Reservoir sediment deposition amount and effective reservoir capacity determination method and device

Through the analysis and calculation of the top view of the reservoir, the error and complexity of the calculation of the effective reservoir capacity and sediment silt volume in the prior art are solved, and a high-precision calculation process is achieved.

CN119884549AActive Publication Date: 2025-04-25HUANENG CLEAN ENERGY RES INST
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411986636.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-31
Publication Date
2025-04-25
Estimated Expiration
2044-12-31

AI Technical Summary

Technical Problem

It is difficult to accurately calculate the effective reservoir capacity and sediment silt volume of the reservoir, and the calculation process is complicated and the error is large.

Method used

By obtaining the top view of the reservoir, marking the reference positioning points, and calculating the scale; obtaining the top view of different water levels, identifying the perimeter, and calculating the total area; calculating the effective reservoir capacity based on the water level and area, and calculating the amount of silt by decomposing the position depth.

Benefits of technology

It has achieved rapid and accurate calculation of the effective reservoir capacity and sediment silt volume of the reservoir, improved calculation accuracy, and reduced manpower and material investment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119884549A_ABST
    Figure CN119884549A_ABST
Patent Text Reader

Abstract

The invention provides a reservoir sediment deposition amount and effective reservoir capacity determination method and device. The method comprises the following steps: calculating a proportional scale between a top view of a whole reservoir and the whole reservoir; obtaining a plurality of top views of the whole reservoir at different water levels, and calculating the total area of the reservoir region at different boundaries based on the boundaries of the reservoir region in each top view and the scale; under the condition that the space of the reservoir area is formed by overlapping a plurality of barrel-shaped bodies, the total effective storage capacity of the reservoir is calculated according to a plurality of different water levels and the total area of the reservoir area; and calculating the decomposition position depths of the sediment scour section and the sediment deposition section in the reservoir at the two time points, and calculating the sediment deposition amount of the reservoir at the two time points according to the effective storage capacity of the reservoir below the decomposition position depths at the two time points. Therefore, through the top view of the whole reservoir and the change trend of the total area of the reservoir area in the top view, the effective reservoir capacity and the sediment deposition amount are rapidly and accurately calculated, and the accuracy of the sediment deposition amount and the calculation of the effective reservoir capacity is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of reservoir management, and in particular to a method, device, electronic equipment and storage medium for determining the amount of sediment deposition and effective storage capacity of a reservoir. Background Art

[0002] Reservoirs are affected by rainstorms and floods, and the sediment transport and soil erosion around the reservoir area have accumulated over a long period of time, causing siltation, which will restrict the healthy operation of the reservoir and the benefits of flood control, irrigation, and water supply. At present, after decades of operation, a large number of reservoirs have serious siltation problems, which has affected the water storage and regulation capacity of the reservoirs and made it impossible to accurately calculate the effective storage capacity of the reservoirs.

[0003] In related technologies, the amount of reservoir siltation is mainly measured by instruments to measure the changes in the water bottom or by statistics during manual dredging and excavation. This requires the use of complex measuring equipment and consumes a lot of manpower and material resources. At the same time, the errors in determining the amount of reservoir siltation and effective storage capacity are large. Therefore, a more reliable method for determining the amount of reservoir siltation and effective storage capacity is urgently needed. Summary of the invention

[0004] The present invention aims to solve one of the technical problems in the related art at least to a certain extent.

[0005] To this end, the first purpose of the present invention is to propose a method for determining the amount of silt accumulation and the effective storage capacity of a reservoir. By using a bird's-eye view of the entire reservoir and the changing trend of the total area of ​​the reservoir area in the bird's-eye view, the effective storage capacity and the amount of silt accumulation can be quickly and accurately calculated, thereby improving the accuracy of the calculation of the amount of silt accumulation and the effective storage capacity.

[0006] The second object of the present invention is to provide a device for determining the amount of silt deposited in a reservoir and the effective storage capacity.

[0007] A third objective of the present invention is to provide an electronic device.

[0008] A fourth object of the present invention is to provide a non-transitory computer-readable storage medium storing computer instructions.

[0009] To achieve the above-mentioned purpose, the first embodiment of the present invention proposes a method for determining the amount of sediment deposition and effective storage capacity of a reservoir, the method comprising:

[0010] Obtain a bird's-eye view of the entire reservoir, on which two reference positioning points around the reservoir area are marked, and calculate the scale between the bird's-eye view and the entire reservoir based on the horizontal distance between the two reference positioning points on the bird's-eye view and the measured horizontal distance between the two reference positioning points in the entire reservoir;

[0011] Get multiple different water levels H1, H2, ..., Hn The top view of the entire reservoir is obtained, the perimeter of the reservoir area in each top view is identified, and the total area S1, S2, ..., S of the reservoir area at different perimeters is calculated based on each perimeter and scale. n , where n is the dead water level of the reservoir;

[0012] In the case where the space of the reservoir area is composed of multiple barrel-shaped bodies superimposed, according to H1, H2, ..., H n and S1, S2, ..., S n , calculate the effective storage capacity of the reservoir between adjacent water levels, and add up the effective storage capacity of the reservoir between adjacent water levels to obtain the total effective storage capacity of the reservoir;

[0013] According to the first total area and the second total area of ​​the reservoir area at multiple identical water levels at two time points, the decomposition position depth H of the sediment scouring section and the sedimentation section in the reservoir within the time interval of the two time points is calculated. k , and based on the first time point H k The effective storage capacity of the reservoir below the depth V0 and the second time point H k The effective storage capacity V of the reservoir below the depth is used to calculate the amount of silt deposited in the reservoir during the time interval.

[0014] To achieve the above-mentioned purpose, the second embodiment of the present invention provides a device for determining the amount of sediment deposition and effective storage capacity of a reservoir, the device comprising:

[0015] An acquisition module is used to acquire a bird's-eye view of the entire reservoir, on which two reference positioning points around the reservoir area are marked, and to calculate the scale between the bird's-eye view and the entire reservoir based on the horizontal distance between the two reference positioning points on the bird's-eye view and the measured horizontal distance between the two reference positioning points in the entire reservoir;

[0016] The first calculation module is used to obtain a plurality of different water levels H1, H2, ..., H n The top view of the entire reservoir is obtained, the perimeter of the reservoir area in each top view is identified, and the total area S1, S2, ..., S of the reservoir area at different perimeters is calculated based on each perimeter and scale. n , where n is the dead water level of the reservoir;

[0017] The second calculation module is used for calculating the water reservoir area according to H1, H2, ..., H n and S1, S2, ..., S n , calculate the effective storage capacity of the reservoir between adjacent water levels, and add up the effective storage capacity of the reservoir between adjacent water levels to obtain the total effective storage capacity of the reservoir;

[0018] The third calculation module is used to calculate the decomposition position depth H of the sediment scouring section and the sedimentation section in the reservoir within the time interval of the two time points according to the first total area and the second total area of ​​the reservoir area at multiple same water levels at two time points. k , and based on the first time point H k The effective storage capacity of the reservoir below the depth V0 and the second time point H k The effective storage capacity V of the reservoir below the depth is used to calculate the amount of silt deposited in the reservoir during the time interval.

[0019] To achieve the above-mentioned purpose, the third aspect of the present invention proposes an electronic device, comprising: at least one processor; and a memory communicatively connected to the at least one processor; wherein the memory stores instructions executable by the at least one processor, and the instructions are executed by the at least one processor so that the at least one processor can execute the method described in the first aspect.

[0020] In order to achieve the above-mentioned purpose, the fourth aspect of the present invention proposes a non-transitory computer-readable storage medium storing computer instructions, where the computer instructions are used to enable the computer to execute the method described in the first aspect.

[0021] The method, device, electronic device and storage medium for determining the amount of sediment accumulation and effective storage capacity of a reservoir provided by the embodiment of the present invention calculate the scale between the bird's-eye view of the entire reservoir and the entire reservoir; obtain bird's-eye views of the entire reservoir at multiple different water levels, and calculate the total area of ​​the reservoir area at different perimeters based on the perimeter and scale of the reservoir area in each bird's-eye view; when the space of the reservoir area is composed of multiple barrel-shaped bodies superimposed, calculate the total effective storage capacity of the reservoir according to multiple different water levels and the total area of ​​the reservoir area; calculate the decomposition position depth of the sediment scouring section and the sediment accumulation section in the reservoir at two time points, and calculate the amount of sediment accumulation in the reservoir at the two time points according to the effective storage capacity of the reservoir below the decomposition position depth at the two time points. Thus, the effective storage capacity and sediment accumulation can be quickly and accurately calculated through the bird's-eye view of the entire reservoir and the change trend of the total area of ​​the reservoir area in the bird's-eye view, thereby improving the accuracy of the calculation of sediment accumulation and effective storage capacity.

[0022] Additional aspects and advantages of the present invention will be given in part in the following description and in part will be obvious from the following description, or will be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] The above and / or additional aspects and advantages of the present invention will become apparent and easily understood from the following description of the embodiments in conjunction with the accompanying drawings, in which:

[0024] Figure 1 A schematic diagram of a flow chart of a method for determining the amount of sediment deposition and effective storage capacity of a reservoir provided by an embodiment of the present invention;

[0025] Figure 2 A schematic diagram of pixel filling of a top view of an entire reservoir provided by an embodiment of the present invention;

[0026] Figure 3 A schematic diagram of pixel filling of multiple top views of an entire reservoir provided by an embodiment of the present invention;

[0027] Figure 4 A schematic diagram of siltation and scouring at the bottom of a reservoir provided by an embodiment of the present invention;

[0028] Figure 5 A schematic diagram of the structure of a device for determining the amount of sediment deposition and effective storage capacity of a reservoir provided in an embodiment of the present invention. DETAILED DESCRIPTION

[0029] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, and should not be construed as limiting the present invention.

[0030] It should be noted that the acquisition, storage, use, and processing of data in the technical solution of the present invention are in compliance with the relevant provisions of relevant laws and regulations.

[0031] The following describes, with reference to the accompanying drawings, a method, device, electronic device, and storage medium for determining the amount of reservoir sedimentation and effective storage capacity according to an embodiment of the present invention.

[0032] Figure 1 A schematic flow chart of a method for determining the amount of sediment deposition and effective storage capacity of a reservoir provided in an embodiment of the present invention.

[0033] like Figure 1 As shown, the method comprises the following steps:

[0034] Step 101, obtain a bird's-eye view of the entire reservoir, on which two reference positioning points around the reservoir area are marked, and calculate the scale between the bird's-eye view and the entire reservoir based on the horizontal distance between the two reference positioning points on the bird's-eye view and the measured horizontal distance between the two reference positioning points in the entire reservoir.

[0035] In some embodiments, a bird's-eye view of the entire reservoir at any water level can be obtained by synthesizing the camera shots at a high position of the reservoir or by taking drone shots. In order to avoid errors caused by the tilt of the camera shooting angle, the angle should be kept level each time the camera is shot.

[0036] In order to correctly convert the scale between the bird's-eye view and the entire reservoir, two fixed and easily identifiable points around the reservoir area should be selected on the bird's-eye view as reference points (e.g., points A and B). The positions of the reference points should be relatively fixed and the horizontal distance should be easy to obtain.

[0037] It is understandable that the two reference positioning points A and B may be fixed buildings or marked objects, but are not limited thereto, and this embodiment does not make any specific limitation thereto.

[0038] Step 102, obtaining a plurality of different water levels H1, H2, ..., H n The top view of the entire reservoir is obtained, the perimeter of the reservoir area in each top view is identified, and the total area S1, S2, ..., S of the reservoir area at different perimeters is calculated based on each perimeter and scale. n , where n is the dead water level of the reservoir.

[0039] In some embodiments, a plurality of different water levels H1, H2, ..., H n The top view of the entire reservoir is obtained, the perimeter of the reservoir area in each top view is identified, and the total area S1, S2, ..., S of the reservoir area at different perimeters is calculated based on each perimeter and scale. n One implementation method may be to obtain a plurality of different water levels H1, H2, ..., H n The whole reservoir is viewed from above, and the perimeter of the reservoir area in each view is identified by image recognition software; the reservoir area within the perimeter of each view is filled with white pixels, and the area of ​​each area filled with white pixels is calculated by image processing software; the product of the area of ​​each area filled with white pixels and the scale is used as the total area S1, S2, ..., S of the reservoir area at different perimeters. n , wherein the image processing software may include but is not limited to Photoshop.

[0040] Optionally, when the perimeter of the reservoir area in each overhead view is automatically identified by image recognition software, a manual conformity check may be performed to manually modify the incorrectly identified perimeter to ensure that the perimeter of the reservoir area is accurately obtained.

[0041] Furthermore, an embodiment of the present invention provides a schematic diagram of pixel filling in a top view of the entire reservoir, such as Figure 2 As shown, specifically, after the perimeter of the reservoir area in the overhead view is identified by image recognition software, the reservoir area (reservoir) within the corresponding perimeter of the overhead view is filled with white pixels, the land outside the reservoir area is filled with gray pixels, and two reference positioning points A and B are calibrated on the overhead view.

[0042] In addition, the embodiment of the present invention also provides a schematic diagram of pixel filling of multiple top views of the entire reservoir, such as Figure 3 As shown, the perimeter (shape) of the reservoir area in the top view under multiple different water levels is identified by image recognition software, and the reservoir area within the corresponding perimeter of each top view is filled with white pixels, and the land outside the reservoir area is filled with gray pixels. Points A and B are used as reference positioning points, and points A and B of each top view are overlapped to obtain the change of the perimeter under different water levels (the contour of the water surface corresponding to different water levels). Therefore, since the positions of the two reference positioning points A and B are always determined, the horizontal distance of the AB line is also fixed, which can be directly measured by measuring or consulting the online map and the distance measurement tool in the map. The scale between the top view and the entire reservoir can be determined by the horizontal distance of AB. At the same time, the area of ​​the area filled with white pixels in each top view is directly calculated by image processing software, and then multiplied by the scale to obtain the total area of ​​the reservoir area under different water levels.

[0043] Step 103: when the space of the reservoir area is composed of multiple barrel-shaped bodies, according to H1, H2, ..., H n and S1, S2, ..., S n , calculate the effective storage capacity of the reservoir between adjacent water levels, and add up the effective storage capacity of the reservoir between adjacent water levels to obtain the total effective storage capacity of the reservoir.

[0044] In some embodiments, when the space of the reservoir area is composed of multiple barrels, according to H1, H2, ..., H n and S1, S2, ..., S n , calculate the effective storage capacity of the reservoir between adjacent water levels, and add up the effective storage capacity of the reservoir between adjacent water levels to obtain the total effective storage capacity of the reservoir. One implementation method may be, when the space of the reservoir area is composed of multiple barrel-shaped bodies superimposed, according to H1, H2, ..., H n and S1, S2, ..., S n , calculate the effective storage capacity V1, V2, ..., V between adjacent water levels n-1 , where V1 = 1 / 2 * (H1-H2)*(S1+S2),...,V n-1 =1 / 2 * (H n-1 -H n )*(S n-1 +S n );The effective storage capacity of the reservoir between adjacent water levels V1, V2, ..., V n-1 Add them up to get the total effective storage capacity of the reservoir V = V1 + V2 + V n-1Therefore, the acquisition and processing of the reservoir's bird's-eye view, the selection of reference positioning points and the determination of the effective storage capacity are given, fully considering the operability and accuracy.

[0045] Among them, different water levels H1, H2, ..., H n The total area of ​​the reservoir area S1, S2, ..., S n The corresponding relationship is shown in Table 1.

[0046] Table 1 Correspondence between different water levels and the total area of ​​the reservoir area

[0047]

[0048]

[0049] Step 104, based on the first total area and the second total area of ​​the reservoir area at the same water level at two time points, calculate the decomposition position depth H of the sediment scouring section and the sedimentation section in the reservoir within the time interval of the two time points k , and based on the first time point H k The effective storage capacity of the reservoir below the depth V0 and the second time point H k The effective storage capacity V of the reservoir below the depth is used to calculate the amount of silt deposited in the reservoir during the time interval.

[0050] In some embodiments, siltation mainly occurs at the bottom of the reservoir and below a certain depth, and the water surface area of ​​the reservoir decreases. Scour is likely to occur above a certain depth, that is, the water surface area increases, such as Figure 4 As shown, Figure 4 An embodiment of the present invention provides a schematic diagram of siltation and scouring at the bottom of a reservoir. Specifically, the daily highest water level of the reservoir, the siltation section and the scouring section of the bottom of the reservoir, the dead water level position (the part below the dead water level position does not affect the effective storage capacity) and (the original bottom of the reservoir) are divided. After the siltation and scouring at the bottom of the reservoir, the bottom of the reservoir after siltation / scouring can be obtained.

[0051] In some embodiments, based on the first total area and the second total area of ​​the reservoir area at multiple same water levels at two time points, the decomposition position depth H of the sediment scouring section and the sedimentation section in the reservoir within the time interval of the two time points is calculated. k , and based on the first time point H k The effective storage capacity of the reservoir below the depth V0 and the second time point H k The effective storage capacity V of the reservoir below the depth, one implementation method for calculating the sediment deposition amount of the reservoir within the time interval can be to calculate the total area S1, S2, ..., S of the reservoir area at the same water level at two time points. n and the second total area S 01 , S 02, ..., S 0n , select S k ≈S 0k And S k-1 >S 0k-1 , S k+1 0k+1 The water level depth at the time of the two time points is used as the decomposition position depth H of the sediment scouring section and the sedimentation section in the reservoir during the time interval between the two time points. k , where k∈(1,2...,n); based on the first time point H k The effective storage capacity of the reservoir below the depth V0 and the second time point H k The effective storage capacity V of the reservoir below the depth is used to calculate the amount of sediment deposition in the reservoir within the time interval. Therefore, the method of determining the decomposition position depth of the sediment scouring section and the sediment deposition section is carried out through the change trend of the total area of ​​the reservoir area in the bird's-eye view, and the calculation formula of the sediment deposition amount is given. The method is simple and accurate.

[0052] Further, based on the first time point H k The effective storage capacity of the reservoir below the depth V0 and the second time point H k The effective storage capacity V of the reservoir below the depth, one implementation method for calculating the sediment deposition amount of the reservoir within the time interval can be, according to the first time point H k Depth below H k , H k+1 , ..., H n , and the corresponding S k , S k+1 , ..., S n , calculate the first time point H k The effective storage capacity of the reservoir below the depth V0; according to the second time point H k Depth below H k , H k+1 , ..., H n , and the corresponding S 0k , S 0k+1 , ..., S 0n , calculate the second time point H k The effective storage capacity V of the reservoir below the depth; the difference between V0 and V is taken as the sediment deposition amount V of the reservoir during the time interval between the two time points s , V s =V0-V.

[0053] Among them, multiple water levels H1, H2, ..., H n The first total area S1, S2, ..., S at the first time point n , the second total area S at the second time point 01 , S 02 , ..., S​0n The decomposition depth H of the sediment scouring section and sedimentation section in the reservoir k The judgment relationship table is shown in Table 2.

[0054] Table 2 The first total area, the second total area and H at multiple same water levels k Judgment relationship

[0055]

[0056] The method for determining the amount of sediment accumulation and effective storage capacity of a reservoir in an embodiment of the present invention calculates the scale between the bird's-eye view of the entire reservoir and the entire reservoir; obtains a plurality of bird's-eye views of the entire reservoir at different water levels, and calculates the total area of ​​the reservoir area at different perimeters based on the perimeter and scale of the reservoir area in each bird's-eye view; in the case where the space of the reservoir area is superimposed by a plurality of barrel-shaped bodies, calculates the total effective storage capacity of the reservoir according to a plurality of different water levels and the total area of ​​the reservoir area; calculates the decomposition position depth of the sediment scouring section and the sedimentation section in the reservoir at two time points, and calculates the amount of sediment accumulation in the reservoir at the two time points according to the effective storage capacity of the reservoir below the decomposition position depth at the two time points. Thus, the effective storage capacity and the amount of sediment accumulation can be quickly and accurately calculated through the bird's-eye view of the entire reservoir and the change trend of the total area of ​​the reservoir area in the bird's-eye view, thereby improving the accuracy of the calculation of the amount of sediment accumulation and the effective storage capacity.

[0057] In summary, the present invention only requires conventional high-definition cameras, water level meters and general image analysis software (such as Photoshop), and does not require a large amount of human and material resources for secondary research and development. The cameras and water level meters involved are common devices with low costs, and a large number of cameras and water level meters have been installed in the reservoir area of ​​ordinary intelligent hydropower plants. The present invention can use existing devices to realize the analysis of reservoir silt accumulation and effective storage capacity without the need to purchase new devices. At the same time, the accuracy of silt accumulation and effective storage capacity is high and easy to operate: the reservoir area can be read directly from the picture with high accuracy. Only ordinary picture analysis software and simple conversion are required, and it is easy to operate.

[0058] In order to realize the above-mentioned embodiment, the present invention also proposes a device for determining the amount of sediment deposition and effective storage capacity of a reservoir.

[0059] Figure 5 A schematic diagram of the structure of a device for determining the amount of sediment deposition and effective storage capacity of a reservoir provided in an embodiment of the present invention.

[0060] like Figure 5 As shown, the reservoir sedimentation amount and effective storage capacity determination device 50 includes: an acquisition module 51, a first calculation module 52, a second calculation module 53 and a third calculation module 54.

[0061] An acquisition module 51 is used to acquire a bird's-eye view of the entire reservoir, on which two reference positioning points around the reservoir area are marked, and to calculate the scale between the bird's-eye view and the entire reservoir based on the horizontal distance between the two reference positioning points on the bird's-eye view and the measured horizontal distance between the two reference positioning points in the entire reservoir;

[0062] The first calculation module 52 is used to obtain a plurality of different water levels H1, H2, ..., H n The top view of the entire reservoir is obtained, the perimeter of the reservoir area in each top view is identified, and the total area S1, S2, ..., S of the reservoir area at different perimeters is calculated based on each perimeter and scale. n , where n is the dead water level of the reservoir;

[0063] The second calculation module 53 is used for calculating the water reservoir area according to H1, H2, ..., H n and S1, S2, ..., S n , calculate the effective storage capacity of the reservoir between adjacent water levels, and add up the effective storage capacity of the reservoir between adjacent water levels to obtain the total effective storage capacity of the reservoir;

[0064] The third calculation module 54 is used to calculate the decomposition position depth H of the sediment scouring section and the sedimentation section in the reservoir within the time interval of the two time points according to the first total area and the second total area of ​​the reservoir area at the same water level at the two time points. k , and based on the first time point H k The effective storage capacity of the reservoir below the depth V0 and the second time point H k The effective storage capacity V of the reservoir below the depth is used to calculate the amount of silt deposited in the reservoir during the time interval.

[0065] Further, in a possible implementation manner of the embodiment of the present invention, the first calculation module 52 is specifically configured to:

[0066] Get multiple different water levels H1, H2, ..., H n A bird's-eye view of the entire reservoir is obtained, and the perimeter of the reservoir area in each bird's-eye view is identified by image recognition software;

[0067] Fill the reservoir area within the corresponding perimeter of each top view with white pixels, and calculate the area of ​​each white pixel filled region by image processing software;

[0068] The product of the area filled with white pixels and the scale is taken as the total area of ​​the reservoir area at different perimeters S1, S2, ..., S n .

[0069] Further, in a possible implementation manner of the embodiment of the present invention, the second calculation module 53 is specifically configured to:

[0070] In the case where the space of the reservoir area is composed of multiple barrel-shaped bodies superimposed, according to H1, H2, ..., H n and S1, S2, ..., S n , calculate the effective storage capacity V1, V2, ..., V between adjacent water levels n-1 , where V1 = 1 / 2(H1-H2)*(S1+S2),...,V n-1 =1 / 2(H n-1 -H n )*(S n-1 +S n );

[0071] The effective storage capacity of the reservoirs between adjacent water levels V1, V2, ..., V n-1 Add them up to get the total effective storage capacity of the reservoir V = V1 + V2 + V n-1 .

[0072] Furthermore, in a possible implementation of the embodiment of the present invention, the third calculation module 54 includes:

[0073] A selection unit is used to select a first total area S1, S2, ..., S of a reservoir area at a plurality of same water levels at two time points. n and the second total area S 01 , S 02 , ..., S 0n , select S k ≈S 0k And S k-1 >S 0k-1 , S k+1 0k+1 The water level depth at the time of the two time points is used as the decomposition position depth H of the sediment scouring section and the sedimentation section in the reservoir during the time interval between the two time points. k , where k∈(1,2...,n);

[0074] A calculation unit is used for calculating the time point H based on the first time point H k The effective storage capacity of the reservoir below the depth V0 and the second time point H k The effective storage capacity V of the reservoir below the depth is used to calculate the amount of silt deposited in the reservoir during the time interval.

[0075] Furthermore, in a possible implementation manner of the embodiment of the present invention, the computing unit is specifically configured to:

[0076] According to the first time point H k Depth below H​k , H k+1 , ..., H n , and the corresponding S k , S k+1 , ..., S n , calculate the first time point H k The effective storage capacity of the reservoir below the depth is V0;

[0077] According to the second time point H k Depth below H k , H k+1 , ..., H n , and the corresponding S 0k , S 0k+1 , ..., S 0n , calculate the second time point H k The effective storage capacity of the reservoir below the depth is V;

[0078] The difference between V0 and V is taken as the sediment deposition amount V of the reservoir during the time interval between the two time points. s , V s =V0-V.

[0079] It should be noted that the above explanation of the method embodiment is also applicable to the device of this embodiment, and will not be repeated here.

[0080] The device for determining the amount of sediment deposition and effective storage capacity of a reservoir in an embodiment of the present invention calculates the scale between the bird's-eye view of the entire reservoir and the entire reservoir; obtains a plurality of bird's-eye views of the entire reservoir at different water levels, and calculates the total area of ​​the reservoir area at different perimeters based on the perimeter and scale of the reservoir area in each bird's-eye view; in the case where the space of the reservoir area is superimposed by a plurality of barrel-shaped bodies, the total effective storage capacity of the reservoir is calculated according to a plurality of different water levels and the total area of ​​the reservoir area; calculates the decomposition position depth of the sediment scouring section and the sedimentation section in the reservoir at two time points, and calculates the amount of sediment deposition in the reservoir at the two time points according to the effective storage capacity of the reservoir below the decomposition position depth at the two time points. Thus, the effective storage capacity and the amount of sediment deposition can be quickly and accurately calculated through the bird's-eye view of the entire reservoir and the change trend of the total area of ​​the reservoir area in the bird's-eye view, thereby improving the accuracy of the calculation of the amount of sediment deposition and the effective storage capacity.

[0081] In order to implement the above embodiment, the present invention further provides an electronic device, including:

[0082] at least one processor; and

[0083] a memory communicatively connected to the at least one processor; wherein,

[0084] The memory stores instructions that can be executed by the at least one processor, and the instructions are executed by the at least one processor so that the at least one processor can perform the aforementioned method.

[0085] In order to implement the above embodiment, the present invention further proposes a non-transitory computer-readable storage medium storing computer instructions, where the computer instructions are used to enable the computer to execute the above method.

[0086] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0087] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0088] Any process or method description in a flowchart or otherwise described herein may be understood to represent a module, segment or portion of code comprising one or more executable instructions for implementing the steps of a custom logical function or process, and the scope of the preferred embodiments of the present invention includes alternative implementations in which functions may not be performed in the order shown or discussed, including performing functions in a substantially simultaneous manner or in reverse order depending on the functions involved, which should be understood by technicians in the technical field to which the embodiments of the present invention belong.

[0089] The logic and / or steps represented in the flowchart or otherwise described herein, for example, can be considered as an ordered list of executable instructions for implementing logical functions, and can be embodied in any computer-readable medium for use by an instruction execution system, device or apparatus (such as a computer-based system, a system including a processor, or other system that can fetch instructions from an instruction execution system, device or apparatus and execute the instructions), or in combination with these instruction execution systems, devices or apparatuses. For the purpose of this specification, "computer-readable medium" can be any device that can contain, store, communicate, propagate or transmit a program for use by an instruction execution system, device or apparatus, or in combination with these instruction execution systems, devices or apparatuses. More specific examples of computer-readable media (a non-exhaustive list) include the following: an electrical connection with one or more wires (electronic device), a portable computer disk box (magnetic device), a random access memory (RAM), a read-only memory (ROM), an erasable and programmable read-only memory (EPROM or flash memory), a fiber optic device, and a portable compact disk read-only memory (CDROM). In addition, the computer-readable medium may even be paper or other suitable medium on which the program is printed, since the program may be obtained electronically, for example, by optically scanning the paper or other medium and then editing, interpreting or processing in other suitable ways if necessary, and then stored in a computer memory.

[0090] It should be understood that the various parts of the present invention can be implemented by hardware, software, firmware or a combination thereof. In the above-mentioned embodiments, a plurality of steps or methods can be implemented by software or firmware stored in a memory and executed by a suitable instruction execution system. For example, if implemented by hardware, as in another embodiment, it can be implemented by any one of the following technologies known in the art or their combination: a discrete logic circuit having a logic gate circuit for implementing a logic function for a data signal, a dedicated integrated circuit having a suitable combination of logic gate circuits, a programmable gate array (PGA), a field programmable gate array (FPGA), etc.

[0091] A person skilled in the art may understand that all or part of the steps in the method for implementing the above-mentioned embodiment may be completed by instructing related hardware through a program, and the program may be stored in a computer-readable storage medium, which, when executed, includes one or a combination of the steps of the method embodiment.

[0092] In addition, each functional unit in each embodiment of the present invention may be integrated into a processing module, or each unit may exist physically separately, or two or more units may be integrated into one module. The above-mentioned integrated module may be implemented in the form of hardware or in the form of software functional modules. If the integrated module is implemented in the form of software functional modules and sold or used as an independent product, it may also be stored in a computer-readable storage medium.

[0093] The storage medium mentioned above may be a read-only memory, a magnetic disk or an optical disk, etc. Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limiting the present invention. A person of ordinary skill in the art may change, modify, replace and modify the above embodiments within the scope of the present invention.

Claims

1. A method for determining the amount of sediment deposited in a reservoir and the effective storage capacity, characterized in that: The method comprises: Obtain a bird's-eye view of the entire reservoir, on which two reference positioning points around the reservoir area are marked, and calculate the scale between the bird's-eye view and the entire reservoir based on the horizontal distance between the two reference positioning points on the bird's-eye view and the measured horizontal distance between the two reference positioning points in the entire reservoir; Get multiple different water levels H1, H2, ..., H n The top view of the entire reservoir is obtained, the perimeter of the reservoir area in each top view is identified, and the total area S1, S2, ..., S of the reservoir area at different perimeters is calculated based on each perimeter and scale. n , where n is the dead water level of the reservoir; In the case where the space of the reservoir area is composed of multiple barrel-shaped bodies superimposed, according to H1, H2, ..., H n and S1, S2, ..., S n , calculate the effective storage capacity of the reservoir between adjacent water levels, and add up the effective storage capacity of the reservoir between adjacent water levels to obtain the total effective storage capacity of the reservoir; According to the first total area and the second total area of ​​the reservoir area at multiple identical water levels at two time points, the decomposition position depth H of the sediment scouring section and the sedimentation section in the reservoir within the time interval of the two time points is calculated. k , and based on the first time point H k The effective storage capacity of the reservoir below the depth V0 and the second time point H k The effective storage capacity V of the reservoir below the depth is used to calculate the amount of silt deposited in the reservoir during the time interval.

2. The method according to claim 1, characterized in that The method of obtaining a plurality of different water levels H1, H2, ..., H n The top view of the entire reservoir is obtained, the perimeter of the reservoir area in each top view is identified, and the total area S1, S2, ..., S of the reservoir area at different perimeters is calculated based on each perimeter and scale. n ,include: Get multiple different water levels H1, H2, ..., H n A bird's-eye view of the entire reservoir is obtained, and the perimeter of the reservoir area in each bird's-eye view is identified by image recognition software; Fill the reservoir area within the corresponding perimeter of each top view with white pixels, and calculate the area of ​​each white pixel filled region by image processing software; The product of the area filled with white pixels and the scale is taken as the total area of ​​the reservoir area at different perimeters S1, S2, ..., S n .

3. The method according to claim 1, characterized in that In the case where the space in the reservoir area is composed of multiple barrel-shaped bodies superimposed, according to H1, H2, ..., H n and S1, S2, ..., S n , calculate the effective storage capacity of the reservoir between adjacent water levels, and add up the effective storage capacity of the reservoir between adjacent water levels to obtain the total effective storage capacity of the reservoir, including: In the case where the space of the reservoir area is composed of multiple barrel-shaped bodies superimposed, according to H1, H2, ..., H n and S1, S2, ..., S n , calculate the effective storage capacity V1, V2, ..., V between adjacent water levels n-1 , where V1 = 1 / 2 * (H1-H2)*(S1+S2),...,V n-1 =1 / 2 / (H n-1 -H n )*(S n-1 +S n ); The effective storage capacity of the reservoirs between adjacent water levels V1, V2, ..., V n-1 Add them up to get the total effective storage capacity of the reservoir V = V1 + V2 + V n-1 .

4. The method according to claim 1, characterized in that The decomposition position depth H of the sediment scouring section and the sedimentation section in the reservoir within the time interval of the two time points is calculated according to the first total area and the second total area of ​​the reservoir area at the same water level at the two time points. k , and based on the first time point H k The effective storage capacity of the reservoir below the depth V0 and the second time point H k The effective storage capacity V of the reservoir below the depth is used to calculate the amount of sediment deposited in the reservoir during the time interval, including: According to the first total area S1, S2, ..., S of the reservoir area at the same water level at two time points n and the second total area S 01 , S 02 , ..., S 0n , select S k ≈S 0k And S k-1 >S 0k-1 , S k+1 0k+1 The water level depth at the time of the two time points is used as the decomposition position depth H of the sediment scouring section and the sedimentation section in the reservoir during the time interval between the two time points. k , where k∈(1,2...,n);​ Based on the first time point H k The effective storage capacity of the reservoir below the depth V0 and the second time point H k The effective storage capacity V of the reservoir below the depth is used to calculate the amount of silt deposited in the reservoir during the time interval.

5. The method according to claim 4, characterized in that Based on the first time point H k The effective storage capacity of the reservoir below the depth V0 and the second time point H k The effective storage capacity V of the reservoir below the depth is used to calculate the amount of sediment deposited in the reservoir during the time interval, including: According to the first time point H k Depth below H k , H k+1 , ..., H n , and the corresponding S k , S k+1 , ..., S n , calculate the first time point H k The effective storage capacity of the reservoir below the depth is V0; According to the second time point H k Depth below H k , H k+1 , ..., H n , and the corresponding S 0k , S 0k+1 , ..., S 0n , calculate the second time point H k The effective storage capacity of the reservoir below the depth is V; The difference between V0 and V is taken as the sediment deposition amount V of the reservoir during the time interval between the two time points. s , V s =V0-V.

6. A device for determining the amount of sediment deposited in a reservoir and the effective storage capacity, characterized in that: The device comprises: An acquisition module is used to acquire a bird's-eye view of the entire reservoir, on which two reference positioning points around the reservoir area are marked, and to calculate the scale between the bird's-eye view and the entire reservoir based on the horizontal distance between the two reference positioning points on the bird's-eye view and the measured horizontal distance between the two reference positioning points in the entire reservoir; The first calculation module is used to obtain a plurality of different water levels H1, H2, ..., H n The top view of the entire reservoir is obtained, the perimeter of the reservoir area in each top view is identified, and the total area S1, S2, ..., S of the reservoir area at different perimeters is calculated based on each perimeter and scale. n , where n is the dead water level of the reservoir; The second calculation module is used for calculating the water reservoir area according to H1, H2, ..., H n and S1, S2, ..., S n , calculate the effective storage capacity of the reservoir between adjacent water levels, and add up the effective storage capacity of the reservoir between adjacent water levels to obtain the total effective storage capacity of the reservoir; The third calculation module is used to calculate the decomposition position depth H of the sediment scouring section and the sedimentation section in the reservoir within the time interval of the two time points according to the first total area and the second total area of ​​the reservoir area at multiple same water levels at two time points. k , and based on the first time point H k The effective storage capacity of the reservoir below the depth V0 and the second time point H k The effective storage capacity V of the reservoir below the depth is used to calculate the amount of silt deposited in the reservoir during the time interval.

7. The device according to claim 6, characterized in that The first calculation module is specifically used for: Get multiple different water levels H1, H2, ..., H n A bird's-eye view of the entire reservoir is obtained, and the perimeter of the reservoir area in each bird's-eye view is identified by image recognition software; Fill the reservoir area within the corresponding perimeter of each top view with white pixels, and calculate the area of ​​each white pixel filled region by image processing software; The product of the area filled with white pixels and the scale is taken as the total area of ​​the reservoir area at different perimeters S1, S2, ..., S n .

8. The device according to claim 6, characterized in that The second calculation module is specifically used for: In the case where the space of the reservoir area is composed of multiple barrel-shaped bodies superimposed, according to H1, H2, ..., H n and S1, S2, ..., S n , calculate the effective storage capacity V1, V2, ..., V between adjacent water levels n-1 , where V1 = 1 / 2 * (H1-H2)*(S1+S2),...,V n-1 =1 / 2 * (H n-1 -H n )*(S n-1 +S n ); The effective storage capacity of the reservoirs between adjacent water levels V1, V2, ..., V n-1 Add them up to get the total effective storage capacity of the reservoir V = V1 + V2 + V n-1 .

9. The device according to claim 6, characterized in that The third computing module comprises: A selection unit is used to select a first total area S1, S2, ..., S of a reservoir area at a plurality of same water levels at two time points. n and the second total area S 01 , S 02 , ..., S 0n , select S k ≈S 0k And S k-1 >S 0k-1 , S k+1 0k+1 The water level depth at the time of the two time points is used as the decomposition position depth H of the sediment scouring section and the sedimentation section in the reservoir during the time interval between the two time points. k , where k∈(1,2...,n);​ A calculation unit is used for calculating the time point H based on the first time point H k The effective storage capacity of the reservoir below the depth V0 and the second time point H k The effective storage capacity V of the reservoir below the depth is used to calculate the amount of silt deposited in the reservoir during the time interval.

10. The device according to claim 9, characterized in that The computing unit is specifically used for: According to the first time point H k Depth below H k , H k+1 , ..., H n , and the corresponding S k , S k+1 , ..., S n , calculate the first time point H k The effective storage capacity of the reservoir below the depth is V0; According to the second time point H k Depth below H k , H k+1 , ..., H n , and the corresponding S 0k , S 0k+1 , ..., S 0n , calculate the second time point H k The effective storage capacity of the reservoir below the depth is V; The difference between V0 and V is taken as the sediment deposition amount V of the reservoir during the time interval between the two time points. s , V s =V0-V.

11. An electronic device, characterized in that: include: at least one processor; as well as a memory communicatively connected to the at least one processor; wherein, The memory stores instructions that can be executed by the at least one processor, and the instructions are executed by the at least one processor to enable the at least one processor to perform the method according to any one of claims 1 to 5.

12. A non-transitory computer-readable storage medium storing computer instructions, characterized in that: The computer instructions are used to cause the computer to execute the method according to any one of claims 1-5.

Citation Information

Patent Citations

  • Quantitative method of flood storage and flood detention effects of coal mining subsidence area

    CN106547974A

  • Guide vane type desilting funnel

    CN114370035A

  • Calculation method for reservoir capacity regulation siltation amount of reservoir

    CN116258441A

  • Sediment control method for hydro-junction project of sandy river

    CN116305435A

  • Method for calculating sediment deposition amount of river mouth and river reach of small-sediment tributary of large reservoir

    CN116776769A