Vulcanization forming device and method for producing rubber sealing ring

By designing the nozzle adjustment assembly and the concentricity adjustment assembly in the vulcanization molding device, high-precision concentricity adjustment between the nozzle and the central hole of the mold is achieved, solving the problem that manual adjustment in the prior art is difficult to ensure accuracy and concentricity deviation due to wear, and improving production efficiency and product quality.

CN120002966APending Publication Date: 2025-05-16WUHAN ARAI OIL SEAL MFG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510205208.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-02-24
Publication Date
2025-05-16

AI Technical Summary

Technical Problem

The existing injection molding vulcanization molding machine needs to manually adjust the concentricity of the injection nozzle and the central hole of the mold before use, which is difficult to ensure high accuracy, and the concentricity shifts due to wear, resulting in a large number of defective products.

Method used

A vulcanization forming device including a nozzle adjustment assembly and a concentricity adjustment assembly is designed to ensure the concentricity of the nozzle and the central hole of the mold by automatically adjusting the nozzle during the mold closing process.

Benefits of technology

High-precision concentricity adjustment between the nozzle and the central hole of the mold is achieved, reducing the generation of defective products, improving production efficiency and product quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120002966A_ABST
    Figure CN120002966A_ABST
Patent Text Reader

Abstract

The invention relates to a vulcanization forming device and method for producing a rubber sealing ring. Rubber ring production raw materials are added into the feeding cavity and conveyed to the charging barrel through the feeding cavity to be heated, and the first transmission piece is controlled to drive the guide table to generate upward displacement, so that the guide table drives the movable mold base to generate upward displacement and form a mold closing state with the fixed mold base; meanwhile, the movable mold base drives a concentricity adjusting assembly to adjust the concentricity of an injection assembly, and an electric push rod is controlled to drive an injection nozzle adjusting assembly and a second transmission part to enable an injection nozzle to generate a downward displacement effect until a limiting table makes contact with the top of a limiting base; at the moment, the nozzle is just inserted into a center hole in the top of the fixed mold base and forms sealing, a second transmission piece is controlled to drive a screw rod in a charging barrel to rotate, and in the rotating process of the screw rod, molten rubber raw materials in the charging barrel can be injected into a forming sliding block to achieve vulcanization forming of a rubber ring.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of vulcanization molding devices, in particular to a vulcanization molding device and a method for producing a rubber sealing ring. Background Art

[0002] Injection vulcanization molding machine is a special equipment that uses injection molding or injection molding to vulcanize. The injection vulcanization molding machine uses a screw or plunger to inject the preheated rubber into the mold cavity at high pressure and high speed, and then vulcanizes it. In this process, the rubber material is molded and vulcanized in the mold to form the desired rubber product. The concentricity between the nozzle and the mold gate is crucial to the injection quality of the injection molding machine. If the concentricity is offset, the molten rubber may not be injected into the mold cavity evenly and accurately, resulting in uneven injection pressure distribution, excessive or low pressure in some areas, poor rubber flow in the mold cavity, eddy currents or dead corners, and affecting the uniformity of crosslinking density; However, in the prior art, the injection vulcanization molding machine usually requires the staff to manually adjust the vulcanization molding machine before use to ensure the concentricity of the injection nozzle and the center hole of the mold; this method has great disadvantages. On the one hand, manual adjustment often relies on the experience and feeling of the staff, and it is difficult to achieve high-precision adjustment requirements; on the other hand, the injection vulcanization molding machine may be deformed due to wear after repeated use, resulting in the difficulty of the injection nozzle to maintain perfect concentricity with the center hole of the mold, and the staff cannot predict in advance that continued production will result in a large number of defective products; therefore, a vulcanization molding device and method for producing rubber sealing rings are proposed to solve the above problems. Summary of the invention

[0003] In view of the shortcomings of the prior art, the present invention provides a vulcanization molding device and method for producing rubber sealing rings, which have the advantages of being able to automatically adjust the nozzle during the mold closing process, etc., solving the problems in the prior art that manual adjustment by staff is difficult to ensure accuracy and concentricity deviation cannot be detected during the operation process.

[0004] To achieve the above-mentioned object, the present invention provides the following technical solution: a vulcanization molding device for producing a rubber sealing ring, comprising a body, the body is provided with a feeding chamber for conveying raw materials and an injection assembly for injection, the feeding chamber is connected with the injection assembly, and the injection assembly is provided with a nozzle adjustment assembly for adjustment; The machine body is also provided with a first transmission member for transmission and a limit seat for limiting, a fixed mold is arranged at the bottom of the limit seat, the first transmission member is transmission-connected to a guide platform, a movable mold is arranged at the top of the guide platform, and a concentricity adjustment component for correcting deviation is also arranged at the top of the limit seat.

[0005] Furthermore, no less than four guide posts are arranged between the first transmission member and the limiting seat, and the guide platform and the guide posts are maintained in sliding connection.

[0006] Furthermore, the injection assembly includes an electric push rod for transmission, the push rod end of the electric push rod is connected to a nozzle adjustment assembly, a second transmission member is provided at the bottom of the nozzle adjustment assembly, a plurality of connecting columns are connected to the bottom of the second transmission member, the other end of the connecting column is connected to a barrel, a screw is provided in the barrel, the output shaft of the second transmission member is transmission-connected to the screw, and a nozzle for injection is provided at the bottom of the barrel.

[0007] Furthermore, a limiting platform for limiting position is also provided on the barrel.

[0008] Furthermore, the movable mold includes a movable mold base, which is provided with at least one slide rail, and two molding sliders are slidably connected in the slide rail, and both molding sliders are provided with guide post holes for guiding, and both molding sliders are provided with molding cavities for molding, and a linkage rod is also provided on the top of the movable mold base, and the linkage rod is transmission-connected to the concentricity adjustment component, and the movable mold base is also provided with an ejection mechanism for stripping, and the movable mold base is also provided with a positioning hole for positioning, and the movable mold base is also provided with a linkage rod, and the linkage rod is slidably connected to the fixed mold.

[0009] Furthermore, the fixed die includes a fixed die seat, the fixed die seat is provided with a connecting groove adapted to the forming slider, the connecting groove is provided with a positioning block, an inclined guide column and a positioning column for guiding, and the fixed die seat is also provided with a linkage hole for guiding.

[0010] Furthermore, the nozzle adjustment assembly includes a first connecting plate, a second connecting plate and a third connecting plate, the first connecting plate has a first adjustment groove at the bottom, the second connecting plate has a second adjustment groove at the bottom, the second connecting plate has a first slider at the top, the first slider is slidably connected to the first adjustment groove, the third connecting plate has a second slider at the top, the second slider is slidably connected to the second adjustment groove.

[0011] Further, the concentricity adjustment assembly includes a mounting seat, the top of the mounting seat is rotatably connected to a connecting platform, the connecting platform is provided with worm gears, the top of the connecting platform is fixedly connected to a support column, the other end of the support column is fixedly connected to a mounting ring, the mounting ring is rotatably connected to a connecting shaft, and the bottom of the connecting shaft is provided with a guide frame; The top of the mounting seat is provided with mounting columns whose number matches the guide frame, the mounting columns are rotatably connected with a correction arm, the correction arm is slidably connected to the guide frame, the other end of the correction arm is rotatably connected with a correction wheel, and the correction wheel is rotatably connected with a plurality of sliding wheels.

[0012] Furthermore, a worm for transmission is also provided on the top of the mounting seat, one end of the worm is rotatably connected to a linkage gear, the linkage gear is transmission-connected to a linkage rack, and the bottom of the linkage rack is fixedly connected to the linkage rod.

[0013] Further, the vulcanization molding method for producing the rubber sealing ring comprises the following steps: S1. Add the raw materials for rubber ring production into the feeding chamber, and transport them to the barrel through the feeding chamber to heat the raw materials; S2, controlling the first transmission member to drive the guide table to move upward, so that the guide table drives the movable mold base to move upward and form a mold-closing state with the fixed mold base, and at the same time, the movable mold base drives the concentricity adjustment component to adjust the concentricity of the injection component; S3, control the electric push rod to drive the nozzle adjustment assembly and the second transmission member to make the nozzle move downward until the limit table contacts the top of the limit seat, at which time the nozzle is just inserted into the center hole at the top of the fixed mold seat and forms a seal; S4. Control the second transmission member to drive the screw in the barrel to rotate. During the rotation of the screw, the molten rubber raw material in the barrel can be injected into the molding slider to realize vulcanization molding of the rubber ring.

[0014] Compared with the prior art, the technical solution of this application has the following beneficial effects: 1. A vulcanization molding device and method for producing a rubber sealing ring can effectively adjust the concentricity of an injection component during use by providing a concentricity adjustment component, and can ensure the adjustability of the injection component during use by providing a nozzle adjustment component on the injection component.

[0015] 2. A vulcanization molding device and method for producing rubber sealing rings is provided with an inclined guide pin so that when the inclined guide pin is just inserted into the bottom of the guide pin hole, the two molding slide blocks just form a closed mold. At the same time, the positioning block provided on the fixed mold seat can achieve the effect of reinforcing and positioning the molding slide block. When the molding is completed, the staff controls the movable mold seat to produce a downward displacement effect, and the inclined guide pin will drive the two molding slide blocks to loosen, thereby achieving an open mold state to facilitate the subsequent removal of the rubber ring. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the structure of the present invention; Figure 2 This is a schematic diagram of the structure of the nozzle adjustment assembly of the present invention; Figure 3 For the present invention Figure 2 A magnified view of the structure; Figure 4 This is a schematic diagram of the fixed mold structure of the present invention; Figure 5 It is a schematic diagram of the movable mold structure of the present invention; Figure 6 It is a structural schematic diagram of the concentricity adjustment assembly of the present invention; Figure 7 It is a side view of the concentricity adjustment component structure of the present invention.

[0017] In the figure: 1, machine body; 11, feeding cavity; 12, limiting seat; 13, guide column; 14, first transmission member; 15, guide platform; 2, injection assembly; 21, electric push rod; 22, second transmission member; 23, connecting column; 24, barrel; 25, nozzle; 26, limiting platform; 3, movable mold; 31, movable mold seat; 32, slide rail; 33, forming slide block; 34, guide column hole; 35, cavity; 36, positioning hole; 37, ejection mechanism; 38, linkage rod; 4, fixed mold; 41, fixed mold seat; 42, connecting groove; 43, positioning block; 44, inclined guide column; 45, positioning column; 46 , linkage hole; 5, nozzle adjustment assembly; 51, first connecting plate; 52, first adjustment slot; 53, second connecting plate; 54, first slider; 55, second adjustment slot; 56, third connecting plate; 57, second slider; 6, concentricity adjustment assembly; 601, mounting seat; 602, connecting table; 603, worm gear; 604, supporting column; 605, mounting ring; 606, connecting shaft; 607, guide frame; 608, mounting column; 609, deviation correction arm; 610, deviation correction wheel; 611, sliding wheel; 612, worm; 613, linkage gear; 614, linkage rack. DETAILED DESCRIPTION

[0018] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0019] See also Figure 1-7A vulcanization molding device for producing a rubber sealing ring in this embodiment includes an organism 1, on which is disposed a feeding chamber 11 for conveying raw materials and an injection assembly 2 for injection, the feeding chamber 11 is connected to the injection assembly 2, and the injection assembly 2 is provided with a nozzle adjustment assembly 5 for adjustment; the organism 1 is also provided with a first transmission member 14 for transmission and a limit seat 12 for limiting, a fixed mold 4 is provided at the bottom of the limit seat 12, the first transmission member 14 is transmission-connected to a guide platform 15, a movable mold 3 is provided at the top of the guide platform 15, and a concentricity adjustment assembly 6 for correcting deviation is also provided at the top of the limit seat 12.

[0020] In the actual use process, when the rubber ring needs to be vulcanized, the staff can first add the raw materials into the feeding chamber 11. Under the conveying action of the feeding chamber 11, the raw materials can be added to the injection component 2 to achieve the effect of heating it. When it is heated to a state suitable for injection, the staff can control the first transmission member 14 to drive the guide table 15 so that the movable mold 3 and the fixed mold 4 complete the mold closing state. During the mold closing process, the fixed mold 4 can drive the concentricity adjustment component 6 to achieve the effect of concentricity adjustment of the injection component 2. When the mold closing is completed, the staff can control the injection component 2 to inject the rubber raw materials into the movable mold 3 and the fixed mold 4, thereby achieving the effect of vulcanization molding.

[0021] As a preferred technical solution in this embodiment: at least four guide posts 13 are arranged between the first transmission member 14 and the limit seat 12, and the guide platform 15 is slidably connected to the guide posts 13. The guide posts 13 are arranged so that the guide platform 15 can achieve a good guiding effect during use, thereby ensuring the stability of the guide platform 15 during displacement.

[0022] As a preferred technical solution in this embodiment: the injection component 2 includes an electric push rod 21 for transmission, the push rod end of the electric push rod 21 is connected to the nozzle adjustment component 5, the bottom of the nozzle adjustment component 5 is provided with a second transmission member 22, the bottom of the second transmission member 22 is connected to a plurality of connecting columns 23, the other end of the connecting column 23 is connected to a barrel 24, a screw is provided in the barrel 24, the output shaft of the second transmission member 22 is transmission-connected to the screw, and the bottom of the barrel 24 is provided with a nozzle 25 for injection. During actual use, when the staff needs to inject into the movable mold 3 and the fixed mold 4 in the mold closing state, the electric push rod 21 can be controlled to drive the second transmission member 22, the barrel 24 and the nozzle 25 to produce a downward displacement, so that the nozzle 25 can enter the center hole of the mold and form a sealed state. Then the staff can control the second transmission member 22 to drive the screw in the barrel 24 to produce a forward and rotating effect, which can achieve the stirring effect of the rubber raw material on the one hand and the pushing effect of the rubber raw material on the other hand, so that the rubber raw material can be effectively injected into the movable mold 3 and the fixed mold 4 to achieve the vulcanization molding effect.

[0023] As a preferred technical solution in this embodiment: a limiting platform 26 for limiting is also provided on the barrel 24. By providing the limiting platform 26, a good limiting effect can be effectively achieved during use, that is, when the nozzle 25 is plugged into the center hole of the mold and sealed, the limiting platform 26 just contacts the top of the limiting seat 12 to achieve the limiting effect.

[0024] It is worth noting that in this embodiment, the bottom diameter of the limiting platform 26 is larger than the diameter of the center hole of the mold, and at the same time, a guide hole matching the nozzle 25 is provided on the limiting seat 12 .

[0025] As a preferred technical solution in this embodiment: the movable mold 3 includes a movable mold base 31, on which is disposed at least one slide rail 32, in which two molding sliders 33 are slidably connected, on which are disposed guide post holes 34 for guiding, in which are disposed mold cavities 35 for molding, and at which are disposed a linkage rod 38 on the top of the movable mold base 31, which is transmission-connected to the concentricity adjustment component 6, and on which is disposed an ejection mechanism 37 for stripping the material, and on which is disposed a positioning hole 36 for positioning, and on which is disposed a linkage rod 38 on the movable mold base 31, which is slidably connected to the fixed mold 4. In actual use, when the staff controls the first transmission member 14 to drive the movable mold base 31 to produce an upward displacement, the movable mold base 31 can drive the molding slide 33 to produce an upward displacement during the upward displacement, and under the action of the fixed mold 4, the two molding slides 33 can achieve the effect of mold closing. At this time, when the mold closing is completed, the staff can control the injection component 2 to inject into the center hole of the mold, and the injected rubber raw material will achieve the effect of vulcanization molding in the cavity 35; when the vulcanization molding is completed, the molded rubber ring can be ejected by controlling the ejection mechanism 37, so as to facilitate the staff to take the material; by providing a positioning hole 36, it can effectively achieve the positioning effect during use, further increasing its accuracy in the vulcanization molding process and improving product quality.

[0026] As a preferred technical solution in this embodiment: the fixed mold 4 includes a fixed mold base 41, and a connecting groove 42 adapted to the forming slider 33 is provided on the fixed mold base 41. A positioning block 43, an inclined guide column 44 and a positioning column 45 for guiding are provided in the connecting groove 42. The fixed mold base 41 is also provided with a linkage hole 46 for guiding the linkage rod 38. In actual use, when the staff controls the movable mold seat 31 to move upward, the positioning column 45 provided on the fixed mold seat 41 will first be inserted into the positioning hole 36 on the movable mold seat 31, thereby achieving the positioning effect. At the same time, during the continuous displacement of the movable mold seat 31, the inclined guide column 44 on the fixed mold seat 41 will be inserted into the guide column hole 34 on the molding slide 33. When the inclined guide column 44 is just inserted to the bottom of the guide column hole 34, the two molding slides 33 just form a mold. At the same time, the positioning block 43 provided on the fixed mold seat 41 can achieve the effect of reinforcing and positioning the molding slide 33. When the molding is completed, when the staff controls the movable mold seat 31 to produce a downward displacement effect, the inclined guide column 44 will drive the two molding slides 33 to loosen, thereby achieving the mold opening state to facilitate the subsequent removal of the rubber ring.

[0027] As a preferred technical solution in this embodiment: the nozzle adjustment assembly 5 includes a first connecting plate 51, a second connecting plate 53 and a third connecting plate 56, the first connecting plate 51 has a first adjustment groove 52 at the bottom, the second connecting plate 53 has a second adjustment groove 55 at the bottom, the second connecting plate 53 has a first slider 54 at the top, the first slider 54 is slidably connected to the first adjustment groove 52, the third connecting plate 56 has a second slider 57 at the top, the second slider 57 is slidably connected to the second adjustment groove 55. During actual use, when the staff controls the concentricity adjustment component 6 to correct the injection component 2, the nozzle adjustment component 5 can achieve the effect of easy adjustment. When the second transmission member 22 needs to be displaced laterally, the third connecting plate 56 and the second slider 57 will produce a lateral movement effect. When the second transmission member 22 and the nozzle 25 need to be displaced longitudinally, the third connecting plate 56 will drive the second connecting plate 53 and the first slider 54 to produce a longitudinal displacement effect, thereby ensuring that the nozzle 25 can effectively achieve the effect of position adjustment during use, and the concentricity adjustment effect can be effectively achieved under the action of the concentricity adjustment component 6.

[0028] As a preferred technical solution in this embodiment: the concentricity adjustment component 6 includes a mounting seat 601, the top of the mounting seat 601 is rotatably connected to a connecting platform 602, the connecting platform 602 is provided with worm gears 603, the top of the connecting platform 602 is fixedly connected to a support column 604, the other end of the support column 604 is fixedly connected to a mounting ring 605, the mounting ring 605 is rotatably connected to a connecting shaft 606, and a guide frame 607 is provided at the bottom of the connecting shaft 606; the top of the mounting seat 601 is provided with mounting columns 608 whose number matches the guide frame 607, the mounting columns 608 are rotatably connected to a correction arm 609, the correction arm 609 is slidably connected to the guide frame 607, the other end of the correction arm 609 is rotatably connected to a correction wheel 610, and the correction wheel 610 is rotatably connected to a plurality of sliding wheels 611. In actual use, when it is necessary to adjust the nozzle 25 and the center hole of the mold, the connecting platform 602 can be controlled to rotate. During the rotation of the connecting platform 602, the mounting ring 605 can be driven to rotate the connecting shaft 606, thereby ensuring that the connecting shaft 606 can drive the guide frame 607 to make multiple correcting arms 609 produce inward or outward displacement with the mounting column 608 as the fulcrum. During the inward displacement of the correcting arms 609, the inward displacement of the barrel 24 can be achieved, thereby ensuring that the nozzle 25 can be displaced to the center of the mounting seat 601, and at this time, it is ensured that the nozzle 25 can be kept concentric with the center hole of the mold, ensuring that the concentricity adjustment effect can be effectively achieved during the use process; by arranging a sliding wheel 611 on the correcting wheel 610, it can be ensured that the barrel 24 can produce a vertical displacement effect while the concentricity of the barrel 24 is adjusted during use.

[0029] It is worth mentioning that, in actual use, the mounting seat 601 is fixedly connected to the limiting seat 12, and the centers of the mounting seat 601, the mounting ring 605 and the center hole of the mold are all located on the same straight line.

[0030] As a preferred technical solution in this embodiment: a worm 612 for transmission is also provided on the top of the mounting seat 601, one end of the worm 612 is rotatably connected to a linkage gear 613, the linkage gear 613 is transmission-connected to a linkage rack 614, and the bottom of the linkage rack 614 is fixedly connected to the linkage rod 38. In actual use, in order to achieve the effect of automatic adjustment, when the staff controls the movable mold base 31 to make it move upward, the movable mold base 31 can drive the linkage rod 38 to move upward, and in the process of the linkage rod 38 moving upward, it can drive the linkage rack 614 to move upward, and in the process of the linkage rack 614 moving upward, it can drive the linkage gear 613 to rotate, and in the process of the linkage gear 613 rotating, it can drive the worm 612 to rotate, and in the process of the worm 612 rotating, it can drive the sliding wheel 611 to rotate. When the movable mold base 31 and the fixed mold base 41 form a mold closing state, the connecting platform 602 just drives the mounting ring 605 so that the deviation correction arm 609 drives the deviation correction wheel 610 to achieve the effect of concentricity adjustment of the barrel 24. At this time, the staff can control the electric push rod 21 to drive the nozzle adjustment assembly 5 and its lower part to move downward, so that the nozzle 25 is inserted into the center hole of the mold to achieve sealing, and finally complete the injection.

[0031] As a preferred technical solution in this embodiment: a vulcanization molding method for producing a rubber sealing ring comprises the following steps: S1, adding the raw materials for rubber ring production into the feeding chamber 11, and conveying them to the barrel 24 through the feeding chamber 11 to heat the raw materials; S2, control the first transmission member 14 to drive the guide platform 15 to move upward, so that the guide platform 15 drives the movable mold base 31 to move upward and form a mold-closing state with the fixed mold base 41, and at the same time, the movable mold base 31 drives the concentricity adjustment component 6 to adjust the concentricity of the injection component 2; S3, control the electric push rod 21 to drive the second transmission member 22 to make the nozzle 25 move downward until the limit table 26 contacts the top of the limit seat 12, at which time the nozzle 25 is just inserted into the center hole at the top of the fixed mold seat 41 and forms a seal; S4, controlling the second transmission member 22 to drive the screw in the barrel 24 to rotate. During the rotation of the screw, the molten rubber material in the barrel 24 can be injected into the molding slider 33 to realize the vulcanization molding of the rubber ring.

[0032] The working principle of the above embodiment is as follows: in actual use, the staff adds the raw material for rubber ring production into the feeding chamber 11, and conveys it to the barrel 24 through the feeding chamber 11 to heat the raw material. When heated to a condition suitable for molding, the staff can control the first transmission member 14 to drive the guide platform 15 to move upward, so that the guide platform 15 drives the movable mold seat 31 to move upward and form a mold-closing state with the fixed mold seat 41, and at the same time, the movable mold seat 31 can drive the concentricity adjustment component 6 to adjust the concentricity of the injection component 2; at this time, the staff can control the electric push rod 21 to drive the second transmission member 22 to make the nozzle 25 move downward until the limit platform 26 contacts the top of the limit seat 12, and at this time, the nozzle 25 is just inserted into the center hole at the top of the fixed mold seat 41 and forms a seal; the second transmission member 22 is controlled to drive the screw in the barrel 24 to rotate, and during the rotation of the screw, the molten rubber raw material in the barrel 24 can be injected into the molding slider 33 to realize the vulcanization molding of the rubber ring.

[0033] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.

[0034] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A vulcanization molding device for producing a rubber sealing ring, comprising an organic body (1), characterized in that: The machine body (1) is provided with a feeding chamber (11) for conveying raw materials and an injection assembly (2) for injection, the feeding chamber (11) is connected to the injection assembly (2), and the injection assembly (2) is provided with a nozzle adjustment assembly (5) for adjustment; The machine body (1) is also provided with a first transmission member (14) for transmission and a limit seat (12) for limiting, a fixed die (4) is provided at the bottom of the limit seat (12), the first transmission member (14) is transmission-connected to a guide platform (15), a movable die (3) is provided at the top of the guide platform (15), and a concentricity adjustment component (6) for correcting deviation is also provided at the top of the limit seat (12).

2. A vulcanization molding device for producing a rubber sealing ring as claimed in claim 1, characterized in that: No less than four guide columns (13) are arranged between the first transmission member (14) and the limit seat (12), and the guide platform (15) and the guide columns (13) are both slidably connected.

3. A vulcanization molding device for producing a rubber sealing ring as claimed in claim 1, characterized in that: The injection assembly (2) comprises an electric push rod (21) for transmission, the push rod end of the electric push rod (21) is connected to a nozzle adjustment assembly (5), a second transmission member (22) is arranged at the bottom of the nozzle adjustment assembly (5), a plurality of connecting columns (23) are connected to the bottom of the second transmission member (22), the other end of the connecting column (23) is connected to a barrel (24), a screw is arranged in the barrel (24), an output shaft of the second transmission member (22) is transmission-connected to the screw, and a nozzle (25) for injection is arranged at the bottom of the barrel (24).

4. A vulcanization molding device for producing a rubber sealing ring as claimed in claim 3, characterized in that: The barrel (24) is also provided with a limiting platform (26) for limiting position.

5. A vulcanization molding device for producing a rubber sealing ring as claimed in claim 1, characterized in that: The movable mold (3) comprises a movable mold base (31), the movable mold base (31) is provided with at least one slide rail (32), two molding slide blocks (33) are slidably connected in the slide rail (32), both molding slide blocks (33) are provided with guide post holes (34) for guiding, both molding slide blocks (33) are provided with molding cavities (35) for molding, a linkage rod (38) is further provided at the top of the movable mold base (31), the linkage rod (38) is transmission-connected to the concentricity adjustment component (6), an ejection mechanism (37) for stripping is further provided on the movable mold base (31), a positioning hole (36) for positioning is further provided on the movable mold base (31), and a linkage rod (38) is further provided on the movable mold base (31), and the linkage rod (38) is slidably connected to the fixed mold (4).

6. A vulcanization molding device for producing a rubber sealing ring as claimed in claim 1, characterized in that: The fixed die (4) comprises a fixed die seat (41), the fixed die seat (41) is provided with a connecting groove (42) adapted to the forming slide block (33), a positioning block (43), an inclined guide column (44) and a positioning column (45) for guiding are arranged in the connecting groove (42), and a linkage hole (46) for guiding is also arranged on the fixed die seat (41).

7. A vulcanization molding device for producing a rubber sealing ring as claimed in claim 1, characterized in that: The nozzle adjustment assembly (5) comprises a first connecting plate (51), a second connecting plate (53) and a third connecting plate (56); a first adjustment slot (52) is provided at the bottom of the first connecting plate (51); a second adjustment slot (55) is provided at the bottom of the second connecting plate (53); a first sliding block (54) is provided at the top of the second connecting plate (53); the first sliding block (54) is slidably connected to the first adjustment slot (52); a second sliding block (57) is provided at the top of the third connecting plate (56); the second sliding block (57) is slidably connected to the second adjustment slot (55).

8. A vulcanization molding device for producing a rubber sealing ring as claimed in claim 5, characterized in that: The concentricity adjustment assembly (6) comprises a mounting seat (601), the top of the mounting seat (601) is rotatably connected to a connecting platform (602), the connecting platform (602) is provided with worm gears (603), the top of the connecting platform (602) is fixedly connected to a support column (604), the other end of the support column (604) is fixedly connected to a mounting ring (605), the mounting ring (605) is rotatably connected to a connecting shaft (606), and the bottom of the connecting shaft (606) is provided with a guide frame (607); The top of the mounting seat (601) is provided with mounting posts (608) whose number matches the guide frame (607); the mounting posts (608) are rotatably connected to a deflection correction arm (609); the deflection correction arm (609) is slidably connected to the guide frame (607); the other end of the deflection correction arm (609) is rotatably connected to a deflection correction wheel (610); the deflection correction wheel (610) is rotatably connected to a plurality of sliding wheels (611).

9. A vulcanization molding device for producing a rubber sealing ring as claimed in claim 8, characterized in that: A worm (612) for transmission is also provided on the top of the mounting seat (601); one end of the worm (612) is rotatably connected to a linkage gear (613); the linkage gear (613) is transmission-connected to a linkage rack (614); the bottom of the linkage rack (614) is fixedly connected to the linkage rod (38).

10. A vulcanization molding method for producing a rubber sealing ring based on the device according to any one of claims 1 to 9, characterized in that: The steps include: S1, adding raw materials for rubber ring production into the feeding chamber (11), and conveying the raw materials to the barrel (24) through the feeding chamber (11) to heat the raw materials; S2, controlling the first transmission member (14) to drive the guide platform (15) to move upward, so that the guide platform (15) drives the movable mold base (31) to move upward and form a mold-closing state with the fixed mold base (41), and at the same time the movable mold base (31) drives the concentricity adjustment component (6) to adjust the concentricity of the injection component (2); S3, controlling the electric push rod (21) to drive the nozzle adjustment assembly (5) and the second transmission member (22) to cause the nozzle (25) to move downward until the limit table (26) contacts the top of the limit seat (12), at which time the nozzle (25) is just inserted into the center hole at the top of the fixed mold seat (41) to form a seal; S4. Control the second transmission member (22) to drive the screw in the barrel (24) to rotate. During the rotation of the screw, the molten rubber raw material in the barrel (24) can be injected into the molding slider (33) to realize vulcanization molding of the rubber ring.