Civil engineering foundation connecting structure for power transformation engineering
By designing a civil foundation connection structure for substation engineering, including base, installation pipe, mounting frame and ground insertion, the problems of construction troubles and low stability in the prior art are solved, and the effect of simplifying construction and improving stability is achieved.
Patent Information
- Application Number
- CN202510283121.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-03-11
- Publication Date
- 2025-05-30
AI Technical Summary
The existing civil engineering foundation connecting structure has problems such as low stability, troublesome construction and high cost during the construction process.
A civil foundation connection structure including base, installation pipe, mounting frame and ground insert was designed. The mounting frame and base are connected through plug-in, and the connection is fixed by pouring concrete to avoid the use of bolts and simplify the construction process.
It realizes that the construction process is simplified and the stability is improved, and the installation of power equipment is facilitated without using bolts.
Smart Images

Figure CN120076228A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of civil engineering foundation connection seats, and particularly relates to a civil engineering foundation connection structure for substation projects. Background Art
[0002] During the construction of power projects, it is necessary to install and fix various large-scale power equipment. For example, equipment such as large transformers and distribution cabinets need to be supported by setting up civil engineering foundations. Therefore, it is necessary to build a connection structure on the ground through civil engineering to achieve the effect of providing fixed support for the power equipment on the top.
[0003] Some of the existing civil engineering foundation connection structures are simple scaffolds built on the construction site. Such scaffolds are suitable for temporary use, but have low stability, are prone to collapse, and the on-site construction is troublesome; some existing civil engineering foundation connection structures are made by pouring concrete, and the overall amount of concrete required is large. Although they can be stably connected to the civil engineering foundation, the construction is troublesome and the cost is high; there are also some such civil engineering foundation connection structures that are bolted and fixed to the ground of the civil engineering foundation using a large number of bolts, and there are also technical problems of troublesome construction. Summary of the Invention
[0004] The present invention provides a civil engineering foundation connection structure for substation projects, which is used to solve the technical problems of troublesome construction and inability to be stably installed on the civil engineering foundation existing in the existing civil engineering foundation connection structures.
[0005] The present invention is achieved through the following technical solutions: A civil engineering foundation connection structure for substation projects includes:
[0006] A base, provided with a pouring cavity inside, the pouring cavity penetrates the bottom end of the base, and a through hole communicating with the pouring cavity is opened on the top surface of the base;
[0007] An installation pipe, passing through the through hole and fixedly connected to the base, the installation pipe is communicated with the pouring cavity, and the upper part of the installation pipe is located above the base and forms an embedded section;
[0008] An installation frame, provided with a connection part for installing power equipment, a base is fixedly provided at the bottom end of the installation frame, a groove is opened at the bottom end of the base, a fixing block is fixedly provided in the groove, and a main pouring hole penetrating the bottom end of the fixing block is provided on the installation frame;
[0009] A ground plug with a tip, the ground plug is slidably installed in the installation pipe, and the tip faces downward;
[0010] The embedding section is inserted into the groove, and the fixing block is inserted into the embedding section. When the fixing block is inserted into the embedding section, the fixing block pushes the ground plug downward so that the tip of the ground plug extends out of the mounting tube and the base.
[0011] Furthermore, in order to better realize the present invention, an inflatable sac is provided on the inner wall of the embedding section, and the inflatable sac is located above the ground plug;
[0012] When the fixing block is inserted into the embedding section, the fixing block squeezes the inflatable bladder to make the inflatable bladder expand downward, and the inflatable bladder that expands downward pushes the ground plug to move downward.
[0013] Further, in order to better realize the present invention, the ground plug includes a connecting column and an insert rod, the insert rod is fixedly connected to the bottom end of the connecting column, the tip is arranged at the end of the insert rod away from the connecting column, the top end of the connecting column is connected to a slider, a guide rail is fixedly arranged on the inner wall of the middle part of the mounting tube, the slider is slidably mounted on the guide rail, and the inflatable bag is connected to the slider;
[0014] When the inflatable bladder expands downward, it pushes the sliding block to move downward, so that the connecting column and the insertion rod move downward.
[0015] Furthermore, in order to better realize the present invention, there are multiple ground plugs, and the multiple ground plugs are divided into two groups. The connecting columns of each group of ground plugs are connected to a slider. There are two guide rails, and the two guide rails are symmetrically distributed on the middle inner wall of the mounting tube. Two sliders are respectively slidably installed on the two guide rails, and there are two inflatable bladders. The two inflatable bladders are respectively arranged above the two sliders, and gaps for concrete to pass through are left between the two inflatable bladders and between the two sliders.
[0016] Furthermore, in order to better implement the present invention, the connecting column includes a push rod and an expansion rod with an outer diameter greater than that of the push rod, the expansion rod is fixed between the push rod and the insertion rod, and the expansion rod is provided with a receiving groove.
[0017] Furthermore, in order to better implement the present invention, the push rod and the expansion rod are both straight rods, and the push rod and the expansion rod are coaxially arranged, and the insertion rod is a curved tube.
[0018] Furthermore, in order to better implement the present invention, the bottom surface of the mounting tube is flush with the bottom surface of the base, and a slurry flow hole is opened on the tube wall of the mounting tube, and the slurry flow hole connects the casting cavity and the inner hole of the mounting tube.
[0019] Further, to better implement the present invention, a guiding block is fixedly provided inside the installation pipe. The guiding block is provided with an arc-shaped through hole adapted to the elbow pipe, and the elbow pipe is slidably inserted into the arc-shaped through hole;
[0020] The guiding block is located below the pulp flow hole, or the guiding block is aligned with the pulp flow hole and the thickness of the guiding block is less than the aperture of the pulp flow hole.
[0021] Further, to better implement the present invention, the radian of the elbow pipe is 5-15°.
[0022] Further, to better implement the present invention, a secondary pouring hole communicating with the main pouring hole is provided in the lower side wall of the fixing block.
[0023] The present invention has the following beneficial effects compared with the prior art:
[0024] The civil engineering foundation connection structure for a substation project provided by the present invention includes a base, an installation pipe, an installation frame, and a ground plug with a tip. A pouring cavity is provided inside the base, and the pouring cavity penetrates through the bottom end of the base. A through hole communicating with the pouring cavity is provided on the top surface of the base. The installation pipe is inserted through the through hole and fixedly connected to the base. The installation pipe communicates with the pouring cavity. The upper part of the installation pipe is located above the base and forms an embedded section. The installation frame is provided with a connecting part for installing electrical equipment. A base is fixedly provided at the bottom end of the installation frame. A groove is provided at the bottom end of the base, and a fixing block is fixedly provided in the groove. The installation frame is provided with a main pouring hole penetrating through the bottom end of the fixing block. The ground plug is slidably installed in the installation pipe, and the tip of the ground plug faces downward. The embedded section is inserted into the groove, and the fixing block is inserted into the embedded section. Moreover, when the fixing block is inserted into the embedded section, the fixing block pushes the ground plug downward so that the tip of the ground plug extends out of the installation pipe and the base.
[0025] With the above-mentioned connecting part, the connection structure can install power equipment. When installing the connection structure, first place the base on the civil engineering foundation, and then insert the above-mentioned embedded section into the groove so that the embedded section is docked with the base. At this time, the fixing block will synchronously embed into the inner hole of the embedded section, thereby pushing the ground plug downward so that the tip of the ground plug extends out of the installation pipe and the base. The tip of the ground plug extending out of the base will be inserted into the civil engineering foundation. Subsequently, pour concrete into the main pouring hole. Since the fixing block is placed in the installation pipe, the concrete entering the main pouring hole will flow into the installation pipe. Since the installation pipe is connected to the pouring cavity of the above-mentioned base, the concrete entering the installation pipe will flow into the pouring cavity. Since the pouring cavity penetrates the bottom surface of the base, the concrete entering the pouring cavity will directly be stacked on the civil engineering foundation. After the concrete solidifies, the base will be connected to the civil engineering foundation. Together with the ground plug inserted into the civil engineering foundation, the base will be firmly connected to the ground of the civil engineering foundation. Of course, the main pouring hole and the installation pipe will also be filled with concrete. After this part of the concrete solidifies, the installation frame will be firmly connected to the base.
[0026] Through the above structure, the civil engineering foundation connection structure provided by the present invention only needs to adopt the plugging method to dock the installation frame and the base and make the ground plug insert into the ground of the civil engineering foundation. Moreover, the connection structure makes the installation frame and the base fixedly connected by pouring concrete and makes the base fixedly connected to the ground of the civil engineering foundation. In this way, the civil engineering foundation connection structure does not need to use bolts during assembly and installation, and the assembly and installation are simple and convenient. And after installation, it can be stably placed on the civil engineering foundation. With the installation part of the installation frame, it is convenient to install power equipment on it. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] In order to more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the following will briefly introduce the drawings required for use in the description of the embodiments or the prior art. Obviously, the following drawings are only some embodiments of the present invention. For those of ordinary skill in the art, without creative efforts, other drawings can also be obtained based on these drawings.
[0028] Figure 1 It is a schematic structural diagram of the civil engineering foundation connection structure for a substation project provided by an embodiment of the present invention;
[0029] Figure 2 is Figure 1 Another perspective view of the civil engineering foundation connection structure for a substation project shown;
[0030] Figure 3 is Figure 1 A schematic structural diagram of the civil engineering foundation connection structure for a substation project shown in an exploded state;
[0031] Figure 4 Yes Figure 1 It is a schematic structural diagram of the civil engineering foundation connection structure for a substation project under another explosion state;
[0032] Figure 5 It is a schematic structural diagram of the ground plug installed in the installation pipe in an embodiment of the present invention;
[0033] Figure 6 It is a schematic structural diagram when the fixing block squeezes the air-filled balloon to expand downward and push the ground plug downward in an embodiment of the present invention;
[0034] Figure 7 It is a schematic structural diagram of the guide block in an embodiment of the present invention;
[0035] Figure 8 It is a schematic structural diagram of the ground plug in an embodiment of the present invention.
[0036] In the figure:
[0037] 100 - base, 110 - pouring cavity, 200 - installation pipe, 210 - slurry flow hole, 300 - installation frame, 310 - connection part, 320 - base, 330 - fixing block, 340 - main pouring hole, 350 - auxiliary pouring hole, 400 - ground plug, 410 - connecting column, 411 - push rod, 412 - diameter-expanding rod, 4121 - accommodating groove, 413 - inserting rod, 414 - slider, 500 - air-filled balloon, 600 - guide rail, 700 - guide block, 710 - arc-shaped through hole. Specific Embodiments
[0038] To make the objectives, technical solutions and advantages of the present invention clearer, the technical solutions of the present invention will be described in detail below. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all of the embodiments. All other embodiments obtained by those of ordinary skill in the art without making creative efforts based on the embodiments of the present invention fall within the scope of protection of the present invention.
[0039] Embodiment:
[0040] As Figures 1-8 shown, the civil engineering foundation connection structure for a substation project provided in this embodiment includes a base 100, an installation pipe 200, an installation frame 300, and a ground plug 400 with a tip, wherein:
[0041] The base 100 is provided with a casting cavity 110 inside. The casting cavity 110 penetrates through the bottom end of the base 100. A through hole communicating with the casting cavity 110 is formed on the top surface of the base 100. The installation pipe 200 is inserted through the through hole and integrally formed with or welded to the base 100. The installation pipe 200 communicates with the casting cavity 110. In this way, part of the concrete entering the installation pipe 200 will flow into the above-mentioned casting cavity 110. The upper part of the installation pipe 200 is located above the base 100. The section of the installation pipe 200 located above the base 100 forms an embedded section. Optionally, the above-mentioned installation pipe 200 is a vertically arranged square pipe, and the above-mentioned through hole is a square hole adapted to the square pipe;
[0042] The mounting bracket 300 is provided with a connecting part 310 for mounting electrical equipment. For example, the connecting part 310 is a wire rack capable of passing through wires. The bottom end of the mounting bracket 300 is integrally formed with or welded to a base 320. A groove is formed at the bottom end of the base 320. The shape and size of the groove are adapted to the outer contour of the above-mentioned embedded section. A fixing block 330 is fixedly provided in the groove. The shape and size of the fixing block 330 are adapted to the inner hole of the above-mentioned embedded section. The mounting bracket 300 is provided with a main casting hole 340 penetrating through the bottom end of the fixing block 330, that is, the above-mentioned main casting hole 340 penetrates through the above-mentioned mounting bracket 300 and the above-mentioned fixing block 330. It can also be understood that the mounting bracket 300 and the fixing block 330 are respectively provided with a first casting hole and a second casting hole, and the first casting hole and the second casting hole communicate to form the above-mentioned main casting hole 340.
[0043] The ground plug 400 is slidably installed in the installation pipe 200. A gap for the concrete to pass through is formed between the ground plug 400 and the pipe wall of the installation pipe 200, that is, the ground plug 400 cannot completely block the above-mentioned installation pipe 200. The tip of the ground plug 400 faces downward.
[0044] During assembly, the embedded section is inserted into the groove, so that the fixing block 330 is inserted into the embedded section. And when the fixing block 330 is inserted into the embedded section, the fixing block 330 pushes the ground plug 400 downward, causing the tip of the ground plug 400 to extend out of the installation pipe 200 and the base 100.
[0045] With the above-mentioned connecting part 310, this connecting structure can install power equipment. When installing this connecting structure, first place the base 100 on the civil engineering foundation, and then insert the above-mentioned embedded section into the groove so that the embedded section is docked with the base 320. At this time, the fixing block 330 will synchronously insert into the inner hole of the embedded section, thereby pushing down the ground plug 400 so that the tip of the ground plug 400 extends out of the installation pipe 200 and the base 100. The tip of the ground plug 400 extending out of the base 100 will be inserted into the civil engineering foundation. Subsequently, pour concrete into the main pouring hole 340. Since the fixing block 330 is placed in the installation pipe 200, the concrete entering the main pouring hole 340 will flow into the installation pipe 200. Since the installation pipe 200 is connected to the pouring cavity 110 of the above-mentioned base 100, the concrete entering the installation pipe 200 will flow into the pouring cavity 110. Since the pouring cavity 110 penetrates the bottom surface of the base 100, the concrete entering the pouring cavity 110 will be directly stacked on the civil engineering foundation. After the concrete solidifies, the base 100 will be connected to the civil engineering foundation. Together with the ground plug 400 inserted into the civil engineering foundation, the base 100 will be firmly connected to the ground of the civil engineering foundation. Of course, the main pouring hole 340 and the installation pipe 200 will also be filled with concrete. After this part of the concrete solidifies, the installation frame 300 will be firmly connected to the base 100.
[0046] Through the above structure, the civil engineering foundation connecting structure provided by the present invention only needs to adopt a plugging method to dock the installation frame 300 and the base 100 and make the ground plug 400 insert into the ground of the civil engineering foundation. Moreover, this connecting structure makes the installation frame 300 and the base 100 fixedly connected by pouring concrete and makes the base 100 fixedly connected to the ground of the civil engineering foundation. In this way, this civil engineering foundation connecting structure does not need to use bolts during assembly and installation, the assembly and installation are simple and convenient, and after installation, it can be stably placed on the civil engineering foundation. With the installation part of the installation frame 300, it is convenient to install power equipment on it.
[0047] An optional implementation manner of this embodiment is as follows: An air-filled balloon 500 is installed in the above-mentioned embedded section. The air-filled balloon 500 is located above the above-mentioned ground plug 400. When the fixing block 330 inserts into the embedded section, the fixing block 330 squeezes the air-filled balloon 500 to make the air-filled balloon 500 expand downward, and the downward-expanded air-filled balloon 500 pushes the ground plug 400 to move downward. In this way, when the fixing block 330 just enters the embedded section, it will squeeze the above-mentioned air-filled balloon 500 to make the air-filled balloon 500 start to expand downward and squeeze the ground plug 400 downward. Therefore, with the help of the above-mentioned air-filled balloon 500, the ground plug 400 can move downward when the fixing block 330 just enters the embedded section. When the fixing block 330 is completely inserted into the embedded section, the air-filled balloon 500 is squeezed and broken by the fixing block 330.
[0048] An alternative implementation of this embodiment is as follows: The above-mentioned ground plug 400 includes a connecting column 410 and a plug rod 413, where:
[0049] The plug rod 413 is fixedly connected to the bottom end of the connecting column 410. The tip of the ground plug 400 is located at one end of the plug rod 413 away from the connecting column 410. A slider 414 is connected to the top end of the above-mentioned connecting column 410. A guide rail 600 is fixedly provided on the inner wall of the middle part of the above-mentioned installation pipe 200. The above-mentioned slider 414 is slidably installed on the above-mentioned guide rail 600 up and down. The above-mentioned air-filled balloon 500 is located above the slider 414. When the fixing block 330 is inserted into the above-mentioned embedding section, the above-mentioned air-filled balloon 500 is in contact with the top end of the slider 414. When the air-filled balloon 500 is squeezed by the fixing block 330 and expands and deforms downward, the downward-expanded air-filled balloon 500 pushes the above-mentioned slider 414 downward, so that the connecting column 410 and the plug rod 413 move downward synchronously.
[0050] Optionally, the number of the above-mentioned ground plugs 400 is multiple. The multiple ground plugs 400 are evenly divided into two groups. The connecting columns 410 of each group of ground plugs 400 are connected to the same slider 414. The number of the above-mentioned guide rails 600 is two. The two guide rails 600 are symmetrically distributed on the inner wall of the middle part of the installation pipe 200. Two sliders 414 are respectively slidably installed on the two above-mentioned guide rails 600. And the number of the above-mentioned air-filled balloons 500 is also two. The two air-filled balloons 500 are respectively located above the two sliders 414. That is, the two air-filled balloons 500 are respectively used to push the two sliders 414. A gap for the concrete to pass through is provided between the two above-mentioned air-filled balloons 500 and between the two above-mentioned sliders 414. In this way, the concrete can smoothly enter the lower part of the installation pipe 200. When multiple ground plugs 400 are inserted into the ground of the civil engineering foundation, the connection force generated is greater.
[0051] More preferably, the above-mentioned connecting column 410 includes a push rod 411 and a diameter-expanded rod 412 with an outer diameter larger than that of the push rod 411. The diameter-expanded rod 412 is fixedly provided between the push rod 411 and the plug rod 413. Both the push rod 411 and the diameter-expanded rod 412 are straight rods, and the push rod 411 and the diameter-expanded rod 412 are coaxially arranged. At this time, the above-mentioned push rod 411 is located above the diameter-expanded rod 412, and the diameter-expanded rod 412 is located above the plug rod 413. A receiving groove 4121 is formed on the top surface of the above-mentioned diameter-expanded rod 412. Because the concrete can smoothly enter the middle and lower parts of the installation pipe 200, the section of the installation pipe 200 where the above-mentioned push rod 411, the diameter-expanded rod 412, and the plug rod 413 are located will also be filled with concrete. And part of the concrete will enter the above-mentioned receiving groove 4121 to increase the weight of the ground plug 400. And when the concrete is injected, a certain impact effect will be generated at the top end of the diameter-expanded rod 412, so that the ground plug 400 can further move downward, and further the ground plug 400 can be inserted deeper into the civil engineering foundation. It should be noted that the above-mentioned plug rod 413 is a solid rod.
[0052] In addition, the above-mentioned insertion rod 413 can also be a pipe body connected to the above-mentioned accommodation groove 4121, with the tip provided at the bottom end of the pipe body. In this way, the insertion rod 413 can not only be inserted into the ground of the civil engineering foundation, but also the concrete entering the accommodation groove 4121 will enter the interior of the insertion rod 413 and finally flow out from the inner hole of the insertion rod 413 into the civil engineering foundation, better playing a fixing role.
[0053] Optionally, the above-mentioned insertion rod 413 is a bent pipe. In this way, when the insertion rod 413 moves downward, the tip does not insert straight down into the ground of the civil engineering foundation, but inserts obliquely downward into the ground of the civil engineering foundation, so that it can be more easily inserted into the ground of the civil engineering foundation 400. Specifically, the radian of the above-mentioned bent pipe is 5-15°, for example, the radian of the bent pipe is 5° or 6° or 7° or 8° or 9° or 10° or 11° or 12° or 13° or 14° or 15°.
[0054] Of course, the above-mentioned ground plug 400 can also include a straight rod and a hollow sliding frame. The hollow sliding frame is adapted to the inner hole of the above-mentioned installation pipe 200, and the hollow sliding frame is slidably installed in the inner hole of the installation pipe 200. The straight rod is fixedly connected to the bottom end of the hollow sliding frame, and the bottom end of the straight rod is provided with a tip. At this time, the above-mentioned air-filled balloon body 500 is located above the hollow sliding frame and is in contact with the top surface of the hollow sliding frame. In this way, when the air-filled balloon body 500 expands and deforms downward, it will push the hollow sliding frame and the straight rod to move downward synchronously, so that the tip of the straight rod extends out of the above-mentioned installation pipe 200 and the base 100 and inserts into the ground of the civil engineering foundation.
[0055] An optional implementation manner of this embodiment is as follows: The bottom surface of the above-mentioned installation pipe 200 is flush with the bottom surface of the base 100. In this way, when the tip of the ground plug 400 extends out of the bottom surface of the installation pipe 200, it will also extend out of the base 100 at the same time. However, when the bottom surface of the base 100 is in contact with the ground of the civil engineering foundation, the bottom surface of the installation pipe 200 will also be in contact with the ground of the civil engineering foundation, which is not conducive to the concrete flowing from the installation pipe 200 into the above-mentioned pouring cavity 110. Therefore, a slurry flow hole 210 is also opened on the pipe wall of the installation pipe 200, and the slurry flow hole 210 communicates the pouring cavity 110 and the inner hole of the installation pipe 200, so that the concrete can smoothly flow from the installation pipe 200 into the above-mentioned pouring cavity 110.
[0056] Of course, the bottom surface of the above-mentioned installation pipe 200 can also be arranged above the bottom surface of the base 100. When the bottom surface of the base 100 is in contact with the ground, the bottom surface of the installation pipe 200 is not in contact with the ground.
[0057] An alternative implementation of this embodiment is as follows: A guiding block 700 is further fixedly provided in the above-mentioned installation pipe 200. The guiding block 700 is provided with an arc-shaped through hole 710 adapted to the elbow pipe. The elbow pipe 400 is slidably inserted into the arc-shaped through hole 710. In this way, it can play a guiding role in the up-and-down movement of the ground plug 400. Moreover, when the fixing block 330 is not inserted into the embedding section, the arc-shaped through hole 710 can also play a certain supporting role for the elbow pipe, so that the ground plug 400 can overcome its own gravity and be placed in the above-mentioned installation pipe 200. The guiding block 700 is located below the slurry flow hole 210, or the guiding block 700 is aligned with the slurry flow hole 210 and the thickness of the guiding block 700 is less than the aperture of the slurry flow hole 210, that is, the slurry flow hole 210 will not be blocked by the guiding block 700, so that the concrete can smoothly enter the above-mentioned pouring cavity 110 from the installation pipe 200 through the slurry flow hole 210.
[0058] An alternative implementation of this embodiment is as follows: A secondary pouring hole 350 communicating with the main pouring hole 340 is provided in the lower side wall of the fixing block 330. After the fixing block 330 is inserted into the embedding section, a small gap will be formed between the outer wall of the fixing block 330 and the inner wall of the embedding section. The setting of the above-mentioned secondary pouring hole 350 enables the concrete in the main pouring hole 340 to pass through the secondary pouring hole 350 and enter the gap between the outer wall of the fixing block 330 and the inner wall of the embedding section. After the concrete in this part solidifies, the fixing block 330 will be firmly connected in the embedding section, so that the mounting frame 300 is more firmly connected to the base 100.
[0059] As described above, the above are only specific embodiments of the present invention, but the protection scope of the present invention is not limited thereto. Any person skilled in the art within the technical scope recorded in the present invention can easily think of changes or substitutions, which should all be covered by the protection scope of the present invention. Therefore, the protection scope of the present invention should be subject to the protection scope of the claims.
Claims
1. A civil foundation connection structure for a power transformation project, characterized in that: include: A base (100) is provided with a casting cavity (110) therein, the casting cavity (110) passes through the bottom end of the base (100), and a through opening communicating with the casting cavity (110) is opened on the top surface of the base (100); A mounting pipe (200) is inserted into the through-hole and fixedly connected to the base (100); the mounting pipe (200) is in communication with the casting cavity (110); the upper portion of the mounting pipe (200) is located above the base (100) and forms an embedded section; The mounting frame (300) is provided with a connection portion (310) for installing the electric equipment, a base (320) is fixedly provided at the bottom end of the mounting frame (300), a groove is provided at the bottom end of the base (320), a fixing block (330) is fixedly provided in the groove, and the mounting frame (300) is provided with a main casting hole (340) penetrating the bottom end of the fixing block (330); a ground plug (400) having a pointed end, the ground plug (400) being slidably mounted in the mounting tube (200), with the pointed end facing downward; The embedded section is inserted into the groove, and the fixed block (330) is inserted into the embedded section. When the fixed block (330) is inserted into the embedded section, the fixed block (330) pushes the ground plug (400) downward so that the tip of the ground plug (400) extends out of the installation tube (200) and the base (100).
2. The civil foundation connection structure for power transformation engineering according to claim 1, characterized in that: An inflatable sac (500) is provided on the inner wall of the embedded section, and the inflatable sac (500) is located above the ground plug (400); When the fixing block (330) is inserted into the embedding section, the fixing block (330) squeezes the inflatable bladder (500) to cause the inflatable bladder (500) to expand downward, and the inflatable bladder (500) that expands downward pushes the ground plug (400) to move downward.
3. The civil foundation connection structure for power transformation engineering according to claim 2, characterized in that: The ground plug (400) comprises a connecting column (410) and an inserting rod (413), wherein the inserting rod (413) is fixedly connected to the bottom end of the connecting column (410), the tip end is arranged at the end of the inserting rod (413) away from the connecting column (410), the top end of the connecting column (410) is connected to a slider (414), a guide rail (600) is fixedly arranged on the inner wall of the middle part of the mounting tube (200), the slider (414) is slidably mounted on the guide rail (600) up and down, and the inflatable bag (500) is connected to the slider (414); When the inflatable bladder (500) expands downward, it pushes the slider (414) to move downward, so that the connecting column (410) and the insertion rod (413) move downward.
4. The civil foundation connection structure for power transformation engineering according to claim 3 is characterized in that: There are a plurality of ground plugs (400), and the plurality of ground plugs (400) are divided into two groups. The connecting column (410) of each group of ground plugs (400) is connected to a slider (414). There are two guide rails (600), and the two guide rails (600) are symmetrically distributed on the middle inner wall of the mounting tube (200). The two sliders (414) are respectively slidably mounted on the two guide rails (600). There are also two inflatable bladders (500), and the two inflatable bladders (500) are respectively arranged above the two sliders (414). A gap for concrete to pass through is left between the two inflatable bladders (500) and between the two sliders (414).
5. The civil foundation connection structure for power transformation engineering according to claim 4, characterized in that: The connecting column (410) comprises a push rod (411) and an expansion rod (412) having an outer diameter greater than that of the push rod (411); the expansion rod (412) is fixed between the push rod (411) and the insertion rod (413); and a receiving groove (4121) is provided on the expansion rod (412).
6. The civil foundation connection structure for power transformation engineering according to claim 5, characterized in that: The push rod (411) and the diameter expansion rod (412) are both straight rods, and the push rod (411) and the diameter expansion rod (412) are coaxially arranged, and the insertion rod (413) is a curved tube.
7. The civil foundation connection structure for power transformation engineering according to claim 6, characterized in that: The bottom surface of the installation tube (200) is flush with the bottom surface of the base (100), and a slurry flow hole (210) is also provided on the tube wall of the installation tube (200), wherein the slurry flow hole (210) communicates with the casting cavity (110) and the inner hole of the installation tube (200).
8. The civil foundation connection structure for power transformation engineering according to claim 7, characterized in that: A guide block (700) is fixedly arranged inside the installation tube (200), the guide block (700) is provided with an arc-shaped through hole (710) adapted to the bent tube, and the bent tube is slidably inserted (400) into the arc-shaped through hole (710); The guide block (700) is located below the slurry flow hole (210), or the guide block (700) is aligned with the slurry flow hole (210) and the thickness of the guide block (700) is smaller than the aperture of the slurry flow hole (210).
9. The civil foundation connection structure for power transformation engineering according to claim 6, characterized in that: The curvature of the curved pipe is 5-15°.
10. The civil foundation connection structure for a power transformation project according to any one of claims 1 to 9, characterized in that: The lower side wall of the fixing block (330) is provided with an auxiliary pouring hole (350) which is connected to the main pouring hole (340).