A resource allocation and mapping method for decoration and renovation majors
By adopting a multi-business data collaboration platform and an automatic progress plan compilation system in the decoration and renovation profession, and utilizing BIM data and the enterprise decoration database, the automatic configuration of decoration models and the automatic generation of progress plans are realized, which solves the problem of digital transformation of decoration and renovation project management and improves construction efficiency and management quality.
Patent Information
- Application Number
- CN202411409142.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-10
- Publication Date
- 2025-09-26
- Estimated Expiration
- 2044-10-10
AI Technical Summary
Existing technologies have failed to effectively realize the digital transformation of project management in the decoration and renovation industry, and the improvement of construction efficiency has been limited.
Adopting a multi-business data collaboration platform and an automatic schedule compilation system, with BIM data as the carrier and combined with the enterprise decoration database, the automatic configuration of the decoration model and the automatic generation of the schedule are realized, including the creation of the target project decoration model, the writing of decoration practices, the addition of model attributes and the calculation of engineering quantities, and the generation and optimization of the project decoration schedule.
It has achieved the digital transformation of decoration and renovation project management, improved construction efficiency and management quality, reduced human errors, and enhanced the application value of data and the company's decision-making support capabilities.
Smart Images

Figure CN119557944B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of construction engineering data processing, and in particular to a resource configuration and mapping method for decoration and renovation professionals. Background Art
[0002] In recent years, with the development and progress of the construction industry, construction companies have increasingly focused on establishing and managing their underlying databases, as these databases serve as crucial foundational data resources for improving construction efficiency and optimizing project management. However, the establishment and management of standard process libraries for construction companies currently face diverse demands and challenges, particularly in the area of professional data for interior and renovation, where research results are complex and lacking in the industry.
[0003] There are some discussions on resource allocation and mapping methods for other professions, such as BDIP and Glodon, but they are all applied to the structural profession, which is relatively simple. Therefore, this invention focuses on the resource allocation and mapping methods for the decoration and renovation profession.
[0004] Patent application number CN202211349635.3 provides a method, system, and storage medium for estimating the quantity of decoration and renovation projects. The method includes: obtaining past project data, classifying it according to basic building category information, and establishing a building category feature database; organizing and analyzing the data for each project category, statistically summarizing the quantity calculation formulas and parameters, and establishing a calculation parameter database; obtaining basic category information for the project to be estimated, searching the building category feature database, determining the project type, and obtaining the corresponding calculation template; inputting relevant building information, searching the calculation parameter database using the calculation template, and obtaining the corresponding calculation formula and calculation parameter category; matching the building-related information with the corresponding calculation formula and calculation parameter category to perform quantity calculation; and summarizing the calculation results to output a bill of quantities. This invention primarily improves the speed and accuracy of estimating the quantity of decoration and renovation projects, but it still does not achieve the digital transformation of project management. Summary of the Invention
[0005] The purpose of the present invention is to provide a resource allocation and mapping method for decoration and renovation professionals, which solves the problem of digital transformation of project management and improves construction efficiency.
[0006] To achieve the above object, the present invention adopts the following technical solutions:
[0007] A resource configuration and mapping method for decoration and renovation professional includes the following steps:
[0008] Step 1: Create the decoration model of the target project, write the decoration methods into the model room, add model attributes and calculate the model quantity;
[0009] Step 2: Basic system configuration: automatically collect target project rooms and decoration practice sheets, import target project decoration models, quantity calculation documents and business lists, and plan and configure project construction flow sections, construction sequence and team information;
[0010] Step 3: Call the system-encapsulated enterprise decoration database based on the target project decoration practice. Call the system-encapsulated enterprise decoration database based on the number, category, name and layered practice of the target project decoration practice to assemble the project decoration practice library. Based on the mapping and linkage relationship between the decoration standard database and the standard decoration schedule template, combined with the basic configuration data of the system, generate the initial project schedule. The initial schedule does not include the project quantity. The resource data includes construction process data, material data, labor data and machinery data.
[0011] Step 4: Configuration of the decoration model: The specialty, building, floor, flow section name, and labor team in the construction planning data are associated with the decoration model; the target project decoration practice library data and the decoration model are mapped through shared information, and the human, material, and machine resource configuration information is transferred to the model; the model is mapped to the initial plan through planning data, name, and layered practices, and the decoration model project quantity and resource configuration information, as well as the linkage information of rooms with similar decoration practices, are transferred to the initial progress plan. The shared information includes coding.
[0012] Step 5: Generate and optimize a project renovation schedule, including renovation workload, labor and machinery resource requirements, and room linkage information for similar renovation practices.
[0013] Step 6: Link construction and management matters to the progress plan, provide real-time warnings, and output management data forms.
[0014] Preferably, the specific steps of step one are:
[0015] A0, use the Swell plug-in to write the architectural practices of the CAD drawings / Excel decoration practice sheets into the functional rooms of the model;
[0016] A1, add attributes to the written decoration model, including building number, building function settings and model component code;
[0017] A2, the written data is mapped through the Swell quantity calculation plug-in to calculate the engineering quantity;
[0018] A3, generate the quantity calculation model and quantity calculation file to be imported into the schedule generation system.
[0019] Preferably, the specific steps of step 2 are:
[0020] B0, automatically collect target project rooms and decoration practice sheets, import CAD drawings / Excel decoration practice sheets for automatic recognition;
[0021] B1, import the target project decoration model and quantity calculation file;
[0022] B2: When different decoration methods are used in the same room, further revisions can be made with the help of business list quantity, or the physical decoration model can be quickly created using the Swell decoration plug-in;
[0023] B3, configure construction planning data information.
[0024] Preferably, the enterprise decoration database includes a professional standard database for decoration and renovation and a standard decoration schedule template; the professional standard database for decoration and renovation includes a building practice selection library, a material library and a standard process library and a mapping linkage relationship between the libraries. The main data of the building practice selection library include name, layered practices and materials. The mapping linkage relationship between the standard process library and the libraries is specifically that the name and layered practices of the building practice selection library are mapped to the standard process library, and then mapped to the standard decoration schedule template. The standard process library is the embodiment of the construction technology of the building practice. The standard process library also includes resource and construction period allocation algorithms, labor quotas, types of work and machinery; the standard decoration schedule template is mapped to the enterprise standard database through the decoration name and decoration layered practices. The standard decoration schedule template also includes the logical relationship between the construction of each layered practice and whether there is a construction overlap or construction gap.
[0025] Preferably, in step three, the data information carried by the initial schedule includes construction planning data information, construction procedures, construction technology and logical relationships between procedures and technologies.
[0026] Preferably, in step four, the model configuration includes obtaining engineering quantities from the decoration model, model association, engineering quantity calculation, linkage of rooms with similar decoration practices, and application of engineering quantities to the plan; the association of construction planning data with the decoration model is specifically the association of professions, buildings, floors, flow section names, and labor teams in the construction planning data with the decoration model; the mapping of the target project decoration practice library data with the model is specifically realized by the mapping between the target project decoration practice library data and the model through the data information carried by the shared decoration model, and after mapping, the decoration model receives differentiated data from the target project decoration practice library; the model engineering quantities and resource allocation information, and linkage information of rooms with similar decoration practices are transmitted to the initial schedule, specifically the transmission of the decoration model engineering quantities and resource allocation information to the initial schedule under the dual drive of the association of construction planning data with the decoration model and the mapping of the target project decoration practice library data with the model.
[0027] Preferably, the data information carried by the decoration model includes the room name, the number and category, name, layering method and engineering quantity of the decoration method.
[0028] Preferably, the specific steps of step five are: when the project plan is modified, optimization configuration is required to generate an optimized schedule, or schedule optimization configuration is performed based on fixed resource input and fixed construction period to generate an optimized schedule.
[0029] Preferably, the digital transformation of project management is achieved through step six, and the management data form includes labor resource curve, plan diagram, monthly plan, weekly plan, general material control and preparation, decoration and renovation plan preparation and decoration and renovation construction visual briefing.
[0030] In the present invention, the multi-business data collaboration platform and the automatic progress plan compilation system (i.e., the system in this application) is to create a project progress plan automatic generation platform with BIM data as the carrier and decoration practices as the core drive, and ultimately realize the construction and management matters to be linked to the progress plan, real-time warning, and output of management data forms, thus realizing the digital transformation of project management. Due to the connectivity of multi-dimensional data of decoration and renovation, the efficiency and quality of decoration and renovation project management are greatly improved.
[0031] The improvement or transformation of digital management is mainly reflected in the digital integration of project data. The data is transformed from static (i.e. list data and model data) to dynamic (i.e. serving the project construction process management system), and the value of data is mined (i.e. engineering quantity data can be converted into human, material and machine data, and engineering quantity is converted into resources required for project construction, thereby mining the value of data). Data is processed and converted into the forms and documents required for project management through the processing and conversion of the enterprise decoration database, and a large amount of repetitive and tedious work of traditional on-site managers is intelligently output, thereby improving management efficiency and reducing human errors.
[0032] This method does not require the creation of a physical decoration and renovation model. By writing the decoration methods in the model room and adding model attributes, and then calculating the engineering quantities after mapping through the Swell quantity calculation plug-in, it can quickly create and generate decoration and renovation engineering quantities, thereby realizing the application of engineering quantity data and project management. The value of engineering quantity data is divided into three levels. The first level is data native value, which serves the application of project management personnel (i.e., data directly obtained from engineering quantities, construction methods, progress, etc.); the second level is data resource value, which uses data analysis results and early warnings to drive project leadership teams to make decisions and manage projects (i.e., the demand for human resources and equipment, which is processed after analysis of the above data); the third level is data asset value, which accumulates project big data to support the company's reference for similar projects in the future (i.e., project construction quotas, including labor quotas, machinery quotas, the impact of construction areas, etc., which can be used as reference for other similar projects by the company).
[0033] Because decoration and renovation involve many methods, various materials, complex processes, huge amounts of data and complex mapping relationships between databases, we have established an enterprise decoration database.
[0034] The innovation of this application is the automatic generation of project decoration progress plan. The target project decoration practice table import platform is equivalent to automatically searching and finding the target project construction practices and material selection in the enterprise decoration database, and assembling it into a set of target project decoration practice library. At the same time, the preset standard process library and standard progress plan template are called to assemble the target project initial progress plan according to the construction content included in the target project. The model configuration also includes floors, construction scope, flow sections, construction sequence, labor team information configuration, project BIM model association, engineering quantity calculation and application of engineering quantity to the plan. This series of configurations perfectly connects the project-specific data with the standard data in the enterprise decoration database and the inherent linkage relationship between data for data connection, data exchange and data synchronization, and ultimately realizes the automatic generation of project decoration progress plan (with decoration engineering quantity). BRIEF DESCRIPTION OF THE DRAWINGS
[0035] Figure 1 This is a schematic diagram of data flow in the present invention;
[0036] Figure 2 Write a room diagram for the decoration method of this invention Figure 1 ;
[0037] Figure 3 Write a room diagram for the decoration method of this invention Figure 2 ;
[0038] Figure 4 Write a room diagram for the decoration method of this invention Figure 3 ;
[0039] Figure 5 Add a schematic to the decoration model attributes of the present invention Figure 1 ;
[0040] Figure 6 Add a schematic to the decoration model attributes of the present invention Figure 2 ;
[0041] Figure 7 Add a schematic to the decoration model attributes of the present invention Figure 3 ;
[0042] Figure 8 This is a schematic diagram of the mapping library between components and quantity calculation rules of the present invention;
[0043] Figure 9 This is a schematic diagram showing an example of the decoration method for the target project of the present invention;
[0044] Figure 10This is the database diagram of the enterprise decoration of the present invention Figure 1 ;
[0045] Figure 11 This is the database diagram of the enterprise decoration of the present invention Figure 2 ;
[0046] Figure 12 This is a schematic diagram of the enterprise standard process library of the present invention;
[0047] Figure 13 This is a schematic diagram of the standard process library of the present invention;
[0048] Figure 14 This is a schematic diagram of the mapping linkage between the building practice selection library and the material library of the present invention;
[0049] Figure 15 This is a schematic diagram of resource configuration of the enterprise standard process library of the present invention;
[0050] Figure 16 This is a schematic diagram of the model configuration interface of the present invention;
[0051] Figure 17 This is a schematic diagram of the model association of the present invention;
[0052] Figure 18 This is a schematic diagram of engineering quantity calculation of the present invention; DETAILED DESCRIPTION
[0053] The present invention will be further described below with reference to the accompanying drawings:
[0054] like Figure 1 The resource configuration and mapping method for decoration and renovation shown includes the following steps:
[0055] Step 1: Create a professional Revit information model for the target project decoration, write the decoration methods into the model room, add model attributes and calculate the model quantity.
[0056] Specifically:
[0057] A0, use the Swell plug-in to write the architectural practices of the CAD drawings / Excel decoration practice tables into the functional rooms of the model without creating a physical decoration model, such as Figures 2 to 4 shown.
[0058] A1, add attributes to the written decoration model, including building number, building function setting and model component code; model building number and floor height information are used for the basic configuration of the project overview of the schedule generation system, building function setting is used to accumulate data of different types of projects, and model component code is used for machine recognition mapping linkage. This attribute addition function secondary developed a plug-in based on Revit, which encapsulates a series of enterprise standards such as model component code, building function, building number setting, etc. Figures 5 to 7 shown.
[0059] A2, the written data is mapped through the Swell quantity calculation plug-in to calculate the engineering quantity. The quantity calculation mapping is a component and quantity calculation rule mapping library built based on the engineering quantity list specification calculation rules. After mapping, the engineering quantity data can be located and viewed in the model. For example, the calculation of the wall will deduct the door and window openings, and the height of the wall exceeding the ceiling will be calculated according to the measurement rules. Figure 8 shown.
[0060] A3. Generate a quantity calculation model and quantity calculation file for import into the schedule generation system. The renovation method number and category, renovation name, and renovation layering method are the linchpin of the schedule generation system. They map not only to the project schedule but also to the assembled project renovation method library. The model also carries other data (building, floor, project quantity, etc.) for use by the schedule generation system.
[0061] Step 2: Basic configuration of the system, enter the decoration practices of the target project, import the decoration model, quantity calculation files, business lists, etc. of the target project, and plan and configure the project construction flow section, construction sequence, work team and other information.
[0062] Specifically:
[0063] B0, automatically collect the target project room and decoration practice table, import CAD drawings / Excel decoration practice table to automatically identify, decoration practice table such as Figure 9 shown.
[0064] B1: Import the target project's renovation model and quantity calculation file. Some of the renovation model data is used for basic project configuration, such as building name and floor level, to automatically identify the model data. The renovation model contains information such as room name, renovation method number and category, name, layering method, and project quantity.
[0065] B2. When different decoration methods are used in the same room, such as a wall with multiple wall methods, it is difficult to split the engineering quantity data without establishing a physical model. This item will be further revised with the help of the business list quantity, and the engineering quantity of the business list decoration method will be evenly distributed to the corresponding room according to the functional room area. During project planning, it ensures that there are no missing management items. If there are detailed requirements for the decoration engineering quantity, the Swell decoration plug-in can also be used to quickly create a physical decoration model.
[0066] B3, configure construction planning data information, including project construction scope, construction flow section, construction sequence, labor team, machinery and other construction deployment and construction process data information.
[0067] Step 3: Call the system-encapsulated enterprise decoration database based on the target project decoration practice. Call the system-encapsulated enterprise decoration database based on the number, category, name and layered practice of the target project decoration practice to assemble the project decoration practice library. Based on the mapping and linkage relationship between the decoration standard database and the standard decoration schedule template, combined with the basic configuration data of the system, generate the initial project schedule. The initial schedule does not include the project quantity. The resource data includes construction process data, material data, labor data and machinery data.
[0068] The enterprise decoration database includes a professional standard database for decoration and renovation and a standard decoration schedule template; the professional standard database for decoration and renovation includes a building practice selection library, a material library and a standard process library and a mapping linkage relationship between each library; the building practice selection library and the material library are compiled into a database with reference to 19BJ1-1 "Engineering Practice: General Atlas of Building Structures", and the main data of the building practice selection library include name, layered practice and materials, wherein the materials are retrieved from the material library, and different materials will be assembled into different building practices; the mapping linkage relationship between the standard process library and each library is specifically the mapping of the name and layered practice of the building practice selection library with the standard process library, and then with the standard decoration schedule template; the standard process library is the embodiment of the construction process of the building practice, such as the construction of the floor is the construction of the cushion layer, leveling layer, waterproof layer, adhesive layer, surface layer in sequence, the standard process library also includes resource and construction period allocation algorithm, labor quota, type of work and machinery, such as Figures 10 to 15 The standard decoration schedule template is mapped to the enterprise standard database through the decoration name and decoration layered practices. The standard decoration schedule template also includes the logical relationship between the construction of each layered practice and whether there are construction overlaps or construction gaps. The standard decoration schedule template can be regarded as an outline catalog of the standard process library. The construction process is equivalent to the decoration name, and the construction process is equivalent to the layered practice. Mapping is achieved through the semantics of the name and layered practice.
[0069] The target project decoration practice calls the data information carried by the enterprise decoration database encapsulated by the system, including the number and category, name, layered practice of the decoration practice, and construction process technology, materials, labor and mechanical resource information.
[0070] Step 4: Configuration of the decoration model: The specialty, building, floor, flow section name, and labor team in the construction planning data are associated with the decoration model; the target project decoration practice library data and the decoration model are mapped through shared information, and the human, material, and machine resource configuration information is transferred to the model; the model is mapped to the initial plan through planning data, name, and layered practices, and the decoration model project quantity and resource configuration information, as well as the linkage information of rooms with similar decoration practices, are transferred to the initial progress plan. The shared information includes coding.
[0071] The data information carried by the initial schedule includes construction planning data, construction procedures (decoration names), construction techniques (layered practices) and the logical relationship between procedures and techniques; the initial schedule is also inseparable from the basic configuration of the system, such as the floor, construction scope, flow section, and construction sequence information are all the basis and prerequisite for generating the schedule.
[0072] Model configuration is as follows Figure 16 As shown, it includes obtaining engineering quantities from the decoration model, model association, engineering quantity calculation, linkage of rooms with similar decoration practices, and application of engineering quantities to plans; the association between the construction planning data and the decoration model is specifically the association between the profession, building, floor, flow section name, and labor team in the construction planning data and the decoration model, so as to realize the reflection of the planning data of the target project such as flow section division in the model space, such as Figure 17 As shown, clustering algorithms and statistical analysis methods are used to analyze the decoration characteristics of rooms with similar decoration practices, such as material usage and color matching, and to classify the rooms with the same decoration practices under each flow section in a linked manner; the mapping between the target project decoration practice library data and the model is specifically achieved through the data information carried by the shared decoration model. The data information carried by the decoration model includes: room name, decoration practice number and category, name, layered practice, engineering quantity and other data. The mapping between the two is achieved through the shared information: decoration practice number and category, name, layered practice; after mapping, the decoration model receives differentiated data from the target project decoration practice library, such as labor, machinery and other resource information, such as Figure 18As shown; the model engineering quantity and resource allocation information, and the linkage information of rooms with similar decoration practices are transmitted to the initial schedule. Specifically, under the dual drive of the association between construction planning data and decoration model and the mapping between target project decoration practice library data and model, the decoration model engineering quantity and resource allocation information are transmitted to the initial schedule. The key to the transmission is to achieve data synchronization through automatic matching of construction planning data information and keywords of decoration number, name and layered practice. Some individual ones that fail to match automatically need to be manually set in the selection association.
[0073] Step 5: Generate and optimize the project decoration schedule, which includes room linkage information including decoration workload, labor and mechanical resources, and similar decoration practices.
[0074] Specifically: when the project plan is modified, it is necessary to optimize the configuration to generate an optimized schedule, or to optimize the configuration based on fixed resource input and fixed construction period to generate an optimized schedule.
[0075] Step 6: Link construction and management matters to the progress plan, provide real-time warnings, and output management data forms.
[0076] Specifically: the digital transformation of project management is realized through step six, and the management data form includes labor resource curve, plan diagram, monthly plan, weekly plan, general material control and preparation, decoration and renovation plan preparation and decoration and renovation construction visual briefing.
[0077] The above embodiments are merely some explanations of the concept and implementation of the present invention, and are not intended to limit the same. Under the concept of the present invention, technical solutions that have not been substantially changed are still within the scope of protection.
Claims
1. A resource configuration and mapping method for decoration and renovation, characterized in that: The following steps are involved: Step 1: Create the decoration model of the target project, write the decoration methods into the model room, add model attributes and calculate the model quantity; Step 2: Basic system configuration: automatically collect target project rooms and decoration practice sheets, import target project decoration models, quantity calculation documents and business lists, and plan and configure project construction flow sections, construction sequence and team information; Step 3: Call the system-encapsulated enterprise decoration database based on the target project decoration practice. Call the system-encapsulated enterprise decoration database based on the number, category, name and layered practice of the target project decoration practice to assemble the project decoration practice library. Based on the mapping and linkage relationship between the decoration standard database and the standard decoration schedule template, combined with the basic configuration data of the system, generate the initial project schedule. The initial schedule does not include the project quantity. The resource data includes construction process data, material data, labor data and machinery data. Step 4: Configuration of the decoration model: The specialty, building, floor, flow section name, and labor team in the construction planning data are associated with the decoration model; the target project decoration practice library data and the decoration model are mapped through shared information, and the human, material, and machine resource configuration information is transferred to the model; the model is mapped to the initial plan through planning data, name, and layered practices, and the decoration model project quantity and resource configuration information, as well as the linkage information of rooms with similar decoration practices, are transferred to the initial progress plan. The shared information includes coding. Step 5: Generate and optimize a project renovation schedule, including renovation workload, labor and machinery resource requirements, and room linkage information for similar renovation practices. Step 6: Link construction and management matters to the progress plan, provide real-time warnings, and output management data forms; The enterprise decoration database includes a professional standard database for decoration and renovation and a standard decoration schedule template; the professional standard database for decoration and renovation includes a building practice selection library, a material library, a standard process library, and a mapping linkage relationship between the libraries. The main data of the building practice selection library includes name, layered practice and materials. The mapping linkage relationship between the standard process library and the libraries is specifically that the name and layered practice of the building practice selection library are mapped to the standard process library, and then mapped to the standard decoration schedule template. The standard process library is the embodiment of the construction process of the building practice. The standard process library also includes resource and construction period allocation algorithms, labor quotas, types of work and machinery; the standard decoration schedule template is mapped to the enterprise standard database through the decoration name and decoration layered practice. The standard decoration schedule template also includes the logical relationship between the construction of each layered practice and whether there is a construction overlap or construction gap; In the step four, the model configuration includes obtaining engineering quantities from the decoration model, model association, engineering quantity calculation, linkage of rooms with similar decoration practices, and application of engineering quantities to the plan; the association of the construction planning data with the decoration model is specifically the association of the profession, building, floor, flow section name, and labor team in the construction planning data with the decoration model; the mapping of the target project decoration practice library data and the model is specifically realized by the mapping between the target project decoration practice library data and the model through the data information carried by the shared decoration model, and after mapping, the decoration model receives differentiated data from the target project decoration practice library; the model engineering quantity and resource allocation information, and the linkage information of rooms with similar decoration practices are transmitted to the initial schedule, specifically under the dual drive of the association of the construction planning data with the decoration model and the mapping of the target project decoration practice library data with the model, the decoration model engineering quantity and resource allocation information are transmitted to the initial schedule.
2. The resource allocation and mapping method for decoration and renovation according to claim 1 is characterized in that: The specific steps of step one are: A0, use the Swell plug-in to write the architectural practices of the CAD drawings / Excel decoration practice sheets into the functional rooms of the model; A1, add attributes to the written decoration model, including building number, building function settings and model component code; A2, the written data is mapped through the Swell quantity calculation plug-in to calculate the engineering quantity; A3, generate the quantity calculation model and quantity calculation file to be imported into the schedule generation system.
3. The resource allocation and mapping method for decoration and renovation according to claim 1 is characterized in that: The specific steps of step 2 are: B0, automatically collect target project rooms and decoration practice sheets, import CAD drawings / Excel decoration practice sheets for automatic recognition; B1, import the target project decoration model and quantity calculation file; B2: When different decoration methods are used in the same room, further revisions can be made with the help of business list quantity, or the physical decoration model can be quickly created using the Swell decoration plug-in; B3, configure construction planning data information.
4. The resource allocation and mapping method for decoration and renovation according to claim 1 is characterized by: In step three, the data information carried by the initial progress plan includes construction planning data information, construction procedures, construction technology and logical relationships between procedures and technologies.
5. The resource allocation and mapping method for decoration and renovation according to claim 1 is characterized in that: The data information carried by the decoration model includes the room name, the number and category, name, layering method and engineering quantity of the decoration method.
6. The resource allocation and mapping method for decoration and renovation according to claim 1 is characterized in that: The specific steps of step five are: when the project plan is modified, optimization configuration is required to generate an optimized schedule, or schedule optimization configuration is performed based on fixed resource input and fixed construction period to generate an optimized schedule.
7. The resource allocation and mapping method for decoration and renovation according to claim 1 is characterized by: The digital transformation of project management is achieved through step six. The management data form includes labor resource curve, plan diagram, monthly plan, weekly plan, general material control and preparation, decoration and renovation plan preparation and decoration and renovation construction visual briefing.
Citation Information
Patent Citations
Decoration project amount estimation method and system and storage medium
CN115907876A
Construction progress prediction method and system based on BIM model
CN111105080A
Model construction method and system for interior decoration design
CN116702298A