Coal mining method for controlling surface subsidence by floor isolation grouting and filling

By injecting backfill grout under the coal seam floor and using the floor pressure-bearing protective layer to lift the floor, the problems of working face interference and low extraction rate in backfill mining are solved, and safe and efficient coal mining is achieved.

CN119686734BActive Publication Date: 2026-05-29CHINA UNIV OF MINING & TECH

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
CHINA UNIV OF MINING & TECH
Filing Date
2024-12-20
Publication Date
2026-05-29

AI Technical Summary

Technical Problem

During the backfilling mining process, the working face recovery is disturbed, the recovery rate is low, and the cost is high, making it difficult to effectively reduce surface subsidence.

Method used

By injecting backfill slurry under the coal seam floor, the floor is lifted using the pressure-bearing protective layer, separating the backfilling operation from the mining face, reducing interference with mining, and improving the extraction rate.

Benefits of technology

It separates the mining and backfilling operations at the working face, improves the extraction rate, reduces surface subsidence, and is suitable for safe and efficient mining in densely built-up areas.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119686734B_ABST
    Figure CN119686734B_ABST
Patent Text Reader

Abstract

The present application relates to the field of mining area subsidence reduction and filling mining, in particular to a floor isolation grouting filling control surface subsidence mining method; a certain thickness of rock stratum is selected as a floor pressure bearing protective layer below a floor failure zone, the floor pressure bearing protective layer arches under grouting pressure, but no fissure leading to the upper floor failure zone is generated; the floor pressure bearing protective layer bottom interface is taken as a grouting layer, a grouting borehole is connected to the grouting layer; working face mining is carried out, when grouting filling can be carried out, filling slurry is injected from the grouting borehole to the grouting layer. The filling slurry lifts the floor grouting pressure bearing layer and the floor failure zone under high pressure, finally fills the entire goaf, reduces the breaking degree of the coal seam roof, controls the subsidence amplitude of the overlying strata, and further reduces the surface subsidence amplitude. In the present application, the mining and grouting filling processes are separated, the influence of grouting filling operation on working face mining is avoided, and the present application is particularly suitable for coal mine areas with dense buildings.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of mining subsidence reduction and backfilling, specifically to a method for controlling surface subsidence in coal mining by bottom plate isolation grouting and backfilling. Background Technology

[0002] The problem of coal seam pressure beneath buildings has always been a major technical challenge in coal mining, especially in eastern mining areas. Due to the dense concentration of surface buildings in these regions, mining activities can easily cause subsidence and damage to these structures and surface facilities. Therefore, a safe and efficient mining method is urgently needed to minimize the impact on surface buildings. Against this backdrop, the development of backfill mining technology has provided an effective solution to the problem of coal seam pressure beneath buildings.

[0003] In recent years, backfilling technology in coal mining has gradually matured, resulting in various methods for filling goafs, including solid backfilling, paste backfilling, and high-water material backfilling. Solid backfilling typically utilizes solid waste such as mine waste rock and gangue to fill goafs, which not only reduces surface subsidence but also effectively utilizes mine waste resources. Paste backfilling uses finely ground mine tailings mixed with water and additives to form a paste slurry for filling, exhibiting high strength and good stability, making it suitable for coal mining in densely built-up areas. High-water material backfilling is a technology that uses high-water solidification materials such as cement to form a solid filler through chemical reaction, which can quickly fill goafs and create high load-bearing capacity, effectively supporting overlying strata and reducing surface subsidence.

[0004] While backfill mining offers significant advantages in mitigating coal seam pressure issues, its implementation also faces several technical and economic challenges. Among these, interference from face mining and the impact on extraction rates are major drawbacks of backfill mining.

[0005] First, the injection and solidification of backfill material requires a large amount of construction equipment and procedures, which directly interferes with the normal mining progress of the working face, leading to reduced production efficiency. For example, the laying and solidification of the backfill takes time, increasing the work cycle, and a certain isolation distance must be maintained between the coal face and the backfill to ensure safety, which limits the mining length and advancement speed of the working face. At the same time, the operation process of backfill mining is relatively complex, requires highly skilled personnel, and requires more manpower and material resources, increasing operating costs.

[0006] Secondly, backfilling mining affects the recovery rate. Because the backfill occupies a portion of the space, the coal seam recovery rate is difficult to reach the level of traditional mining methods, leading to a decrease in resource utilization. During the backfilling process, in order to ensure the strength and stability of the backfill, a portion of the coal seam is usually left unmined, which further reduces the economic benefits of the mine.

[0007] In addition, due to the addition of backfill materials and the need for filling operations, the cost of extracting coal per unit is relatively high, which poses a certain challenge to the economics of backfill mining. This is especially true when resources are scarce or coal prices fluctuate, making the cost-effectiveness of this method even less than ideal. Summary of the Invention

[0008] To address the problems existing in the prior art, this invention proposes a method for controlling surface subsidence in coal mining by bottom plate isolation grouting and backfilling. This method can separate the backfilling process from the working face mining, effectively avoid interference from backfilling operations on the working face mining, and improve the working face extraction rate. Specifically, it includes the following steps:

[0009] S1: Determine the extent of the failure zone of the floor below the coal seam, and select a rock layer of a certain thickness below the failure zone as the pressure-bearing protective layer of the floor. The pressure-bearing protective layer of the floor arches upward under the grouting pressure, but does not generate cracks that connect to the upper failure zone of the floor, or the generated cracks are not connected to the cracks of the failure zone of the floor.

[0010] S2: The bottom interface of the pressure-bearing protective layer of the base plate is used as the grouting layer, and the grouting borehole is connected to the grouting layer.

[0011] S3: When the working face is being mined, and grouting is possible, fill the grouting slurry into the grouting layer through the grouting borehole.

[0012] Preferably, in step S1, the rock stratum at the bottom of the pressure-bearing protective layer of the base plate has a low elastic modulus and good water-proof properties.

[0013] Preferably, in step S2, when the working face adopts a single-lane layout, the grouting boreholes are constructed in the horizontal lanes on both sides of the working face towards the grouting layer of the coal seam floor in advance of the working face mining position. The grouting boreholes are inclined in the direction of the cut in the plane. The grouting boreholes are constructed in pairs in the horizontal lanes on both sides of the working face at a certain distance from the cut in the working face advancing direction.

[0014] Preferably, in step S2, when both horizontal roadways on both sides of the working face adopt a double-roadway arrangement, grouting boreholes are constructed in the two outer horizontal roadways toward the grouting layer of the coal seam floor inside the working face. The grouting boreholes are inclined in the direction of the cut in the plane. The grouting boreholes are constructed in pairs in the horizontal roadways on both sides of the working face at a certain distance from the cut, along the working face advancement direction.

[0015] Preferably, in step S2, directional grouting boreholes are drilled from the ground outside the cut-out on the working face. The horizontal section of the directional grouting borehole is drilled close to the bottom interface of the pressure-bearing protective layer of the base plate, and the drilling extends at least to a certain range within the working face.

[0016] Preferably, in step S2, directional grouting boreholes are constructed from the ground outside the horizontal tunnel on one side of the working face. The horizontal section of the directional grouting borehole is constructed close to the bottom interface of the pressure-bearing protective layer of the bottom plate, and is constructed to at least a certain range within the working face. Several directional grouting boreholes are constructed at certain intervals along the working face advancing direction.

[0017] Preferably, in step S3, the filling slurry is made of fly ash slurry or gangue powder slurry.

[0018] Preferably, in step S3, when the working face adopts a single-lane layout, when the working face is backed up to above the final hole of a certain pair of grouting boreholes, trial grouting is started for the pair of grouting boreholes. When it is possible to inject, filling grout is injected into the grouting layer through the pair of grouting boreholes. When the working face is backed up to the position of the opening of the pair of grouting boreholes, grouting is stopped and the holes are sealed. Then, the next pair of grouting boreholes are grouted in the same way.

[0019] Preferably, in step S3, when both horizontal tunnels on both sides of the working face adopt a double-tunnel arrangement, when the working face is back-mined to above the final hole of a certain pair of grouting boreholes, trial grouting is started on the pair of grouting boreholes. When it is possible to inject, filling grout is injected into the grouting layer through the pair of grouting boreholes. When the pair of grouting boreholes cannot be injected due to high grouting pressure, grouting is stopped and the holes are sealed. Then, the next pair of grouting boreholes are grouted in the same way.

[0020] Preferably, in step S3, when drilling directional grouting holes from the ground outside the working face cut, when grouting can be carried out, filling grout is injected from the directional grouting hole into the grouting layer. When grouting cannot be injected due to high grouting pressure, grouting is stopped and the hole is sealed.

[0021] Preferably, in step S3, when directional grouting boreholes are drilled from the ground outside the horizontal tunnel on one side of the working face, for each directional grouting borehole, when grouting and filling can be carried out, filling grout is injected from the directional grouting borehole to the grouting layer. When a certain directional grouting borehole cannot be injected due to high grouting pressure, grouting through that directional grouting borehole is stopped and the borehole is sealed.

[0022] The inventive points and beneficial effects of this invention: This invention creatively proposes a method for controlling surface subsidence in coal mining through bottom plate isolation grouting and filling. During coal seam mining, filling grout is injected into the bottom interface of the bottom grouting pressure layer beneath the coal seam floor through grouting boreholes. Under high pressure, the filling grout lifts the bottom grouting pressure layer and the floor failure zone, ultimately filling the entire goaf, reducing the degree of roof fracture, controlling the subsidence of the overlying strata, and thus reducing the surface subsidence. In this invention, the coal mining and grouting processes are separated, avoiding the impact of grouting and filling operations on the working face recovery, making it particularly suitable for coal mining areas with dense buildings. Attached Figure Description

[0023] Figure 1 This is a schematic diagram of the single-lane straight hole arrangement for bottom plate isolation grouting filling in this invention;

[0024] Figure 2 This is a schematic diagram of the double-lane straight hole arrangement for bottom plate isolation grouting filling in this invention;

[0025] Figure 3 This is a schematic diagram of the ground drilling arrangement along the direction of the bottom plate isolation grouting filling in this invention;

[0026] Figure 4 This is a schematic diagram of the ground drilling holes arranged along the directional direction for the bottom plate isolation grouting filling in this invention;

[0027] In the diagram: grouting bearing layer-1, uniform fracture zone of the bottom plate-2, fracture expansion zone of the bottom plate-3, section coal pillar-4, horizontal roadway-5, caving zone-6, fissure zone-7, grouting borehole-8, filling slurry-9. Detailed Implementation

[0028] To better understand the technical content of this invention, specific embodiments are described below in conjunction with the accompanying drawings. Various aspects of this invention are described with reference to the accompanying drawings, which illustrate numerous illustrative embodiments. The embodiments of this invention are not limited to those shown in the drawings. It should be understood that this invention is implemented through any of the various concepts and embodiments described above, as well as the concepts and embodiments described in detail below, because the concepts and embodiments disclosed in this invention are not limited to any particular implementation. Furthermore, some aspects of this invention can be used alone or in any suitable combination with other aspects disclosed in this invention.

[0029] like Figure 1-4 As shown, this invention proposes a method for controlling surface subsidence in coal mining through bottom plate isolation grouting and filling, comprising the following steps: S1: Determine the range of the bottom plate failure zone below the coal seam. The bottom plate failure zone includes a bottom plate fracture expansion zone 3 and a bottom plate uniform fracture zone 2. In the bottom plate fracture expansion zone 3, the bottom plate rock strata are fractured in an irregular network pattern, and the fractured blocks are relatively small. Due to the gaps between the fractured blocks, they have a certain expansion characteristic. In the bottom plate uniform fracture zone 2, the bottom plate rock strata are fractured with regular longitudinal and transverse cracks, forming relatively large regular fractured blocks. The bottom plate failure zone can form water-conducting channels. Below the bottom plate failure zone, a rock stratum of a certain thickness (usually containing multiple rock strata) is selected as the bottom plate pressure-bearing protective layer 1. The bottom plate pressure-bearing protective layer 1 arches upward under grouting pressure, but does not generate cracks that connect to the upper bottom plate failure zone, or the generated cracks do not connect with the cracks in the bottom plate failure zone. The rock stratum at the bottom of the bottom plate pressure-bearing protective layer is preferably a rock stratum with low elastic modulus and good water-impermeability, such as mudstone.

[0030] S2: The bottom interface of the pressure-bearing protective layer 1 of the base plate is taken as the grouting layer, and the grouting borehole 8 is connected to the grouting layer.

[0031] There are several ways to arrange the grouting boreholes 8, such as:

[0032] S201: As Figure 1 As shown, the working face adopts a single-lane layout, that is, a return airway and a transport airway are arranged on both sides of the working face. The single-lane layout is a well-known layout in the field and will not be described in detail here. At the advance working face mining position, grouting boreholes 8 are constructed in the horizontal roadways 5 on both sides of the working face towards the grouting layer of the coal seam floor. The grouting boreholes 8 are inclined in the plane towards the cutting direction. The grouting boreholes 8 are constructed in pairs in the horizontal roadways 5 on both sides of the working face at a certain distance from the cutting direction along the working face advancement direction. The vertical depth, angle and plane inclination of each pair of grouting boreholes 8 are the same.

[0033] S202: As Figure 2 As shown, both horizontal roadways 5 on both sides of the working face adopt a double-roadway layout. A section coal pillar 4 is left between the two horizontal roadways 5 on the same side. Grouting boreholes 8 are constructed in the two outer horizontal roadways 5 towards the grouting layer of the coal seam floor inside the working face. The grouting boreholes 8 are inclined in the plane towards the cutting direction. The grouting boreholes 8 are constructed in pairs in the horizontal roadways 5 on both sides of the working face along the working face advancement direction, starting from the cutting direction and spaced at a certain distance. The vertical depth, angle and plane inclination of each pair of grouting boreholes 8 are the same.

[0034] S203: As Figure 3 As shown, directional grouting borehole 8 is constructed from the ground outside the cut-out on the working face. The horizontal section of the directional grouting borehole 8 is constructed close to the bottom interface of the pressure-bearing protective layer 1 of the bottom plate, and is constructed to at least a certain range within the working face.

[0035] S204: As Figure 4 As shown, directional grouting boreholes 8 are constructed from the ground outside the horizontal tunnel 5 on one side of the working face. The horizontal section of the directional grouting boreholes 8 is constructed close to the bottom interface of the pressure-bearing protective layer 1 of the bottom plate, and is constructed at least to a certain range within the working face. Several directional grouting boreholes 8 are constructed at certain intervals along the working face advancing direction (i.e., direction).

[0036] S3: When the working face is being mined and grouting is possible, filling grout 9 is injected into the grouting layer from the grouting borehole. Filling grout 9 is preferably made of coal-based solid waste materials such as fly ash grout or gangue grout. The injected high-pressure grout 9 gradually lifts the pressure-bearing protective layer 1 of the bottom plate and the uniform fracture zone 2 and the fracture expansion zone 3 of the bottom plate above it. Under the action of grouting, the uniform fracture zone 2 and the fracture expansion zone 3 of the bottom plate will increase the damage range, and the looseness of the irregular rock blocks in the fracture expansion zone 3, i.e. the degree of fragmentation, will also increase, further filling the goaf space. Together with the filling grout 9, it offsets part of the space formed by coal seam mining, thereby reducing the equivalent mining height of the coal seam, thereby reducing the subsidence of the overlying strata and reducing surface subsidence.

[0037] The matching relationship between grouting and coal mining is as follows, depending on the different arrangements of the grouting boreholes 8:

[0038] S301: As Figure 1 As shown, when the working face adopts a single-lane layout, when the working face is backed up to above the final hole of a pair of grouting boreholes 8, trial grouting of the pair of grouting boreholes 8 is started. When it is possible to inject, filling grout 9 is injected into the grouting layer through the pair of grouting boreholes 8. When the working face is backed up to the position of the opening of the pair of grouting boreholes 8, grouting is stopped and the hole is sealed. Then, the next pair of grouting boreholes is grouted in the same way.

[0039] S302: As Figure 2 As shown, when both horizontal tunnels 5 on both sides of the working face adopt a double-tunnel layout, when the working face is back-mined to above the final hole of a certain pair of grouting boreholes 8, trial grouting is started on the pair of grouting boreholes 8. When it is possible to inject, filling grout 9 is injected into the grouting layer through the pair of grouting boreholes 8. When the pair of grouting boreholes 8 cannot be injected due to high grouting pressure, grouting is stopped and the holes are sealed. Then, the next pair of grouting boreholes 8 is grouted in the same way.

[0040] S203: As Figure 3 As shown, when directional grouting borehole 8 is drilled from the ground outside the working face cut, when grouting can be carried out, filling grout 9 is injected from directional grouting borehole 8 into the grouting layer. When grouting cannot be injected due to high grouting pressure, grouting is stopped and the borehole is sealed.

[0041] S204: As Figure 4 As shown, when directional grouting boreholes 8 are drilled from the ground outside the horizontal tunnel 5 on one side of the working face, for each directional grouting borehole 8, when grouting and filling can be carried out, filling grout 9 is injected from the directional grouting borehole 8 into the grouting layer. When a certain directional grouting borehole 8 cannot be injected due to high grouting pressure, grouting through that directional grouting borehole is stopped and the borehole is sealed.

[0042] This invention is not limited to the preferred embodiments described above. Anyone can derive other methods in various forms under the guidance of this invention. Any technical solution that is the same as or similar to this application falls within the protection scope of this invention.

Claims

1. A method for controlling surface settlement in coal mining by bottom plate isolation grouting and filling, characterized in that, Includes the following steps: S1: Determine the extent of the floor failure zone below the coal seam. The floor failure zone includes a floor fracture and expansion zone and a floor uniform fracture zone. In the floor fracture and expansion zone, the floor strata are fractured in an irregular network pattern, and the fractured blocks are relatively small. Due to the gaps between the fractured blocks, they have a certain expansion characteristic. In the floor uniform fracture zone, the floor strata have regular longitudinal and transverse fractures, forming relatively large, regular fractured blocks. The floor failure zone can form water-conducting channels. Below the floor failure zone, a certain thickness of rock strata is selected as the floor pressure-bearing protective layer. Under grouting pressure, the floor pressure-bearing protective layer arches upward, but does not generate fractures that connect to the upper floor failure zone, or the generated fractures do not connect with the fractures in the floor failure zone. The lowest rock strata of the floor pressure-bearing protective layer have low elastic modulus and good water-tightness. S2: When the working face adopts a single-lane layout, the grouting boreholes are constructed in the horizontal roadways on both sides of the working face towards the grouting layer of the coal seam floor. The grouting boreholes are inclined in the direction of the cut in the plane. The grouting boreholes are constructed in pairs in the horizontal roadways on both sides of the working face at a certain distance from the cut in the working face advancing direction. S3: During the longwall face mining, when the longwall face reaches above the final hole of a pair of grouting boreholes, test grouting is started on the pair of grouting boreholes. When injection is possible, filling grout is injected into the grouting layer through the pair of grouting boreholes. When the longwall face reaches the position of the borehole opening of the pair of grouting boreholes, grouting is stopped and the boreholes are sealed. Then, the next pair of grouting boreholes are grouted in the same way. Under high pressure, the filling grout lifts the grouting bearing layer and the failure zone of the bottom plate, and finally fills the entire goaf, reduces the degree of roof fracture of the coal seam, controls the subsidence of the overlying strata, and thus reduces the subsidence of the surface. The filling grout uses fly ash slurry or gangue slurry.

2. A method for controlling surface settlement in coal mining by bottom plate isolation grouting and filling, characterized in that, Includes the following steps: S1: Determine the extent of the floor failure zone below the coal seam. The floor failure zone includes a floor fracture and expansion zone and a floor uniform fracture zone. In the floor fracture and expansion zone, the floor strata are fractured in an irregular network pattern, and the fractured blocks are relatively small. Due to the gaps between the fractured blocks, they have a certain expansion characteristic. In the floor uniform fracture zone, the floor strata have regular longitudinal and transverse fractures, forming relatively large, regular fractured blocks. The floor failure zone can form water-conducting channels. Below the floor failure zone, a certain thickness of rock strata is selected as the floor pressure-bearing protective layer. Under grouting pressure, the floor pressure-bearing protective layer arches upward, but does not generate fractures that connect to the upper floor failure zone, or the generated fractures do not connect with the fractures in the floor failure zone. The lowest rock strata of the floor pressure-bearing protective layer have low elastic modulus and good water-tightness. S2: When both horizontal roadways on both sides of the working face adopt a double-roadway layout, grouting boreholes are constructed in the two outer horizontal roadways toward the grouting layer of the coal seam floor inside the working face. The grouting boreholes are inclined in the direction of the cut in the plane. The grouting boreholes are constructed in pairs in the horizontal roadways on both sides of the working face at a certain distance from the cut in the working face advancing direction. S3: During the longwall face mining, when the longwall face reaches above the final borehole of a pair of grouting boreholes, test grouting is started on the pair of grouting boreholes. If injection is possible, filling grout is injected into the grouting layer through the pair of grouting boreholes. When the pair of grouting boreholes cannot be injected due to high grouting pressure, grouting is stopped and the boreholes are sealed. Then, the next pair of grouting boreholes are grouted in the same way. Under high pressure, the filling grout lifts the grouting bearing layer and the failure zone of the bottom plate, and finally fills the entire goaf, reduces the degree of roof fracture of the coal seam, controls the subsidence of the overlying strata, and thus reduces the subsidence of the surface. The filling grout uses fly ash slurry or gangue slurry.

3. A method for controlling surface settlement in coal mining by bottom plate isolation grouting and filling, characterized in that, Includes the following steps: S1: Determine the extent of the floor failure zone below the coal seam. The floor failure zone includes a floor fracture and expansion zone and a floor uniform fracture zone. In the floor fracture and expansion zone, the floor strata are fractured in an irregular network pattern, and the fractured blocks are relatively small. Due to the gaps between the fractured blocks, they have a certain expansion characteristic. In the floor uniform fracture zone, the floor strata have regular longitudinal and transverse fractures, forming relatively large, regular fractured blocks. The floor failure zone can form water-conducting channels. Below the floor failure zone, a certain thickness of rock strata is selected as the floor pressure-bearing protective layer. Under grouting pressure, the floor pressure-bearing protective layer arches upward, but does not generate fractures that connect to the upper floor failure zone, or the generated fractures do not connect with the fractures in the floor failure zone. The lowest rock strata of the floor pressure-bearing protective layer have low elastic modulus and good water-tightness. S2: Directional grouting boreholes are drilled from the ground outside the cut-out on the working face. The horizontal section of the directional grouting borehole is drilled close to the bottom interface of the pressure-bearing protective layer of the bottom plate, and is drilled to at least a certain range within the working face. The horizontal section of the directional grouting borehole extends along the advancing direction of the working face. S3: When carrying out the working face mining, when drilling directional grouting boreholes from the ground outside the working face cut, if grouting and filling can be carried out, inject filling grout into the grouting layer from the directional grouting borehole. If grouting cannot be injected due to high grouting pressure, stop grouting and seal the borehole. Under high pressure, the filling grout lifts the grouting bearing layer and the failure zone of the bottom plate, and finally fills the entire goaf, reduces the degree of coal seam roof fracture, controls the subsidence of the overlying strata, and thus reduces the subsidence of the surface. The filling grout uses fly ash slurry or gangue slurry.

4. A method for controlling surface settlement in coal mining by bottom plate isolation grouting and filling, characterized in that, Includes the following steps: S1: Determine the extent of the floor failure zone below the coal seam. The floor failure zone includes a floor fracture and expansion zone and a floor uniform fracture zone. In the floor fracture and expansion zone, the floor strata are fractured in an irregular network pattern, and the fractured blocks are relatively small. Due to the gaps between the fractured blocks, they have a certain expansion characteristic. In the floor uniform fracture zone, the floor strata have regular longitudinal and transverse fractures, forming relatively large, regular fractured blocks. The floor failure zone can form water-conducting channels. Below the floor failure zone, a certain thickness of rock strata is selected as the floor pressure-bearing protective layer. Under grouting pressure, the floor pressure-bearing protective layer arches upward, but does not generate fractures that connect to the upper floor failure zone, or the generated fractures do not connect with the fractures in the floor failure zone. The lowest rock strata of the floor pressure-bearing protective layer have low elastic modulus and good water-tightness. S2: Directional grouting boreholes are constructed from the ground outside the horizontal tunnel on one side of the working face. The horizontal section of the directional grouting borehole is constructed close to the bottom interface of the pressure-bearing protective layer of the bottom plate, and is constructed to at least a certain range within the working face. Several directional grouting boreholes are constructed at certain intervals along the working face advancement direction, and the horizontal section of the directional grouting borehole extends perpendicular to the working face advancement direction. S3: During the working face mining, for each directional grouting borehole, when grouting and filling are possible, filling grout is injected from the directional grouting borehole into the grouting layer. When grouting cannot be carried out through a certain directional grouting borehole due to high grouting pressure, grouting through that directional grouting borehole is stopped and the borehole is sealed. Under high pressure, the filling grout lifts the grouting bearing layer and the failure zone of the bottom plate, and finally fills the entire goaf, reduces the degree of roof fracture of the coal seam, controls the subsidence of the overlying strata, and thus reduces the subsidence of the surface. The filling grout uses fly ash slurry or gangue slurry.