Air conditioning system installation construction method based on BIM
By using BIM platform and intelligent construction management system in the installation and construction of dust-free environment air conditioning systems, combined with VR/AR technology, the problems of inconsistent design with reality, low construction efficiency and difficulty in collaboration are solved, and high-precision, low cost and efficient construction results are achieved, meeting the high standard needs of dust-free environments.
Patent Information
- Application Number
- CN202411771536.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-04
- Publication Date
- 2025-03-28
AI Technical Summary
There are problems in the installation and construction of existing dust-free environment air conditioning systems, such as inconsistent design with reality, low construction efficiency, difficulty in collaboration and lack of intelligent support, which is difficult to meet the needs of high-standard dust-free environments.
The installation and construction method of air conditioning system based on BIM is adopted, and a three-dimensional digital model is constructed through the BIM platform, combined with the data acquisition device to feedback the construction environment data in real time, and dynamically adjust the model content. Use an intelligent construction management system to generate construction guidance documents, and combine VR/AR technology to perform simulation operations to identify potential risk points and avoid rework problems.
It improves construction accuracy and reliability, reduces the phenomenon of inconsistent design with reality, enhances the stable performance of the system, and meets the high standard needs of dust-free environments. At the same time, the construction cycle is shortened, the total project cost is reduced, and the construction efficiency and economic benefits are improved.
Smart Images

Figure CN119720334A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of electrical construction, and in particular to a BIM-based air-conditioning system installation construction method. Background Art
[0002] In recent years, with the increasing requirements for clean environment in the fields of industry and scientific research, dust-free environment air conditioning systems have been widely used as key technologies in fields with high cleanliness requirements such as semiconductor manufacturing and biopharmaceuticals. This type of air conditioning system needs to ensure the cleanliness of the environment during installation and construction, while meeting the technical requirements of high precision and high reliability. At present, the installation and construction of dust-free environment air conditioning systems mainly adopt the following technical methods: First, manual measurement and drawing, which allows the construction personnel to obtain dimensional data through on-site measurement, and the designers manually draw construction drawings based on these data. This method relies heavily on the experience of workers. Secondly, traditional CAD software assisted design, CAD software is widely used in the drawing of construction drawings, which can improve the design accuracy to a certain extent, but it only provides two-dimensional plane design functions. Finally, the initial integrated BIM technology application, some existing engineering projects have begun to introduce building information modeling (BIM) technology in the design stage to create three-dimensional digital models to optimize the design effect. Although these technical means have improved the design and construction level of dust-free environment air conditioning systems to a certain extent, there are still significant deficiencies in the accuracy, efficiency and collaboration of installation and construction, and it is difficult to fully meet the needs of high-standard dust-free environments.
[0003] However, in the existing technology, manual measurement, CAD design, and the initial application of BIM technology cannot be dynamically adjusted during the construction phase, resulting in the design model not being consistent with the actual construction situation and large construction errors. Traditional construction methods rely heavily on manual operation and experience, and measurement errors and installation deviations occur from time to time, making it difficult to meet the strict requirements of dust-free environments for high-precision construction. In addition, due to the disconnection between design and actual construction, the operating performance of the air-conditioning system after installation is often unstable, affecting the cleanliness of the environment and the overall reliability of the system.
[0004] Secondly, during the construction process, existing methods such as manual measurement and rework adjustments are time-consuming and inefficient, which directly prolongs the construction period. Frequent rework is required when the design plan does not match the construction site, resulting in material waste and increased labor costs. In addition, there is a lack of effective construction progress management tools, the construction process is not smooth, the resource allocation efficiency is low, and the construction period delay is common. These problems directly lead to an increase in the construction cost of the dust-free environment air conditioning system and limit the effectiveness of the project.
[0005] Furthermore, in the current construction methods, the information between the design, construction and supervision teams is highly isolated, lacking a unified real-time sharing mechanism, resulting in low collaboration efficiency, which can easily lead to information misunderstandings and construction deviations. Quality supervision mainly relies on manual inspections, which are backward and difficult to detect problems in a timely manner, and cannot meet the needs of efficient quality control. These problems result in the final system results often failing to fully meet customers' high expectations for a dust-free environment, affecting the overall quality of the project and customer satisfaction.
[0006] Finally, the existing construction technology lacks virtualization support, and construction workers cannot rehearse operations in a virtual environment, which makes it difficult to identify and avoid risks in a timely manner during the construction process, and there is a lot of rework. In addition, the application of BIM technology is limited to the design stage, and it fails to effectively run through the entire construction process, and the integration with intelligent technology is low. Traditional construction methods rely more on manual experience, lack of intelligence, and are difficult to adapt to the complexity and high requirements of dust-free environment construction, further limiting the industry's intelligent development space. Summary of the invention
[0007] In view of the shortcomings of the prior art, the present invention provides a BIM-based air-conditioning system installation and construction method, which solves the problems of design inconsistency with reality, low construction efficiency, difficulty in collaboration and lack of intelligent support in the installation and construction of existing dust-free environment air-conditioning systems.
[0008] To achieve the above objectives, the present invention is implemented through the following technical solutions: A BIM-based air conditioning system installation construction method, comprising the following steps: S1. BIM initial modeling: Establish a three-dimensional digital model of the dust-free environment air conditioning system on the BIM platform; S2. Installation and debugging: Install and debug the data acquisition device; S3. Start and data import: Start the intelligent construction management system, import the BIM model and related parameter settings; S4, Task instruction execution: Apply virtual reality and augmented reality simulation operations according to the construction guidance documents generated by the intelligent construction management system, and execute construction activities after confirmation; S5. Inspection and maintenance: Regularly inspect and maintain data acquisition devices and other hardware facilities; S6. Safety protection: Implement safety protection measures during the construction process.
[0009] Preferably, in step S1, the BIM platform is used to collect and organize construction information, and the construction information includes but is not limited to managing building design, structural layout and electromechanical pipelines.
[0010] Preferably, in step S1, the three-dimensional digital model is established and managed by Revit and Navisworks software, which includes the spatial distribution inside the building and the directions of various pipeline lines.
[0011] Preferably, in the step S2, the data acquisition device is specifically a temperature and humidity sensing device, which is used to monitor the temperature and humidity parameters of the construction site and feed the data back to the BIM platform to dynamically update the three-dimensional digital model.
[0012] Preferably, in step S3, the intelligent construction management system interacts with multiple subsystems to manage and control the subsystems. The functions of the intelligent construction management system include but are not limited to project management functions, progress tracking and bill of materials generation.
[0013] Preferably, in the step S3, the intelligent construction management system and the three-dimensional digital model data of the BIM platform interact with each other through an open API interface, thereby achieving seamless connection of model updating, progress feedback and environmental parameter synchronization through data interaction.
[0014] Preferably, in the step S4, the construction guidance document includes: Component installation location: Mark the installation location of each component in detail so that construction personnel can accurately locate the installation location and reduce the risk of installation errors; Environmental condition requirements, which specify the range of environmental parameters required during construction, including but not limited to temperature, humidity and cleanliness requirements; Equipment operating status, which provides information on equipment commissioning and operating status, including the operating mode, air volume and filtration status of air-conditioning system equipment at different construction stages, to support testing and acceptance work during construction; Quality inspection standards, which list the quality inspection requirements and standards for each link and guide construction personnel to conduct construction quality inspections in accordance with the corresponding standards; Construction steps and operation instructions, which include specific construction steps and operation specifications to guide construction personnel to correctly install and debug the system according to the steps; Safety precautions, which list the safety measures that need to be taken during the construction process; Schedule and construction period nodes, which provide a timetable and key nodes for the construction progress, helping construction personnel complete construction tasks at each stage according to the planned schedule; A bill of materials, which includes the specific specifications and quantities of the materials.
[0015] Preferably, in the step S4, the construction instruction document needs to be imported into a virtual reality and augmented reality platform before it is officially used, so as to provide a virtual working environment for operators to check the construction content.
[0016] Preferably, in the step S5, regular inspection and maintenance require the preparation of spare components for quick replacement.
[0017] Preferably, in step S6, the safety protection measures include: Personal protective equipment: All construction workers shall be equipped with necessary personal protective equipment, including hard hats, protective gloves, protective glasses, dust masks, protective clothing and non-slip shoes; Dust-free environment protection: Since the construction is carried out in a dust-free environment, construction workers need to go through an air shower to remove surface dust before entering; Construction area isolation: Use isolation barriers to isolate the construction area from other work areas to prevent unrelated personnel from mistakenly entering the construction area and reduce the impact of dust and noise. At the same time, set up warning signs to indicate risk areas and prohibited areas during construction; Environmental monitoring: Real-time monitoring of temperature, humidity, and air quality environmental parameters at the construction site to ensure that the construction environment meets dust-free requirements, while monitoring the concentration of harmful gases and substances to avoid exceeding the standard and ensure the health and safety of construction workers; Power safety measures: During the installation and commissioning of power equipment, it is necessary to ensure that the power of all power equipment is turned off and locked to avoid accidental electric shock, and install leakage protection devices to ensure the safety of power equipment operation. In addition, cables, sockets and grounding devices must be checked regularly to prevent electrical failures; Equipment operation safety training: Provide equipment operation training to construction personnel to familiarize them with the safe operation specifications of various equipment used in construction, especially for tasks involving high-risk tasks such as aerial work and heavy equipment operation, which must be carried out in strict accordance with the operating procedures; Emergency plans and drills: formulate and publish emergency plans, including solutions for emergencies such as fire, leakage, power outage, and sudden illness, to ensure that construction workers can respond quickly in emergency situations. At the same time, conduct emergency drills regularly to familiarize construction workers with escape routes and emergency response procedures; Safety of aerial work: For construction workers working at heights, safety belts, safety ropes and protective nets are provided to prevent falling accidents. At the same time, the stability of aerial work equipment such as scaffolding and lifting platforms is regularly inspected and reinforced; Material management and channel maintenance: stack construction materials and tools reasonably, keep channels unobstructed, prevent tripping and slipping accidents caused by messy stacking, and use closed containers to store materials that may cause pollution to avoid affecting the clean environment; Daily safety inspections: The safety officer regularly inspects the construction site to check the implementation of various safety measures and promptly identify and rectify hidden dangers.
[0018] The present invention provides an air conditioning system installation and construction method based on BIM. It has the following beneficial effects: 1. The present invention constructs a three-dimensional digital model through the BIM platform, combines the data acquisition device to feedback the construction environment data in real time, dynamically adjusts the model content, ensures that the design is consistent with the actual construction, and generates accurate guidance documents by combining the VR / AR technology to simulate the construction in advance, identify potential risk points, and avoid rework problems, thereby improving the construction accuracy and reliability, reducing the phenomenon of design not being consistent with reality, and enhancing the stability of the system to meet the high standards of a dust-free environment.
[0019] 2. The present invention uses the BIM platform and intelligent construction management system throughout the entire construction process, reducing rework and adjustments caused by the disconnection between design and construction. Construction progress monitoring and real-time material lists optimize resource allocation and reduce waste. By simulating construction through VR / AR technology, construction personnel can familiarize themselves with the process and optimize operations in advance, further shortening the construction period. The overall solution reduces construction time and labor input, significantly reduces the total project cost, and improves construction efficiency and economic benefits.
[0020] 3. The present invention integrates design, construction and supervision information through the BIM platform, realizes real-time data sharing, eliminates the information asymmetry problem in traditional multi-party collaboration, and the intelligent construction management system dynamically feedbacks the construction progress. Combined with VR / AR technology, the construction process is more transparent and controllable. All parties involved in the construction can monitor and adjust key links in real time to ensure that the construction quality always meets high standards and fully meets the customer's expected results, while improving the reliability of project delivery.
[0021] 4. The present invention uses VR technology to rehearse the construction process in a virtual scene, so that construction personnel can identify risks in advance and optimize the plan; combined with AR technology during construction, the three-dimensional model is superimposed on the site to provide intuitive operation guidance and accurately complete the installation. The in-depth application of VR / AR reduces construction deviations and improves construction efficiency, providing a successful case of intelligent solutions for dust-free environment construction. This technological breakthrough provides replicable reference experience for the implementation of similar projects and promotes the further development of intelligent construction in the industry. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a schematic diagram of the construction logic of the present invention; Figure 2 The figure is a flow chart of the method steps of the present invention. DETAILED DESCRIPTION
[0023] The following will be combined with the drawings in the specification of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0024] Embodiment 1: Technical solution of the present invention Please see attached Figure 1 -Attached Figure 2 The embodiment of the present invention provides a BIM-based air conditioning system installation and construction method, comprising the following steps: S1. BIM initial modeling: Establish a three-dimensional digital model of the dust-free environment air conditioning system on the BIM platform; S2. Installation and debugging: Install and debug the data acquisition device; S3. Start and data import: Start the intelligent construction management system, import the BIM model and related parameter settings; S4, Task instruction execution: Apply virtual reality and augmented reality simulation operations according to the construction guidance documents generated by the intelligent construction management system, and execute construction activities after confirmation; S5. Inspection and maintenance: Regularly inspect and maintain data acquisition devices and other hardware facilities; S6. Safety protection: Implement safety protection measures during the construction process; In step S1, the BIM platform is used to collect and organize construction information, including but not limited to managing building design, structural layout, and mechanical and electrical pipelines; In step S1, the three-dimensional digital model is established and managed through Revit and Navisworks software, which includes the spatial distribution inside the building and the directions of various pipeline lines; In step S2, the data acquisition device is specifically a temperature and humidity sensing device, which is used to monitor the temperature and humidity parameters of the construction site and feed the data back to the BIM platform to dynamically update the three-dimensional digital model; In step S3, the intelligent construction management system interacts with multiple subsystems to manage and control the subsystems. The functions of the intelligent construction management system include but are not limited to project management functions, progress tracking, and bill of materials generation; In step S3, the intelligent construction management system and the 3D digital model data of the BIM platform interact with each other through an open API interface, which enables seamless connection of model updates, progress feedback, and environmental parameter synchronization through data interaction; In step S4, the construction guidance documents include: Component installation location: Mark the installation location of each component in detail so that construction personnel can accurately locate the installation location and reduce the risk of installation errors; Environmental condition requirements, which specify the range of environmental parameters required during construction, including but not limited to temperature, humidity and cleanliness requirements; Equipment operating status, which provides information on equipment commissioning and operating status, including the operating mode, air volume and filtration status of air-conditioning system equipment at different construction stages, to support testing and acceptance work during construction; Quality inspection standards, which list the quality inspection requirements and standards for each link and guide construction personnel to conduct construction quality inspections in accordance with the corresponding standards; Construction steps and operation instructions, which include specific construction steps and operation specifications to guide construction personnel to correctly install and debug the system according to the steps; Safety precautions, which list the safety measures that need to be taken during the construction process; Schedule and construction period nodes, which provide a timetable and key nodes for the construction progress, helping construction personnel complete construction tasks at each stage according to the planned schedule; Bill of materials, which includes the specific specifications and quantities of the materials; In step S4, the construction guidance document needs to be imported into the virtual reality and augmented reality platform before it is officially used, so as to provide the operators with a virtual working environment to check the construction content; In step S5, regular inspection and maintenance require the preparation of spare components for quick replacement; In step S6, the safety protection measures include: Personal protective equipment: All construction workers shall be equipped with necessary personal protective equipment, including hard hats, protective gloves, protective glasses, dust masks, protective clothing and non-slip shoes; Dust-free environment protection: Since the construction is carried out in a dust-free environment, construction workers need to go through an air shower to remove surface dust before entering; Construction area isolation: Use isolation barriers to isolate the construction area from other work areas to prevent unrelated personnel from mistakenly entering the construction area and reduce the impact of dust and noise. At the same time, set up warning signs to indicate risk areas and prohibited areas during construction; Environmental monitoring: Real-time monitoring of temperature, humidity, and air quality environmental parameters at the construction site to ensure that the construction environment meets dust-free requirements, while monitoring the concentration of harmful gases and substances to avoid exceeding the standard and ensure the health and safety of construction workers; Power safety measures: During the installation and commissioning of power equipment, it is necessary to ensure that the power of all power equipment is turned off and locked to avoid accidental electric shock, and install leakage protection devices to ensure the safety of power equipment operation. In addition, cables, sockets and grounding devices must be checked regularly to prevent electrical failures; Equipment operation safety training: Provide equipment operation training to construction personnel to familiarize them with the safe operation specifications of various equipment used in construction, especially for tasks involving high-risk tasks such as aerial work and heavy equipment operation, which must be carried out in strict accordance with the operating procedures; Emergency plans and drills: formulate and publish emergency plans, including solutions for emergencies such as fire, leakage, power outage, and sudden illness, to ensure that construction workers can respond quickly in emergency situations. At the same time, conduct emergency drills regularly to familiarize construction workers with escape routes and emergency response procedures; Safety of aerial work: For construction workers working at heights, safety belts, safety ropes and protective nets are provided to prevent falling accidents. At the same time, the stability of aerial work equipment such as scaffolding and lifting platforms is regularly inspected and reinforced; Material management and channel maintenance: stack construction materials and tools reasonably, keep channels unobstructed, prevent tripping and slipping accidents caused by messy stacking, and use closed containers to store materials that may cause pollution to avoid affecting the clean environment; Daily safety inspections: The safety officer regularly inspects the construction site to check the implementation of various safety measures and promptly identify and rectify hidden dangers.
[0025] Specifically, in step S1, the three-dimensional digital model of the dust-free environment air-conditioning system is established on the BIM platform, which is the basic step of this method; the construction information is collected and sorted through the BIM platform, including the specific data of the building design, structural layout and mechanical and electrical pipelines; the professional software Revit and Navisworks are used to combine the spatial distribution inside the actual building and the direction of various pipeline lines to build an accurate three-dimensional digital model; this modeling process can clearly present the positional relationship of each component and provide an intuitive reference basis for subsequent construction; at the same time, the BIM platform supports multi-party collaboration and data sharing, and can update and optimize the model in real time, improve the matching degree between the design and the actual construction, and reduce the risk of rework caused by inaccurate design; this modeling method ensures the efficiency and accuracy of the construction preparation stage, and lays a solid foundation for subsequent steps; In step S2, installing and debugging the data acquisition device is an important part of dynamically monitoring the construction environment. The data acquisition device mainly uses high-precision temperature and humidity sensing equipment to monitor the temperature and humidity parameters of the construction site in real time. These devices are connected to the BIM platform to dynamically feed back the collected environmental data to the three-dimensional digital model, thereby updating the model content in real time, so that each step of the construction process can be adjusted according to the current environmental conditions. This process not only ensures the accuracy of environmental data, but also makes the construction plan more flexible and adaptable. Through dynamic data updates, construction personnel can quickly determine whether the current construction conditions meet the dust-free environment standards, thereby effectively avoiding construction problems caused by environmental parameter deviations. In step S3, start Starting the intelligent construction management system and importing BIM models and related parameter settings are important steps to achieve intelligent management; the intelligent construction management system comprehensively controls all aspects of the project through interaction with multiple subsystems; its functions include project management, progress tracking and bill of materials generation, and can monitor construction progress and material usage in real time; through the open API interface, the intelligent construction management system and the BIM platform achieve seamless data interaction, and model data updates, construction progress feedback and environmental parameter synchronization can all be completed in real time in the system; this intelligent management method significantly improves construction efficiency, reduces the need for manual intervention, and ensures a high degree of consistency in information during the construction process, providing strong support for precise construction; In step S4, according to the construction guidance document generated by the intelligent construction management system, the construction personnel first perform simulation operations on the virtual reality and augmented reality (VR / AR) platform; the construction guidance document contains the installation location of the components, environmental conditions, equipment operating status, quality inspection standards, construction steps and operation instructions, safety protection measures, schedule and bill of materials information; these details provide a comprehensive reference for the construction personnel; on the VR / AR platform, the construction personnel can conduct virtual operation drills in advance, identify possible construction risks and optimize the construction process; after confirmation, the construction personnel will carry out actual construction operations according to the guidance document; this task instruction execution method reduces the rework caused by problems found in the actual construction, and improves the accuracy of the construction through simulation verification; In step S5, regular inspection and maintenance of data acquisition devices and other hardware facilities are key links to ensure the continuity and accuracy of the construction process. During the construction process, since the data acquisition devices are exposed to the construction environment for a long time, their performance may be affected by external factors, so they need to be calibrated and functionally inspected regularly. At the same time, necessary spare components are prepared for quick replacement to ensure the normal operation of the monitoring equipment. This maintenance work enables the construction environment data to be continuously and stably fed back to the BIM platform, ensuring that each step of the construction process meets the requirements of a dust-free environment. In addition, this real-time maintenance mechanism greatly reduces the risk of construction interruption due to equipment failure, and improves construction efficiency and project quality. In step S6, implementing comprehensive safety protection measures during the construction process is an important guarantee for ensuring the safety of construction workers and the smooth progress of the project; construction workers are required to wear personal protective equipment such as safety helmets, protective gloves, protective glasses, dust masks, protective clothing and non-slip shoes; dust is removed through an air shower before construction to ensure that the dust-free environment standard is not damaged; the construction area is separated from other areas by isolation barriers to prevent unauthorized entry, and warning signs are set up in the area to indicate potential risks; in addition, the temperature, humidity and air quality parameters of the construction area are monitored in real time by environmental monitoring equipment to ensure that the construction conditions meet the standards; for power safety, it is required to turn off the power before construction and install a leakage protection device to avoid electrical accidents; workers working at heights are equipped with safety belts and protective nets to prevent falling; emergency drills are organized regularly during the construction process to familiarize construction workers with the emergency handling process; and a series of safety protection measures are taken to minimize safety hazards during construction.
[0026] Example 2: Installation and construction method of dust-free environment air conditioning system based on CAD design step: S1. CAD design: Use CAD software to design two-dimensional plane construction drawings, mainly relying on manual data input and manual verification; S2. On-site measurement and recording: Construction personnel conduct on-site measurements, record the data on paper, and manually input them into the CAD drawing; S3. Construction operation: Install according to the design drawings and manually calibrate the installation position; S4. Manual inspection and adjustment: Perform quality inspection based on the actual installation results and make manual adjustments if any problems are found; S5. Equipment maintenance: Regular manual inspection after equipment commissioning is completed, without using data acquisition devices and intelligent management systems.
[0027] Summarize: In this embodiment, the construction drawings are only two-dimensional, and the design is often inconsistent with the actual situation, which makes adjustments difficult, resulting in a lot of rework and a long construction period. The lack of dynamic adjustment and accurate monitoring makes the stability of the construction system poor.
[0028] Example 3: Installation and construction method of dust-free environment air conditioning system based on on-site manual measurement step: S1. Manual measurement: Construction personnel directly measure manually on site and record data section by section; S2. Component installation and adjustment: Manually install components according to the measurement data, and repeatedly debug during the process; S3. Manual data recording: During the installation process, the construction personnel manually recorded the data for reference; S4. Progress management: Using manual methods to track construction progress and lacking accurate project management tools; S5. Inspection and maintenance: After the construction is completed, regular manual inspection and maintenance are carried out.
[0029] Summarize: Due to reliance on manual measurement and recording, construction accuracy is difficult to ensure, data accuracy is low, and adjustments are cumbersome. The lack of information support and precise project management tools leads to low construction efficiency and extended construction periods.
[0030] Example 4: Traditional single-department collaboration dust-free environment air conditioning system installation and construction method step: S1. Separate design by department: The design department completes the drawing design, and the construction department only constructs according to the plan; S2. On-site manual measurement and construction: Construction personnel manually measure on-site and install step by step according to the two-dimensional design drawings; S3. Manual communication between departments: The design department and the construction department use manual communication to provide feedback on issues, but the information is not timely; S4. Quality supervision: Quality supervision needs to manually check the construction quality and lacks real-time progress feedback; S5. Regular equipment maintenance: After the equipment is installed, construction personnel will conduct regular manual inspection and maintenance.
[0031] Summarize: Due to poor communication between departments, data cannot be shared, and information asymmetry, construction deviations are easily caused. The quality supervision process is cumbersome and lacks real-time monitoring, which affects the quality of the project and the progress of the project.
[0032] Example 5: Installation and construction method of dust-free environment air conditioning system with limited BIM technology application step: S1. BIM preliminary modeling: Use BIM software to create a three-dimensional model during the design phase. This is limited to the initial design and should not be used in the construction process. S2. Generation of 2D construction drawings: Generate 2D construction drawings from BIM models for construction use; S3. On-site construction adjustment: If the design does not match the actual situation during construction, the on-site personnel will make manual adjustments; S4. Manual construction management: Construction progress relies on manual tracking and recording, lacking automated management; S5. On-site manual maintenance: After the equipment is installed, on-site personnel are required to perform manual inspection and maintenance.
[0033] Summarize: Although BIM technology was applied, it was limited to the design stage and not throughout the entire construction process, resulting in a disconnect between the model and actual construction data. Information could not be updated dynamically, and a complete construction management process could not be formed, resulting in low project controllability and reference value.
[0034] Summary: These five embodiments demonstrate the differences between different technical solutions, further highlighting the advantages of the present invention: Accuracy and reliability: In the second, third and fourth embodiments, there is a phenomenon that the design is inconsistent with the construction, and it is difficult to ensure the accuracy of the construction. The present invention achieves a high degree of matching between the construction plan and the actual situation through real-time data interaction between the BIM platform and the data acquisition equipment, ensuring the accuracy and stability of the construction.
[0035] Project cycle and cost: The manual measurement and data recording in the second and third embodiments prolong the project cycle and consume a lot of manpower and material resources. The present invention uses an intelligent construction management system to achieve automatic data tracking and progress management, greatly shortening the construction cycle and reducing project costs.
[0036] Multi-party collaboration and quality supervision: The single-department collaboration model of Example 4 has information asymmetry and is difficult to meet the needs of project quality supervision. The present invention enhances collaboration among all parties and improves quality management efficiency through data sharing and real-time updating of the intelligent construction management system.
[0037] Industry promotion and technical reference: The preliminary BIM technology application in Example 5 has not formed a complete construction process and lacks reference technical methods. The present invention integrates BIM technology throughout the entire design and construction process, forming a complete technical system, providing a reference case for similar projects in the future, and has promotion value.
[0038] In general, Example 1 of the present invention demonstrates significant technological progress, not only having significant advantages in accuracy, efficiency and cost control, but also having important innovation and application value in multi-party collaboration and industry promotion.
[0039] Test experiment: Experimental scenario: Simulate the construction of a small dust-free environment air conditioning system, including a 100 square meter clean area, including the installation and commissioning of 5 pipes, 10 filters and 1 air conditioning host.
[0040] Test items: Construction accuracy test: measure the deviation between the component installation position and the design value; Construction cycle test: statistics on the total time from design to construction completion; Resource consumption test: record the labor, material and rework costs required during the construction process; Collaboration efficiency test: statistics on information transmission and response time between design, construction and supervision; Construction quality testing: Evaluate whether the operating parameters of the final system meet the standards.
[0041] Test process overview: Under the same construction conditions (same construction site, equipment, and personnel), different implementation examples are used to perform construction operations; Collect relevant data during the construction process and compare the performance indicators of various implementation examples.
[0042] Actual test process: a. Construction accuracy test: Objective: To test the deviation of the installation position of pipes, filters and air conditioners from the design value; Process: Use a laser distance meter to measure the installation position deviation; Calculate the deviation value and record the number of components with a deviation within 5 mm; Indicator: The proportion of components with a deviation within 5 mm; b. Construction cycle test: Objective: To calculate the total time from design to completion of construction; process: Record the key node time of each implementation example; Count the total time and calculate the time for each stage; Metrics: Total construction time; c. Resource consumption test: Objective: To measure the manpower, materials, number of reworks and their costs during the construction process; Process: Record the number of people and hours required for construction; Count the actual amount of materials consumed and the material loss from rework; Calculate total cost; Indicators: Total cost; d. Collaboration efficiency test: Objective: To evaluate the efficiency of information transfer between design, construction and supervision teams; process: Record the response time for each information transfer between teams; Statistics of total delivery times and average response time; Metrics: Average response time; e. Construction quality test: Objective: To verify that the operating performance of the installed system meets the dust-free environment standards; process: Run the air conditioning system and record temperature, humidity and cleanliness data; Compare the actual value with the target value and calculate the proportion of parameters that meet the standards; Indicators: parameter qualification rate; Test data: Test items Embodiment 1 Embodiment 2 Embodiment 3 Embodiment 4 Embodiment 5 Construction accuracy / % 98 75 70 78 85 Construction cycle / h 50 120 150 100 90 Resource consumption / yuan 80,000 110,000 120,000 105,000 95,000 Collaboration efficiency / min 5 20 25 15 12 Construction quality / % 99 85 82 87 90 Test results: In terms of construction accuracy, the first embodiment realizes real-time adjustment through the BIM platform and the intelligent construction management system, and the installation deviation is minimal; the second and third embodiments have low construction accuracy due to large manual input and measurement errors.
[0043] In terms of construction period, the first embodiment uses the intelligent construction management system to accelerate the construction progress, which only takes 50 hours; the second and third embodiments take the most time due to manual measurement and adjustment.
[0044] In terms of resource consumption, the first embodiment reduces rework and material waste, and has the lowest total cost; the third embodiment has the highest cost due to frequent rework due to manual adjustment.
[0045] In terms of collaboration efficiency, the first embodiment significantly improves collaboration efficiency through real-time data sharing; the single-department collaboration in the fourth embodiment results in a long response time.
[0046] In terms of construction quality, the first embodiment has the highest parameter qualification rate, which reflects the high stability and high reliability of the system; the other embodiments have low construction accuracy or insufficient collaboration, which affects the operating performance of the system.
[0047] Summarize: Technical advantages of the present invention (Example 1): Through the combination of BIM platform, data acquisition equipment and intelligent construction management system, the construction accuracy, collaboration efficiency and system performance have been significantly improved.
[0048] Significantly shorten the construction period and reduce resource consumption.
[0049] Other example limitations: Embodiments 2 and 3 rely too much on manual operation, resulting in low accuracy and efficiency; Embodiment 4 has insufficient collaboration, which affects the construction progress and quality; Embodiment 5 has initially applied BIM technology, but has not formed a complete management process.
[0050] Overall test results: The present invention is superior to other embodiments in terms of five core indicators: construction accuracy, cycle, resource consumption, collaboration efficiency and construction quality, which fully demonstrates its innovation and industry value. Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A BIM-based air conditioning system installation and construction method, characterized in that: The following steps are involved: S1. BIM initial modeling: Establish a three-dimensional digital model of the dust-free environment air conditioning system on the BIM platform; S2. Installation and debugging: Install and debug the data acquisition device; S3. Start and data import: Start the intelligent construction management system, import the BIM model and related parameter settings; S4, Task instruction execution: Apply virtual reality and augmented reality simulation operations according to the construction guidance documents generated by the intelligent construction management system, and execute construction activities after confirmation; S5. Inspection and maintenance: Regularly inspect and maintain data acquisition devices and other hardware facilities; S6. Safety protection: Implement safety protection measures during the construction process.
2. The BIM-based air conditioning system installation and construction method according to claim 1, characterized in that: In the step S1, the BIM platform is used to collect and organize construction information, which includes but is not limited to managing building design, structural layout, and electromechanical pipelines.
3. The BIM-based air conditioning system installation and construction method according to claim 1, characterized in that: In the step S1, the three-dimensional digital model is established and managed by Revit and Navisworks software, which includes the spatial distribution inside the building and the directions of various pipeline lines.
4. The BIM-based air conditioning system installation and construction method according to claim 1, characterized in that: In the step S2, the data acquisition device is specifically a temperature and humidity sensing device, which is used to monitor the temperature and humidity parameters of the construction site and feed the data back to the BIM platform to dynamically update the three-dimensional digital model.
5. The BIM-based air conditioning system installation and construction method according to claim 1, characterized in that: In the step S3, the intelligent construction management system interacts with multiple subsystems to manage and control the subsystems. The functions of the intelligent construction management system include but are not limited to project management, progress tracking and bill of materials generation.
6. The BIM-based air conditioning system installation and construction method according to claim 1, characterized in that: In the step S3, the intelligent construction management system and the three-dimensional digital model data of the BIM platform interact with each other through an open API interface, thereby achieving seamless connection of model updating, progress feedback and environmental parameter synchronization through data interaction.
7. The BIM-based air conditioning system installation and construction method according to claim 1, characterized in that: In the step S4, the construction guidance document includes: Component installation location: Mark the installation location of each component in detail so that construction personnel can accurately locate the installation location and reduce the risk of installation errors; Environmental condition requirements, which specify the range of environmental parameters required for construction, including but not limited to temperature, humidity and cleanliness requirements; Equipment operating status, which provides information on equipment commissioning and operating status, including the operating mode, air volume, and filtration status of air conditioning system equipment at different construction stages, to support testing and acceptance work during construction; Quality inspection standards, which list the quality inspection requirements and standards for each link and guide construction personnel to conduct construction quality inspections in accordance with the corresponding standards; Construction steps and operation instructions, which include specific construction steps and operation specifications, to guide construction personnel to correctly install and debug the system according to the steps; Safety precautions, which list the safety measures that need to be taken during the construction process; Schedule and construction period nodes, which provide a timetable and key nodes for the construction progress, helping construction personnel complete construction tasks at each stage according to the planned schedule; A bill of materials, which includes the specific specifications and quantities of the materials.
8. The BIM-based air conditioning system installation and construction method according to claim 1, characterized in that: In the step S4, the construction instruction document needs to be imported into the virtual reality and augmented reality platform before it is officially used, so as to provide a virtual working environment for operators to check the construction content.
9. The BIM-based air conditioning system installation and construction method according to claim 1, characterized in that: In the step S5, regular inspection and maintenance require the preparation of spare components for quick replacement.
10. The BIM-based air conditioning system installation and construction method according to claim 1, characterized in that: In step S6, the safety protection measures include: Personal protective equipment: All construction workers shall be equipped with necessary personal protective equipment, including hard hats, protective gloves, protective glasses, dust masks, protective clothing and non-slip shoes; Dust-free environment protection: Since the construction is carried out in a dust-free environment, construction workers need to go through an air shower to remove surface dust before entering; Isolation of construction areas: Use isolation barriers to isolate the construction area from other work areas to prevent unauthorized personnel from mistakenly entering the construction area and reduce the impact of dust and noise. At the same time, set up warning signs to indicate risk areas and prohibited areas during construction; Environmental monitoring: Real-time monitoring of temperature, humidity, and air quality parameters at the construction site to ensure that the construction environment meets dust-free requirements. At the same time, the concentration of harmful gases and substances is monitored to avoid exceeding the standard and ensure the health and safety of construction workers. Power safety measures: During the installation and commissioning of power equipment, it is necessary to ensure that the power of all power equipment is turned off and locked to avoid accidental electric shock, and install leakage protection devices to ensure the safety of power equipment operation. In addition, cables, sockets and grounding devices must be checked regularly to prevent electrical failures; Equipment operation safety training: Provide equipment operation training to construction personnel to familiarize them with the safe operation specifications of various equipment used in construction, especially for tasks involving high-risk tasks such as aerial work and heavy equipment operation, which must be carried out in strict accordance with the operating procedures; Emergency plans and drills: formulate and publish emergency plans, including solutions for emergencies such as fire, leakage, power outage, and sudden illness, to ensure that construction workers can respond quickly in emergency situations. At the same time, conduct emergency drills regularly to familiarize construction workers with escape routes and emergency response procedures; Safety of aerial work: For construction workers working at heights, safety belts, safety ropes and protective nets are provided to prevent falling accidents. At the same time, the stability of aerial work equipment such as scaffolding and lifting platforms is regularly inspected and reinforced; Material management and channel maintenance: stack construction materials and tools reasonably, keep the channels unobstructed, prevent tripping and slipping accidents caused by messy stacking, and use closed containers to store materials that may cause pollution to avoid affecting the clean environment; Daily safety inspections: The safety officer regularly inspects the construction site to check the implementation of various safety measures and promptly identify and rectify hidden dangers.