supporting plates, the upper ends of the two supporting plates are respectively fixedly connected to a concrete delivery pump and a cleaning pump through a plurality of buffer springs, the output ends of the concrete delivery pump and the cleaning pump are fixedly connected with a connecting pipe, one end of the two connecting pipes is fixedly connected with the same Y-shaped delivery pipe, one end of the connecting pipe is also fixedly connected with a plug-in cylinder that is sealed and plugged into the Y-shaped delivery pipe, one end of the connecting pipe is fixedly sleeved with a first connecting flange on the outer side, and the two ends of the Y-shaped delivery pipe are fixedly sleeved with a second connecting flange that fits the first connecting flange on the outer side. This application does not require the operation of disassembling and replacing the delivery pipe, and can realize rapid cleaning and flushing of the pipeline, which is convenient for actual pouring and use. However, there is still a problem that it takes a lot of time to disassemble the delivery pipe for high piles at different positions. Therefore, it is very necessary to design a concrete pouring device for high-pile wharf engineering. Summary of the invention

[0004] The object of the present invention is to provide a high-pile wharf engineering concrete pouring device to solve the problems raised in the above background technology.

[0005] In order to solve the above technical problems, the present invention provides the following technical solutions: a concrete pouring device for a high-pile wharf project, comprising a pipe hanging plate, an input pipe is arranged below the pipe hanging plate, one end of the input pipe is fixedly connected to a spherical joint, one end of the spherical joint away from the input pipe is movably connected to a bent pipe, and the bottom end of the bent pipe is fixedly connected to a pouring pipe;

[0006] A pipe hanging ring is fixedly connected to the rear side of the pipe hanging plate, a hanging plate is fixedly connected to the front side of the pipe hanging plate, and four hanging wire seats are fixedly connected to the outer edge of the hanging plate;

[0007] The inner side of each of the suspension wire seats is movably connected with a steel cable, and the bottom end of the steel cable is provided with a casting structure, and the casting structure includes a swing frame, and the four corners of the swing frame are fixedly connected with a sling block, and the bottom surface of the swing frame is fixedly connected with two track bars, and the bottom surface of the track bar is slidably connected with a gear ring fixed block, and the bottom surface of the gear ring fixed block is fixedly connected with a track gear ring, and the bottom surface of the track gear ring is slidably connected with a ring rail slide seat, and the outer side surface of the track gear ring is meshed and connected with a driving gear, and the bottom surface of the ring rail slide seat is slidably connected with a connecting ring rail;

[0008] A short screw is arranged below the link rail, and one of the gear ring fixed blocks is fixedly connected to a threaded sheet on the bottom surface, and a long screw is threadedly connected to the side surface of the threaded sheet. One end of the link rail away from the link rail slide is fixedly connected to a limited pipe ring, and a convex block is fixedly connected to the inner side of the limited pipe ring, and a convex strip is fixedly connected to the outer side surface of the casting pipe. The driving gear is rotatably connected to the link rail slide, and a rotating rod seat extends downward from the bottom surface of the link rail slide, and a short screw is rotatably connected to the side surface of the rotating rod seat, and the end of the short screw away from the rotating rod seat is rotatably connected to the link rail, and the long screw The rod is rotatably connected to the track bar, the pipe hanging ring is fixedly connected to the outer wall of the input pipe, the sling block is movably connected to the bottom end of the steel cable, the pipe hanging plate is lifted by the hanging seat on the hanging plate, and the input pipe is fixed by the pipe hanging ring connected to the pipe hanging plate, and the hanging wire seat connected to the hanging plate lifts the swing frame through the steel cable, so that the overall center of gravity of the swing frame is downward, and when the hook cable lifts the hanging seat to move the swing frame to the top of the high pile mold of the dock, the external motor connected to the driving gear drives the driving gear to move in a circle around the meshing track gear ring, so that the ring rail slide slides along the track gear ring. The movement of the ring rail slide will also drive the connected linked rails to pull the limiting pipe to rotate around the casting pipe, so that the external motor on the side of the ring rail slide rotating rod seat drives the short screw to rotate, so that the other end of the short screw pulls the linked rail and the ring rail slide to slide relative to each other, so that the limiting pipe ring and the track gear ring change from a concentric state to a deviated state. At this time, the limiting pipe ring that deviates from the center of the circle rotates around the track gear ring with the ring rail slide, so that the limiting pipe ring pulls the casting pipe to move in a circle around the track gear ring, so that the concrete sprayed from the casting pipe can be evenly poured into the inner side of the high pile mold, so that the concrete is evenly distributed, thereby reducing the concrete The bubbles between the soil can improve the pouring effect, and the rotation of the long screw can drive the toothed ring block connected to the threaded piece to slide along the track bar, so that the track toothed ring connected to the toothed ring block drives the connected structure to move left and right. At the same time, when the pipe limiting ring moves, the convex block on the pipe limiting ring contacts the convex bar on the side of the pouring pipe, so that the convex block contacts the convex bar to make the pipe limiting ring vibrate, and the pouring pipe contacted by the pipe limiting ring vibrates, so that through tiny vibrations, the material in the pouring pipe is prevented from being blocked and affecting the discharge rate, and the material is prevented from adhering to the inner wall of the pouring pipe, which affects the subsequent material transportation efficiency.

[0009] The cam is connected to the side of the lifting block by the spring, and the cam is connected to the side of the lifting block by the spring. At the same time, the extrusion block connected to the limit block moves together, so that the extrusion block squeezes and fills the gap of the hook cable, thereby reducing the sliding of the hook cable during lifting, and increasing the friction between the extrusion block and the pressure flip bar to prevent shaking caused by the movement of the seat and the hook cable during lifting.

[0010] The top end of the vertical sliding rod is fixedly connected with the upper pressure rod, and the lower end of the vertical sliding rod is fixedly connected with the compression rod. The bottom end of the vertical sliding rod is fixedly connected with four folding rod hinge seats, and each folding rod hinge seat is hinged with a bending groove rod on the outer side of each folding rod hinge seat, and the inner side of the bending groove rod is slidably connected with a hanging rod, and the bottom end of the bending groove rod is hinged with an arc edge foot plate, and the vertical sliding rod slides through the top surface of the swing frame to the bottom surface, and the hanging rod is fixedly connected with the upper pressure rod, and a spring is provided on the outer side of the vertical sliding rod, and the two ends of the spring are fixedly connected with the compression rod and the swing frame respectively. When the swing frame moves to the top of the high pile mold, in order to align the casting pipe to the specified position, the swing frame is slowly approached to the top of the high pile mold so that the compression rod and the high When the upper pressure rod is connected to the vertical sliding rod and moves upward away from the swing frame, the upper pressure rod pulls the bent groove rod through the suspension rod to deflect around the connection point of the bent groove rod hinge seat, so that the bottom end of the bent groove rod is close to the outer wall of the high pile mold, and the curved edge foot plate is driven by the bent groove rod to approach and fit the outer wall of the high pile mold, so as to quickly position the swing frame, prevent the swing frame in the hoisting state from swinging due to the influence of wind, and prevent the concrete sprayed from the casting pipe from being thrown out of the mold due to the influence of wind, thereby improving the casting effect. At the same time, when the pressure rod is not compressed and the curved edge foot plate is in contact with the ground, the bent groove rod can be used to provide support for the casting pipe to prevent the casting pipe from directly contacting the ground, thereby supporting and protecting the casting pipe.

[0011] Compared with the prior art, the beneficial effects achieved by the present invention are:

[0012] The present invention is provided with a hanging seat, a pressure block, a linkage rod, a pressure turning rod, a threaded rotating rod, a limit block, a spring connecting rod, a spring fixing sheet, and an extrusion block, so that the limit block is matched with the top of the pressure block to prevent the pressure block from loosening, thereby realizing rapid fixation and detachment installation. At the same time, the extrusion block connected to the limit block moves together, so that the extrusion block squeezes and fills the gap of the hook rope, thereby reducing the sliding of the hook rope during hoisting, and increasing the friction between the extrusion block and the pressure turning rod, thereby preventing the shaking caused by the movement of the hanging seat and the hook rope during the hoisting process.

[0013] The present invention is provided with a swing frame, a track bar, a gear ring solid block, a track gear ring, a ring rail slide seat, a driving gear, a short screw, a threaded sheet, a long screw, a linked track, a pipe limiting ring, a convex block, and a convex strip, so that the concrete sprayed out of the casting pipe can be evenly poured into the inner side of the high pile mold, so that the concrete is evenly distributed, thereby reducing the bubbles existing in the concrete and improving the casting effect. At the same time, when the pipe limiting ring moves, the convex block on the pipe limiting ring contacts the convex strip on the side of the casting pipe, and the contact between the convex block and the convex strip causes the pipe limiting ring to vibrate, and causes the casting pipe contacted by the pipe limiting ring to vibrate, so that through small vibration, the material in the casting pipe is prevented from being blocked and affecting the material discharge rate, and the material is prevented from being attached to the inner wall of the casting pipe, thereby affecting the subsequent material conveying efficiency;

[0014] The present invention is provided with an upper pressure rod, a hanging rod, a folding rod hinge seat, a bent groove rod, an arc-edge foot plate, a pressure rod and a vertical sliding rod. The bent groove rod drives the arc-edge foot plate to approach and fit the outer wall of the high pile mold, so as to quickly position the swing frame, prevent the swing frame in a hoisted state from swinging due to the influence of wind force, and prevent concrete sprayed from the casting pipe from being thrown out of the mold due to the influence of wind force, thereby improving the casting effect. At the same time, when the pressure rod is not compressed and the arc-edge foot plate is in contact with the ground, the bent groove rod can be used to provide support for the casting pipe, prevent the casting pipe from directly contacting the ground, and play a role of supporting and protecting the casting pipe. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] The accompanying drawings are used to provide further understanding of the present invention and constitute a part of the specification. They are used to explain the present invention together with the embodiments of the present invention and do not constitute a limitation of the present invention.

[0016] In the attached picture:

[0017] Figure 1 It is a schematic diagram of the overall front three-dimensional structure of the present invention;

[0018] Figure 2 It is a rear-view stereoscopic structural schematic diagram of the present invention;

[0019] Figure 3 It is a schematic diagram of the pipe plate connection structure of the present invention;

[0020] Figure 4 It is a schematic diagram of the lifting and locking structure of the present invention;

[0021] Figure 5 It is a schematic diagram of the pouring structure of the present invention;

[0022] Figure 6 The present invention Figure 5 A is a schematic diagram of the enlarged structure;

[0023] Figure 7 It is a schematic diagram of the high pile positioning structure of the present invention.

[0024] In the figure: 1, pipe plate; 2, input pipe; 21, wire seat; 22, lifting plate; 23, pipe ring; 3, spherical joint; 4, elbow; 5, lifting locking structure; 51, hanging seat; 52, pressure block; 53, linkage rod; 54, pressure turning rod; 55, threaded rotating rod; 56, limit block; 57, spring connecting rod; 58, spring fixing plate; 59, extrusion block; 6, casting structure; 61, swing frame; 62, track bar; 63, gear ring fixing block; 6 4. Track gear ring; 65. Ring rail slide; 66. Driving gear; 67. Short screw; 68. Threaded sheet; 69. Long screw; 610. Link rail; 611. Pipe limit ring; 612. Bump; 613. Bump; 7. High pile positioning structure; 71. Upper pressure rod; 72. Suspension rod; 73. Folding rod hinge seat; 74. Bending groove rod; 75. Arc edge foot plate; 76. Compression rod; 77. Vertical slide rod; 8. Steel cable; 9. Casting pipe; 10. Suspension block. DETAILED DESCRIPTION

[0025] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0026] See also Figure 1-Figure 7 One embodiment of the present invention is a concrete pouring device for a high-pile wharf project, comprising a pipe hanging plate 1, an input pipe 2 is arranged below the pipe hanging plate 1, one end of the input pipe 2 is fixedly connected to a spherical joint 3, an end of the spherical joint 3 away from the input pipe 2 is movably connected to a bent pipe 4, and the bottom end of the bent pipe 4 is fixedly connected to a pouring pipe 9;

[0027] A pipe hanging ring 23 is fixedly connected to the rear side of the pipe hanging plate 1, a hanging plate 22 is fixedly connected to the front side of the pipe hanging plate 1, and four hanging wire seats 21 are fixedly connected to the outer edge of the hanging plate 22;

[0028] A steel cable 8 is movably connected to the inner side of each suspension wire seat 21, and a casting structure 6 is arranged at the bottom end of the steel cable 8. The casting structure 6 includes a swing frame 61, and the four corners of the swing frame 61 are fixedly connected to the sling block 10, and the bottom surface of the swing frame 61 is fixedly connected to two track bars 62, and the bottom surface of the track bar 62 is slidably connected to a gear ring fixed block 63, and the bottom surface of the gear ring fixed block 63 is fixedly connected to a track gear ring 64, and the bottom surface of the track gear ring 64 is slidably connected to a ring rail slide seat 65, and the outer side surface of the track gear ring 64 is meshed and connected to a driving gear 66, and the bottom surface of the ring rail slide seat 65 is slidably connected to a connecting ring rail 610;

[0029] A short screw 67 is provided below the link rail 610, wherein a toothed ring fixed block 63 is fixedly connected to a threaded sheet 68 on the bottom surface, and a long screw 69 is threadedly connected to the side surface of the threaded sheet 68, and the link rail 610 is fixedly connected to a limited pipe ring 611 at one end away from the ring rail slide 65, and a convex block 612 is fixedly connected to the inner side of the limited pipe ring 611, and a convex strip 613 is fixedly connected to the outer side surface of the casting pipe 9, and the driving gear 66 is rotatably connected to the ring rail slide 65, and a rotating rod seat is extended downward from the bottom surface of the ring rail slide 65, and a short screw 67 is rotatably connected to the side surface of the rotating rod seat, and the end of the short screw 67 away from the rotating rod seat is rotatably connected to the link rail 610, and the long screw 69 is rotatably connected to the track bar 62, and the pipe hanging ring 23 is fixedly connected to the outer wall of the input pipe 2, and the sling block 10 is movably connected to the bottom end of the steel cable 8, so that the casting pipe 9 The sprayed concrete can be evenly poured into the inner side of the high pile mold, so that the concrete is evenly distributed, thereby reducing the bubbles between the concrete and improving the pouring effect. The rotation of the long screw 69 can drive the toothed ring block 63 connected to the threaded sheet 68 to slide along the track bar 62, so that the track toothed ring 64 connected to the toothed ring block 63 drives the connected structure to move left and right. At the same time, when the tube limiting ring 611 moves, the protrusion 612 on the tube limiting ring 611 contacts the convex strip 613 on the side of the pouring pipe 9, so that the protrusion 612 contacts the convex strip 613 to vibrate the tube limiting ring 611, and the pouring pipe 9 contacted by the tube limiting ring 611 vibrates, so that through small vibrations, the material in the pouring pipe 9 is prevented from being blocked and affecting the material discharge rate, and the material is prevented from adhering to the inner wall of the pouring pipe 9 and affecting the subsequent material transportation efficiency.

[0030] The top surface of the hanging plate 22 is provided with a hanging locking structure 5, which includes a hanging seat 51, a pressure block 52 is hinged on the side of the hanging seat 51, and linkage rods 53 are hinged on both sides of the pressure block 52. The end of the linkage rod 53 away from the pressure block 52 is hinged with a pressure turning rod 54, and a limit block 56 is provided above the pressure block 52. A threaded rotating rod 55 is fixedly connected to one side of the limit block 56, and an extrusion block 59 is fixedly connected to the other side of the limit block 56. A spring connecting rod 57 is fixedly connected to the side of the pressure turning rod 54 away from the pressure block 52, and a spring fixing plate 58 is fixedly connected to the end of the spring connecting rod 57 away from the pressure turning rod 54. The pressure turning rod 54 is connected to the bottom end of the hanging seat 51. Hinged, the threaded rotating rod 55 is threadedly connected to the hanging seat 51, a spring is arranged on the outer side of the spring connecting rod 57, and one end of the spring is fixedly connected to the spring fixing plate 58, a vertical groove is opened on the side of the hanging seat 51, and the spring connecting rod 57 passes through the inner side of the vertical groove, so that the limit block 56 fits with the top of the pressure block 52 to prevent the pressure block 52 from loosening, and realizes rapid fixation and detachment of the installation. At the same time, the extrusion block 59 connected to the limit block 56 moves together, so that the extrusion block 59 squeezes and fills the gap of the hook rope, thereby reducing the sliding of the hook rope during hoisting, and increasing the friction between the extrusion block 59 and the pressure turning rod 54, to prevent the shaking caused by the movement of the hanging seat 51 and the hook rope during the hoisting process.

[0031] The high pile positioning structure 7 includes an upper pressure rod 71, an upper pressure rod 71 is arranged above the swing frame 61, the bottom surface of the upper pressure rod 71 is fixedly connected to two vertical sliding rods 77, the bottom end of the vertical sliding rod 77 is fixedly connected to a compression rod 76, the bottom surface of the swing frame 61 is fixedly connected to four folding rod hinge seats 73, the outer side of each folding rod hinge seat 73 is hinged with a bending groove rod 74, the inner side of the bending groove rod 74 is slidably connected to a suspension rod 72, the bottom end of the bending groove rod 74 is hinged with an arc edge foot plate 75, the vertical sliding rod 77 slides from the top surface of the swing frame 61 to the bottom surface, the suspension rod 72 is fixedly connected to the upper pressure rod 71, and the outer side surface of the vertical sliding rod 77 is arranged There is a spring, and the two ends of the spring are fixedly connected to the compression rod 76 and the swing frame 61 respectively. The curved groove rod 74 drives the arc edge foot plate 75 to approach and fit the outer wall of the high pile mold, so as to quickly position the swing frame 61 to prevent the swing frame 61 in the hoisting state from swinging due to the influence of wind, and to prevent the concrete sprayed from the casting pipe 9 from being thrown out of the mold due to the influence of wind, thereby improving the casting effect. At the same time, when the compression rod 76 is not compressed and the arc edge foot plate 75 is in contact with the ground, the curved groove rod 74 can be used to provide support for the casting pipe 9 to prevent the casting pipe 9 from directly contacting the ground, thereby supporting and protecting the casting pipe 9.

[0032] Working principle: one end of the input pipe 2 needs to be connected to the pipeline for conveying concrete, and the pipe plate 1 is lifted by a lifting device, and the hook cable of the lifting device is connected to the hanging seat 51, so that the hook cable squeezes the pressure block 52. At this time, the limit block 56 is in a state of not contacting the pressure block 52, and the hook cable passes over the top of the pressure block 52 and moves between the pressure block 52 and the pressure turning rod 54. In this process, when the pressure block 52 is subjected to force, the pressure block 52 pushes the linkage rod 53, so that the linkage rod 53 pushes the pressure turning rod 54. At this time, the pressure turning rod 54 is pressed and pushes the connected spring connecting rod 57 through The spring fixing piece 58 stretches the spring, and the pressure block 52 is reset according to the above process. Then the threaded rotating rod 55 is rotated to drive the connected limit block 56 to rotate together, so that the limit block 56 fits with the top of the pressure block 52 to prevent the pressure block 52 from loosening, and realizes rapid fixation and detachment installation. At the same time, the extrusion block 59 connected to the limit block 56 moves together, so that the extrusion block 59 squeezes and fills the gap of the hook rope, thereby reducing the sliding of the hook rope during hoisting, and increasing the friction between the extrusion block 59 and the pressure turning rod 54, to prevent the shaking caused by the movement of the hanging seat 51 and the hook rope during the hoisting process;

[0033] The pipe plate 1 is lifted by the hanging seat 51 on the hanging plate 22, and the input pipe 2 is fixed by the pipe ring 23 connected to the pipe plate 1. The hanging wire seat 21 connected to the hanging plate 22 lifts the swing frame 61 through the steel cable 8, so that the overall center of gravity of the swing frame 61 is downward. When the hook cable lifts the hanging seat 51 to move the swing frame 61 to the top of the high pile mold of the dock, the external motor connected to the driving gear 66 drives the driving gear 66 to move in a circle around the meshing track gear ring 64. The ring rail slide 65 slides along the track gear ring 64, and the movement of the ring rail slide 65 drives the connected link rail 610 to pull the pipe limiting ring 611 to rotate around the casting pipe 9, so that the external motor on the side of the ring rail slide 65 rotating rod seat drives the short screw 67 to rotate, so that the other end of the short screw 67 pulls the link rail 610 and the ring rail slide 65 to slide relative to each other, so that the pipe limiting ring 611 and the track gear ring 64 change from a concentric state to a state deviated from the center of the circle. 611 rotates around the track gear ring 64 along with the ring rail slide 65, so that the pipe limiting ring 611 pulls the casting pipe 9 to move in a circle around the track gear ring 64, so that the concrete sprayed from the casting pipe 9 can be evenly placed on the inner side of the high pile mold, so that the concrete is evenly distributed, thereby reducing the bubbles between the concrete and improving the casting effect. The rotation of the long screw 69 can drive the gear ring block 63 connected to the threaded sheet 68 to slide along the track bar 62, so that the track gear ring 64 connected to the gear ring block 63 drives the connected structure to move left and right. At the same time, when the pipe limiting ring 611 moves, the convex block 612 on the pipe limiting ring 611 contacts the convex strip 613 on the side of the casting pipe 9, so that the convex block 612 contacts the convex strip 613 to cause the pipe limiting ring 611 to vibrate, and the casting pipe 9 contacted by the pipe limiting ring 611 vibrates, thereby preventing the material in the casting pipe 9 from being blocked and affecting the material discharge rate through slight vibration, and preventing the material from adhering to the inner wall of the casting pipe 9 and affecting the subsequent material transportation efficiency.

[0034] When the swing frame 61 moves to the top of the high pile mold, in order to align the pouring pipe 9 to the specified position, the swing frame 61 is slowly moved closer to the top of the high pile mold, so that the pressure rod 76 contacts the edge of the high pile mold, so that the swing frame 61 and the above-mentioned connected structure slide downward along the vertical slide rod 77 under the action of gravity, and the pressure rod 76 squeezes the spring to be compressed. When the vertical slide rod 77 is connected to the upper pressure rod 71 and moves upward away from the swing frame 61, the upper pressure rod 71 pulls the bending groove rod 74 through the suspension rod 72 to deflect around the connection with the bending rod hinge seat 73, so that the bottom of the bending groove rod 74 The end is close to the outer wall of the high pile mold, and the curved edge foot plate 75 is driven by the bent groove rod 74 to approach and fit the outer wall of the high pile mold, so as to quickly position the swing frame 61 to prevent the swing frame 61 in the hoisting state from swinging due to the influence of wind, and to prevent the concrete sprayed from the casting pipe 9 from being thrown out of the mold due to the influence of wind, thereby improving the casting effect. At the same time, when the compression rod 76 is not compressed and the curved edge foot plate 75 is in contact with the ground, the bent groove rod 74 can be used to provide support for the casting pipe 9 to prevent the casting pipe 9 from directly contacting the ground, thereby supporting and protecting the casting pipe 9.

[0035] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0036] Finally, it should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A concrete pouring device for a high-pile wharf project, comprising a pipe hanging plate (1), characterized in that: An input pipe (2) is arranged below the pipe hanging plate (1); one end of the input pipe (2) is fixedly connected to a spherical joint (3); an end of the spherical joint (3) away from the input pipe (2) is movably connected to a bent pipe (4); and the bottom end of the bent pipe (4) is fixedly connected to a casting pipe (9); A pipe hanging ring (23) is fixedly connected to the rear side of the pipe hanging plate (1), a hanging plate (22) is fixedly connected to the front side of the pipe hanging plate (1), and four hanging wire seats (21) are fixedly connected to the outer edge of the hanging plate (22); A steel cable (8) is movably connected to the inner side of each of the suspension wire seats (21), a casting structure (6) is provided at the bottom end of the steel cable (8), the casting structure (6) comprises a swing frame (61), the four corners of the swing frame (61) are fixedly connected to a suspension cable block (10), the bottom surface of the swing frame (61) is fixedly connected to two track bars (62), the bottom surface of the track bar (62) is slidably connected to a toothed ring fixed block (63), the bottom surface of the toothed ring fixed block (63) is fixedly connected to a track toothed ring (64), the bottom surface of the track toothed ring (64) is slidably connected to a ring rail slide seat (65), the outer side surface of the track toothed ring (64) is meshingly connected to a driving gear (66), and the bottom surface of the ring rail slide seat (65) is slidably connected to a connecting ring rail (610); A short screw (67) is provided below the link rail (610); a threaded sheet (68) is fixedly connected to the bottom surface of one of the toothed ring fixed blocks (63); a long screw (69) is threadedly connected to the side surface of the threaded sheet (68); an end of the link rail (610) away from the ring rail slide seat (65) is fixedly connected to a limiting pipe ring (611); a convex block (612) is fixedly connected to the inner side of the limiting pipe ring (611); and a convex strip (613) is fixedly connected to the outer side surface of the casting pipe (9); The driving gear (66) is rotatably connected to the ring rail slide (65); a rotating rod seat extends downward from the bottom surface of the ring rail slide (65); and a short screw rod (67) is rotatably connected to the side surface of the rotating rod seat; an end of the short screw rod (67) away from the rotating rod seat is rotatably connected to the connecting rail (610); and the long screw rod (69) is rotatably connected to the track bar (62); The top surface of the hanging plate (22) is provided with a hanging locking structure (5), the hanging locking structure (5) comprises a hanging seat (51), a pressure block (52) is hingedly connected to the side of the hanging seat (51), linkage rods (53) are hingedly connected to both sides of the pressure block (52), a pressure turning rod (54) is hingedly connected to one end of the linkage rod (53) away from the pressure block (52), and a limit block (56) is provided above the pressure block (52); One side of the limit block (56) is fixedly connected to a threaded rotating rod (55), the other side of the limit block (56) is fixedly connected to an extrusion block (59), the side of the pressure-applying lever (54) away from the pressure block (52) is fixedly connected to a spring connecting rod (57), and the end of the spring connecting rod (57) away from the pressure-applying lever (54) is fixedly connected to a spring fixing plate (58); The pressure-applying turning rod (54) is hinged to the bottom end of the hanging seat (51), the threaded rotating rod (55) is threadedly connected to the hanging seat (51), a spring is arranged on the outer side of the spring connecting rod (57), and one end of the spring is fixedly connected to the spring fixing plate (58), a vertical groove is opened on the side of the hanging seat (51), and the spring connecting rod (57) passes through the inner side of the vertical groove; The high pile positioning structure (7) comprises an upper pressure rod (71), and the upper pressure rod (71) is arranged above the swing frame (61), the bottom surface of the upper pressure rod (71) is fixedly connected to two vertical sliding rods (77), and the bottom end of the vertical sliding rod (77) is fixedly connected to a pressure rod (76); Four folding rod hinge seats (73) are fixedly connected to the bottom surface of the swing frame (61); a bending groove rod (74) is hingedly connected to the outer side of each folding rod hinge seat (73); a suspension rod (72) is slidably connected to the inner side of the bending groove rod (74); and an arc-edge foot plate (75) is hingedly connected to the bottom end of the bending groove rod (74); The vertical sliding rod (77) slides from the top surface of the swing frame (61) to the bottom surface, the suspension rod (72) is fixedly connected to the upper pressure rod (71), and a spring is provided on the outer side surface of the vertical sliding rod (77), and the two ends of the spring are respectively fixedly connected to the pressure rod (76) and the swing frame (61).

2. A high-pile wharf engineering concrete pouring device according to claim 1, characterized in that: The pipe hanging ring (23) is fixedly connected to the outer wall of the input pipe (2), and the sling block (10) is movably connected to the bottom end of the steel cable (8).

Citation Information

Patent Citations

  • Pouring device for long-distance concrete long-pile wharf engineering construction

    CN216892216U

  • Concrete pouring equipment for hydraulic engineering construction

    CN115354660A

  • Pouring device for bridge prestressed concrete cast-in-place box girder construction

    CN213571568U

  • High-strength rigging for ocean engineering

    CN214087326U