Electric power standardized operation construction scheme digital compilation system
The digital compilation system for standardized power operation construction plans has solved the problems of uneven resource allocation and safety hazards in power operations, realized transparent management of construction resources and improved efficiency, and ensured the optimization of construction progress and equipment utilization.
Patent Information
- Application Number
- CN202510992911.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-07-18
- Publication Date
- 2025-10-24
AI Technical Summary
The dispersed nature of power workers, the prevalence of temporary jobs, and insufficient staffing lead to significant safety hazards in power grid construction and maintenance. Furthermore, uneven resource allocation affects construction efficiency and equipment utilization.
A digital compilation system for standardized power operation construction plans was designed, including a construction design module, a project audit module, an approval module, a construction supervision module, a project material supply traceability module, a project material certification module, a construction unit qualification module, a government construction reporting module, a preliminary progress query module, and a construction business progress module, to achieve transparent management and rational allocation of resources.
The digital compilation system enabled the rational allocation of construction resources, improved construction progress and efficiency, ensured clear division of responsibilities, reduced equipment idleness or overuse, and enhanced the safety and efficiency of power supply.
Smart Images

Figure CN120833008A_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to a power standardization operation construction system, in particular, the present application relates to a power standardization operation construction scheme digital preparation system. BACKGROUND
[0002] The power station generates electric energy, which is the carrier of the power grid flowing between regions, and is also the carrier of the power department entering enterprises, institutions, factories, mines, commercial streets and residential areas after the electric energy is distributed through the power grid. The construction, maintenance and maintenance of the power grid are the responsibility of the power department. Due to the wide range of power grid, the complexity of voltage level, cross-span, and the main setting of power distribution equipment in densely populated areas, the dispersion of power operation personnel, the large number of temporary operations, the insufficient personnel and other practical reasons, it is easy to cause the laxity and paralysis of the guardian and the command organizer, and further cause safety accidents. Standardized management is a management means to overcome the above defects and improve efficiency. Through the standardized management operation construction scheme, the digital optimization preparation process is used, and the standardized equipment maintenance process can greatly shorten the maintenance time, improve the availability of equipment, and further improve the efficiency of the entire power supply. In resource integration, standardized management helps to integrate human, material and financial resources. The integration of these resources can be used according to the power demand of different regions and the operation state of the equipment, and the optimal allocation of the equipment can be realized according to the standardized allocation principle, and the unnecessary equipment idle or overuse situation can be reduced. Therefore, it is necessary to develop a set of power standardization operation construction scheme digital preparation system. SUMMARY
[0003] The purpose of the present application is based on the existing deficiencies, and discloses a power standardization operation construction scheme digital preparation system, which can effectively allocate and utilize the construction resources, improve the construction progress, and realize transparent management.
[0004] In order to achieve the purpose of the present application, the following technical scheme is disclosed: A power standardization operation construction scheme digital preparation system, the construction scheme digital preparation system includes a construction design module, a project audit module, an approval module, a construction supervision module, a project supply traceability module, a project material certification module, a construction unit qualification module, a government construction reporting module, a pre-procedure progress query module and a construction business progress module. The construction design module is connected with the project audit module through a signal channel, the project audit module is connected with the approval module through a signal channel, the approval module is connected with the construction supervision module, the project supply traceability module, the project material authentication module and the construction unit qualification module through a signal channel for sharing, the government construction reporting module and the early progress query module are arranged in the construction supervision module, the project supply traceability module, the project material authentication module and the construction unit qualification module, the government construction reporting module and the early progress query module are used for interacting with the construction supervision unit, the project supply unit and the construction unit to fill in related matters, and are used for querying the government construction reporting module and the early progress query module, and updating the respective responsible part of the construction business progress module.
[0005] The construction design module of the power standardization operation construction scheme digital preparation system is designed and constructed by importing the project audit module after project audit, importing the approval module after project audit, and importing the construction supervision module, the project supply traceability module, the project material authentication module and the construction unit qualification module after the approval of the superior, the construction supervision unit, the project supply unit and the construction unit prepare the early work, and the government construction approval unit reports the construction, the construction supervision unit, the project supply unit and the construction unit can check the reporting progress through the government construction reporting module, and make preparations of personnel, materials, power construction equipment and personnel and upload the preparation progress to the early progress query module, and start the construction operation according to the plan after the approval of the government construction reporting module; the construction supervision unit uploads the supervision log, the project supply unit uploads the supply list, and the construction unit uploads the construction progress to the construction business progress module The construction design module of the power standardization operation construction scheme digital preparation system includes the total plan, the plan, the three-dimensional graph, the planar graph, the structure description, the node detail graph, the material strength, the load parameter, the construction technology requirement, the personnel allocation, the equipment option, the matters needing attention, the construction time limit, the design basis, the design date and the design unit.
[0006] The project audit module of the power standardization operation construction scheme digital preparation system includes the project bidding information publicizing, the bidding audit information publicizing, the economic supervision information publicizing, the economic evaluation information publicizing and the economic identification information publicizing; the approval module includes the bidding information publicizing, the bidding audit result, the economic supervision result, the economic evaluation result and the economic identification result.
[0007] The construction supervision module is used for query of the construction supervision unit and development of subsequent preparation work, the project supply traceability module is used for procurement of construction materials, the project material authentication module is used for comparison of the purchased construction materials and the reported materials, and the construction unit qualification module is used for uploading of the qualification of the construction unit, outsourcing or non-outsourcing and addition of a cooperative unit by the construction unit.
[0008] The government construction reporting module is used for land pre-examination, compliance examination, ecological environment influence, use of government budget funds examination and display of the reply file of the government to the project.
[0009] The early progress query module is used for confirmation of the construction supervision unit personnel, supply and preparation of the project, equipment preparation condition uploading and confirmation of the basis for the start date.
[0010] The construction business progress module is used for real-time data uploading of the construction progress, manufacturer information, quantity, usage, construction progress, construction quality and remaining quantity of the construction materials by the construction supervision, and the uploaded data cannot be changed; and the data information of the construction business progress module is used for evidence checking after a problem occurs.
[0011] Through the above disclosure, the beneficial effects of the present application are as follows: The power standardization operation construction scheme digital preparation system has the construction design module, the project audit module, the approval module, the construction supervision module, the project supply traceability module, the project material authentication module, the construction unit qualification module, the government construction reporting module, the early progress query module and the construction business progress module, so that the design, audit, approval and mid-term construction supervision, project supply and material and construction unit qualification of the project are clear at a glance, a foundation for the post-construction business progress standardization is laid, and the division of the responsibilities, rights and interests of each responsible party is ensured; the construction resources can be effectively and reasonably allocated and utilized, the construction progress is improved, and transparent management is achieved. BRIEF DESCRIPTION OF DRAWINGS
[0012] Figure 1 It is a power standardization operation construction scheme digital preparation system diagram of the present application. DETAILED DESCRIPTION
[0013] The preferred embodiments of the present application will be described in detail below with reference to the drawings, so that the inventive purpose, features and advantages of the present application can be more clearly understood. It should be understood that the embodiments shown in the drawings are not a limitation on the scope of the present application, but are only for the purpose of explaining the technical solutions of the present application which are not limited to one embodiment.
[0014] The power standardization construction scheme digital preparation system described above is prepared by setting a national power grid local power supply company APP, setting a power engineering channel in the APP, setting an interactive platform for power engineering bidding service, material procurement and construction supervision service in the power engineering channel, or setting a power construction bidding website, or using a local government platform and a local administrative service center service website. Figure 1 The construction scheme digital preparation system includes a construction design module, a project audit module, an approval module, a construction supervision module, a project supply traceability module, a project material certification module, a construction unit qualification module, a government construction reporting module, a preliminary progress query module and a construction business progress module. The construction design module includes a total plan, a plan, a perspective view, a planar view, a structural description, a node detail view, material strength, load parameters, construction process requirements, personnel allocation, equipment options, matters needing attention, construction time limit, design basis, design date and design unit of the project construction. The project audit module includes bidding information publicity, bidding audit information publicity, economic supervision information publicity, economic evaluation information publicity and economic appraisal information publicity of the project. The approval module includes bidding information publicity, bidding audit results, economic supervision results, economic evaluation results and economic appraisal results. The construction supervision module is used for the query of the construction supervision unit and the subsequent preparation work. The project supply traceability module is used for the procurement of construction materials. The project material certification module is used for the comparison of the purchased construction materials and the reported materials. The construction unit qualification module is used for the construction unit to upload the qualification of the construction unit, outsourcing and newly added cooperative units. The government construction reporting module is used for the land pre-examination, compliance review, ecological environment impact, use of government budget funds review and display of the reply documents of the government for the project. The preliminary progress query module is used for the confirmation of the construction supervision personnel, the supply and preparation of the project, the allocation of the construction unit personnel and the preparation of the equipment. After uploading, it is used as the basis for confirming the commencement date.
[0015] The construction business progress module is used for the real-time data upload of the construction progress by the construction supervision, the manufacturer information, quantity, usage, construction progress, construction quality and remaining quantity of the construction materials. The uploaded data cannot be changed. The data information of the construction business progress module is used for evidence checking after problems occur. The construction design module is connected with the project audit module through a signal channel, the project audit module is connected with the approval module through a signal channel, the approval module is connected with the construction supervision module, the project supply traceability module, the project material authentication module and the construction unit qualification module through a signal channel for sharing, the government construction reporting module and the early progress inquiry module are arranged in the construction supervision module, the project supply traceability module, the project material authentication module and the construction unit qualification module, the government construction reporting module and the early progress inquiry module are used for interacting with the construction supervision unit, the project supply unit and the construction unit to fill in related matters, and are used for inquiring the government construction reporting module and the early progress inquiry module, and updating the respective responsible part of the construction business progress module.
[0016] Further, the design construction of the construction design module is imported into the project audit module after the project audit, is imported into the approval module after the project audit, is respectively imported into the construction supervision module, the project supply traceability module, the project material authentication module and the construction unit qualification module after the approval of the superior, the early work is prepared by the construction supervision unit, the project supply unit and the construction unit, and the government construction approval unit is reported, and the construction supervision unit, the project supply unit and the construction unit can check the reporting progress through the government construction reporting module, and make preparations of personnel, materials, power construction equipment and personnel according to the construction quantity and progress planning, after the preparation is completed, the preparation condition and the preparation progress are uploaded to the early progress inquiry module, so that the owner unit understands the construction state, after the approval of the government construction reporting module, the construction operation is started according to the planning; the construction supervision unit participating in the construction uploads the supervision log, the project supply unit uploads the supply list, and the construction unit uploads the construction progress to the construction business progress module.
[0017] The preferred embodiments of the present application have been described in detail above, but it should be understood that, after reading the above description of the present application, those skilled in the art can make various modifications or changes within the scope of the present application. These equivalent forms also fall within the scope defined by the appended claims of the present application.
[0018] The part of the present application not described in detail is the prior art.
Claims
1. A digital compilation system for standardized power operation construction plans, characterized by: The construction scheme digital preparation system comprises a construction design module, a project audit module, an approval module, a construction supervision module, a project supply traceability module, a project material authentication module, a construction unit qualification module, a government construction reporting module, a preliminary progress query module and a construction business progress module; The construction design module is connected with the project audit module through a signal channel, the project audit module is connected with the approval module through a signal channel, the approval module is connected with the construction supervision module, the project supply traceability module, the project material authentication module and the construction unit qualification module through signal channels for sharing, the construction supervision module, the project supply traceability module, the project material authentication module and the construction unit qualification module are provided with the government construction reporting module and the preliminary progress query module, the government construction reporting module and the preliminary progress query module are used for interacting with the construction supervision unit, the project supply unit and the construction unit to fill in related matters, and are used for querying the government construction reporting module and the preliminary progress query module and updating the respective responsible parts of the construction business progress module.
2. The electrical power standardization job construction plan digitizing system according to claim 1, characterized in that: The designed construction of the construction design module is imported into the project audit module after project audit, is imported into the approval module after project audit, and is respectively imported into the construction supervision module, the project supply traceability module, the project material authentication module and the construction unit qualification module after approval by the superior, the preliminary work is prepared by the construction supervision unit, the project supply unit and the construction unit, and the construction reporting is performed in the government construction approval unit, the construction supervision unit, the project supply unit and the construction unit can check the reporting progress through the government construction reporting module, and simultaneously make preparations for personnel, materials, power construction equipment and personnel and upload the preparation progress to the preliminary progress query module, and start the construction operation according to the plan after the approval of the government construction reporting module; the construction supervision unit participating in the construction synchronously uploads the supervision log, the project supply unit synchronously uploads the supply list, and the construction unit synchronously uploads the construction progress to the construction business progress module.
3. The electrical power standardization job plan digital preparation system according to claim 1, characterized in that: The construction design module comprises a total plan of project construction, a plan, a perspective view, a planar view, a structure description, a node detail view, material strength, load parameters, construction process requirements, personnel allocation, equipment options, matters needing attention, construction time limit, design basis, design date and design unit.
4. The electrical power standardization job plan digitizing system according to claim 1, characterized in that: The project audit module comprises bidding information publicity, bidding audit information publicity, economic supervision information publicity, economic evaluation information publicity and economic identification information publicity; the approval module comprises bidding information publicity, bidding audit results, economic supervision results, economic evaluation results and economic identification results.
5. The electrical power standardization job plan digitizing system according to claim 1, characterized in that: The construction supervision module is used for the query of the construction supervision unit and the development of subsequent preparation work, the project supply traceability module is used for the procurement of construction materials, the project material authentication module is used for the comparison of the purchased construction materials and the reported materials, and the construction unit qualification module is used for the construction unit to upload the qualification of the construction unit, outsourcing or addition of cooperative units.
6. The digital compilation system for electric power standardization operation construction plan according to claim 1 is characterized by: The government construction reporting module is used for the land pre-audit, compliance review, ecological environment impact, use of government budget funds review and display of the reply documents of the government for the project.
7. The electrical power standardization job plan digitizing system of claim 1, wherein: The early progress query module is used for confirmation of construction supervision unit personnel, supply and preparation of project, preparation of construction unit personnel, and uploading of equipment preparation situation for confirmation of construction start date.
8. The electrical power standardization job plan digitizing system of claim 1, wherein: The construction business progress module is used for real-time data uploading of construction supervision on construction progress, data uploading of manufacturer information, quantity, usage, construction progress, construction quality, and remaining quantity of construction materials, and the uploaded data cannot be changed; the data information of the construction business progress module is used for evidence checking after problems occur.