Super high-rise tube well pipeline assembly type rapid construction method based on BIM (Building Information Modeling) technology

Parameterized modeling and integrated construction of ultra-high-rise pipe well pipelines through BIM technology, solving problems such as tight construction periods and few construction sites for ultra-high-rise building electromechanical pipe well pipelines, achieving efficient and accurate rapid construction results.

CN119740292APending Publication Date: 2025-04-01CHINA MCC17 GRP CO LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411802964.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-10
Publication Date
2025-04-01

AI Technical Summary

Technical Problem

The installation of electromechanical and pipe well pipelines in super high-rise buildings has difficulties such as tight construction periods, many cross-operations, large coordination volumes, and few construction sites. The existing overall assembly method is difficult to effectively solve these problems.

Method used

The prefabricated rapid construction method of ultra-high-rise pipe well pipelines based on BIM technology is adopted, and parameterized modeling and integrated construction are carried out through BIM software to realize the modular construction and assembly construction of mechatronic pipelines.

Benefits of technology

It reduces the difficulty of electromechanical installation of ultra-high-rise pipe wells, improves the accuracy and efficiency of complex electromechanical pipeline construction, and realizes precise control and rapid construction of the entire design and construction process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119740292A_ABST
    Figure CN119740292A_ABST
Patent Text Reader

Abstract

The invention relates to the field of electromechanical engineering construction technology application, in particular to a super high-rise tube well pipeline assembly type rapid construction method based on a BIM technology. Modularization modeling, assembly construction and rapid building of the super high-rise tube well electromechanical pipeline are achieved through BIM parameterization software, the method can be suitable for places where the site is small and installation is inconvenient, the construction efficiency is improved, the purpose of accurate control over the whole process of design and building can be achieved, working procedures are interspersed, and the construction efficiency is improved. And the construction efficiency of the super high-rise electromechanical pipeline is greatly improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the application field of electromechanical engineering construction technology, and in particular to a method for rapid assembly construction of super-high-rise pipe wells and pipelines based on BIM technology. Background Art

[0002] Prefabricated construction in my country's construction industry is in a stage of rapid development. Electromechanical assembly technology is gradually being applied to different projects in various forms due to its advantages of standardization, refinement, and pre-processing. At present, electromechanical assembly technology can be divided into two types, namely split assembly and integral assembly. Split assembly is divided into large split assembly and small split assembly with on-site splicing of components. The use of integral assembly is more demanding and is suitable for locations with small sites, moderate equipment, relatively regular and convenient transportation. Electromechanical installation projects are limited by the progress of the main construction, and have difficulties such as tight construction period, many cross-operations, large coordination, and few construction sites. Integrated assembled electromechanical will solve these problems well, especially for super high-rise buildings. Summary of the invention

[0003] The purpose of the present invention is to provide a method for the rapid assembly construction of super high-rise pipe wells based on BIM technology, using BIM related software to achieve parametric modeling and integrated construction of electromechanical pipelines, reduce the difficulty of electromechanical installation of super high-rise pipe wells, and improve the construction accuracy and efficiency of complex electromechanical pipelines. The construction method includes the following steps:

[0004] Step 1: Create the initial model of the main body of the project, electromechanical, etc. according to the design drawings, pipeline comprehensive layout rules and other modeling standards, integrate the completed models, and optimize and determine the pipeline comprehensive construction plan;

[0005] Step 2: According to the contents described in step 1, design the bracket, structural beam and slab reservation according to the deepened BIM pipe model, and generate the final material list including pipelines, bracket steel and other auxiliary materials;

[0006] Step 3: According to the contents described in step 2, the determined integrated electromechanical pipe well is subjected to stress analysis to determine the position and number of hanging points, and the integrated processing and production of civil engineering and electromechanical pipelines are carried out in the factory according to the final electromechanical pipeline plan;

[0007] Step 4: According to the contents described in step 3, after the construction site is ready for construction, the integrated electromechanical pipe well unit is transported to the range of the lifting equipment and hoisted to the designated construction location. After temporary fixation and accurate detailed positioning, it is formally fixed and poured with self-compacting concrete;

[0008] Step 5: After the construction of the pipe well electromechanical module unit is completed, it is connected to the horizontal main pipe and branch pipe on the same floor to close the water supply to achieve rapid construction;

[0009] Furthermore, in step 1, BIM software is used to construct and integrate subsystem models, perform collision detection on mechanical and electrical pipelines and structures, adjust the comprehensive layout model of mechanical and electrical pipelines in the pipe well, optimize the design model layout, and determine the precise positioning of each pipeline in the plane and space in the pipe well;

[0010] Furthermore, in step 2, the brackets are arranged according to the final pipe layout, and the arrangement should meet the relevant requirements of the specifications; the structural beams and slabs around the pipe well are optimized to form tongues and grooves to facilitate overlap with the prefabricated slabs of the integrated unit module, and are cast into a whole by reserving dowels; the electromechanical pipeline model is planned according to the material list at a height of 2 floors to facilitate cutting and integrated assembly, and the pipe fittings of each system in the pipe well are numbered and the final material list and plane details are exported to guide subsequent construction; finite element analysis software is used to perform force analysis on the connection position between the integrated unit and the main structure. During the modeling process, the steel plate loaded on the top surface is coupled to a pre-set reference point, and the vertical displacement (using displacement loading) can be directly applied to the reference point, and then the displacement of the loaded steel plate in the x, y, and z directions at the bottom of the model and the displacement of the reference point in the x and z directions are constrained respectively. The interface between new and old concrete is simulated by nonlinear three-dimensional spring elements. The normal spring element constitutive model perpendicular to the bonding surface adopts the normal stress-bond slip model. The transverse tangent spring element constitutive model of the bonding surface (perpendicular to the loading direction) takes a large number of the same order of magnitude as the elastic modulus of concrete. The spring element constitutive model of the longitudinal tangent spring element (along the loading direction) of the bonding surface is uniformly adopted (K1s, 0 <s≤Se;K2(S-Se)+te,Se<s≤Su;K3(S-Su)+tu,Su<s≤Sr;tr,S> Sr) and the elastic-brittle bond-slip relationship of the specimen are determined;

[0011] Furthermore, in step 3, a 3D solid model of the integrated hoisting unit is established by using 3D modeling software, and then the center of gravity of the hoisting unit is obtained by querying the software; the number and position of the hoisting points are determined by factors such as the lifting capacity of the hoisting equipment, the number of hoists, the influence of the setting of the hoisting points on the internal force and deformation of the structural members, and the stress characteristics of the structure itself, and the optimal number of hoisting points and the most reasonable hoisting point positions that should be used when the integrated hoisting unit is hoisted as a whole are analyzed, and the feasibility of the hoisting scheme is verified; the prefabrication and assembly of the integrated electromechanical pipe well is carried out in the factory, and the upper and lower structural floor slabs are first prefabricated by the tire frame through the model scheme, detailed drawings and blanking lists, and the reserved casing positions of the prefabricated panels are placed strictly according to the scheme, and concrete pouring can be carried out only after acceptance; after the concrete strength reaches the standard, the longitudinal filling wall is first built and plastered, and then the pipeline is installed, and finally the transverse walls on both sides are installed;

[0012] Furthermore, after the integrated electromechanical pipe well unit is hoisted to the designated position in step 4, the prefabricated structural plate of the integrated unit is aligned with the tongue and groove of the upper and lower structural beams, and the integrated unit is temporarily fixed to the surrounding main structure using materials such as channel steel, and then the verticality and flatness of the integrated unit are checked. It can only be formally fixed after the accuracy meets the requirements of the specification, and finally, after the prefabricated plate and the reserved dowels of the structural beam are tied and accepted, high-strength self-compacting concrete is poured around the pipe well structural plate;

[0013] Furthermore, the installation of pipelines such as horizontal main pipes and branch pipes in step 5 can achieve the water-tightening phenomenon of the floor, and can realize the interlacing of processes, so as to achieve rapid construction; the riser of the pipe well electromechanical pipeline module should be connected to the horizontal pipeline of the floor in a relatively spacious position to avoid affecting the net height of the floor, and also reduce the construction difficulty of the pipeline connection;

[0014] The beneficial effects of the present invention are:

[0015] The present invention realizes modular modeling, assembly construction and rapid construction of super-high-rise pipe shaft electromechanical pipelines by utilizing BIM parametric software. It is not only applicable to places with small sites and inconvenient installation to improve construction efficiency, but also can achieve the purpose of precise control of the entire process of design and construction, realize process interlacing, and greatly improve the construction efficiency of super-high-rise electromechanical pipelines. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 This is a flow chart of a method for rapid assembly construction of super high-rise pipe wells and pipelines based on BIM technology. DETAILED DESCRIPTION

[0017] A method for rapid assembly construction of super high-rise pipe wells and pipelines based on BIM technology, comprising the following steps:

[0018] Step 1: Create the initial model of the main body of the project, electromechanical, etc. according to the design drawings, pipeline comprehensive layout rules and other modeling standards, integrate the completed models, and optimize and determine the pipeline comprehensive construction plan;

[0019] Step 2: According to the contents described in step 1, design the bracket, structural beam and slab reservation according to the deepened BIM pipe model, and generate the final material list including pipelines, bracket steel and other auxiliary materials;

[0020] Step 3: According to the contents described in step 2, the determined integrated electromechanical pipe well is subjected to stress analysis to determine the position and number of hanging points, and the integrated processing and production of civil engineering and electromechanical pipelines are carried out in the factory according to the final electromechanical pipeline plan;

[0021] Step 4: According to the contents described in step 3, after the construction site is ready for construction, the integrated electromechanical pipe well unit is transported to the range of the lifting equipment and hoisted to the designated construction location. After temporary fixation and accurate detailed positioning, it is formally fixed and poured with self-compacting concrete;

[0022] Step 5: After the construction of the pipe well electromechanical module unit is completed, it is connected to the horizontal main pipe and branch pipe on the same floor to close the water supply to achieve rapid construction;

[0023] Furthermore, in step 1, BIM software is used to construct and integrate subsystem models, perform collision detection on mechanical and electrical pipelines and structures, adjust the comprehensive layout model of mechanical and electrical pipelines in the pipe well, optimize the design model layout, and determine the precise positioning of each pipeline in the plane and space in the pipe well;

[0024] Furthermore, in step 2, the brackets are arranged according to the final pipe layout, and the arrangement should meet the relevant requirements of the specifications; the structural beams and slabs around the pipe well are optimized to form tongues and grooves to facilitate overlap with the prefabricated slabs of the integrated unit module, and are cast into a whole by reserving dowels; the electromechanical pipeline model is planned according to the material list at a height of 2 floors to facilitate cutting and integrated assembly, and the pipe fittings of each system in the pipe well are numbered and the final material list and plane details are exported to guide subsequent construction; finite element analysis software is used to perform force analysis on the connection position between the integrated unit and the main structure. During the modeling process, the steel plate loaded on the top surface is coupled to a pre-set reference point, and the vertical displacement (using displacement loading) can be directly applied to the reference point, and then the displacement of the loaded steel plate in the x, y, and z directions at the bottom of the model and the displacement of the reference point in the x and z directions are constrained respectively. The interface between new and old concrete is simulated by nonlinear three-dimensional spring elements. The normal spring element constitutive model perpendicular to the bonding surface adopts the normal stress-bond slip model. The transverse tangent spring element constitutive model of the bonding surface (perpendicular to the loading direction) takes a large number of the same order of magnitude as the elastic modulus of concrete. The spring element constitutive model of the longitudinal tangent spring element (along the loading direction) of the bonding surface is uniformly adopted (K1s, 0 <s≤Se;K2(S-Se)+te,Se<s≤Su;K3(S-Su)+tu,Su<s≤Sr;tr,S> Sr) and the elastic-brittle bond-slip relationship of the specimen are determined;

[0025] Furthermore, in step 3, a 3D solid model of the integrated hoisting unit is established by using 3D modeling software, and then the center of gravity of the hoisting unit is obtained by querying the software; the number and position of the hoisting points are determined by factors such as the lifting capacity of the hoisting equipment, the number of hoists, the influence of the setting of the hoisting points on the internal force and deformation of the structural members, and the stress characteristics of the structure itself, and the optimal number of hoisting points and the most reasonable hoisting point positions that should be used when the integrated hoisting unit is hoisted as a whole are analyzed, and the feasibility of the hoisting scheme is verified; the prefabrication and assembly of the integrated electromechanical pipe well is carried out in the factory, and the upper and lower structural floor slabs are first prefabricated by the tire frame through the model scheme, detailed drawings and blanking lists, and the reserved casing positions of the prefabricated panels are placed strictly according to the scheme, and concrete pouring can be carried out only after acceptance; after the concrete strength reaches the standard, the longitudinal filling wall is first built and plastered, and then the pipeline is installed, and finally the transverse walls on both sides are installed;

[0026] Furthermore, after the integrated electromechanical pipe well unit is hoisted to the designated position in step 4, the prefabricated structural plate of the integrated unit is aligned with the tongue and groove of the upper and lower structural beams, and the integrated unit is temporarily fixed to the surrounding main structure using materials such as channel steel, and then the verticality and flatness of the integrated unit are checked. It can only be formally fixed after the accuracy meets the requirements of the specification, and finally, after the prefabricated plate and the reserved dowels of the structural beam are tied and accepted, high-strength self-compacting concrete is poured around the pipe well structural plate;

[0027] Furthermore, the installation of horizontal main pipes and branch pipes in step 5 can achieve water-tightening of the floors, enable interlacing of processes, and achieve rapid construction; the risers of the pipe well electromechanical pipeline modules should be connected to the horizontal pipelines of the floors in a relatively spacious location to avoid affecting the net height of the floors, and also reduce the construction difficulty of the pipeline connection.

[0028] The above is only a specific implementation of the present invention, but the protection scope of the present invention is not limited thereto. Any modifications and improvements made by any ordinary technician in the field without departing from the principle and essential connotation of the present invention should be deemed to belong to the protection scope of the present invention.

Claims

1. A method for rapid assembly construction of super high-rise pipe wells and pipelines based on BIM technology, characterized in that: The following steps are involved: Step 1: Create the initial model of the main body of the project, electromechanical, etc. according to the design drawings, pipeline comprehensive layout rules and other modeling standards, integrate the completed models, and optimize and determine the pipeline comprehensive construction plan; Step 2: According to the contents described in step 1, design the bracket, structural beam and slab reservation according to the deepened BIM pipe model, and generate the final material list including pipelines, bracket steel and other auxiliary materials; Step 3: According to the contents described in step 2, the determined integrated electromechanical pipe well is subjected to stress analysis to determine the position and number of hanging points, and the integrated processing and production of civil engineering and electromechanical pipelines are carried out in the factory according to the final electromechanical pipeline plan; Step 4: According to the contents described in step 3, after the construction site is ready for construction, the integrated electromechanical pipe well unit is transported to the range of the lifting equipment and hoisted to the designated construction location. After temporary fixation and accurate detailed positioning, it is formally fixed and poured with self-compacting concrete; Step 5: According to the contents described in step 4, after the construction of the pipe well electromechanical module unit is completed, it is connected to the horizontal main pipe and branch pipe on the same floor to close the water supply to the floor to achieve rapid construction.

2. According to the BIM technology-based rapid assembly construction method for super high-rise pipe wells and pipelines according to claim 1, it is characterized in that: In step 1, BIM software is used to construct and integrate subsystem models, perform collision detection on mechanical and electrical pipelines and structures, adjust the comprehensive layout model of mechanical and electrical pipelines in the pipe well, optimize the design model layout, and determine the precise positioning of each pipeline in the plane and space in the pipe well.

3. According to the BIM technology-based rapid assembly construction method for super high-rise pipe wells and pipelines according to claim 1, it is characterized in that: In step 2, the brackets are arranged according to the final pipe layout, and the arrangement should meet the relevant requirements of the specification; Optimize the structural beams and slabs around the pipe well to form tongue and groove to facilitate the overlap with the prefabricated slabs of the integrated unit module, and cast them into a whole by reserving dowel bars; According to the material list, the electromechanical pipeline model is planned at a height of two floors to facilitate cutting and integrated assembly. The pipes and fittings of each system in the pipe well are numbered and the final material list and plane detailed drawings are exported to guide subsequent construction; Finite element analysis software is used to analyze the stress at the connection position between the integrated unit and the main structure. During the modeling process, the steel plate loaded on the top surface is coupled to a pre-set reference point. The vertical displacement can be directly applied to the reference point, and then the displacement of the loaded steel plate at the bottom of the model in the x, y, and z directions and the displacement of the reference point in the x and z directions are constrained respectively. The interface between new and old concrete is simulated by nonlinear three-dimensional spring elements. The normal spring element constitutive model perpendicular to the bonding surface adopts the normal stress-bond slip model. The transverse tangential spring element constitutive model of the bonding surface takes a large number of the same order of magnitude as the elastic modulus of concrete. The longitudinal tangential spring element constitutive model of the bonding surface is uniformly adopted (K1 s, 0 <s≤Se;K2(S-Se)+te,Se<s≤Su;K3(S-Su)+tu,Su<s≤Sr;tr,S> The elastic-brittle bond-slip relationship of Sr and the specimen is determined.

4. According to the BIM technology-based rapid assembly method for super high-rise pipe wells and pipelines according to claim 3, it is characterized in that: In step 3, a three-dimensional solid model of the integrated lifting unit is established by using three-dimensional modeling software, and then the center of gravity of the lifting unit is obtained by querying the software; Determine the number and position of lifting points by considering factors such as the lifting capacity of the lifting equipment, the number of cranes, the influence of the setting of lifting points on the internal force and deformation of the structural components, and the stress characteristics of the structure itself. Analyze the optimal number of lifting points and the most reasonable lifting point positions that should be used when the integrated lifting unit is hoisted as a whole, and verify the feasibility of the lifting plan. The prefabrication and assembly of the integrated electromechanical manifold is carried out in the factory. Based on the model plan, detailed drawings and material list, the upper and lower structural floor slabs are first prefabricated using the tire frame. The reserved casing positions of the prefabricated panels are placed strictly according to the plan. Concrete pouring can only be carried out after acceptance. After the concrete strength reaches the standard, the longitudinal filling wall is built and plastered first, then the pipeline is installed, and finally the horizontal walls on both sides are installed.

5. According to the BIM-based rapid assembly method for super high-rise pipe wells and pipelines according to claim 4, it is characterized in that: After the integrated electromechanical pipe well unit is hoisted to the designated position in step 4, the prefabricated structural panel of the integrated unit is aligned with the tongue and groove of the upper and lower structural beams, and the integrated unit is temporarily fixed to the surrounding main structure using materials such as channel steel. The verticality and flatness of the integrated unit are then checked, and formal fixation can only be performed after the accuracy meets the requirements of the specifications. Finally, after the prefabricated panel and the reserved dowels of the structural beam are tied together and accepted, high-strength self-compacting concrete is poured around the pipe well structural panel.

Citation Information

Patent Citations

  • Mechatronics composite floor slab, production method thereof and composite floor slab of bathroom fall slab

    CN108316532A

  • Electromechanical and steel structure integrated construction method

    CN112926114A

  • Assembly type construction method for electromechanical integrated pipeline

    CN113282986A

  • Prefabricated building prefabricated PC board and wire pipe integrated construction method

    CN114790793A

  • Complex electromechanical pipeline fabricated construction method based on BIM + AI technology

    CN118656902A