By using a water suspended platform pile head hoist system to construct on the pond water surface, the problems of complex processes, long time, high cost, large safety hazards and great environmental impact in traditional methods are solved, and a fast, safe and efficient construction of a water suspended platform is achieved.
Patent Information
- Application Number
- CN202411919299.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-25
- Publication Date
- 2025-03-21
AI Technical Summary
When building suspended platforms on the water surface of the pond, the existing technology requires the excavation of foundations, scaffolding, pouring concrete and other processes, which consumes a lot of manpower and material resources, has a long construction period, high construction costs, many safety hazards, and has a great impact on the fish pond environment, and farmers cannot carry out breeding operations.
The water suspended pile head hoist system is adopted. By positioning and sinking piles at points where piles need to be sink, installing hoist, steel beam and formwork, binding steel bars and pouring concrete, removing the formwork after the concrete strength is qualified, and the construction is completed.
It realizes rapid positioning and fixing suspended formwork in the water environment, reduces complex processes in traditional construction methods, improves construction efficiency, provides good load-bearing capacity and stability, reduces the requirements for underwater foundation treatment and construction difficulty, avoids large-area foundation excavation and concrete foundation pouring, and has basically no impact on the surrounding environment.
Smart Images

Figure CN119663824A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of construction, and in particular relates to an above-water suspended cap pile head clamp system and a construction method. Background Art
[0002] With the continuous development of water engineering construction, the complementary use of fish and photovoltaics has gradually shown its importance in photovoltaic power generation projects. In the water environment of large areas of ponds, the research and application of the construction technology of the suspended high-capped platform on the water as an important infrastructure that does not occupy land area is particularly important. Traditional foundations cannot be smoothly constructed in the water surface of ponds, and are greatly restricted by construction conditions in water areas. The proposal of the construction method of the suspended high-capped platform on the water aims to standardize the construction process of the suspended high-capped platform on the water, improve construction efficiency, ensure project quality, and meet the needs of modern water engineering construction. In the photovoltaic power generation project of complementary use of fish and photovoltaics, the suspended high-capped platform on the water can provide equipment foundation for the switch station and booster station, and its construction quality is directly related to the safety and stable operation of the entire switch station and booster station.
[0003] A suspended platform is built on the surface of a pond. The existing technical solutions are mostly drainage and pond cleaning, excavation of foundation, and cast-in-place concrete. The Chinese patent document with publication number CN115710863A discloses a method for constructing a suspended cap on a steep slope of a mountain, which includes the following steps: excavating and leveling a multi-step construction platform from top to bottom on the upper part of the steep slope of the mountain; excavating the lower construction platform step by step according to the actual situation; excavating the pile foundation at the construction platform of each step; after the pile foundation excavation is completed, the steel casing is extended and the pile foundation concrete is poured; the bracket structure is installed on the top of the extended steel casing; the cap is erected and the steel bar is tied; the concrete of the cap is poured and maintained; and the bracket structure except the hoop is removed. The present invention is aimed at caps with complex terrain and landforms in mountainous areas, large ground undulations, and located on cliffs and the bottom part is suspended. It improves the safety and construction efficiency of the construction of suspended caps on cliffs, reduces the damage to the original terrain and landforms, and realizes green construction. This method still requires foundation excavation; it does not solve the problem that in the prior art, foundation excavation, scaffolding erection, concrete pouring and other processes are required in the pit, which consumes a lot of manpower and material resources, has a long construction period, high construction cost, and many safety hazards. It has a great impact on the fish pond environment and is not conducive to the benign cycle of the ecological environment. In addition, the farmers cannot carry out breeding operations during this period. Summary of the invention
[0004] The present invention provides an above-water suspended pedestal pile head clamp system and a construction method, aiming to overcome the problem that in the prior art, a suspended platform is built on the water surface of a pond, and the processes of foundation excavation, scaffolding erection, concrete pouring, etc. are required in the pond, which consumes a large amount of manpower and material resources, has a long construction period, high construction cost, and many safety hazards. It has a great impact on the fish pond environment, is not conducive to the benign cycle of the ecological environment, and farmers cannot carry out breeding operations during this period.
[0005] To this end, the present invention provides a method for constructing a water suspended cap pile head clamp system, comprising the following steps: S1. Locate the point where piles need to be sunk, and hammer the piles at the located points; S2. Install clamps on the piles that have been sunk; S3. Install steel beams on the clamps and the pipe piles, connect the multiple pipe piles together through the steel beams, install templates on the steel beams and tie steel bars; S4. Pour concrete on the formwork and the tied steel bars; S5. After the concrete strength meets the requirements, remove the formwork and complete the construction.
[0006] Preferably, the clamp comprises two clamping pieces, the middle part of the clamping piece is a semi-cylindrical protrusion facing outwards, and when installed, the inner side of the semi-cylindrical protrusion is close to the outer wall of the pipe pile.
[0007] Preferably, a non-slip pad is provided on the inner side of the holding piece.
[0008] Preferably, a plurality of corbels are connected to the outer surface of the upper portion of the holding piece, and the plurality of corbels are circumferentially evenly spaced.
[0009] Preferably, a support plate is arranged on the upper side of the clamp, and the upper side of the corbel is connected to the lower side of the support plate.
[0010] Preferably, the support plate is internally sleeved with pipe piles.
[0011] Preferably, the two pieces are connected by a plurality of bolts.
[0012] Preferably, the steel beam includes a plurality of main beams and longitudinal beams, the support plates on two adjacent pipe piles are laterally connected by two groups of main beams, and the two groups of main beams are symmetrically distributed around the two adjacent pipe piles, and a plurality of longitudinal beams are longitudinally connected to the top of the two groups of main beams, and the plurality of longitudinal beams are distributed at intervals.
[0013] Preferably, the template includes a base template and a beam template; when installing the template, the base template is installed on the steel beam at the position of the pipe pile, the template support is installed on the steel beam between adjacent pipe piles, and the beam template is installed on the template support.
[0014] A water suspended cap pile head clamp system comprises a plurality of pipe piles, clamps, steel beams and templates. The outer side of each of the plurality of pipe piles is sleeved with a clamp, the clamps on the plurality of pipe piles are connected via steel beams, and the templates are installed on the steel beams.
[0015] Beneficial effects of the present invention: 1. The pile head clamp system and construction method of the suspended cap provided by the present invention include the following steps: S1, locate the point where the pile needs to be sunk, and hammer the pile at the located pile sinking point; S2, install the clamp on the pipe pile that has been sunk; S3, install the steel beam on the clamp and the pipe pile, connect multiple pipe piles into one through the steel beam, install the template on the steel beam and tie the steel bars; S4, pour concrete on the template and the tied steel bars; S5, remove the template after the concrete strength is qualified, and complete the construction; after the pile is sunk by the pipe pile, the suspended template can be installed immediately, and rapid positioning and fixing can be achieved, which reduces the complex procedures in the traditional construction method, thereby improving the construction efficiency. Using the pipe pile as the foundation can provide good bearing capacity and stability, ensuring the long-term safety of the concrete platform. It can build a stable template system in the water environment without solid ground support to realize the pouring construction of the concrete platform, while reducing the requirements for underwater foundation treatment and the difficulty of construction. The suspended construction over water avoids large-scale foundation excavation, replacement filling, and concrete foundation pouring, reduces a lot of noise pollution to surrounding residents, and has basically no impact on the surrounding environment.
[0016] 2. The above-water suspended pedestal pile head clamp system and construction method provided by the present invention comprises two clamping pieces, the middle part of which is a semi-cylindrical protrusion facing outwards. During installation, the inner side of the semi-cylindrical protrusion is pressed against the outer wall of the pipe pile, so that the pipe pile can effectively transfer and disperse the load of the superstructure, thereby ensuring the stability and safety of the foundation.
[0017] 3. The above-water suspended foundation pile head clamp system and construction method provided by the present invention improves the friction between the pipe pile and the clamp by arranging an anti-skid pad connected to the inner side of the clamp.
[0018] 4. The above-water suspended pedestal pile head clamp system and construction method provided by the present invention is to provide a support plate connected to the clamp, and to connect the support plates on two adjacent pipe piles through a steel beam or other load-bearing structure to form a whole, so as to facilitate the dispersion and transmission of the upper load. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] The present invention will be further described in detail below with reference to the accompanying drawings.
[0020] Figure 1 It is a schematic diagram of the construction method of the pile head clamp system of the suspended cap on water; Figure 2It is a structural diagram of the construction method of the pile head hoop system of the suspended cap on water; Figure 3 It is a top view of the structure where the clamp holds the pipe pile tightly; Figure 4 It is a schematic diagram of the foundation template structure; Figure 5 It is a structural schematic diagram of the beam formwork and formwork support.
[0021] Description of reference numerals: 1. pipe pile; 2. hoop; 3. steel beam; 4. cap formwork; 5. beam formwork; 6. formwork support; 2.1, bracket; 2.2, bracket; 2.3, support plate; 2.4, bolt; 2.5, anti-slip pad; 3.1, main beam; 3.2, longitudinal beam; 4.1. Base formwork; 4.2. Base formwork; 4.3. Platform base formwork; 4.11. Secondary keel at the bottom of the pedestal; 4.12. Bottom formwork panel of the pedestal; 4.21, side ribs of the pedestal; 4.22, side panels of the pedestal; 4.23, tensioning screws of the pedestal; 4.24, fixtures of the pedestal; 5.1, beam bottom formwork; 5.2, beam side formwork; 5.3, plate platform formwork; 5.11, main keel at the bottom of beam; 5.12, secondary keel at the bottom of beam; 5.13, formwork at the bottom of beam; 5.21, beam side formwork; 5.22, beam side back rib; 5.23, beam side clamp; 5.31. Main keel of the bottom of the board; 5.32. Secondary keel of the bottom of the board; 5.33. Formwork of the bottom of the board; 6.1. Horizontal rod; 6.2. Vertical rod; 6.3. Support base. DETAILED DESCRIPTION
[0022] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The examples given are only used to explain the present invention and are not used to limit the scope of the present invention.
[0023] Embodiment 1: like Figure 1 and Figure 2 As shown, a construction method of a water suspended cap pile head clamp system comprises the following steps: S1. Locate the point where piles need to be sunk, and hammer the piles at the located points; Specifically, the pile head treatment construction can be started when the working surface meets the construction requirements and has no impact on other work. For piles that are higher than the design elevation, first use a level to copy the design elevation position, pop out a black line along the pile circle on the design elevation position line, and use a marble saw to saw the pile along the popped-out line. The pile sawing is carried out twice, and the pile head is firmly tied to the gantry crane with a sling. After cutting, the gantry crane is used to lift the cut pile head from its original position to the shore. After docking, the truck crane prepared on the shore is used to lift the pile head to the transport vehicle and transport it to the designated yard.
[0024] S2, installing a clamp 2 on the pile 1 that has been completed; S3, installing a steel beam 3 on the hoop 2 and the pipe pile 1, connecting the multiple pipe piles 1 together through the steel beam 3, installing a template on the steel beam 3 and tying steel bars; S4. Pour concrete on the formwork and the tied steel bars; S5. After the concrete strength meets the requirements, remove the formwork and complete the construction.
[0025] After the pipe pile 1 is sunk, the suspended formwork can be installed immediately to achieve rapid positioning and fixing, reducing the complex processes in the traditional construction method, thereby improving construction efficiency. Using the pipe pile 1 as the foundation can provide good bearing capacity and stability to ensure the long-term safety of the concrete platform. In an aquatic environment, a stable formwork system can be built without solid ground support to achieve the pouring construction of the concrete platform, while reducing the requirements for underwater foundation treatment and the difficulty of construction. The suspended construction on water avoids large-scale foundation excavation, replacement and concrete foundation pouring, reduces a lot of noise pollution to surrounding residents, and has little impact on the surrounding environment.
[0026] The present invention solves the problems of existing foundation excavation and concrete pouring, which are easy to pollute the surrounding environment, require large-scale foundation excavation, and avoid the need to set up full-house scaffolding; and the economic losses caused by large-scale drainage and emptying of fish ponds during construction. After the formwork is quickly installed using the pile head clamp 2, the construction period is greatly shortened, the use of manpower and material resources is reduced, the construction efficiency is high, and the construction quality of the suspended platform is guaranteed.
[0027] Preferably, the pipe pile 1 is a prestressed high-strength concrete pipe pile 1.
[0028] Specifically, the prestressed high-strength concrete pipe pile 1 is a PHC pipe pile, and the template is an above-water high-cap suspended template. The above-water high-cap suspended template utilizes the PHC (prestressed high-strength concrete) pipe pile with high strength, high durability and good bearing performance, and is suitable for foundation construction in an aquatic environment. The vertical bearing capacity and stability of the PHC pipe pile are used as the basis of the supporting structure, and the pipe pile 1 can provide reliable vertical support by being driven into the underwater stratum.
[0029] Preferably, the pile driving is controlled by penetration.
[0030] Preferably, the depth of the full cross section of the pile end of the pipe pile 1 (excluding the pile tip) into the strongly weathered rock is not less than 0.8m, and the depth of the weathered layer is not less than 0.2m. The stop hammer standard of the PHC pipe pile is: the final penetration (average value of 10 hits) should be controlled at 5-10mm.
[0031] Specifically, the construction is carried out in accordance with this standard to ensure that the quality of pile driving meets the construction requirements. During construction, when the pile driving reaches the design elevation, the penetration is controlled above the upper limit, and when the pile driving does not reach the design elevation, the penetration is controlled below the lower limit. If the top of the pile has reached the design elevation and the penetration is still large, the pile should continue to be driven until the penetration is or approaches the penetration control standard. Under normal circumstances, the pile 1 is stopped when it is 50-80cm into the soil, and then the verticality is adjusted. A dedicated person is assigned to monitor the verticality using two theodolites (a plumb bob can also be used for observation). The theodolites should be set at a place that is not affected by the pile driving (about 20 meters away from the pile point) and in a direction approximately 90° to each other. They should be leveled frequently to monitor the verticality of the guide frame, and the adjustment should be made by sliding and stopping the guide frame of the pile driver.
[0032] Embodiment 2: On the basis of Example 1, a construction method of a water suspended pedestal pile head clamp system is provided, wherein the clamp 2 comprises two clamping pieces 2.1, and the middle part of the clamping piece 2.1 is a semi-cylindrical protrusion facing outwards. During installation, the inner side of the semi-cylindrical protrusion is tightly attached to the outer wall of the pipe pile 1.
[0033] Specifically, the clamp 2 of this structure enables the two clamps 2.1 to be stably attached to the outer wall of the pipe pile 1, and has a simple structure and is easy to install and disassemble.
[0034] Preferably, the holding piece 2.1 is made of Q235B steel with a thickness of 12 mm and has a strong bearing capacity.
[0035] Preferably, Figure 3 As shown, a non-slip pad 2.5 is provided and connected to the inner side of the holding piece 2.1.
[0036] Specifically, by providing an anti-skid pad 2.5 connected to the inner side of the holding piece 2.1, the friction between the pipe pile 1 and the holding hoop 2 is increased to prevent the holding piece 2.1 from sliding when in use.
[0037] Preferably, the anti-slip pad 2.5 is a rubber pad.
[0038] Specifically, the rubber pad improves wear resistance, anti-slip and anti-fatigue properties when used in construction.
[0039] Preferably, the thickness of the rubber pad is 5 mm.
[0040] Specifically, the inside of the clamp 2 is covered with a 5 mm thick rubber pad pasted with a universal adhesive, which has better wear resistance, anti-skid and fatigue resistance.
[0041] Preferably, the upper outer surface of the holding piece 2.1 is connected with a plurality of corbels 2.2, and the plurality of corbels 2.2 are distributed at equal intervals in the circumferential direction.
[0042] Specifically, through the arrangement of the corbel 2.2, the pipe pile 1 can effectively transfer and disperse the load of the superstructure, thereby ensuring the stability and safety of the foundation.
[0043] Preferably, a support plate 2.3 is arranged on the upper side of the clamp 2, and the upper side of the corbel 2.2 is connected to the lower side of the support plate 2.3.
[0044] Specifically, by providing the support plate 2.3, the steel beam 3 and other bearing structures can be better installed on the pipe pile 1.
[0045] Preferably, the support plate 2.3 is sleeved on the outer wall of the pipe pile 1.
[0046] Specifically, the socket connection has better stability and support.
[0047] Preferably, the support plate 2.3 is in the shape of a ring.
[0048] Specifically, the annular structure is simple and has good bearing capacity.
[0049] Preferably, the two pieces of the holding parts 2.1 are connected by a plurality of bolts 2.4.
[0050] Specifically, the bolt 2.4 connection is a detachable connection, which is easy to install and disassemble.
[0051] Preferably, the outer wall of the holding piece 2.1 at positions other than the raised positions is provided with a plurality of stiffening plates connected thereto.
[0052] Specifically, the pipe piles 1 can effectively transfer and disperse the load of the superstructure through the stiffener, thereby ensuring the stability and safety of the foundation.
[0053] Preferably, the number of the brackets 2.2 in the clamp 2 is 6, and the number of the stiffening plates is 10.
[0054] Specifically, the construction quality requirements can be met with a minimum number of components, and the system is economical and practical.
[0055] Embodiment 3: On the basis of Example 2, a construction method for a pile head clamp system of an above-water suspended pedestal is provided, wherein the steel beam 3 includes a plurality of main beams 3.1 and longitudinal beams 3.2, the support plates 2.3 on two adjacent pipe piles 1 are laterally connected by two groups of main beams 3.1, and the two groups of main beams 3.1 are symmetrically distributed around the two adjacent pipe piles 1, and the two groups of main beams 3.1 are longitudinally connected to a plurality of longitudinal beams 3.2, and the plurality of longitudinal beams 3.2 are distributed at intervals.
[0056] Specifically, the support plates 2.3 on two adjacent pipe piles 1 are connected as a whole through steel crossbeams or other load-bearing structures to facilitate the dispersion and transmission of upper loads. After the installation of the hoop 2 is completed, two 43-track main beams 3.1 are installed on the support plate 2.3. The steel beam 3 is arranged close to the pipe pile 1 as the main beam 3.1, and the main beam 3.1 is directly placed on the bracket 2.2 of the hoop 2. The longitudinal beam 3.2 is fixed to the pipe pile 1 with bolts 2.4 to facilitate the adjustment of the height of the longitudinal beam 3.2 and the removal of the bottom formwork after the beam plate is completed; the longitudinal beams 3.2 are connected to form a whole with tie rods; then the bottom formwork of the cap is laid and the side formwork is installed.
[0057] Embodiment 4: On the basis of Example 3, a construction method for an above-water suspended pedestal pile head clamp system is provided, wherein the template comprises a pedestal template 4 and a beam template 5; when installing the template, the pedestal template 4 is installed on the steel beam 3 at the position of the pipe pile 1, the template support 6 is installed on the steel beam 3 between adjacent pipe piles 1, and the beam template 5 is installed on the template support 6.
[0058] Specifically, the design and installation of the formwork must ensure that it has sufficient strength, rigidity and stability to withstand the lateral pressure and construction load during concrete pouring. When pouring concrete, the deadweight of the concrete and the construction vibration force are borne by the suspended formwork and its suspension support system, and are transmitted to the underwater stratum through the pipe pile 1 foundation.
[0059] Preferably, the templates are all assembled on-site using wooden templates.
[0060] Specifically, the formwork is assembled on-site using wooden formwork, which is convenient for transportation and construction.
[0061] Embodiment 5: On the basis of Example 4, Figure 4As shown, the cap formwork 4 includes a cap bottom formwork 4.1, a cap side formwork 4.2 and a platform bottom formwork 4.3, the cap bottom formwork 4.1 includes a cap bottom secondary keel 4.11 and a cap bottom formwork panel 4.12, the cap side formwork 4.2 includes a cap side rib 4.21, a cap side panel 4.22, a cap tension screw 4.23, and a cap clamp 4.24; the longitudinal beam 3.2 around the pipe pile 1 is connected to the cap bottom secondary keel 4.11, the cap bottom secondary keel 4.12 .11 is connected to the pedestal bottom formwork panel 4.12, and the upper side of the pedestal bottom formwork panel 4.12 is connected to the pedestal side panel 4.22, the pedestal side rib 4.21 and the pedestal clamp 4.24 in sequence from the outside to the inside. The pedestal side panel 4.22 is located at the periphery of the pipe pile 1 and does not contact the outer wall of the pipe pile 1. The pedestal clamp 4.24 is connected through the pedestal tension screw 4.23; the pedestal bottom formwork 4.3 is connected between the upper ends of the pedestal side forms 4.2 in two adjacent pedestal formworks 4.
[0062] Specifically, during construction, first install the pedestal bottom formwork 4.1, then install the pedestal side formwork 4.2, and finally install the platform bottom formwork 4.3; during disassembly, first disassemble the platform bottom formwork 4.3, then disassemble the pedestal side formwork 4.2, and finally disassemble the pedestal bottom formwork 4.1, which is easy to construct.
[0063] Preferably, the pedestal bottom secondary keel 4.11 and pedestal side ribs 4.21 are made of wooden beams, the pedestal bottom formwork panel 4.12 and pedestal side panel 4.22 are made of plywood, and the pedestal clamp 4.24 is made of Φ48 steel pipe.
[0064] Specifically, the plywood is 15mm plywood, the wooden beam is 40×90mm with a horizontal spacing of 30cm, the Φ48 steel pipe is arranged with a spacing of 0.8m, and the tension screw 4.23 has a diameter of 14mm; this material selection and arrangement better meets the construction quality requirements. During the specific construction, it can also be selected and arranged according to needs to meet the construction quality requirements.
[0065] Preferably, the adjustment of the foundation bottom formwork 4.1 is carried out by inserting a wooden wedge between the longitudinal beam 3.2 and the foundation bottom secondary keel 4.11.
[0066] Specifically, the flatness of a large area of the pedestal bottom formwork panel 4.12 and the close contact between the pedestal bottom secondary keel 4.11 and the pedestal bottom formwork panel 4.12 are ensured by inserting wooden wedges.
[0067] Preferably, when laying the panels of the foundation bottom formwork panel 4.12, the joints between the panels are spliced with 15mm thick double-sided sponge tape to reduce the leakage of concrete.
[0068] Preferably, Figure 5As shown, the formwork support 6 includes two layers of horizontal rods 6.1 and multiple vertical rods 6.2. The two layers of horizontal rods 6.1 are horizontally distributed up and down, and the two layers of horizontal rods 6.1 are connected by multiple vertical rods 6.2. The lower ends of the vertical rods 6.2 are connected to the longitudinal beams 3.2 and / or the main beams 3.1, and the upper ends of the vertical rods 6.2 are provided with brackets 6.3.
[0069] Specifically, the vertical pole 6.2 is a φ48 steel pipe, the cantilever length of the bracket 6.3 extending out of the top horizontal pole 6.2 is 200mm, and the length of the bracket 6.3 inserted into the vertical pole 6.2 shall not be less than 150mm; the formwork support structure of this structure is simple and stable.
[0070] Preferably, the beam formwork 5 includes a beam bottom formwork 5.1, a beam side formwork 5.2 and a plate platform formwork 5.3, wherein the beam bottom formwork 5.1 includes a beam bottom main keel 5.11, a beam bottom secondary keel 5.12 and a beam bottom formwork 5.13, the beam side formwork 5.2 includes a beam side formwork 5.21, a beam side back rib 5.22 and a beam side clamp 5.23, and the plate platform formwork 5.3 includes a plate bottom main keel 5.31, a plate bottom secondary keel 5.32 and a plate bottom formwork 5.33; the horizontal rod 6 directly above the pipe pile 1 .1 is connected to the bottom main keel 5.11, the bottom main keel 5.11 is connected to the beam bottom template 5.13 through the beam bottom secondary keel 5.12, the outer periphery of the beam bottom template 5.13 is connected to the beam side template 5.21, the beam side back rib 5.22 and the beam side clamp 5.23 in sequence from the inside to the outside, the beam side templates 5.2 of two adjacent beam templates 5 are connected to the board platform template 5.3, and the board bottom main keel 5.31, the board bottom secondary keel 5.32 and the board bottom template 5.33 are connected in sequence from bottom to top.
[0071] Specifically, during construction, first install the beam bottom formwork 5.1, then install the beam side formwork 5.2, and finally install the board platform formwork 5.3; during disassembly, first disassemble the board platform formwork 5.3, then disassemble the beam side formwork 5.2, and finally disassemble the beam bottom formwork 5.1. Easy to construct. When laying the panels, the joints between the panels are spliced with 15mm thick double-sided sponge tape to reduce the leakage of concrete.
[0072] Preferably, the beam bottom secondary keel 5.12, beam side back rib 5.22, board bottom main keel 5.31 and board bottom secondary keel 5.32 are all made of wooden beams, the beam bottom formwork 5.1, beam side formwork 5.2 and board bottom formwork 5.33 are all made of plywood, and the beam bottom main keel 5.11 and beam side clamp 5.23 are all made of Φ48 steel pipe.
[0073] Specifically, the plywood is 15mm plywood, the wooden beam is 40×90mm with a horizontal spacing of 30cm, the Φ48 steel pipe is arranged with a spacing of 0.8m, and the tension screw 4.23 has a diameter of 14mm; this material selection and arrangement better meets the construction quality requirements. During the specific construction, it can also be selected and arranged according to needs to meet the construction quality requirements.
[0074] During the specific construction, the column and wall formwork can be installed according to the requirements. The column and wall formwork adopts wooden plywood formwork. The formwork adopts 40×90mm wooden beams with a 200mm arrangement vertically and 48×3.0mm steel pipes horizontally. The lower two are 400mm and the upper 550mm. The horizontal spacing of the pull-stop bolts is 450mm, and the vertical spacing is 450-550mm steel pipe spacing. Considering that the binding and formwork process of the wall panel reinforcement are cross-operations, when supporting the formwork, the outer side can be erected first, and the formwork of the other side can be assembled after the wall reinforcement process is completed. The assembly height of the wall formwork should be coordinated with the bottom formwork of the beam and slab, and the external wall formwork should be assembled to the platform surface elevation at one time.
[0075] Embodiment 6: A water suspended cap pile head clamp system comprises a plurality of pipe piles 1, clamps 2, steel beams 3 and a template. The outer side of each pipe pile 1 is sleeved with the clamp 2. The clamps 2 on the plurality of pipe piles 1 are connected via the steel beams 3, and the template is installed on the steel beams 3.
[0076] The present invention utilizes the high strength, high durability and good bearing performance of the pipe pile 1, and is suitable for foundation construction in an aquatic environment. The vertical bearing capacity and stability of the pipe pile 1 are utilized as the basis of the supporting structure, and by driving the pipe pile 1 into the underwater stratum, reliable vertical support can be provided. By sleeve-connecting the clamp 2 on the outside of the pipe pile 1, the pipe pile 1 can effectively transfer and disperse the load of the upper structure, ensuring the stability and safety of the foundation. A steel beam is arranged on the clamp 2, and a plurality of pipe piles 1 are connected into a whole by the steel beam to disperse and transfer the upper load. A template is installed on the steel beam 3, and the design and installation of the template must ensure that it has sufficient strength, rigidity and stability to withstand the lateral pressure and construction load during concrete pouring. When pouring concrete, the deadweight and construction vibration force of the concrete are borne by the template and its suspension support system, and are transmitted to the underwater stratum through the foundation of the pipe pile 1. The present invention can build a stable template system in an aquatic environment without solid ground support to realize the pouring construction of a concrete platform, while reducing the requirements for underwater foundation treatment and the difficulty of construction.
[0077] In the description of the present invention, it is necessary to understand that if there are terms such as "upper" and "lower" indicating an orientation or positional relationship, it is based on the orientation or positional relationship shown in the drawings, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, the terms describing the positional relationship in the drawings are only used for illustrative purposes and cannot be understood as a limitation on the present invention.
[0078] The above implementation modes are merely examples of the present invention and do not limit the protection scope of the present invention. All designs identical or similar to the present invention fall within the protection scope of the present invention.
Claims
1. A construction method for a suspended cap pile head hoop system on water, characterized in that: The steps include: S1. Locate the point where piles need to be sunk, and hammer the piles at the located pile sinking points; S2, installing a clamp (2) on the pile (1) that has been sunk; S3, installing a steel beam (3) on the hoop (2) and the pipe pile (1), connecting the plurality of pipe piles (1) together through the steel beam (3), installing a template on the steel beam (3) and tying steel bars; S4. Pour concrete on the formwork and the tied steel bars; S5. After the concrete strength meets the requirements, remove the formwork and complete the construction.
2. The method for constructing a suspended cap pile head hoop system on water as claimed in claim 1, characterized in that: The clamp (2) comprises two clamping pieces (2.1), the middle of the clamping piece (2.1) is a semi-cylindrical protrusion facing outwards, and when installed, the inner side of the semi-cylindrical protrusion is closely attached to the outer wall of the pipe pile (1).
3. The method for constructing a pile head clamp system for an overhead suspended platform as claimed in claim 2, characterized in that: An anti-slip pad (2.5) is provided and connected to the inner side of the holding piece (2.1).
4. The method for constructing a pile head clamp system for an overhead suspended platform as claimed in claim 2, characterized in that: The upper outer surface of the holding piece (2.1) is provided with a plurality of brackets (2.2) connected thereto, and the plurality of brackets (2.2) are distributed at equal intervals in the circumferential direction.
5. The method for constructing a pile head clamp system for a suspended cap above water as claimed in claim 4, characterized in that: The hoop (2) is provided with a support plate (2.3) on its upper side, and the upper side of the bracket (2.2) is connected to the lower side of the support plate (2.3).
6. The method for constructing a pile head clamp system for an overhead suspended platform as claimed in claim 5, characterized in that: The support plate (2.3) is sleeved with a pipe pile (1).
7. The method for constructing a water suspended cap pile head clamp system according to claim 2, characterized in that: The two pieces of the holding parts (2.1) are connected via a plurality of bolts (2.4).
8. The method for constructing a pile head clamp system for an overhead suspended platform as claimed in claim 5, characterized in that: The steel beam (3) comprises a plurality of main beams (3.1) and longitudinal beams (3.2); the upper surfaces of the support plates (2.3) on two adjacent pipe piles (1) are laterally connected via two groups of main beams (3.1); the two groups of main beams (3.1) are symmetrically distributed around the two adjacent pipe piles (1); the upper surfaces of the two groups of main beams (3.1) are longitudinally connected to a plurality of longitudinal beams (3.2); the plurality of longitudinal beams (3.2) are distributed at intervals.
9. The method for constructing a pile head clamp system for an overhead suspended platform as claimed in claim 8, characterized in that: The template comprises a cap template (4) and a beam template (5); when installing the template, the cap template (4) is installed on the steel beam (3) at the position of the pipe pile (1), a template support (6) is installed on the steel beam (3) between adjacent pipe piles (1), and the beam template (5) is installed on the template support (6).
10. An above-water suspended cap pile head clamp system, characterized in that: The invention comprises a plurality of pipe piles (1), a clamp (2), a steel beam (3) and a template, wherein the outer surface of each pipe pile (1) in the plurality of pipe piles (1) is sleeved with a clamp (2), the clamps (2) on the plurality of pipe piles (1) are connected via the steel beam (3), and the template is installed on the steel beam (3).
Citation Information
Patent Citations
Construction method of mountain abrupt slope suspended bearing platform
CN115710863A