Underground operation team performance evaluation method based on analytic hierarchy process
Through the performance evaluation method of underground operation teams based on hierarchical analysis, the problem of low underground operation quality in the existing technology has been solved, comprehensive and scientific evaluation of the team has been achieved, and the quality and management level of underground operation have been improved.
Patent Information
- Application Number
- CN202311477774.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-08
- Publication Date
- 2025-05-09
AI Technical Summary
The quality of underground operations in the existing technology is low, mainly due to the lack of unified standards for assessment, and the failure to fully consider factors such as process type, safety and environmental protection, and well control.
The performance evaluation method of underground operation teams based on hierarchical analysis is adopted. By determining the weight and scoring standards of various assessment indicators, reasonably adjusting according to the types of operations, the management and production performance of the team are comprehensively assessed.
It has achieved a comprehensive, scientific and effective assessment of the underground operation team, improved the quality and management level of underground operation, and promoted the rectification of problems and quality improvement.
Smart Images

Figure CN119963013A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of evaluation methods and relates to a performance evaluation method for an underground operation team based on a hierarchical analysis method. Background Art
[0002] At present, the performance evaluation of the underground operation management team is mainly based on the effect of specific process measures and economic indicators, without considering factors such as process type, safety and environmental protection, and well control. In addition, there is no unified standard for evaluation, and most of the evaluation indicators are about single measures. It is particularly important to promote problem rectification and improve the quality and management level of underground operations through comprehensive and reasonable evaluation of underground operation teams.
[0003] Liu Jiansheng, Wu Tianjiang, Tian Yuhong and others published a paper titled "Research and Application of Downhole Operation Management System Based on Market-oriented Team" (IFEDC2016689) at the 2016 "Oil and Gas Field Exploration and Development" conference, which introduced a downhole operation information management system, including five modules: measures operation, maintenance operation, information query, design management and system maintenance. The system is responsible for the entry of grassroots personnel to evaluate the performance of the operation effect, and the construction team is automatically evaluated and ranked according to the calculation formula, but the specific calculation method is not clear. Li Xianyong published a 2016 engineering master's thesis "Research on the Management Plan of Contractors for the A Oil Production Plant Project" at China University of Petroleum (East China), which used the contractor evaluation model and selection method based on G-AHP to determine the appropriate contractor for the project, designed a contractor performance evaluation index system including construction quality satisfaction, construction progress control satisfaction, HSE risk control satisfaction and construction technology satisfaction, and dynamically managed the contractors. It did not distinguish between the types of engineering projects, resulting in low downhole operation quality. Summary of the invention
[0004] The purpose of the present invention is to provide a method for evaluating the performance of underground operation teams based on the analytic hierarchy process, which solves the problem of low quality of underground operation in the prior art.
[0005] The technical solution adopted by the present invention is a method for evaluating the performance of underground operation teams based on the hierarchical analysis method, which comprises the following steps:
[0006] Step 1: Determine the performance evaluation indicators for the underground operation team, and set the evaluation standards for each performance evaluation indicator according to the type of operation;
[0007] Step 2: Calculate the weight of each assessment indicator and determine the assessment model of the underground operation team for each operation;
[0008] Step 3: Score the underground operation team for individual assessment indicators according to each operation assessment standard;
[0009] Step 4: Obtain a comprehensive score for the underground operation team based on the scores of the individual assessment indicators and the corresponding underground operation team assessment model;
[0010] Step 5: Evaluate the underground operation team based on the comprehensive score.
[0011] The present invention is also characterized in that:
[0012] The types of operations include maintenance operations, measures operations, overhaul operations, pressure operations, and fracturing and acidizing operations. Corresponding assessment standards are set for the construction progress organization and measures effectiveness of each operation.
[0013] Performance evaluation indicators include management department evaluation indicators and team evaluation indicators. Management department evaluation indicators include standardized management, safe production and performance of production technology managers, department performance, safety, construction progress organization, and problem rectification. Team evaluation indicators include production organization, equipment management, personnel management, data management, construction site management, well control management, effectiveness of measures, process quality, and problem rectification.
[0014] Standardized management indicators include the personnel configuration, department setup, office facilities, and system construction of the contractors belonging to the operating team. The performance indicators of the safety and production technology manager include the execution and on-site verification of the contractors belonging to the operating team. The performance indicators of the department include the safety management, equipment management, and well control management of the contractors belonging to the operating team. The safety indicators include the pollution-free operation rate and well control safety and quality accidents of the contractors belonging to the operating team. The construction progress organization indicators include the cumulative number of completed wells in a preset time period. The problem rectification indicators in the management department's assessment indicators include the rectification of problems found by the contractors belonging to the operating team in the construction site, data construction, well control safety, and construction quality during Party A's preliminary inspection.
[0015] Production organization indicators include well control requirements in the construction design, preparation of materials and equipment according to the construction design before construction, safety measures during the construction process, and oil and water well handover procedures before and after construction; equipment management indicators include the completion of maintenance and servicing of well repair equipment, and compliance of the performance of safety protection equipment with national standards; personnel management indicators include labor protection wear, certification, and mastery of technical standards; data management indicators include data completeness and data review; well control management indicators include on-site well control system formulation, well control equipment management, well control device number management, protection equipment configuration and management, and blowout prevention drills; measure effectiveness indicators include assessment of the construction effect of the operating team; problem rectification indicators in the team assessment indicators are to assess the rectification of problems found by the operating team in the construction site, data construction, well control safety, construction quality, etc. during the preliminary inspection of Party A.
[0016] The assessment criteria for standardized management are: each assessment indicator is given a full score, no score is awarded for failure to complete the above assessment indicator, and preset scores are awarded or deducted for partial completion; the performance assessment criteria for safety and production technology managers are: preset scores are deducted according to the number of safety tasks or on-site safety inspections that are not performed on time;
[0017] Among the department's performance indicators: the safety management assessment standards include the investigation of hidden dangers at the work site, participation in the acceptance inspection, and the emergency medicines on site for the work team. Each missing item will be deducted from the corresponding preset score; the equipment management assessment standard is to calibrate, maintain and service the equipment on time. Each missing item will be deducted from the corresponding preset score; the well control management assessment standard includes the calibration of relevant equipment, well control regular meetings, well control inspections, well control certification, and well control training. Each missing item will be deducted from the corresponding preset score;
[0018] The safety index assessment standard is: full marks for 100% pollution-free operation rate, and preset marks will be deducted if it is lower; no marks will be awarded for well control safety and quality accidents; the construction progress organization assessment standard is: preset marks will be given or deducted according to the number of well completions, and each operation has a corresponding number of well completions and preset marks; the problem rectification assessment standard in the management department assessment index is: whether the contractor to which the operation team belongs has rectified and recorded the problems found in the construction site, data construction, well control safety, and construction quality during the preliminary inspection of Party A on time, and the preset marks will be deducted according to the number of rectifications that were not made on time.
[0019] The production organization assessment standards are: well control requirements in the construction design, preparation of materials and equipment according to the construction design before construction, safety measures during the construction process, and oil and water well handover procedures before and after construction. Pre-set scores will be deducted according to the number of missing items. The equipment management assessment standards are: pre-set scores will be deducted according to the completion of the maintenance of the well repair equipment and the performance of the safety protection equipment in accordance with the national standards. The personnel management assessment standards are: pre-set scores will be deducted according to the number of people who do not wear full labor protection clothes, the number of people who do not hold certificates, and the number of people who do not master technical standards. The data management assessment standards are: if the design data is missing or the review and approval are not completed, no points will be awarded for this item, and the pre-set scores will be deducted according to the number of missing items.
[0020] The assessment standards for well control management are as follows: whether the on-site well control system is fully formulated, and the preset score will be deducted for each missing item; the type and quantity of well control equipment will be deducted according to the number of missing items, and timely maintenance will be deducted according to the number of missing items; the well control equipment is managed by listing, and the score will be deducted according to the number of unnumbered equipment; the configuration and management of protective equipment will be deducted according to the number of missing protective equipment; according to the national standard blowout prevention drill, no score will be awarded if this item is not drilled, and points will be deducted according to the missing items in the drill content;
[0021] The assessment standard for measure effectiveness indicators is: the comparison value between the current effect of each operation and the design effect, and preset scores are given or deducted according to the specific values; the assessment standard for problem rectification in the team assessment indicators is: whether the operating team has promptly rectified and recorded the problems found in the construction site, data construction, well control safety, construction quality, etc. during the preliminary inspection of Party A as required, and the preset scores are deducted according to the number of rectifications that were not made on time.
[0022] Step 2 specifically includes the following steps:
[0023] Step 2.1, determine the importance ratio of each assessment indicator for each task and construct a judgment matrix;
[0024] Step 2.2, perform consistency check on the judgment matrix, if yes, proceed to the next step, otherwise return to the previous step;
[0025] Step 2.3: Calculate the weights of the assessment indicators and obtain the performance assessment model for the underground operation team.
[0026] The method for determining the importance ratio in step 2.1 is:
[0027] Collect the scores of M assessment indicators of N sample underground operation teams for each operation; compare the scores of M assessment indicators in pairs. When the value is <0.5, the importance ratio of the two indicators is 8 or 9; when the value is 0.5-0.7, the importance ratio of the two indicators is 6 or 7; when the value is 0.7-0.9, the importance ratio of the two indicators is 4 or 5; when the value is 0.9-1, the importance ratio of the two indicators is 2 or 3; when the value is 1, the importance ratio of the two indicators is The ratio is 1; when the value is 1.01-1.1, the current importance ratio of the two indicators is 1 / 2 or 1 / 3; when the value is 1.1-1.4, the current importance ratio of the two indicators is 1 / 4 or 1 / 5; when the value is 1.4-2, the current importance ratio of the two indicators is 1 / 6 or 1 / 7; when the value is >2, the current importance ratio of the two indicators is 1 / 8 or 1 / 9; calculate the arithmetic mean of the current importance ratio of the two indicators of N samples to get the current importance ratio of the two indicators.
[0028] Step 2.3 The specific steps are as follows:
[0029] Step 2.3.1, normalize the judgment matrix by column to obtain a normalized judgment matrix;
[0030] Step 2.3.2: Sum and average each row of the normalized judgment matrix to obtain the weight of each assessment indicator, that is, to obtain the underground operation team assessment model for each operation.
[0031] The beneficial effects of the present invention are as follows: the performance evaluation method for underground operation teams of the present invention based on the hierarchical analysis method can realize a comprehensive evaluation of the underground operation teams in terms of basic management such as data, safe production, equipment, materials, personnel, and production organization, risk prevention and control, process quality, operation effect, and problem rectification, and can reasonably adjust the evaluation index weights and scoring standards according to the operation type, so as to realize analysis, evaluation and assessment in a more scientific and efficient manner, which is conducive to improving the quality of underground operations and management level. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 The present invention is a flow chart of the performance evaluation method of underground operation team based on the hierarchical analysis method. DETAILED DESCRIPTION
[0033] The present invention is described in detail below with reference to the accompanying drawings and specific embodiments.
[0034] Example 1
[0035] The performance evaluation method of underground operation team based on hierarchical analysis method includes the following steps:
[0036] Step 1: Determine the performance evaluation indicators for the underground operation team, and set the evaluation standards for each performance evaluation indicator according to the type of operation;
[0037] Step 2: Calculate the weight of each assessment indicator and determine the assessment model of the underground operation team for each operation;
[0038] Step 3: Score the underground operation team for individual assessment indicators according to each operation assessment standard;
[0039] Step 4: Obtain a comprehensive score for the underground operation team based on the scores of the individual assessment indicators and the corresponding underground operation team assessment model;
[0040] Step 5: Evaluate the underground operation team based on the comprehensive score.
[0041] Example 2
[0042] The performance evaluation method of underground operation team based on hierarchical analysis method includes the following steps:
[0043] Step 1: Determine the performance evaluation indicators for the underground operation team, and set the evaluation standards for each performance evaluation indicator according to the type of operation;
[0044] In this embodiment, the types of operations include maintenance operations, measures operations, overhaul operations, pressure operations, and fracturing and acidizing operations. Corresponding assessment standards are set for the construction progress organization and measures effect of each operation.
[0045] Performance evaluation indicators include management department evaluation indicators and team evaluation indicators. Management department evaluation indicators include standardized management, safe production and performance of production technology managers, department performance, safety, construction progress organization, and problem rectification. Team evaluation indicators include production organization, equipment management, personnel management, data management, construction site management, well control management, effectiveness of measures, process quality, and problem rectification.
[0046] Furthermore, the standardized management indicators include the personnel configuration, departmental settings, office facilities, and system construction of the contractors to which the work team belongs. The assessment standards for standardized management are: a full score is set for each assessment indicator. No points will be awarded if the above assessment indicators are not completed. If they are partially completed, the preset scores will be given or deducted accordingly.
[0047] The performance indicators of the safety and production technology manager include the assessment of the execution ability and on-site verification of the contractors belonging to the operating team. The assessment criteria are: deducting preset points according to the number of times safety tasks are not performed on time or on-site safety inspections are not carried out.
[0048] The department's performance indicators include assessing the safety management, equipment management, and well control management of the contractors to which the operating team belongs. The assessment standards are: safety management, investigation of hidden dangers at the operating site, participation in commencement acceptance, and emergency drug supplies for the operating team on site. Each missing item will be deducted from the corresponding preset score; equipment management, calibration, maintenance, and servicing of equipment on time. Each missing item will be deducted from the corresponding preset score; well control management, calibration of relevant equipment, regular well control meetings, well control inspections, well control certification, and well control training. Each missing item will be deducted from the corresponding preset score.
[0049] Safety indicators include the pollution-free operation rate and well control safety and quality accidents of the contractors belonging to the operating team. The assessment standards are: a pollution-free operation rate of 100% will get full marks, and a lower score will be deducted from the preset score; no points will be awarded if a well control safety or quality accident occurs.
[0050] The construction progress organization indicators include the cumulative number of completions in a preset time period. The assessment criteria are: give or deduct preset scores according to the number of completions, and each operation is set with a corresponding number of completions and preset scores.
[0051] The problem rectification indicators in the management department's assessment indicators include the rectification of problems found by the contractors of the operating team in the construction site, data construction, well control safety, and construction quality during the preliminary inspection by Party A. The assessment standard is: whether the contractors of the operating team have rectified and recorded the problems found by Party A in the construction site, data construction, well control safety, and construction quality during the preliminary inspection by Party A on time, and the preset points will be deducted according to the number of rectifications that were not made on time.
[0052] Production organization indicators include well control requirements in the construction design, preparation of materials and equipment according to the construction design before construction, safety measures during construction, and handover procedures for oil and water wells before and after construction; the assessment standards are: well control requirements in the construction design, preparation of materials and equipment according to the construction design before construction, safety measures during construction, and handover procedures for oil and water wells before and after construction. The preset scores will be deducted according to the number of missing items.
[0053] Equipment management indicators include the completion of maintenance of well repair equipment and the compliance of safety protection equipment's performance with national standards; the assessment standard is: deduct preset scores according to the completion of maintenance of well repair equipment and the compliance of safety protection equipment's performance with national standards.
[0054] Personnel management indicators include labor protection wear, certification, and mastery of technical standards; the assessment criteria are: deduct the preset score according to the number of people who do not wear complete labor protection wear, the number of people who do not hold certificates, and the number of people who do not master technical standards.
[0055] Data management indicators include data completeness and data review; the assessment criteria are: if design data is missing or the review and approval are not completed, no points will be awarded for this item, and the preset score will be deducted according to the number of missing items.
[0056] Well control management indicators include on-site well control system formulation, well control equipment management, well control device number management, protection equipment configuration and management, and blowout prevention drills; the assessment criteria are: whether the on-site well control system is completely formulated, with a preset score deducted for each missing item; type and quantity of well control equipment, with points deducted according to the number of missing items, and timely maintenance, with points deducted according to the number of missing items; well control devices are managed with signs, with points deducted according to the number of unnumbered devices; protection equipment configuration and management, with points deducted according to the number of missing protective equipment; and blowout prevention drills according to national standards, no points will be awarded if this item is not exercised, and points will be deducted according to the missing items in the drill content.
[0057] The measure effect index includes the construction effect of the assessment team; the assessment standard is: the comparison value of the current effect of each operation with the design effect, and the preset score is given or deducted according to the specific value. Specifically, the assessment standards for measure operations and fracturing and acidizing operations include: the percentage of the average daily oil increase of oil wells to the geological design oil increase, the percentage of water injection wells after injection and geological injection, and the preset score is given or deducted according to the specific value; the assessment standards for maintenance operations include: the percentage of liquid production during the warranty period of oil wells to the normal level of liquid before well repair, the percentage of production injection to the design level, the number of wells that reach the geological injection inspection string and the number of reworked wells during the warranty period of water injection wells, and the preset score is given or deducted according to the specific value; the assessment standards for overhaul operations include: giving or deducting preset points according to whether the design purpose is achieved; the assessment standards for pressure operations include: giving or deducting preset points whether the water injection meets the normal injection requirements.
[0058] The problem rectification indicator in the team assessment index is to assess the rectification of the problems found by the operating team in the construction site, data construction, well control safety, construction quality, etc. during the preliminary inspection of Party A; the assessment standard is: whether the operating team has rectified and recorded the problems found by Party A in the construction site, data construction, well control safety, construction quality, etc. during the preliminary inspection of Party A in a timely manner as required, and the preset points will be deducted according to the number of rectifications not made on time.
[0059] Step 2: Calculate the weight of each assessment indicator and determine the assessment model of the underground operation team for each operation;
[0060] Specifically, step 2.1, determine the importance ratio of each assessment indicator of each task and construct a judgment matrix;
[0061] Step 2.2, perform consistency check on the judgment matrix, if yes, proceed to the next step, otherwise return to the previous step;
[0062] Step 2.2.1, calculate the consistency index CI:
[0063]
[0064] In the formula, n is the number of indicators, λ max is the maximum eigenvalue of the judgment matrix;
[0065] Step 2.2.2, calculate the consistency ratio CR:
[0066]
[0067] Among them, RI is the random consistency index, and the RI value corresponding to n can be obtained by looking up the table;
[0068] Step 2.2.3: If the RI value is less than 0.1, the consistency is satisfied and go to the next step; otherwise, return to the previous step.
[0069] Step 2.3: Calculate the weights of the assessment indicators and obtain the performance assessment model for the underground operation team.
[0070] Step 3: Score the underground operation team for individual assessment indicators according to each operation assessment standard;
[0071] Step 4: Obtain a comprehensive score for the underground operation team based on the scores of the individual assessment indicators and the corresponding underground operation team assessment model;
[0072] Step 5: Evaluate the underground operation team based on the comprehensive score.
[0073] Example 3
[0074] The performance evaluation method of underground operation team based on hierarchical analysis method includes the following steps:
[0075] Step 1: Determine the performance evaluation indicators for the underground operation team, and set the evaluation standards for each performance evaluation indicator according to the type of operation;
[0076] The types of operations include maintenance operations, measures operations, overhaul operations, pressure operations, and fracturing and acidizing operations. Corresponding assessment standards are set for the construction progress organization and measures effectiveness of each operation.
[0077] Performance evaluation indicators include management department evaluation indicators and team evaluation indicators. Management department evaluation indicators include standardized management, safe production and performance of production technology managers, department performance, safety indicators, construction progress organization, and problem rectification. Team evaluation indicators include production organization, equipment management, personnel management, data management, construction site management, well control management, effectiveness of measures, process quality, and problem rectification.
[0078] Standardized management includes assessing the personnel configuration, department setting, office support, and system construction of the contractors to which the operation team belongs. In this embodiment, the assessment criteria are as follows: Personnel configuration: no score if no full-time safety and production technology manager is assigned, 5 points for each safety or production technology manager assigned, and the full score is 10 points; Department setting: no score if no functional department responsible for on-site safety and technical management is set up, 5 points for the combined operation of the safety and technical departments, and 5 points for the establishment of a safety or technical department, and the full score is 10 points; Office support: no score if no centralized office space is configured, 10 points will be deducted for each missing item of office equipment (computers, printers, cameras, etc.) and production site command vehicles, and the full score is 50 points; System construction: Classify and establish the company and the operation team's HSE, safety, technology, quality, well control and other management systems, and 5 points will be deducted for each missing item, and the full score is 30 points.
[0079] The duties of the safety and production technology manager include assessing the execution and on-site verification of the contractors of the operating team. The specific assessment standards are as follows: execution, organizing the team to make repairs on time, and deducting 10 points for each untimely repair; on-site verification, conducting a safety inspection on the team once a month focusing on well control, safety, technical quality, data, etc., and getting full marks for personally participating and keeping records, and deducting 20 points for only organizing but not participating once.
[0080] The department's duties include assessing the safety management, equipment management, and well control management of the contractors of the operation team. The specific safety management assessment standards are as follows: Safety management: full marks for full supervision of each well, 10 points will be deducted for each failure to supervise the following processes: relocation, well cleaning, lifting and lowering of large-diameter tools, wellhead replacement, perforation, fracturing, acidizing, completion, drilling, grinding, and milling. For other processes, 5 points will be deducted for each failure to supervise, and the deduction will be continued; for acceptance inspection, 10 points will be deducted for each failure to personally participate, and the deduction will be continued; for emergency medicines on site of the operation team, 2 points will be deducted for each failure to meet the expiration or incomplete types. Equipment management: equipment (well repair vehicles, derricks, etc.) shall be recorded, maintained, and serviced, and well repair vehicles and other equipment shall be calibrated, maintained, and serviced in a timely manner. 2 points will be deducted for each failure, and the deduction will be continued. In terms of well control management, well control and protective equipment calibration, 10 points will be deducted if one piece of equipment is not calibrated on time, and no points will be awarded for well control management of more than two pieces of equipment; in terms of well control regular meetings, they are held regularly every month, and no points will be awarded if they are not held in time; in terms of well control inspections, they are conducted once a month, and no points will be awarded if they are not conducted in time; in terms of well control inspection items, 2 points will be deducted if one item is missing; in terms of well control certification, 3 points will be deducted if one person is missing, and no points will be awarded if more than five people are not certified; in terms of well control training, it is conducted once a month, and no points will be awarded if it is not organized in time, and 1 point will be deducted for each time the lesson plans and notes are incomplete.
[0081] Safety indicators include the pollution-free operation rate and well control safety and quality accidents of the contractors belonging to the operating team. The specific assessment standards are: 100% pollution-free operation rate will get full marks, and 25 points will be deducted for each percentage point decrease; for well control safety and quality accidents, no points will be awarded for each accident that occurs.
[0082] The construction progress organization index is the cumulative number of well completions in a preset time period. The score = the sum of the scores of the assessment teams / the total number of contractor teams. The assessment standard is: give or deduct preset scores according to the number of well completions, and each operation is set with a corresponding number of well completions and preset scores. The details are as follows:
[0083] Measures and operations: Full marks will be awarded if the cumulative number of completed wells is ≥ 9 in a quarter, 10 marks will be deducted for each well reduced, and no marks will be awarded for less than 2 completed wells. Each completed horizontal well will be converted into 2 normal wells.
[0084] Maintenance work: full marks will be awarded for a cumulative completion of ≥33 wells in a quarter, and 5 points will be deducted for each well reduced until all points are deducted. For lifting, deepening the pump hanger, replacing the light rod, etc., every 4 wells will be converted into 1 pump inspection well, and every 2 wells for inspection and production will be converted into 1 pump inspection well.
[0085] Overhaul operations: Full marks will be awarded if the cumulative number of completed wells in a quarter is ≥ 5. 20 points will be deducted for each well reduced. No points will be awarded for less than 2 wells.
[0086] Pressure work: Full marks will be awarded if the cumulative completion of ≥ 9 wells in a quarter, 15 marks will be deducted for each well reduced, and no marks will be awarded for less than 2 wells completed. For special work such as wellhead replacement, every 5 wells will be converted into 1 well for normal work.
[0087] Fracturing and acidizing operations: 5 points for each completed well.
[0088] The problem rectification indicators include assessing whether the contractors of the operating team have rectified and recorded the problems found in the construction site, data construction, well control safety, construction quality, etc. during Party A's preliminary inspection on time. If one problem is not rectified within the specified time, 50 points will be deducted.
[0089] Production organization indicators include well control requirements in the construction design, preparation of materials and equipment according to the construction design before construction, safety measures during construction, and oil and water well handover procedures before and after construction. The specific assessment standards are: well control requirements such as equipment, tools, materials, etc. in the construction design, 5 points will be deducted for each missing item; preparation of required materials, tools, well control equipment and fire-fighting facilities according to the design before construction, 10 points will be deducted for each missing item; detection and protection measures for harmful gases such as hydrogen sulfide during construction, 5 points will be deducted for each missing item; handover procedures for oil and water wells before and after construction, 10 points will be deducted for each missing item.
[0090] Equipment management includes the completion of maintenance of well repair equipment and compliance of the performance of safety protection equipment with national standards. The specific assessment standards are: equipment is regularly maintained and records are complete, 10 points will be deducted for each equipment use accident and 5 points will be deducted for each failure to maintain equipment; the equipment fire cover must comply with the performance requirements of national standard GB13365-2005, and 10 points will be deducted for each non-compliance.
[0091] Personnel management indicators include wearing of labor protection, holding of certificates, and mastery of technical standards. The assessment criteria are: according to the number of people who do not wear complete labor protection, the number of people who do not hold certificates, and the number of people who do not master technical standards, each person will be deducted a preset score. In this embodiment, 25 points will be deducted for each person who does not wear complete labor protection; 25 points will be deducted for each person who does not hold a certificate; and 10 points will be deducted for each person who is not familiar with the operation risks and mitigation measures and related technical standards.
[0092] The data management indicators include data completeness and data review. The assessment criteria are: no points will be awarded for missing design data or incomplete review and approval. 10 points will be deducted for each missing item and 5 points will be deducted for each error.
[0093] Well control management indicators include on-site well control system formulation, well control equipment management, well control device number management, protection equipment configuration and management, and blowout prevention exercises. Specific assessment standards are: on-site well control system formulation, setting up a post observation system, a cadre duty system, and a well control regular meeting system. If one item is missing, 5 points will be deducted; well control equipment management, well control equipment types and quantities, well control equipment on-site pressure testing and inspection and maintenance, if one item is missing, no points will be awarded, and if one item is not repaired and maintained, 10 points will be deducted; number management, well control equipment is managed by listing, and if one item (set) is not numbered, 5 points will be deducted; protection equipment configuration and management, if one portable multi-gas detection instrument and protective equipment is missing, no points will be awarded, and if one item is not intact, 5 points will be deducted; blowout prevention exercises, implement the provisions of standard SY / T6610-2005 / 10.2.3, if this item is not exercised, no points will be awarded, and if one item is missing in the exercise content, 5 points will be deducted.
[0094] The effectiveness indicators of measures include the assessment of the construction effect of the operating team. The assessment criteria are: the comparison value between the current effect of each operation and the design effect, and the preset score is given or deducted according to the specific value.
[0095] The specific assessment criteria are:
[0096] (a) Measures: If the oil well is opened normally for more than 30 days after the completion of the measures, and the average daily oil increase is greater than or equal to the geological design oil increase, each well will be awarded 10 points; if the average daily oil increase is greater than or equal to 80% of the geological design oil increase but less than 100%, each well will be awarded 8 points; if the average daily oil increase is greater than or equal to 60% of the geological design oil increase but less than 80%, each well will be awarded 3 points; if it is less than 60% of the geological design oil increase, no points will be awarded. If the water injection well is opened normally for 30 days after the injection measures are taken, and the geological injection reaches 100%, each well will be awarded 8 points; if the geological injection reaches 100-80%, each well will be awarded 3 points; if the geological injection reaches 80-60%, each well will be awarded 1 point; if it is less than 60% of the geological injection, no points will be awarded.
[0097] Maintenance work: If the liquid production of an oil well reaches 100% or more of the normal level before well repair during the warranty period, 3 points will be awarded for each well; if the production volume reaches more than 100% of the design level during the warranty period, 2 points will be awarded for each well; if the production volume reaches 80%-100% of the design level during the warranty period, 1 point will be awarded for each well that has been reworked, until all points are deducted; if a water injection well reaches the geological matching and injection inspection during the warranty period, 1 point will be awarded for each well that has been reworked, and 8 points will be deducted for each well that has been reworked, until all points are deducted.
[0098] Overhaul work: 20 points will be awarded for each well that achieves the design objective, and no points will be awarded for failing to achieve the objective; 30 points will be deducted for each well that causes wellbore complexity.
[0099] Operation under pressure: If the water injection reaches 100% of the normal injection requirement, 10 points will be awarded for each well; if the return water volume is ≥ 8 cubic meters, 15 points will be deducted for each well until all points are deducted.
[0100] Fracturing and acidizing operations: If the oil well is opened normally for more than 30 days after the completion of the well measures, and the average daily oil increase is greater than or equal to the geological design oil increase, each well will be awarded 3 points; if the average daily oil increase is greater than or equal to 80% and less than 100% of the geological design oil increase, each well will be awarded 2 points; if the average daily oil increase is greater than or equal to 60% and less than 80% of the geological design oil increase, each well will be awarded 1 point; if it is less than 60% of the geological design oil increase, no points will be awarded; if the water injection well is opened normally for 30 days after the injection measures, and reaches 100% of the geological injection, each well will be awarded 3 points; if it reaches 100-80% of the geological injection, each well will be awarded 2 points; if it reaches 80-60% of the geological injection, each well will be awarded 1 point; if it is less than 60% of the geological injection, no points will be awarded.
[0101] The problem rectification indicator is to assess whether the operating team has promptly rectified and recorded the problems found in the construction site, data construction, well control safety, construction quality, etc. during the preliminary inspection by Party A as required. 50 points will be deducted if one problem is not rectified within the specified time.
[0102] Step 2: Calculate the weight of each assessment indicator and determine the assessment model of the underground operation team for each operation;
[0103] Specifically, step 2.1, determine the importance ratio of each assessment indicator of each task and construct a judgment matrix;
[0104] Collect the scores of M assessment indicators of N sample underground operation teams for each operation; compare the scores of M assessment indicators in pairs. When the value is <0.5, the importance ratio of the two indicators is 8 or 9; when the value is 0.5-0.7, the importance ratio of the two indicators is 6 or 7; when the value is 0.7-0.9, the importance ratio of the two indicators is 4 or 5; when the value is 0.9-1, the importance ratio of the two indicators is 2 or 3; when the value is 1, the importance ratio of the two indicators is The ratio is 1; when the value is 1.01-1.1, the current importance ratio of the two indicators is 1 / 2 or 1 / 3; when the value is 1.1-1.4, the current importance ratio of the two indicators is 1 / 4 or 1 / 5; when the value is 1.4-2, the current importance ratio of the two indicators is 1 / 6 or 1 / 7; when the value is >2, the current importance ratio of the two indicators is 1 / 8 or 1 / 9; calculate the arithmetic mean of the current importance ratio of the two indicators of N samples to get the current importance ratio of the two indicators.
[0105] Step 2.2, perform consistency check on the judgment matrix, if yes, proceed to the next step, otherwise return to the previous step;
[0106] Step 2.2.1, calculate the consistency index CI:
[0107]
[0108] In the formula, n is the number of indicators, λ maxis the maximum eigenvalue of the judgment matrix;
[0109] Step 2.2.2, calculate the consistency ratio CR:
[0110]
[0111] Among them, RI is the random consistency index, and the RI value corresponding to n can be obtained by looking up the table;
[0112] Step 2.2.3: If the RI value is less than 0.1, the consistency is satisfied and go to the next step; otherwise, return to the previous step.
[0113] Step 2.3: Calculate the weights of the assessment indicators and obtain the performance assessment model for the underground operation team.
[0114] Step 2.3.1, normalize the judgment matrix by column to obtain a normalized judgment matrix;
[0115] Step 2.3.2: Sum and average each row of the normalized judgment matrix to obtain the weight of each assessment indicator, that is, to obtain the underground operation team assessment model for each operation.
[0116] Step 3: Score the underground operation team for individual assessment indicators according to each operation assessment standard;
[0117] Step 4: Obtain a comprehensive score for the underground operation team based on the scores of individual assessment indicators and the corresponding underground operation team assessment model; specifically, multiply the score of each assessment indicator by the corresponding assessment indicator weight, and then sum them up to obtain the comprehensive score for the underground operation team.
[0118] Step 5: Evaluate the underground operation team based on the comprehensive score.
[0119] In this embodiment, if the total score is <60 points, it is considered unqualified; if 60 points ≤ total score <70 points, it is considered basically qualified; if 70 points ≤ total score <90 points, it is considered qualified; if the total score is ≥90 points, it is considered excellent.
[0120] Example 4
[0121] Taking a certain measures operation team as an example, its contractor completed 7 wells in a certain quarter, and the wells were opened normally for more than 30 days after completion. The average daily oil increase of 4 wells was greater than the geological design oil increase, the average daily oil increase of 2 wells reached 85% of the geological design oil increase, and the average daily oil increase of 1 well reached 75% of the geological design oil increase.
[0122] The performance evaluation method of underground operation team based on hierarchical analysis method includes the following steps:
[0123] Step 1: Determine 6 management department assessment indicators, including standard management, performance of production safety and production technology managers, performance of departmental duties, safety indicators, construction progress organization, and problem rectification, and 9 team assessment indicators, including production organization, equipment management, personnel management, data management, construction site management, well control management, measure effect, process quality, and problem rectification, for a total of 15 performance assessment indicators for underground operation teams; the assessment standards are the assessment standards for measure operations;
[0124] Step 2: Determine the importance ratio of each pair of assessment indicators of the current measure operation and construct a judgment matrix;
[0125] Table 1: Judgment matrix for performance evaluation of measures
[0126]
[0127]
[0128] Among them, A-standard management, B-performance of production safety and production technology manager, C-performance of department, D-safety index, E-construction progress organization, F-problem rectification, G-production organization, H-equipment management, I-personnel management, J-data management, K-construction site management, L-well control management, M-measure effect, N-process quality, O-problem rectification,
[0129] Let i be the number of rows and j be the number of columns, then the meaning of the element Aij in the judgment matrix is: the importance of the i-th indicator relative to the j-th indicator.
[0130] Calculate the consistency index CI:
[0131]
[0132] In the above formula, n = 15, λ max =15.046, CI=0.0032;
[0133] Calculate the consistency ratio CR:
[0134]
[0135] In the above formula, n = 15, RI = 1.59, CR = 0.002;
[0136] Then CR=0.002<0.1, which satisfies consistency.
[0137] Normalize the judgment matrix by column, such as A11, and calculate it as:
[0138]
[0139] Get the normalized judgment matrix:
[0140] Table 2: Judgment matrix for performance evaluation of measures
[0141]
[0142]
[0143] Each row is summed and averaged to get the weight of each assessment indicator. For example, the weight of assessment indicator A is calculated as:
[0144]
[0145] Finally, the weights of 15 assessment indicators of the measure operation team are obtained, that is, the assessment model of the measure operation team is:
[0146] [0.084, 0.049, 0.198, 0.026, 0.094, 0.049, 0.027, 0.058, 0.026, 0.027, 0.087, 0.094, 0.084, 0.049, 0.049]
[0147] Step 3: Score the underground operation team for individual assessment indicators according to each operation assessment standard;
[0148] Construction progress organization scoring standard: full score for cumulative completion of ≥9 wells in a quarter, 10 points will be deducted for each well reduced, and no points will be awarded for less than 2 wells;
[0149] Scoring standard for measures effect: if the oil well is opened normally for more than 30 days after the completion of the measures, and the average daily oil increase is greater than or equal to the geological design oil increase, each well will get 10 points; if it is ≥80% and <100%, each well will get 8 points; if it is ≥60% and <80%, each well will get 3 points; if it is <60%, no points will be awarded;
[0150] The underground operation management department scores the assessment indicators of the management department to which the team belongs, the underground operation supervision department scores the assessment indicators of production organization, equipment management, personnel management, data management, construction site management, well control management, process quality, etc., and the underground operation unit scores the effectiveness of the measures. The scores of the individual assessment indicators of the team for this measure are: [100, 80, 82, 100, 80, 100, 95, 90, 95, 90, 95, 59, 50, 100].
[0151] Step 4: Multiply the score of each assessment indicator by the corresponding assessment indicator weight, and then sum them up to get the comprehensive score of the underground operation team, which is 86.3 points;
[0152] Step 5. Based on the classification evaluation standards, the team responsible for this measure is evaluated as qualified and can continue to be selected to further strengthen problem rectification.
[0153] Through the above methods, the performance evaluation method of the underground operation team based on the hierarchical analysis method of the present invention can realize a comprehensive evaluation of the underground operation team in basic management such as data, safe production, equipment, materials, personnel, and production organization, risk prevention and control, process quality, operation effect, problem rectification, etc., and reasonably adjust the evaluation index weights and scoring standards according to the operation type, which can realize analysis, evaluation and assessment more scientifically and efficiently, and is conducive to improving the quality of underground operations and management level.
Claims
1. The performance evaluation method of underground operation team based on hierarchical analysis method is characterized by: The following steps are involved: Step 1: Determine the performance evaluation indicators for the underground operation team, and set the evaluation standards for each performance evaluation indicator according to the type of operation; Step 2: Calculate the weight of each assessment indicator and determine the assessment model of the underground operation team for each operation; Step 3: Score the underground operation team for individual assessment indicators according to each operation assessment standard; Step 4: Obtain a comprehensive score for the underground operation team based on the scores of the individual assessment indicators and the corresponding underground operation team assessment model; Step 5: Evaluate the underground operation team based on the comprehensive score.
2. The method for evaluating the performance of underground operation teams based on the analytic hierarchy process as claimed in claim 1, characterized in that: The types of operations include maintenance operations, measures operations, overhaul operations, pressure operations, and fracturing and acidizing operations. Corresponding assessment standards are set for the construction progress organization and measures effectiveness of each operation.
3. The method for evaluating the performance of underground operation teams based on the analytic hierarchy process as claimed in claim 2, characterized in that: The performance evaluation indicators include management department evaluation indicators and team evaluation indicators. The management department evaluation indicators include standardized management, safe production and performance of production technology managers, department performance, safety, construction progress organization, and problem rectification. The team evaluation indicators include production organization, equipment management, personnel management, data management, construction site management, well control management, effectiveness of measures, process quality, and problem rectification.
4. The method for evaluating the performance of underground operation teams based on the analytic hierarchy process as claimed in claim 3, characterized in that: The standardized management indicators include the personnel configuration, department setting, office facilities, and system construction of the contractors belonging to the operating team; the performance indicators of the safety and production technology manager include the execution and on-site verification of the contractors belonging to the operating team; the department performance indicators include the safety management, equipment management, and well control management of the contractors belonging to the operating team; the safety indicators include the pollution-free operation rate and well control safety and quality accidents of the contractors belonging to the operating team; the construction progress organization indicators include the cumulative number of completed wells in a preset time period; the problem rectification indicators in the management department assessment indicators include the rectification of problems found by the contractors belonging to the operating team in the construction site, data construction, well control safety, and construction quality during Party A's preliminary inspection.
5. The method for evaluating the performance of underground operation teams based on the analytic hierarchy process as claimed in claim 3, characterized in that: The production organization indicators include the well control requirements in the construction design, the preparation of materials and equipment according to the construction design before construction, the safety measures during the construction process, and the handover procedures of oil and water wells before and after construction; the equipment management indicators include the completion of the maintenance of well repair equipment, and the compliance of the performance of safety protection equipment with national standards; the personnel management indicators include labor protection wear, certification, and mastery of technical standards; the data management indicators include data completeness and data review; the well control management indicators include on-site well control system formulation, well control equipment management, well control device number management, protection equipment configuration and management, and blowout prevention drills; the measure effectiveness indicators include the assessment of the construction effect of the operating team; the problem rectification indicators in the team assessment indicators are the assessment of the operating team's rectification of problems found in the construction site, data construction, well control safety, and construction quality during Party A's preliminary inspection.
6. The method for evaluating the performance of underground operation teams based on the analytic hierarchy process as claimed in claim 4, characterized in that: The assessment criteria for standardized management are: full marks are set for each assessment indicator, no marks are awarded for failure to complete the above assessment indicator, and preset marks are awarded or deducted for partial completion; the performance assessment criteria for safety and production technology managers are: preset marks are deducted according to the number of safety tasks or on-site safety inspections that are not performed on time; Among the performance indicators of the departments mentioned above: the safety management assessment standards include the investigation of hidden dangers at the work site, participation in the acceptance inspection of the commencement of work, and the emergency medicines on site for the work team. For each missing item, the corresponding preset score will be deducted; the equipment management assessment standards include the calibration, maintenance and servicing of equipment on time. For each missing item, the corresponding preset score will be deducted; the well control management assessment standards include the calibration of relevant equipment, well control regular meetings, well control inspections, well control certification, and well control training. For each missing item, the corresponding preset score will be deducted; The safety index assessment standard is: full marks for 100% pollution-free operation rate, and preset marks will be deducted if the rate is lower than the above limit; no marks will be awarded for well control safety or quality accidents; the construction progress organization assessment standard is: preset marks will be awarded or deducted according to the number of well completions, and each operation has a corresponding number of well completions and preset marks; the problem rectification assessment standard in the management department assessment indicator is: whether the contractor to which the operating team belongs has rectified and recorded the problems found in the construction site, data construction, well control safety, and construction quality during Party A's preliminary inspection on time, and the preset marks will be deducted according to the number of rectifications that were not made on time.
7. The method for evaluating the performance of underground operation teams based on the analytic hierarchy process as claimed in claim 5, characterized in that: The production organization assessment standards are: well control requirements in the construction design, preparation of materials and equipment according to the construction design before construction, safety measures during the construction process, and oil and water well handover procedures before and after construction. Pre-set scores will be deducted according to the number of missing items; the equipment management assessment standards are: pre-set scores will be deducted according to the completion of the maintenance of the well repair equipment and the compliance of the performance of the safety protection equipment with the national standards; the personnel management assessment standards are: pre-set scores will be deducted according to the number of people who do not wear full labor protection clothes, the number of people who do not hold certificates, and the number of people who do not master technical standards; the data management assessment standards are: if the design data is missing or the review and approval are not completed, no points will be awarded for this item, and the pre-set scores will be deducted according to the number of missing items; The assessment standards for well control management are as follows: whether the on-site well control system is fully formulated, and the preset score will be deducted for each missing item; the type and quantity of well control equipment, points will be deducted according to the number of missing items; timely maintenance, points will be deducted according to the number of missing items; well control equipment is managed by listing, points will be deducted according to the number of unnumbered equipment; the configuration and management of protective equipment, points will be deducted according to the number of missing protective equipment; according to the national standard blowout prevention drill, no points will be awarded if this item is not drilled, and points will be deducted according to the missing items in the drill content; The assessment standard for the effectiveness of the measures is: the comparison value between the current effect of each operation and the design effect, and a preset score is given or deducted according to the specific value; the assessment standard for problem rectification in the team assessment indicator is: assess whether the operating team has promptly rectified and recorded the problems found in the construction site, data construction, well control safety, and construction quality during Party A's preliminary inspection as required, and deduct the preset score according to the number of rectifications that were not made on time.
8. The method for evaluating the performance of underground operation teams based on the analytic hierarchy process as claimed in claim 1, characterized in that: Step 2 specifically includes the following steps: Step 2.1, determine the importance ratio of each assessment indicator for each task and construct a judgment matrix; Step 2.2, perform consistency check on the judgment matrix, if yes, proceed to the next step, otherwise return to the previous step; Step 2.3: Calculate the weights of the assessment indicators and obtain the performance assessment model for the underground operation team.
9. The method for evaluating the performance of underground operation teams based on the analytic hierarchy process as claimed in claim 8, characterized in that: The method for determining the importance ratio in step 2.1 is: Collect the scores of M assessment indicators of N sample underground operation teams for each operation; compare the scores of M assessment indicators in pairs. When the value is <0.5, the importance ratio of the two indicators is 8 or 9; when the value is 0.5-0.7, the importance ratio of the two indicators is 6 or 7; when the value is 0.7-0.9, the importance ratio of the two indicators is 4 or 5; when the value is 0.9-1, the importance ratio of the two indicators is 2 or 3; when the value is 1, the importance ratio of the two indicators is The ratio is 1; when the value is 1.01-1.1, the current importance ratio of the two indicators is 1 / 2 or 1 / 3; when the value is 1.1-1.4, the current importance ratio of the two indicators is 1 / 4 or 1 / 5; when the value is 1.4-2, the current importance ratio of the two indicators is 1 / 6 or 1 / 7; when the value is >2, the current importance ratio of the two indicators is 1 / 8 or 1 / 9; calculate the arithmetic mean of the current importance ratio of the two indicators of N samples to get the current importance ratio of the two indicators.
10. The method for evaluating the performance of underground operation teams based on the analytic hierarchy process as claimed in claim 8, characterized in that: Step 2.3 The specific steps are as follows: Step 2.3.1, normalize the judgment matrix by column to obtain a normalized judgment matrix; Step 2.3.2: Sum and average each row of the normalized judgment matrix to obtain the weight of each assessment indicator, that is, to obtain the underground operation team assessment model for each operation.