Method for constructing and laying semi-living sand ridge sand barrier in arid region
By building trapezoidal sand ridges in arid areas and planting drought-resistant plants, and combining water retention agents to form semi-living sand barriers, the problems of poor economicality and maintenance difficulties of traditional sand barriers are solved, and efficient and economical wind-proof and sand-fixing effect are achieved.
Patent Information
- Application Number
- CN202510945917.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-07-09
- Publication Date
- 2025-09-02
AI Technical Summary
The existing windproof and sand fixing technology has poor economicality, difficulty in implementation, high maintenance costs and short service life in arid areas. Traditional sand barrier materials are costly and difficult to maintain, and living vegetative sand barriers have long growth cycles and require irrigation and maintenance.
Trapezoidal sand ridges are built on the mobile sandy land in arid areas, drought-resistant plants are planted and water retention agents are applied to form semi-living sand barriers, and the plant roots are used to fix sand and the sand is still fixed after the plants wither. The flexibility of the above-ground parts weakens the wind speed.
It improves the wind and sand fixing effect, reduces construction and maintenance costs, and provides low-cost and sustainable wind and sand fixing solutions, which are suitable for large-scale promotion and application.
Smart Images

Figure CN120575552A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of windbreak and sand fixation, and in particular to a method for constructing and laying out semi-living sand ridges and sand barriers in arid areas. Background Art
[0002] At present, in arid and desertified areas, traditional windbreak and sand fixation technologies mainly include physical sand barriers and plant sand barriers. Although artificial sand barriers can effectively block wind and sand temporarily, their structure usually relies on fixing materials such as stones, polymers, and plant straw. These materials have high transportation and production costs and are difficult to maintain. Especially in extreme climatic conditions, they become ineffective immediately after being buried. Living plant sand barriers, such as shelterbelts, fix quicksand by planting wind-resistant plants, and have a strong windbreak and sand fixation effect. However, the growth cycle of plants is long, and in arid areas, they must rely on irrigation to maintain normal growth. The overall maintenance cost is high, and the technology of tree species selection and sustainable maintenance is relatively difficult. In addition, although traditional grass grid sand barriers have a simple structure and significant effect, with the use of large areas of grass grids, the price of materials such as plant straw has risen, the manual construction cycle is long, and the labor cost is high. At the same time, they cannot be updated after being buried, so their overall lifespan is short. Therefore, existing technologies often face problems such as poor economic efficiency, difficulty in implementation, high maintenance costs, and short service life. Summary of the Invention
[0003] In response to the above-mentioned deficiencies in the prior art, the present invention provides a method for constructing and laying out semi-living sand ridges and sand barriers in arid areas, which solves the technical problems mentioned in the above-mentioned background technology and improves the effect of windbreak and sand fixation in arid areas.
[0004] To achieve the above object, the technical solution adopted by the present invention is: Provided is a method for constructing and laying out semi-living sand ridges and sand barriers in arid areas, comprising: S1: constructing sand ridges on mobile sand in the arid area; S2: planting drought-tolerant plants and applying a water-retaining agent to the drought-tolerant plants; S3: forming a living sand barrier after the drought-tolerant plants grow for a certain period of time; when the water in the water-retaining agent is exhausted, the drought-tolerant plants gradually wither and form a semi-living sand barrier with roots fixed in the sand and trunks remaining flexible.
[0005] Furthermore, the cross section of the sand ridge is trapezoidal in shape, the height of the sand ridge is 30-40 cm, the width of the upper bottom is 30-40 cm, the width of the lower bottom is 45-55 cm, and the spacing between the sand ridges is 4-6 m.
[0006] Furthermore, the sand ridges in step S1 are constructed using mechanized ridging equipment, and after the sand ridges are constructed, a sand-fixing agent is sprayed on their surface to enhance the cohesion of the sand and prevent the sand from flowing.
[0007] Furthermore, the drought-tolerant plants are fast-growing shrubs, semi-shrubs or herbaceous plants that are adapted to the local climate and sandy soil conditions.
[0008] Furthermore, in step S2, the drought-tolerant plants are planted by seeds or cuttings according to the selected drought-tolerant plant types.
[0009] Furthermore, when drought-tolerant plants are planted using seeds, water-retaining agents are sprayed on the surface of the sand ridges until a water-containing sand layer 3-5 cm from the surface of the sand ridges is formed. After the seeds are sown, the water-retaining agent is used to provide water supply for 3-4 months until a living sand barrier of a certain height is formed.
[0010] Furthermore, when drought-tolerant plants are planted using cuttings, the length of the cuttings is 20 cm, the insertion depth of the cuttings is 15-20 cm, the spacing between the cuttings is 10 cm, and a certain amount of water-retaining agent and irrigation water are injected at the cutting position. After the cuttings are planted, the water-retaining agent and irrigation water are used to provide water supply for 3-4 months until a living sand barrier of a certain height is formed.
[0011] Furthermore, the water retaining agent is a high molecular weight water absorbing material that can continuously supply water to drought-tolerant plants in the early stages of growth.
[0012] The beneficial effects of the present invention are: 1. Compared with traditional straw grid sand barriers, this solution has a higher height, thus having better wind-proof and sand-fixing performance. At the same time, the roots of the semi-living sand barrier are fixed in the sand, and the trunk remains flexible. Compared with conventional plastic, straw or stone materials, it is more flexible and can better reduce wind speed and intercept wind and sand flow, thereby improving the wind-proof and sand-fixing effect.
[0013] 2. Once the sand barrier of this scheme is formed, even if the drought-tolerant plants die, the natural sand-fixing effect of their roots can still continue to fix the sand in the sand ridges. The above-ground trunk part can still weaken the wind speed and intercept the wind and sand flow, thus providing a long-term wind-proof and sand-fixing effect. It does not require subsequent maintenance and irrigation, reducing construction and subsequent maintenance costs. Compared with traditional sand barrier technology, this scheme has significant advantages in economy and ease of operation, providing an innovative, low-cost and sustainable solution for ecological restoration and desertification control in arid areas. At the same time, it also has significant advantages in mechanized construction and large-scale promotion and application, which can significantly improve the efficiency and effectiveness of wind and sand disaster prevention and control. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 Flowchart of the method for constructing and deploying semi-living sand ridge barriers in arid areas. DETAILED DESCRIPTION
[0015] The specific embodiments of the present invention are described below to facilitate understanding of the present invention by those skilled in the art. However, it should be clear that the present invention is not limited to the scope of the specific embodiments. For those skilled in the art, as long as various changes are within the spirit and scope of the present invention as defined and determined by the appended claims, these changes are obvious, and all inventions and creations utilizing the concepts of the present invention are protected.
[0016] like Figure 1 As shown, the method for constructing and laying out semi-living sand ridges and sand barriers in arid areas of this scheme includes: S1: Sand ridges are constructed on mobile sand in arid areas. Specifically, the cross-section of the sand ridge is trapezoidal in shape, with a ridge height of 30-40 cm, an upper base width of 30-40 cm, and a lower base width of 45-55 cm. Depending on the intensity of wind and sand activity, the spacing between sand ridges is 4-6 m, and a total of 10-20 rows of sand ridges can be set up. The sand ridges are constructed using mechanized ridging equipment, and after the sand ridges are constructed, a sand-fixing agent is sprayed on their surface to enhance the cohesion of the sand and prevent sand from flowing.
[0017] S2: Plant drought-tolerant plants and apply water-retaining agents to them. Water-retaining agents are polymers that continuously supply water to drought-tolerant plants during their early growth stages. Specifically, drought-tolerant plants are fast-growing shrubs, semi-shrubs, or herbs adapted to the local climate and sandy soil conditions, such as Artemisia sphaerocarpa, Artemisia ordosica, Nitraria tangutorum, Tamarix chinensis, and Calligonum mongolicum. These plants have well-developed root systems, large above-ground biomass, and rapid growth, allowing them to survive quickly in harsh desert environments and effectively stabilize sand. Plant drought-tolerant plants from seeds or cuttings, depending on the type of drought-tolerant plant you choose: When drought-tolerant plants are planted using seeds, water-retaining agents are sprayed on the surface of the sand ridges until a water-containing sand layer 3-5 cm from the surface of the sand ridges is formed. After the seeds are sown, the water-retaining agent is used to provide water supply for 3-4 months to promote seed germination and growth until a living sand barrier of a certain height is formed.
[0018] When drought-tolerant plants are planted by cuttings, the length of the cuttings is 20 cm, the insertion depth of the cuttings is 15-20 cm, the spacing between the cuttings is 10 cm, and 10 ml of water-retaining agent and irrigation water are injected at the cutting position. After the cuttings are planted, the water-retaining agent and irrigation water are used to provide water supply for 3-4 months. The role of the water-retaining agent is to provide the water needed for the cuttings in the early growth stage, while the irrigation water provides the necessary basic water source for the roots of the cuttings until a living sand barrier of a certain height is formed.
[0019] S3: When the water in the water-retaining agent is exhausted, the drought-resistant plants gradually wither and form a semi-living sand barrier; specifically, because the roots of the plants have formed a network structure inside the sand ridges, even if the branches and leaves wither or die, their roots can still effectively fix the sand and prevent sand loss, while the above-ground trunk part forms a flexible sand barrier, which can weaken the wind speed and intercept the wind and sand flow. The open space between the two rows of sand ridges can intercept the wind and sand and form a sand-fixing belt, thereby significantly improving the wind and sand prevention effect.
[0020] This solution optimizes wind and sand fixation measures by combining the natural sand-fixing ability of plant roots with the structural stability of artificial materials. Compared with traditional grass grid sand barriers, semi-living sand barriers have more significant wind and sand fixation effects. They can not only resist strong wind and sand invasion, but also reduce the amount of materials used, lowering construction and subsequent maintenance costs. At the same time, the design structure of this sand barrier structure is simple and easy to implement, and the construction process can be easily mechanized, which can be effectively promoted and applied in a large area. Compared with traditional sand barrier technology, this solution has significant advantages in economy and ease of operation, providing an innovative, low-cost and sustainable solution for ecological restoration and desertification control in arid areas, and significantly improving the efficiency and effectiveness of wind and sand disaster prevention and control.
Claims
1. A method for constructing and laying out semi-living sand ridges and sand barriers in arid areas, characterized in that: include: S1: Construction of sand ridges on mobile sand in arid areas; S2: Plant drought-tolerant plants and apply water-retaining agents to drought-tolerant plants; S3: After the drought-tolerant plants grow for a certain period of time, they form a living sand barrier; when the water in the water-retaining agent is exhausted, the drought-tolerant plants gradually wither and form a semi-living sand barrier with roots fixed in the sand and trunks remaining flexible.
2. The method for constructing and laying out semi-living sand ridges and sand barriers in arid areas according to claim 1, characterized in that: The cross section of the sand ridge is trapezoidal in shape, the height of the sand ridge is 30-40 cm, the width of the upper bottom is 30-40 cm, the width of the lower bottom is 45-55 cm, and the spacing between the sand ridges is 4-6 m.
3. The method for constructing and laying out semi-living sand ridges and sand barriers in arid areas according to claim 1, characterized in that: The sand ridges in step S1 are constructed using mechanized ridge-forming equipment, and after the sand ridges are constructed, a sand-fixing agent is sprayed on their surface to enhance the cohesion of the sand and prevent the sand from flowing.
4. The method for constructing and laying out semi-living sand ridges and sand barriers in arid areas according to claim 1, characterized in that: The drought-tolerant plants are fast-growing shrubs, semi-shrubs or herbaceous plants that are adapted to local climate and sandy soil conditions.
5. The method for constructing and laying out semi-living sand ridges and sand barriers in arid areas according to claim 4, characterized in that: In step S2, the drought-tolerant plants are planted using seeds or cuttings according to the selected drought-tolerant plant types.
6. The method for constructing and laying out semi-living sand ridges and sand barriers in arid areas according to claim 5, characterized in that: When the drought-resistant plants are planted using seeds, a water-retaining agent is sprayed on the surface of the sand ridge until a water-containing sand layer 3-5 cm away from the surface of the sand ridge is formed. After the seeds are sown, the water-retaining agent is used to provide water supply for 3-4 months until a living sand barrier with a certain height is formed.
7. The method for constructing and laying out semi-living sand ridges and sand barriers in arid areas according to claim 5, characterized in that: When the drought-resistant plants are planted using cuttings, the length of the cuttings is 20 cm, the insertion depth of the cuttings is 15-20 cm, the spacing between the cuttings is 10 cm, and a certain amount of water-retaining agent and irrigation water are injected at the cutting position. After the cuttings are planted, the water-retaining agent and irrigation water are used to provide water supply for 3-4 months until a living sand barrier with a certain height is formed.
8. The method for constructing and laying out semi-living sand ridges and sand barriers in arid areas according to claim 1, characterized in that: The water retaining agent is a high molecular water absorbing material that can continuously supply water in the early growth stage of drought-tolerant plants.