Construction method of concrete distributing machine penetrating supporting foot
By designing a concrete placing boom support method with adjustable support feet and spring shock absorbers, the problems of rebar displacement and pipeline damage caused by traditional support methods were solved, achieving a stable and environmentally friendly support effect.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- HUNAN NO 2 ENG
- Filing Date
- 2026-04-14
- Publication Date
- 2026-06-05
AI Technical Summary
In existing technologies, the support method of concrete placing booms is prone to causing steel bar displacement and deformation, damage to embedded pipelines, and the support device is unstable, affecting construction quality and safety, and is also not environmentally friendly.
The construction method of using adjustable support legs and spring dampers for through-reinforcement support legs includes adjusting screws, adjusting nuts, fastening nuts and support leg pads, combined with spring dampers, to form a height-adjustable support structure that avoids steel bars and pipelines and ensures stable force transmission.
It achieves stable support without damaging the steel bars and pipelines, improves construction quality and safety, reduces material consumption, and meets the requirements of green construction.
Smart Images

Figure CN122148062A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of concrete placing boom support technology for floor slab concrete pouring, specifically to a construction method for a concrete placing boom with reinforcing bar support feet. Background Technology
[0002] In the construction of concrete slabs for building floors, the concrete placing boom is the core pumping and placing equipment, and its support method directly affects the construction quality and safety. In traditional construction, the placing boom's supports are usually placed directly on the floor slab reinforcement, or simply supported by wooden beams and formwork. This traditional approach has the following drawbacks: 1. The continuous vibration generated by the placing boom's pumping and rotating operation can easily cause displacement and deformation of the floor slab reinforcement, affecting the structural performance of the floor slab; 2. Vibration can easily squeeze and damage embedded electrical and plumbing pipelines, leading to rework and repairs, increasing construction costs and time; 3. The wooden beams and formwork supports lack sufficient rigidity and stability, easily slipping and tilting, posing safety hazards; 4. The wooden beams and formwork have a low turnover rate and high wear and tear, generating a large amount of construction waste, which does not meet the requirements of green construction. Currently, there is a lack of a tool-based, adjustable, reusable, non-damaging, and reliably stable support device for placing booms to meet the needs of construction safety, quality, efficiency, and energy conservation and environmental protection. Summary of the Invention
[0003] The technical problem to be solved by the present invention is to provide a construction method for the reinforcing bar support foot of a concrete placing boom, which addresses the shortcomings of the existing technology, and realizes tool-based, adjustable, and reusable support, avoids damage to reinforcing bars and embedded pipelines, improves pouring quality and operational safety, and reduces material waste.
[0004] The technical solution adopted by the present invention to solve its technical problem is: a construction method for a concrete placing boom with reinforcing bar support foot, wherein the reinforcing bar support foot used in the method includes an adjustable support foot and a spring shock absorber; The adjustable support foot includes an adjusting screw, an adjusting nut, a fastening nut, and a support leg pad; there are four sets of adjusting screws, the bottom of the four sets of adjusting screws is provided with anti-slip rubber base, the upper part of the four sets of adjusting screws passes through the adjusting nut, the support leg pad, and the fastening nut, and is locked and fixed by the adjusting nut and the fastening nut to form a height-adjustable support foot; The spring shock absorber includes a lower outer shell, an upper inner shell, a shock absorber spring, a connecting screw, and a connecting nut. The lower outer shell is placed on the outrigger pad, the shock absorber spring is installed in the lower outer shell, and the upper inner shell is installed in the lower outer shell and located above the shock absorber spring. The connecting screw passes sequentially through the outrigger pad, the lower outer shell, the shock absorber spring, the upper inner shell, and the support leg base of the fabric placing machine, and is fixed with the connecting nut. Specifically, the following steps are included: Design of reinforcing bar support legs: Determine the parameters of the reinforcing bar support legs based on the dimensions of the concrete placing boom legs, the thickness of the floor slab, and the spacing of the reinforcing bars, and complete the design; Fabrication of reinforcing bar support legs: Process adjustable support legs and spring shock absorbers according to the design drawings, and complete the assembly; Measurement and positioning: Based on the coverage area of the concrete placing boom and the position of the outriggers, lay out the lines to determine the placement points of the reinforcing bar supports; Installation of reinforcing bar support feet: Place the reinforcing bar support feet at the positioning point, avoiding reinforcing bars and pipelines, and adjust the adjusting nuts to make the support foot pads level and consistent in elevation; add additional support rods to the formwork frame below the wooden formwork area for reinforcement; Concrete placing boom setup: Hoist the concrete placing boom so that the outrigger bases are aligned with the spring shock absorbers. After placing it stably, tighten the connecting nuts to secure it. Commissioning and trial operation: No-load trial operation to check the stability of the support and the normal operation of the equipment; Concrete pouring: Pour evenly in the specified order, avoiding collisions between the reinforcing bar supports and the reinforcing bars; reposition and reinstall the reinforcing bar supports when moving the concrete placing boom; Demolition and Cleaning Maintenance: After pouring, promptly remove the reinforcing bar supports and compact the concrete at the reinforcing bar supports with secondary vibration; clean the equipment, inspect the threads, spray rust inhibitor, wrap and protect it for reuse.
[0005] Furthermore, the outrigger pad is a square steel plate with holes for installing adjusting screws at the four corners and a hole for installing connecting screws in the middle.
[0006] Furthermore, the adjusting screw is a stainless steel foot cup with a rubber bottom.
[0007] Furthermore, the adjusting nuts are installed in pairs on the adjusting screw, are threadedly connected to the adjusting screw, and are located below and above the support leg pad.
[0008] Furthermore, the fastening nuts are installed in pairs on the adjusting screw, are threadedly connected to the adjusting screw, and are located below the lower adjusting nut and above the upper adjusting nut.
[0009] Furthermore, the spring shock absorbers are provided in four groups, arranged in a rectangular array on the outrigger pads.
[0010] Furthermore, the overall reinforcement arrangement passes through the gaps in the floor slab reinforcement and is directly supported on the bottom formwork, transmitting force from the bottom formwork to the formwork support frame, forming an overall force-bearing system.
[0011] Compared with the prior art, the present invention has the following beneficial effects: Reliable quality: The through-beam support does not press on the reinforcing bars or touch the pipelines, eliminating the deformation of the reinforcing bars and damage to the embedded pipes caused by vibration, thus improving the quality of the floor slab formation; Safe and stable: The overall force transmission is clear, the rigidity is sufficient, it is adjustable and prevents loosening, avoiding settlement, tilting and instability; Highly efficient and convenient: Tool-based installation, adjustment, and dismantling make operation simple and significantly shorten setup time; Economical and environmentally friendly: It can be reused more than 20 times, significantly reducing the consumption of timber and formwork, lowering costs and construction waste, and conforming to green construction. Attached Figure Description
[0012] Figure 1 This is a schematic diagram of the installation of a concrete placing boom support foot provided in an embodiment of the present invention; Figure 2 This is a schematic diagram of the structure of a concrete placing boom support foot provided in an embodiment of the present invention; Figure 3 for Figure 2 A schematic diagram of the spring shock absorber in the embodiment shown; Figure 4 for Figure 2 A schematic diagram of the partial structural connections of the embodiment shown; Explanation of the reference numerals in the figure: 1. Adjustable support feet; 1.1. Adjusting screw; 1.2. Adjusting nut; 1.3. Fastening nut; 1.4. Support leg pads; 2. Spring shock absorber; 2.1 Lower outer shell of shock absorber; 2.2 Upper inner shell of shock absorber; 2.3 Shock absorber spring; 2.4 Connecting screw; 2.5 Connecting nut; 3. Support legs and base for the fabric placing machine; 4. Anti-slip rubber bottom. Detailed Implementation
[0013] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0014] Please see Figures 1 to 4 As shown, this embodiment provides a construction method for a concrete placing boom support foot, the support foot used in this method includes an adjustable support foot 1 and a spring shock absorber 2; The adjustable support foot 1 includes an adjusting screw 1.1, an adjusting nut 1.2, a fastening nut 1.3, and a support leg pad 1.4. There are four sets of adjusting screws 1.1. The bottom of the four sets of adjusting screws 1.1 is provided with an anti-slip rubber base 3, which plays a role in shock absorption, anti-slip, and protection of the bottom mold. The upper part of the four sets of adjusting screws 1.1 passes through the adjusting nut 1.2, the support leg pad 1.4, and the fastening nut 1.3, and is locked and fixed by the adjusting nut 1.2 and the fastening nut 1.3 to form a height-adjustable support foot. The spring shock absorber 2 includes a lower outer shell 2.1, an upper inner shell 2.2, a shock absorber spring 2.3, a connecting screw 2.4, and a connecting nut 2.5. The lower outer shell 2.1 is placed on the support leg pad 1.4. The shock absorber spring 2.3 is installed in the lower outer shell 2.1. The upper inner shell 2.2 is installed in the lower outer shell 2.1 and is located above the shock absorber spring 2.3. The connecting screw 2.4 passes through the support leg pad 1.4, the lower outer shell 2.1, the shock absorber spring 2.3, the upper inner shell 2.2, and the support leg base 3 of the fabric placing machine in sequence, and is fixed with the connecting nut 2.5. Specifically, the following steps are included: Design of reinforcing bar support legs: Determine the parameters of the reinforcing bar support legs based on the dimensions of the concrete placing boom legs, the thickness of the floor slab, and the spacing of the reinforcing bars, and complete the design; Fabrication of reinforcing bar support: Fabricate adjustable support leg 1 and spring shock absorber 2 according to the design drawings, and complete the assembly; Measurement and positioning: Based on the coverage area of the concrete placing boom and the position of the outriggers, lay out the lines to determine the placement points of the reinforcing bar supports; Installation of reinforcing bar support feet: Place the reinforcing bar support feet at the positioning point, avoiding reinforcing bars and pipelines, and adjust the adjusting nut 1.2 to make the support foot pad 1.4 level and consistent in elevation; add additional support rods to the formwork frame below the wooden formwork area for reinforcement; Concrete placing boom setup: Hoist the concrete placing boom so that the outrigger base is aligned with the spring shock absorber 2. After placing it stably, tighten and secure it with connecting nut 2.5. Commissioning and trial operation: No-load trial operation to check the stability of the support and the normal operation of the equipment; Concrete pouring: Pour evenly in the specified order ("far first, then near; middle first, then sides") to avoid collisions with the reinforcing bar supports and reinforcing bars; reposition and reinstall the reinforcing bar supports when moving the concrete placing boom. Demolition and Cleaning Maintenance: After pouring, promptly remove the reinforcing bar supports and compact the concrete at the reinforcing bar supports with secondary vibration; clean the equipment, inspect the threads, spray rust inhibitor, wrap and protect it for reuse.
[0015] In this embodiment, the outrigger pad 1.4 is a 300mm×300mm×12mm square steel plate, with holes for installing adjusting screws 1.1 at the four corners and holes for installing connecting screws 2.4 in the middle.
[0016] In this embodiment, the adjusting screw 1.1 is a D60×M24×250mm stainless steel foot cup with a rubber bottom.
[0017] In this embodiment, the adjusting nuts 1.2 are installed in pairs on the adjusting screw 1.1, are threadedly connected to the adjusting screw 1.1, and are located below and above the support leg pad 1.4.
[0018] In this embodiment, the fastening nuts 1.3 are installed in pairs on the adjusting screw 1.1, are threadedly connected to the adjusting screw 1.1, and are located below the lower adjusting nut 1.2 and above the upper adjusting nut 1.2.
[0019] In this embodiment, the spring shock absorber 2 is provided in four groups, arranged in a rectangular array on the outrigger pad 1.4.
[0020] In this embodiment, the bottom surface of the support leg pad 1.4 is 15mm higher than the top surface of the floor slab. It is arranged with reinforcing bars through the entire structure, passing through the gaps in the floor slab reinforcing bars and directly supporting the bottom formwork. The force is transmitted from the bottom formwork to the support frame, forming an overall force-bearing system.
[0021] Although embodiments of the present invention have been shown and described above, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.
Claims
1. A construction method for a concrete placing boom with reinforcing bar support legs, characterized in that: The through-rigid support legs used in this method include adjustable support legs and spring shock absorbers; The adjustable support foot includes an adjusting screw, an adjusting nut, a fastening nut, and a support leg pad; there are four sets of adjusting screws, the bottom of the four sets of adjusting screws is provided with anti-slip rubber base, the upper part of the four sets of adjusting screws passes through the adjusting nut, the support leg pad, and the fastening nut, and is locked and fixed by the adjusting nut and the fastening nut to form a height-adjustable support foot; The spring shock absorber includes a lower outer shell, an upper inner shell, a shock absorber spring, a connecting screw, and a connecting nut. The lower outer shell is placed on the outrigger pad, the shock absorber spring is installed in the lower outer shell, and the upper inner shell is installed in the lower outer shell and located above the shock absorber spring. The connecting screw passes sequentially through the outrigger pad, the lower outer shell, the shock absorber spring, the upper inner shell, and the support leg base of the fabric placing machine, and is fixed with the connecting nut. Specifically, the following steps are included: Design of reinforcing bar support legs: Determine the parameters of the reinforcing bar support legs based on the dimensions of the concrete placing boom legs, the thickness of the floor slab, and the spacing of the reinforcing bars, and complete the design; Fabrication of reinforcing bar support legs: Process adjustable support legs and spring shock absorbers according to the design drawings, and complete the assembly; Measurement and positioning: Based on the coverage area of the concrete placing boom and the position of the outriggers, lay out the lines to determine the placement points of the reinforcing bar supports; Installation of reinforcing bar support feet: Place the reinforcing bar support feet at the positioning point, avoiding reinforcing bars and pipelines, and adjust the adjusting nuts to make the support foot pads level and consistent in elevation; add additional support rods to the formwork frame below the wooden formwork area for reinforcement; Concrete placing boom setup: Hoist the concrete placing boom so that the outrigger bases are aligned with the spring shock absorbers. After placing it stably, tighten the connecting nuts to secure it. Commissioning and trial operation: No-load trial operation to check the stability of the support and the normal operation of the equipment; Concrete pouring: Pour evenly in the specified order, avoiding collisions between the reinforcing bar supports and the reinforcing bars; reposition and reinstall the reinforcing bar supports when moving the concrete placing boom; Demolition and Cleaning Maintenance: After pouring, promptly remove the reinforcing bar supports and compact the concrete at the reinforcing bar supports with secondary vibration; clean the equipment, inspect the threads, spray rust inhibitor, wrap and protect it for reuse.
2. The construction method for a concrete placing boom with reinforcing bar support as described in claim 1, characterized in that: The outrigger pad is a square steel plate with holes for installing adjusting screws at the four corners and a hole for installing connecting screws in the middle.
3. A construction method for a concrete placing boom with reinforcing bar support as described in claim 1 or 2, characterized in that: The adjusting screw is a stainless steel foot cup with a rubber bottom.
4. A construction method for a concrete placing boom with reinforcing bar support as described in claim 1 or 2, characterized in that: The adjusting nuts are installed in pairs on the adjusting screw, are threadedly connected to the adjusting screw, and are located below and above the support leg pad.
5. The construction method for a concrete placing boom with reinforcing bar support as described in claim 4, characterized in that: The fastening nuts are installed in pairs on the adjusting screw, are threadedly connected to the adjusting screw, and are located below the lower adjusting nut and above the upper adjusting nut.
6. A construction method for a concrete placing boom with reinforcing bar support as described in claim 1 or 2, characterized in that: The spring shock absorbers are provided in four sets, arranged in a rectangular array on the outrigger pads.
7. A construction method for a concrete placing boom with reinforcing bar support as described in claim 1 or 2, characterized in that: The overall reinforcement arrangement passes through the gaps in the floor slab reinforcement and is directly supported on the bottom formwork. The force is transmitted from the bottom formwork to the support frame, forming an overall force-bearing system.