Digital management and tracking method for prefabricated outer wall production

By using RFID tags and automated quality inspection, the entire lifecycle of prefabricated exterior wall production is digitally managed, solving the problems of low information level and lagging quality control, improving production efficiency and quality, and achieving efficient prefabricated exterior wall production.

CN121119664APending Publication Date: 2025-12-12MODIANGOU INTELLIGENT TECH (DONGGUAN) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202511450674.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-10-11
Publication Date
2025-12-12

AI Technical Summary

Technical Problem

Traditional precast exterior wall production suffers from low levels of information technology, lagging quality control, and opaque production progress, leading to difficulties in quality traceability, resource waste, and project delays. Furthermore, the lack of dynamic management methods results in unstable production efficiency.

Method used

By using RFID tags to bind production data and quality inspection results, we can achieve full lifecycle digital recording. Combined with automated quality inspection and early warning, we can track production progress in real time and optimize production parameters through periodic evaluation.

Benefits of technology

It enables precise traceability of prefabricated exterior wall production, rapid identification of defective products, reduction of defect rate, and improvement of pass rate. It solves the problems of information silos and extensive management, and provides efficient and high-quality production support.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN121119664A_ABST
    Figure CN121119664A_ABST
Patent Text Reader

Abstract

The invention discloses a digital management and tracking method for prefabricated outer wall production, and belongs to the technical field of constructional engineering, and the method comprises the steps: carrying out the information collection of the whole production process of each prefabricated outer wall, and obtaining production data; an RFID tag is installed on each prefabricated outer wall and used for recording corresponding production data; performing quality detection on the produced prefabricated outer wall, wherein the quality detection comprises size quality detection and mechanical property detection; the production data of the prefabricated outer wall are read in real time through the RFID tag, the production data are compared with a preset production plan, and the production progress of the prefabricated outer wall is tracked in real time; the quality qualification rate and the production rate of the prefabricated outer wall are periodically calculated and summarized to form a production evaluation coefficient; and the obtained production evaluation coefficient is compared with a preset evaluation threshold value, and if the obtained production evaluation coefficient is smaller than the evaluation threshold value, an alarm is given, and production operation parameters in prefabricated outer wall production in the period are optimized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of building engineering technology, specifically to a digital management and tracking method for the production of prefabricated exterior walls. Background Technology

[0002] With the advancement of industrialized construction, prefabricated exterior walls are widely used in prefabricated building construction due to their advantages of high efficiency and standardization. However, the traditional prefabricated exterior wall production process suffers from problems such as low levels of informatization, lagging quality control, and lack of transparency in production progress.

[0003] Currently, production data largely relies on manual recording, which is prone to missing or incorrect information, making quality traceability difficult. Quality inspection is scattered across various processes, and the data lacks a systematic correlation, making it difficult to provide real-time feedback on production status. Production progress tracking depends on experience-based judgment, lacking dynamic and visualized management methods, which can easily lead to resource waste or delays. In addition, traditional production models lack systematic analysis of the production cycle and cannot optimize production parameters based on data, resulting in large fluctuations in pass rates and unstable production efficiency.

[0004] While some companies have attempted to introduce barcode or RFID technology for identification management, these technologies are mostly limited to data recording in a single stage and have failed to achieve end-to-end digital integration and intelligent analysis. Summary of the Invention

[0005] The purpose of this invention is to overcome the shortcomings of the prior art and provide a digital management and tracking method for prefabricated exterior wall production, so as to solve the problems mentioned in the background art.

[0006] The objective of this invention can be achieved through the following technical solution: a digital management and tracking method for prefabricated exterior wall production, comprising the following steps: Step 1: Collect information throughout the entire production process of each precast exterior wall, convert the collected information into digital data to obtain production data; and install RFID tags on each precast exterior wall to record its corresponding production data. Step 2: Conduct quality inspection on the completed precast exterior walls, including dimensional quality inspection and mechanical performance testing. Obtain the quality inspection results and associate them with the corresponding RFID tags of the precast exterior walls, then upload them to the cloud database. The quality inspection results include qualified and unqualified. Step 3: Use RFID tags to read the production data of the prefabricated exterior wall in real time, compare it with the preset production plan, and track the production progress of the prefabricated exterior wall in real time; Step 4: Perform periodic analysis on prefabricated exterior wall production, including: periodically calculating the quality pass rate and production rate of prefabricated exterior walls, summarizing them to form a production evaluation coefficient; comparing the obtained production evaluation coefficient with the preset evaluation threshold; if the obtained production evaluation coefficient is less than the evaluation threshold, an alarm is issued and the production operation parameters in the prefabricated exterior wall production within that period are optimized.

[0007] Preferably, in step one, the method for obtaining production data is as follows: S101. Based on the design drawings of the prefabricated exterior wall, obtain the design information of the prefabricated exterior wall, including design dimension information and mechanical performance design standards; wherein, the design dimension information refers to the geometric dimension parameters of the prefabricated exterior wall; the mechanical performance design standards include the standard value of load-bearing capacity; S102. Collect information on raw materials required for the production of precast exterior walls, including the specifications, batch numbers, arrival time, and quality inspection reports of the raw materials; among which, the raw materials required for the production of precast exterior walls include concrete, steel bars, and admixtures. S103. By deploying various sensors at each production process of the prefabricated exterior wall, the operating parameters of the production equipment and production progress information are collected in real time.

[0008] Preferably, the production data for the precast exterior wall is determined based on the collected design information, raw material information, production equipment operating parameters, and production progress information.

[0009] Preferably, in step two, the process of quality inspection of the completed prefabricated exterior walls includes: S201. Use a laser scanner to measure the completed prefabricated exterior wall to obtain the actual size information of the prefabricated exterior wall; when measuring the actual size of the prefabricated exterior wall, multiple tests are required, and abnormal data is removed before taking the average value. S202. Compare the geometric dimension parameters of the actual dimensions of the precast exterior wall with the design dimensions, and calculate the absolute value of the dimensional deviation of the precast exterior wall. S203. Compare the absolute value of the dimensional deviation with the corresponding preset deviation threshold. If the absolute value of the dimensional deviation is less than or equal to the deviation threshold of the corresponding dimension, it indicates that the dimensional quality of the prefabricated exterior wall is qualified; otherwise, an abnormal signal is triggered and the prefabricated exterior wall is marked as unqualified.

[0010] Preferably, the process of quality inspection of the completed prefabricated exterior walls also includes: S204. The maximum load-bearing capacity of the prefabricated exterior wall is obtained by conducting mechanical performance tests on the completed prefabricated exterior wall, i.e., the actual load-bearing capacity test value. Among them, when testing the mechanical performance of the prefabricated exterior wall, multiple sets of tests need to be conducted, and the average value is taken after removing abnormal data. S205. Obtain the standard value of bearing capacity. By establishing a bearing capacity assessment model, obtain the bearing capacity assessment value to test and evaluate the mechanical performance of the precast exterior wall. If the bearing capacity assessment value is 1, it means that the mechanical performance of the precast exterior wall is qualified. If the bearing capacity assessment value is 0, an abnormal signal is triggered and the precast exterior wall is marked as unqualified. S206. Based on S201 to S205, obtain prefabricated exterior walls that pass dimensional quality inspection and mechanical performance inspection, and mark the prefabricated exterior walls as qualified.

[0011] Preferably, in S205, the expression for the bearing capacity assessment model is: ; In the formula, CP(SJ) represents the load-bearing capacity assessment value; SJ is the actual load-bearing capacity test value; and CB is the standard load-bearing capacity value.

[0012] Preferably, in step three, the process of tracking the production progress of the prefabricated exterior wall includes: S301. Based on the production data of prefabricated exterior walls, obtain the corresponding production progress information, and obtain the actual time consumed by each production process by calculating the difference between the actual start time and the actual end time of each production process. S302. Similarly, based on the pre-set production plan, calculate the planned time for each production process of the corresponding prefabricated exterior wall. S303. By calculating the difference between the actual time and the planned time in each production process of the prefabricated exterior wall, a production progress tracking record is generated and compared with the preset progress deviation threshold of the corresponding production process. Then, a production progress prompt signal is generated. The production progress tracking record includes the progress deviation of each production process of the prefabricated exterior wall.

[0013] Preferably, in S303, the comparison process includes: If the progress difference of the corresponding production process is greater than or equal to the progress deviation threshold, it indicates that the progress of the production process is abnormal and an abnormality prompt signal is generated. If the progress difference of the corresponding production process is less than the progress deviation threshold, it indicates that the progress of the production process is normal and a normal prompt signal is generated. Abnormal or normal error signals constitute production progress indication signals.

[0014] Preferably, in step four, the process of periodically analyzing the production of prefabricated exterior walls includes: S401. Periodically traverse the quality inspection results of prefabricated exterior walls to obtain the number of qualified and unqualified prefabricated exterior walls, and calculate the quality pass rate of prefabricated exterior walls within this period. The calculation formula is as follows: ; In the formula, HL is the quality pass rate of prefabricated exterior walls within the period; HG is the number of qualified prefabricated exterior walls; and BG is the number of unqualified prefabricated exterior walls. S402. Calculate the production rate of prefabricated exterior walls within a preset period by statistically analyzing the actual total output of prefabricated exterior walls within that period. The calculation formula is as follows: ; In the formula, V is the production rate of prefabricated exterior walls within a cycle; YT is the preset cycle.

[0015] Preferably, the process of periodically analyzing the production of prefabricated exterior walls further includes: S403. Normalize and summarize the quality pass rate and production rate of precast exterior walls within the cycle to form a production evaluation coefficient. ; In the formula, P is the production evaluation coefficient; and This represents the weighting coefficients corresponding to the quality pass rate and production rate, and ; S404. Compare the obtained production evaluation coefficient with the preset evaluation threshold. If the obtained production evaluation coefficient is less than the evaluation threshold, issue an alarm and optimize the production operation parameters in the prefabricated exterior wall production within the cycle, including adjusting the values ​​of the production operation parameters in the prefabricated exterior wall production, until the recalculated production evaluation coefficient is greater than or equal to the evaluation threshold.

[0016] Compared to existing solutions, the beneficial effects achieved by this invention are: This invention uses RFID tags to bind production data and quality inspection results, enabling digital recording of the entire lifecycle from raw material processing, molding and curing to quality inspection, and achieving precise traceability of production data for each precast exterior wall. This invention automates the quality inspection and early warning of prefabricated exterior walls after production. It can quickly identify defective products and trigger warnings. Furthermore, by dynamically monitoring and intelligently scheduling the production progress, as well as periodically evaluating and optimizing, it effectively reduces the defect rate and improves the pass rate of prefabricated exterior walls. It also solves the problems of information silos, extensive management, and insufficient dynamic response in traditional production methods, providing technical support for the efficient and high-quality production of prefabricated exterior walls. Attached Figure Description

[0017] The invention will now be further described with reference to the accompanying drawings.

[0018] Figure 1 This is a flowchart of the digital management and tracking method for prefabricated exterior wall production proposed in this invention. Detailed Implementation

[0019] The technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present invention. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments.

[0020] like Figure 1 As shown, this invention provides a digital management and tracking method for prefabricated exterior wall production, comprising the following steps: Step 1: Collect information throughout the entire production process of each precast exterior wall, convert the collected information into digital data to obtain production data; and install RFID tags on each precast exterior wall to record its corresponding production data. In step one, the method for obtaining production data is as follows: S101. Based on the design drawings of the prefabricated exterior wall, obtain the design information of the prefabricated exterior wall, including design dimension information and mechanical performance design standards; Among them, design dimension information refers to the geometric dimension parameters of the prefabricated exterior wall, such as length, width, height, and curvature; mechanical performance design standards include standard values ​​for load-bearing capacity; S102. Collect information on raw materials required for the production of precast exterior walls, including the specifications, batch numbers, arrival time, and quality inspection reports of the raw materials; among which, the raw materials required for the production of precast exterior walls include concrete, steel bars, and admixtures. S103. By deploying various sensors in each production process of prefabricated exterior walls, production operation parameters and production progress information are collected in real time. The production operation parameters include, but are not limited to, mixing time, vibration frequency, and mold temperature; production progress information is obtained by recording the actual start and end times of each production process of the precast exterior wall; furthermore, the production processes of the precast exterior wall include, but are not limited to, concrete pouring, vibration, and curing. Based on the collected design information, raw material information, production equipment operating parameters and production progress information, the production data of the precast exterior wall is determined. It should be further explained that the RFID tags are radio frequency tags, and each RFID tag has a unique ID number to identify the corresponding prefabricated exterior wall, enabling accurate tracking.

[0021] Step 2: Conduct quality inspection on the completed precast exterior walls, including dimensional quality inspection and mechanical performance testing. Obtain the quality inspection results and associate them with the corresponding RFID tags of the precast exterior walls, then upload them to the cloud database. The quality inspection results include qualified and unqualified. It should be further explained that, in the specific implementation process, the quality inspection of the completed prefabricated exterior walls includes: S201. Use a laser scanner to measure the completed prefabricated exterior wall to obtain the actual size information of the prefabricated exterior wall; when measuring the actual size of the prefabricated exterior wall, multiple tests are required, and abnormal data is removed before taking the average value. S202. Compare the geometric dimensional parameters of the actual dimensions of the prefabricated exterior wall with those of the design dimensions, and calculate the absolute value of the dimensional deviation of the prefabricated exterior wall; wherein, the absolute value of the dimensional deviation includes, but is not limited to, the absolute value of the length deviation, the absolute value of the height deviation, and the absolute value of the width deviation. S203. Compare the absolute value of the dimensional deviation with the corresponding preset deviation threshold. If the absolute value of the dimensional deviation is less than or equal to the deviation threshold of the corresponding dimension, it indicates that the dimensional quality of the prefabricated exterior wall is qualified; otherwise, an abnormal signal is triggered and the prefabricated exterior wall is marked as unqualified. Among them, the preset deviation threshold is the deviation threshold for different dimensions, and the specific value is set by experts in this field in combination with the design requirements of prefabricated exterior walls in actual production tasks; S204. The maximum load-bearing capacity of the prefabricated exterior wall is obtained by conducting mechanical performance tests on the completed prefabricated exterior wall, i.e., the actual load-bearing capacity test value. Among them, when testing the mechanical performance of the prefabricated exterior wall, multiple sets of tests need to be conducted, and the average value is taken after removing abnormal data. S205. Obtain the standard value of bearing capacity. By establishing a bearing capacity assessment model, obtain the bearing capacity assessment value to test and evaluate the mechanical performance of the precast exterior wall. If the bearing capacity assessment value is 1, it means that the mechanical performance of the precast exterior wall is qualified. If the bearing capacity assessment value is 0, an abnormal signal is triggered and the precast exterior wall is marked as unqualified. The expression for the carrying capacity assessment model is as follows: ; In the formula, CP(SJ) represents the load-bearing capacity assessment value; SJ is the actual load-bearing capacity test value; and CB is the standard load-bearing capacity value. S206. Based on S201 to S205, obtain prefabricated exterior walls that pass dimensional quality inspection and mechanical performance inspection, and mark the prefabricated exterior walls as qualified. It should be further explained that, based on the quality inspection results, RFID tags can be scanned on substandard precast exterior walls to obtain and analyze their production data, thereby determining the reasons for the substandard quality inspection results and enabling digital tracking and tracing of substandard precast exterior walls; for example, Step 3: Use RFID tags to read the production data of the prefabricated exterior wall in real time, compare it with the preset production plan, and track the production progress of the prefabricated exterior wall in real time; It should be further explained that, in the specific implementation process, the process of tracking the production progress of prefabricated exterior walls includes: S301. Based on the production data of prefabricated exterior walls, obtain the corresponding production progress information, and obtain the actual time consumed by each production process by calculating the difference between the actual start time and the actual end time of each production process. S302. Similarly, based on the pre-set production plan, calculate the planned time for each production process of the corresponding prefabricated exterior wall. S303. By calculating the difference between the actual time and the planned time in each production process of the prefabricated exterior wall, a production progress tracking record is generated and compared with the preset progress deviation threshold of the corresponding production process. Then, a production progress prompt signal is generated. The production progress tracking record includes the progress deviation of each production process of the prefabricated exterior wall. If the progress difference of the corresponding production process is greater than or equal to the progress deviation threshold, it indicates that the progress of the production process is abnormal and an abnormality prompt signal is generated. If the progress difference of the corresponding production process is less than the progress deviation threshold, it indicates that the progress of the production process is normal and a normal prompt signal is generated. Anomaly alerts or normal alerts constitute production progress alerts; It should be noted that the preset schedule deviation threshold is a key parameter for balancing production efficiency and flexibility, and needs to be dynamically set and corrected by those skilled in the art in combination with historical production data and equipment process characteristics; in addition, the schedule deviation value is an absolute value. Step 4: Perform periodic analysis on prefabricated exterior wall production, including: periodically calculating the quality pass rate and production rate of prefabricated exterior walls, summarizing them, and forming a production evaluation coefficient; comparing the obtained production evaluation coefficient with the preset evaluation threshold; if the obtained production evaluation coefficient is less than the evaluation threshold, an alarm is issued and the production operation parameters in the prefabricated exterior wall production within that period are optimized. It should be further explained that, in the specific implementation process, the periodic analysis of prefabricated exterior wall production includes: S401. Periodically traverse the quality inspection results of prefabricated exterior walls to obtain the number of qualified and unqualified prefabricated exterior walls, and calculate the quality pass rate of prefabricated exterior walls within the period; wherein, the preset period is set according to the production batch of prefabricated exterior walls. The calculation formula is as follows: ; In the formula, HL is the quality pass rate of prefabricated exterior walls within the period; HG is the number of qualified prefabricated exterior walls; and BG is the number of unqualified prefabricated exterior walls. S402. Calculate the production rate of prefabricated exterior walls within a preset period by statistically analyzing the actual total output of prefabricated exterior walls within that period. The calculation formula is as follows: ; In the formula, V is the production rate of prefabricated exterior walls within a cycle; YT is the preset cycle. S403. Normalize and summarize the quality pass rate and production rate of precast exterior walls within the cycle to form a production evaluation coefficient. ; In the formula, P is the production evaluation coefficient; and This represents the weighting coefficients corresponding to the quality pass rate and production rate, and Its specific value can be adjusted and modified by experts in the field according to actual design requirements; S404. Compare the obtained production evaluation coefficient with the preset evaluation threshold. If the obtained production evaluation coefficient is less than the evaluation threshold, issue an alarm and optimize the production operation parameters in the prefabricated exterior wall production within the cycle, including adjusting the values ​​of the production operation parameters in the prefabricated exterior wall production, until the recalculated production evaluation coefficient is greater than or equal to the evaluation threshold. The preset evaluation threshold can be set to 0.7.

[0022] In the several embodiments provided by this invention, it should be understood that the disclosed system can be implemented in other ways. For example, the embodiments of the invention described above are merely illustrative; for example, the division of modules is only a logical functional division, and there may be other division methods in actual implementation.

[0023] The modules described as separate components may or may not be physically separate. The components shown as modules may or may not be physical units; that is, they may be located in one place or distributed across multiple network units. Some or all of the modules can be selected to achieve the purpose of this embodiment according to actual needs.

[0024] Furthermore, the functional modules in the various embodiments of the present invention can be integrated into one processing unit, or each unit can exist physically separately, or two or more units can be integrated into one unit. The integrated unit can be implemented in hardware or in the form of hardware plus software functional modules.

[0025] It will be apparent to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential characteristics of the present invention.

[0026] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and are not intended to limit it. Although the present invention has been described in detail with reference to preferred embodiments, those skilled in the art should understand that modifications or equivalent substitutions can be made to the technical solutions of the present invention without departing from the spirit and scope of the technical solutions of the present invention.

Claims

1. A digital management and tracking method for precast exterior wall production, characterized in that, Includes the following steps: Step 1: Collect information throughout the entire production process of each precast exterior wall, and convert the collected information into digital data to obtain production data; RFID tags are installed on each prefabricated exterior wall to record its corresponding production data; Step 2: Conduct quality inspection on the completed precast exterior walls, including dimensional quality inspection and mechanical performance testing. Obtain the quality inspection results and associate them with the corresponding RFID tags of the precast exterior walls, then upload them to the cloud database. The quality inspection results include qualified and unqualified. Step 3: Use RFID tags to read the production data of the prefabricated exterior wall in real time, compare it with the preset production plan, and track the production progress of the prefabricated exterior wall in real time; Step 4: Perform periodic analysis on prefabricated exterior wall production, including: periodically calculating the quality pass rate and production rate of prefabricated exterior walls, summarizing them to form a production evaluation coefficient; comparing the obtained production evaluation coefficient with the preset evaluation threshold; if the obtained production evaluation coefficient is less than the evaluation threshold, an alarm is issued and the production operation parameters in the prefabricated exterior wall production within that period are optimized.

2. The digital management and tracking method for prefabricated exterior wall production according to claim 1, characterized in that, In step one, the method for obtaining production data is as follows: S101. Based on the design drawings of the prefabricated exterior wall, obtain the design information of the prefabricated exterior wall, including design dimension information and mechanical performance design standards; wherein, the design dimension information refers to the geometric dimension parameters of the prefabricated exterior wall; the mechanical performance design standards include the standard value of load-bearing capacity; S102. Collect information on raw materials required for the production of precast exterior walls, including the specifications, batch numbers, arrival time, and quality inspection reports of the raw materials; among which, the raw materials required for the production of precast exterior walls include concrete, steel bars, and admixtures. S103. By deploying various sensors at each production process of the prefabricated exterior wall, the operating parameters of the production equipment and production progress information are collected in real time.

3. The digital management and tracking method for prefabricated exterior wall production according to claim 2, characterized in that, Based on the collected design information, raw material information, production equipment operating parameters, and production progress information, the production data for prefabricated exterior walls is determined.

4. The digital management and tracking method for prefabricated exterior wall production according to claim 1, characterized in that, Step two involves quality inspection of the completed prefabricated exterior walls, including: S201. Use a laser scanner to measure the completed prefabricated exterior wall to obtain the actual size information of the prefabricated exterior wall; when measuring the actual size of the prefabricated exterior wall, multiple tests are required, and abnormal data is removed before taking the average value. S202. Compare the geometric dimension parameters of the actual dimensions of the precast exterior wall with the design dimensions, and calculate the absolute value of the dimensional deviation of the precast exterior wall. S203. Compare the absolute value of the dimensional deviation with the corresponding preset deviation threshold. If the absolute value of the dimensional deviation is less than or equal to the deviation threshold of the corresponding dimension, it indicates that the dimensional quality of the prefabricated exterior wall is qualified; otherwise, an abnormal signal is triggered and the prefabricated exterior wall is marked as unqualified.

5. The digital management and tracking method for prefabricated exterior wall production according to claim 4, characterized in that, The process of quality inspection of the completed precast exterior walls also includes: S204. The maximum load-bearing capacity of the prefabricated exterior wall is obtained by conducting mechanical performance tests on the completed prefabricated exterior wall, i.e., the actual load-bearing capacity test value. Among them, when testing the mechanical performance of the prefabricated exterior wall, multiple sets of tests need to be conducted, and the average value is taken after removing abnormal data. S205. Obtain the standard value of bearing capacity. By establishing a bearing capacity assessment model, obtain the bearing capacity assessment value to test and evaluate the mechanical performance of the precast exterior wall. If the bearing capacity assessment value is 1, it means that the mechanical performance of the precast exterior wall is qualified. If the bearing capacity assessment value is 0, an abnormal signal is triggered and the precast exterior wall is marked as unqualified. S206. Based on S201 to S205, obtain prefabricated exterior walls that pass dimensional quality inspection and mechanical performance inspection, and mark the prefabricated exterior walls as qualified.

6. The digital management and tracking method for prefabricated exterior wall production according to claim 5, characterized in that, In S205, the expression for the bearing capacity assessment model is: ; In the formula, CP(SJ) represents the load-bearing capacity assessment value; SJ is the actual load-bearing capacity test value; and CB is the standard load-bearing capacity value.

7. The digital management and tracking method for prefabricated exterior wall production according to claim 6, characterized in that, Step three involves tracking the production progress of the precast exterior walls, including: S301. Based on the production data of prefabricated exterior walls, obtain the corresponding production progress information, and obtain the actual time consumed by each production process by calculating the difference between the actual start time and the actual end time of each production process. S302. Similarly, based on the pre-set production plan, calculate the planned time for each production process of the corresponding prefabricated exterior wall. S303. By calculating the difference between the actual time and the planned time in each production process of the prefabricated exterior wall, a production progress tracking record is generated and compared with the preset progress deviation threshold of the corresponding production process. Then, a production progress prompt signal is generated. The production progress tracking record includes the progress deviation of each production process of the prefabricated exterior wall.

8. The digital management and tracking method for prefabricated exterior wall production according to claim 7, characterized in that, In S303, the process of conducting the comparison includes: If the progress difference of the corresponding production process is greater than or equal to the progress deviation threshold, it indicates that the progress of the production process is abnormal and an abnormality prompt signal is generated. If the progress difference of the corresponding production process is less than the progress deviation threshold, it indicates that the progress of the production process is normal and a normal prompt signal is generated. Abnormal or normal error signals constitute production progress indication signals.

9. The digital management and tracking method for prefabricated exterior wall production according to claim 8, characterized in that, Step four involves periodic analysis of prefabricated exterior wall production, including: S401. Periodically traverse the quality inspection results of prefabricated exterior walls to obtain the number of qualified and unqualified prefabricated exterior walls, and calculate the quality pass rate of prefabricated exterior walls within this period. The calculation formula is as follows: ; In the formula, HL is the quality pass rate of prefabricated exterior walls within the period; HG is the number of qualified prefabricated exterior walls; and BG is the number of unqualified prefabricated exterior walls. S402. Calculate the production rate of prefabricated exterior walls within a preset period by statistically analyzing the actual total output of prefabricated exterior walls within that period. The calculation formula is as follows: ; In the formula, V is the production rate of prefabricated exterior walls within a cycle; YT is the preset cycle.

10. The digital management and tracking method for prefabricated exterior wall production according to claim 9, characterized in that, The process of periodically analyzing prefabricated exterior wall production also includes: S403. Normalize and summarize the quality pass rate and production rate of precast exterior walls within the cycle to form a production evaluation coefficient. ; In the formula, P is the production evaluation coefficient; and This represents the weighting coefficients corresponding to the quality pass rate and production rate, and ; S404. Compare the obtained production evaluation coefficient with the preset evaluation threshold. If the obtained production evaluation coefficient is less than the evaluation threshold, issue an alarm and optimize the production operation parameters in the prefabricated exterior wall production within the cycle, including adjusting the values ​​of the production operation parameters in the prefabricated exterior wall production, until the recalculated production evaluation coefficient is greater than or equal to the evaluation threshold.