Construction process method of anti-typhoon type floating fan steel-concrete floating foundation

By setting grid-like shear studs and reinforcing ribs on the inner wall of the steel shell, using high-performance crack-resistant concrete for layered pouring and a three-layer composite anti-corrosion coating, and installing a compartmentalized sealed buoyancy regulating chamber, the problems of insufficient shear strength, poor corrosion resistance and poor attitude stability of the steel-concrete connection interface in existing floating wind turbine foundations have been solved, and stable operation under typhoon conditions has been achieved.

CN123061552APending Publication Date: 2026-11-10ZHONGSHAN GSI MARINE ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611218930.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-12
Publication Date
2026-11-10

AI Technical Summary

Technical Problem

The existing floating wind turbine foundations have insufficient shear strength at the interface between the steel shell and concrete, which easily leads to interface cracking due to stress concentration. They also have poor corrosion resistance and lack active buoyancy adjustment methods, resulting in poor attitude stability under typhoon conditions and making it difficult to meet the safe operation requirements of ultra-large wind turbines under extreme sea conditions.

Method used

The steel shell is welded with a grid of shear studs and reinforcing plates on the inner wall, combined with high-performance crack-resistant concrete poured in layers and a three-layer composite anti-corrosion coating. It is equipped with a compartmentalized sealed buoyancy adjustment chamber, a buoyancy adjustment system and stress monitoring sensors, forming a mechanical interlocking interface and an active buoyancy adjustment means.

Benefits of technology

It significantly improves the shear bearing capacity of the steel-concrete joint interface, enhances corrosion resistance and attitude stability, ensures the foundation maintains floating stability under typhoon conditions, and extends service life.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123061552A_ABST
    Figure CN123061552A_ABST
Patent Text Reader

Abstract

The application provides an anti-typhoon type floating wind turbine steel-concrete floating foundation construction process method, which solves the problems of insufficient shear capacity of the existing floating wind turbine foundation steel-concrete connection interface, poor corrosion resistance and lack of active buoyancy adjustment means. The process comprises the following steps: prefabricating a ring-shaped steel shell main body, welding shear pins, reinforcing rib plates and a separate sealing buoyancy adjustment cabin; binding a steel reinforcement cage, fixing a tower cylinder connection embedded sleeve and reserving grooves matched with the shear pins; hoisting the steel shell and the steel reinforcement cage to butt joint, installing a detachable steel formwork; pouring high-performance anti-cracking concrete, composite curing; installing a water filling and draining pump and a pressure sensor, sealing test; sand blasting and rust removal on the outer surface of the steel shell, spraying a corrosion-resistant coating and installing a wave-resistant fender; transporting to the designated position by a semi-submersible barge, adjusting the draft, installing a mooring system and connecting with a seabed anchor bowl. The process improves the shear capacity of the steel-concrete connection interface, prolongs the service life and realizes stable control of the floating posture under typhoon conditions.
Need to check novelty before this filing date? Find Prior Art

Description

Technical fields: This invention relates to the field of offshore wind power foundation engineering technology, and in particular to a construction process for a typhoon-resistant ultra-large floating wind turbine steel-concrete floating foundation. Background technology: Currently, floating wind turbine foundations are the key load-bearing structures for the safe operation of ultra-large offshore wind turbines in deep-sea areas. Existing floating wind turbine foundations mostly adopt pure steel structures or ordinary steel-concrete composite structures. Pure steel foundations are exposed to the high salt spray and strong wave currents of the marine environment for extended periods, making them prone to electrochemical corrosion and fatigue damage. In ordinary steel-concrete composite structures, the shear strength of the interface between the steel shell and concrete is insufficient, and under the repeated impact of typhoon waves, stress concentration can easily lead to interface cracking, reducing the overall structural integrity. Furthermore, existing foundations generally lack effective active buoyancy adjustment mechanisms, resulting in poor attitude stability under typhoon conditions, making it difficult to meet the safe operation requirements of ultra-large wind turbines in extreme sea conditions.

[0003] Therefore, this invention provides a construction process for a typhoon-resistant, ultra-large floating wind turbine steel-concrete floating foundation, which helps to solve the technical problem of the lack of effective active buoyancy adjustment means in the prior art. Summary of the Invention: In one embodiment, the present invention provides a construction process for a typhoon-resistant floating wind turbine steel-concrete floating foundation. Through the prefabrication and reinforcement of the steel shell, the binding and pre-embedding of the steel reinforcement cage in the concrete foundation, and the assembly and positioning of the steel shell and the steel reinforcement cage, it helps to solve the technical problem of the lack of effective active buoyancy adjustment means in the prior art.

[0005] The construction process for the steel-concrete floating foundation of the typhoon-resistant floating wind turbine includes: The steel shell is prefabricated and reinforced. The main body of the annular steel shell is prefabricated, and the inner wall of the steel shell is welded with a grid-like shear nail and reinforcing ribs. A partitioned sealed buoyancy regulating chamber is welded to the bottom of the steel shell, and a pressure sensor and filling and draining interface are reserved. The concrete foundation steel reinforcement cage is tied and embedded. The steel truss type steel reinforcement cage is tied, the tower tube is fixed at the top of the steel reinforcement cage and the embedded sleeve is connected. The bottom is reserved with a groove that matches the steel shell shear nails. Multiple sets of stress monitoring sensors are embedded inside. The steel shell and reinforcing cage are assembled and positioned. The steel shell is hoisted to the pouring area and leveled. The reinforcing cage is hoisted into the steel shell so that the groove of the reinforcing cage is connected with the shear studs of the steel shell. It is then fixed with temporary supports. A detachable steel formwork is installed in the gap between the steel shell and the reinforcing cage.

[0006] In one embodiment, after the steel shell and reinforcing cage assembly and positioning step, the method further includes: High-performance crack-resistant concrete pouring and curing: High-performance crack-resistant concrete with polypropylene fiber and expansion agent is prepared and poured in layers. After pouring, it is cured by a composite curing method of covering with moisture and steam curing. The buoyancy adjustment system is installed and debugged. The filling and draining pump and pressure sensor are installed in the buoyancy adjustment chamber, a sealing test is conducted, the buoyancy adjustment system is debugged, and filling and draining operations at different drafts are simulated. The overall anti-corrosion and anti-wave coating construction involves sandblasting the outer surface of the steel shell to remove rust, spraying three layers of anti-corrosion coating, and installing polyurethane arc-shaped anti-wave fenders at the bottom edge of the foundation. The prefabricated steel-concrete floating foundation is transported to the designated location by a semi-submersible barge. The positioning is assisted by tugboats and satellite positioning system. The buoyancy adjustment system is activated to adjust the draft. The mooring system is installed and connected to the seabed anchor.

[0007] In one embodiment, the steel shell is made of high-strength weather-resistant steel with a thickness of 80-120mm, the shear stud spacing is 150-200mm, and the reinforcing ribs are made of H-beams and are fully welded to the inner wall of the steel shell.

[0008] In one embodiment, the stiffening ribs are arranged at a 45° angle to the prevailing wind direction of the typhoon.

[0009] In one embodiment, the main reinforcement bars of the steel cage are made of high-strength threaded steel with a diameter of 40-50mm, the stirrup spacing is 100-150mm, and the stress monitoring sensor is wirelessly connected to an external data acquisition terminal.

[0010] In one embodiment, the polypropylene fiber content of the high-performance crack-resistant concrete is 0.8-1.2 kg / m³, the expansion agent content is 8%-10% of the mass of the cementitious material, the water-cement ratio is controlled at 0.3-0.35, and the slump is 180-220 mm; the thickness of each layer in the layered pouring is 300-500 mm, the composite curing temperature is controlled at 20-30℃, and the curing time is not less than 28 days.

[0011] In one embodiment, the water filling pressure for the buoyancy regulating chamber sealing test is 1.2 times the design pressure, and the system is considered qualified if there is no leakage after 24 hours of pressure holding. The system response time is no more than 10 seconds.

[0012] In one embodiment, the outer surface of the steel shell is sandblasted to a rust removal grade of Sa2.5; the three-layer anti-corrosion coating consists of a bottom layer of epoxy zinc-rich primer, a middle layer of epoxy micaceous iron oxide intermediate paint, and a top layer of polyurea anti-wave and wear-resistant topcoat, with a total coating thickness of not less than 300μm, a polyurea topcoat Shore hardness of not less than D80, and a seawater immersion performance of 5000 hours without powdering or peeling.

[0013] In one embodiment, the basic positioning deviation is controlled within ±50cm, the mooring system adopts a catenary arrangement, the mooring cable is made of polyester fiber cable, and the safety factor is not less than 6.

[0014] In one embodiment, the detachable steel formwork is made of Q355 steel plate with a thickness of not less than 6mm. The installation gap between the formwork and the inner wall of the steel shell and the reinforcing cage is controlled within ±3mm. The joints of the formwork are filled with sealing strips to prevent grout leakage. The formwork can only be removed after the concrete strength reaches more than 75% of the design strength. Attached image description: Figure 1 This is a schematic flowchart of a construction process for a typhoon-resistant ultra-large floating wind turbine steel-concrete floating foundation according to an embodiment of the present invention. Figure 2 This is a detailed flowchart of a construction process for a typhoon-resistant, ultra-large floating wind turbine steel-concrete floating foundation, according to another embodiment of the present invention. Detailed implementation method: The present application will now be described in further detail with reference to the accompanying drawings and embodiments. It should be understood that the following embodiments are used to illustrate the technical solutions of the present application, and are not intended to limit the scope of protection of the present application.

[0017] The purpose of this invention is to provide a construction process for a typhoon-resistant, ultra-large floating wind turbine steel-concrete floating foundation, in order to solve the following technical problems existing in the prior art: the shear resistance of the connection interface between the steel shell and concrete in existing floating wind turbine foundations is insufficient, and under the repeated impact of typhoon waves, stress concentration can easily lead to interface cracking and a decrease in the overall structural integrity; the steel shell is exposed to the deep-sea environment of high salt spray and strong waves for a long time, resulting in insufficient corrosion resistance and wave impact resistance, and a short service life; and existing foundations lack effective active buoyancy adjustment means, resulting in poor attitude stability under typhoon conditions and difficulty in meeting the technical problems of safe operation requirements of ultra-large wind turbines under extreme sea conditions.

[0018] To achieve the above objectives, the present invention adopts the following technical solution: Figure 1 This is a schematic flowchart of a construction process for a typhoon-resistant ultra-large floating wind turbine steel-concrete floating foundation according to an embodiment of the present invention. Figure 2 This is a detailed flowchart of a construction process for a typhoon-resistant, ultra-large floating wind turbine steel-concrete floating foundation, according to another embodiment of the present invention.

[0019] like Figures 1 to 2 As shown, in one embodiment, the present invention provides a construction process for a typhoon-resistant ultra-large floating wind turbine steel-concrete composite foundation, the construction process comprising: S1: Steel shell prefabrication and reinforcement treatment, prefabrication of the annular steel shell body, welding of grid-like shear studs and reinforcing ribs to the inner wall of the steel shell, welding of a partitioned sealed buoyancy regulating chamber to the bottom of the steel shell, and reserving pressure sensors and filling and draining interfaces; S2: Binding and pre-embedding of steel reinforcement cage for concrete foundation; binding of steel truss-type steel reinforcement cage; fixing of tower connection pre-embedded sleeve at the top of steel reinforcement cage; pre-reservation of groove at the bottom to match steel shell shear nails; and pre-embedding of multiple sets of stress monitoring sensors inside. S3: Steel shell-reinforcing cage assembly and positioning: hoist the steel shell to the pouring area and level it, hoist the reinforcing cage into the steel shell, align the groove of the reinforcing cage with the shear studs of the steel shell, fix it with temporary supports, and install detachable steel formwork in the gap between the steel shell and the reinforcing cage. S4: High-performance crack-resistant concrete pouring and curing. High-performance crack-resistant concrete with polypropylene fiber and expansion agent is prepared and poured in layers. After pouring, it is cured by a composite curing method of covering with moisture and steam curing.

[0020] In one embodiment, the high-performance crack-resistant concrete pouring and curing method involves using high-performance crack-resistant concrete incorporating polypropylene fibers and an expansion agent, pouring it in layers, and then curing it using a composite curing method of membrane covering for moisture retention and steam curing. The method further includes: S5: Installation and commissioning of the buoyancy adjustment system. Install the filling and draining pump and pressure sensor in the buoyancy adjustment chamber, conduct a sealing test, and commission the buoyancy adjustment system to simulate filling and draining operations at different drafts. S6: Overall anti-corrosion and anti-wave coating construction, sandblasting and rust removal of the outer surface of the steel shell, spraying three layers of anti-corrosion coating, and installing polyurethane arc-shaped anti-wave fenders at the bottom edge of the foundation; S7: Marine Transportation and Positioning Installation. The prefabricated steel-concrete floating foundation is transported to the designated location via a semi-submersible barge. Positioning is assisted by tugboats and a satellite positioning system. The buoyancy adjustment system is activated to adjust the draft. The mooring system is then installed and connected to the seabed anchor. Through the orderly implementation of these seven steps, the grid-like shear studs and reinforcing ribs on the inner wall of the steel shell mechanically interlock with the concrete, significantly improving the shear bearing capacity of the steel-concrete interface. The compartmentalized, sealed buoyancy adjustment chamber, combined with the filling and draining system, enables active attitude control, ensuring the foundation's floating stability under typhoon conditions.

[0021] In one embodiment, in step S1, the steel shell is made of high-strength weathering steel with a thickness of 80-120mm, shear studs spaced at 150-200mm intervals, and the reinforcing ribs are made of H-beams and fully welded to the inner wall of the steel shell. The high-strength weathering steel improves the steel shell's resistance to seawater corrosion and structural strength. The fully welded H-beam reinforcing ribs to the steel shell form a stable load-bearing structure, enhancing the steel shell's ability to withstand typhoon wave impact loads and preventing deformation of the steel shell under strong external forces.

[0022] Preferably, in step S1, the arrangement direction of the reinforcing rib plates forms an included angle of 45° with the dominant typhoon direction. This angle setting can decompose the lateral impact force of the typhoon into component forces perpendicular and parallel to the reinforcing rib plates, disperse the concentrated load in a single direction, reduce the local stress concentration effect of the typhoon on the steel shell, and improve the overall wind resistance stability of the steel shell.

[0023] In one embodiment, in step S2, the main reinforcement of the steel reinforcement cage adopts high-strength deformed steel bars with a diameter of 40 to 50 mm, the spacing of the stirrups is 100 to 150 mm, and the stress monitoring sensor is wirelessly connected to an external data acquisition terminal. The combination of large-diameter high-strength deformed steel bars and densely arranged stirrups can improve the tensile and shear resistance of the steel reinforcement cage, and the wireless stress monitoring sensor can collect stress data in real time during concrete pouring and service, provide timely warning of abnormal stress risks, and prevent structural cracking.

[0024] Specifically, in step S3, the levelness error of the steel shell after leveling is controlled within ±2mm / m. High-precision levelness control is a prerequisite for ensuring uniform concrete pouring thickness, avoiding uneven stress distribution caused by local over-thickness or under-thickness, ensuring uniform stress of the steel-concrete composite structure, and improving the overall structural stability of the foundation.

[0025] In one embodiment, in step S4, the polypropylene fiber content of the high-performance crack-resistant concrete is 0.8 to 1.2 kg / m³, the expansion agent content is 8% to 10% of the mass of the cementitious material, the water-binder ratio is controlled at 0.3 to 0.35, and the slump is 180 to 220 mm; the thickness of each layer in layered pouring is 300 to 500 mm, the composite curing temperature is controlled at 20 to 30°C, and the curing period is no less than 28 days. Polypropylene fibers can inhibit early shrinkage cracks of concrete, the expansion agent can compensate for the hydration shrinkage of concrete, a low water-binder ratio ensures the strength of concrete, layered pouring combined with high-frequency vibration can avoid defects such as honeycombs and pitting, and constant-temperature composite curing can promote the steady growth of concrete strength, greatly improving the crack resistance and compactness of concrete.

[0026] In one embodiment, preferably, in step S5, the water filling pressure for the sealing test of the buoyancy adjustment cabin is 1.2 times the design pressure, the cabin is qualified if there is no leakage after 24 hours of pressure holding, and the system response time is no more than 10 seconds. The sealing test with pressure exceeding the design pressure can verify the pressure resistance and seepage prevention performance of the buoyancy adjustment cabin, and the rapid response water filling and drainage system can adjust the draft depth of the foundation in time, ensuring that the buoyancy adjustment system can respond quickly under the action of typhoon, wave and current, and maintain the floating stability of the foundation.

[0027] In one embodiment, in step S6, the outer surface of the steel shell is sandblasted to a rust removal grade of Sa2.5. The three-layer anti-corrosion coating consists of a bottom epoxy zinc-rich primer, a middle epoxy micaceous iron oxide intermediate paint, and a top polyurea wave-resistant and wear-resistant topcoat. The total coating thickness is not less than 300 μm, the polyurea topcoat has a Shore hardness of not less than D80, and its seawater immersion performance reaches 5000 hours without powdering or peeling. Sa2.5 grade sandblasting can thoroughly remove rust and impurities from the surface of the steel shell. The three-layer composite anti-corrosion coating forms a dual physical and electrochemical anti-corrosion barrier. The high-hardness polyurea topcoat has excellent wave impact resistance and wear resistance, extending the service life of the steel shell in harsh marine environments.

[0028] Preferably, in step S7, the foundation positioning deviation is controlled within ±50cm, the mooring system adopts a catenary arrangement, the mooring cables are made of polyester fiber, and the safety factor is not less than 6. High-precision positioning ensures accurate docking between the wind turbine foundation and the turbine location, the catenary mooring arrangement effectively buffers the impact of typhoon waves, and the high-safety-factor polyester fiber cables combine high strength and corrosion resistance to ensure that the foundation does not shift under the action of a super typhoon.

[0029] Compared with the prior art, the present invention has the following beneficial effects: 1. By welding mesh-like shear studs and reinforcing plates to the inner wall of the steel shell, and reserving grooves at the bottom of the reinforcing cage to match the shear studs, combined with the layered pouring and composite curing process of high-performance crack-resistant concrete mixed with polypropylene fiber and expansion agent, a reliable mechanical interlocking interface is formed between the steel shell and the concrete. This significantly improves the shear bearing capacity of the steel-concrete connection, effectively avoids the interface cracking problem caused by stress concentration under repeated impacts of typhoon waves, and overcomes the defect of insufficient shear resistance of the connection interface in existing ordinary steel-concrete composite structures.

[0030] 2. After the outer surface of the steel shell is sandblasted to remove rust using Sa2.5 grade sandblasting, a three-layer composite anti-corrosion coating is sequentially applied: a base layer of epoxy zinc-rich primer, a middle layer of epoxy micaceous iron oxide intermediate paint, and a top layer of polyurea anti-wave and wear-resistant topcoat. The total thickness is not less than 300μm, and the Shore hardness of the polyurea topcoat is not less than D80. A polyurethane arc-shaped anti-wave fender is installed at the bottom edge of the foundation, constructing a dual protection system that combines physical barriers and electrochemical corrosion protection. This enables the steel shell to withstand seawater immersion for 5000 hours without powdering or peeling, significantly improving the corrosion resistance and wave impact resistance of the foundation in high-salt spray, strong wave and current deep-sea environments, and extending the service life of the foundation.

[0031] 3. By welding a partitioned, sealed buoyancy adjustment chamber to the bottom of the steel shell and installing a filling and draining pump and pressure sensor inside the chamber, the reliability of the system was verified by conducting a sealing and pressure holding test at 1.2 times the design pressure. The system response time was no more than 10 seconds, which enabled active and precise adjustment of the foundation's draft. This allowed the foundation to respond quickly to changes in wave and current loads under typhoon conditions and maintain its floating attitude stability. This solved the technical problems of existing floating foundations lacking active buoyancy adjustment methods and having poor attitude stability under typhoon conditions.

[0032] This application relates to a construction process for a typhoon-resistant, ultra-large floating wind turbine steel-concrete composite floating foundation, aiming to solve the technical problems of insufficient shear strength, poor corrosion resistance, and lack of active buoyancy adjustment methods at the steel-concrete interface in existing floating wind turbine foundations. This process utilizes core technologies such as setting grid-like shear studs and reinforcing ribs on the inner wall of the steel shell, employing high-performance crack-resistant concrete for layered pouring, applying a three-layer composite anti-corrosion coating, and installing a compartmentalized, sealed buoyancy adjustment chamber. These technologies achieve an overall improvement in the steel-concrete composite structure and stable control of its floating attitude under typhoon conditions.

[0033] Reference Figure 1 In one embodiment, the construction process includes steps S1 to S7 in sequence, and each step is implemented in order to form a complete steel-concrete floating foundation construction process.

[0034] Step S1 involves the prefabrication and reinforcement of the steel shell. First, a ring-shaped steel shell is prefabricated. This shell serves as the external load-bearing shell for the entire foundation, providing support for subsequent concrete pouring. Shear studs are welded to the inner wall of the steel shell in a grid pattern. The grid distribution of the shear studs creates a multi-point mechanical interlocking interface between them and the subsequently poured concrete. Under the shear force generated by the repeated impact of typhoon waves, the shear studs can transfer the shear force from the concrete to the steel shell, effectively inhibiting relative slippage at the interface.

[0035] Reinforcing ribs are simultaneously welded to the inner wall of the steel shell, forming a fixed connection between the ribs and the inner wall, together constituting the internal reinforcing skeleton of the steel shell, enhancing its resistance to deformation under the impact loads of typhoon waves and currents. A partitioned, sealed buoyancy regulating chamber is welded to the bottom of the steel shell. This buoyancy regulating chamber is fixedly connected to the bottom of the steel shell by welding, and has reserved installation interfaces for pressure sensors and filling / draining interfaces, providing a structural foundation for the subsequent installation of the buoyancy regulating system.

[0036] In some embodiments, in step S1, the steel shell is made of high-strength weathering steel with a thickness of 80–120 mm, shear stud spacing of 150–200 mm, and the reinforcing ribs are made of H-beams and fully welded to the inner wall of the steel shell. The seawater corrosion resistance and high strength of the high-strength weathering steel give the steel shell a long structural life in the high-salt-fog environment of the deep sea; the reinforcing ribs of the H-beam section are fully welded to the inner wall of the steel shell, forming a stable load-bearing support structure, preventing local buckling deformation of the steel shell under the impact load of typhoon waves.

[0037] In another embodiment, the stiffening ribs in step S1 are arranged at a 45° angle to the prevailing typhoon wind direction. When the typhoon's lateral impact force acts on the steel shell, the stiffening ribs arranged at a 45° angle can decompose the impact force into two components, one perpendicular and one parallel to the rib direction. This disperses the concentrated load from one direction to two directions, reducing the stress concentration effect of the typhoon on local areas of the steel shell and improving the overall wind resistance stability of the steel shell.

[0038] Step S2 involves the binding and pre-embedding of the reinforcing cage for the concrete foundation. The reinforcing cage is a truss-type structure, with main bars and stirrups mutually constraining each other to form a spatial load-bearing skeleton. A pre-embedded sleeve for tower connection is fixed to the top of the reinforcing cage. This sleeve is fixed to the top of the reinforcing cage by binding or welding and is used for subsequent tower installation and positioning. A groove is pre-drilled at the bottom of the reinforcing cage to match the position of the shear studs on the steel shell, ensuring precise alignment with the shear studs during assembly and guaranteeing a mechanically effective steel-concrete connection.

[0039] Multiple sets of stress monitoring sensors are pre-embedded inside the reinforcing cage, with each sensor distributed at different locations within the cage. This allows for real-time acquisition of structural stress data during concrete pouring and foundation service. In some embodiments, in step S2, the main reinforcing bars of the cage are made of high-strength threaded steel with a diameter of 40–50 mm, and the stirrup spacing is 100–150 mm. The stress monitoring sensors are wirelessly connected to an external data acquisition terminal. The combination of large-diameter high-strength threaded steel and densely packed stirrups enhances the tensile and shear bearing capacity of the reinforcing cage. The wireless connection eliminates the need for extensive wired cabling, enabling the stress monitoring sensors to transmit data to an external terminal without the need for extensive wired cabling. This facilitates real-time monitoring of the structural stress state under typhoon conditions and allows for timely warnings of abnormal risks.

[0040] Step S3 involves the assembly and positioning of the steel shell and reinforcing cage. The steel shell is hoisted to the pouring area and leveled. After leveling, the steel shell is in a stable horizontal state, providing a reference for the subsequent uniform pouring of concrete. The reinforcing cage is hoisted into the steel shell, ensuring that the pre-drilled groove at the bottom of the reinforcing cage precisely aligns with the shear studs on the inner wall of the steel shell. A mechanical positioning relationship is established between the groove and the shear studs, ensuring the accurate positioning of the reinforcing cage within the steel shell. Temporary supports are used to fix the relative position between the reinforcing cage and the steel shell to prevent displacement during concrete pouring. A detachable steel formwork is installed in the gap between the steel shell and the reinforcing cage. This formwork is used to control the concrete pouring area and can be removed after pouring.

[0041] In some implementations, the levelness error of the steel shell after leveling in step S3 is controlled within ±2mm / m. High-precision levelness control is a prerequisite for ensuring uniform distribution of concrete pouring thickness. Since the leveling accuracy of the steel shell directly affects the uniformity of the concrete layer thickness after pouring, if the levelness deviation is too large, it will lead to local concrete layers being too thick or too thin, which in turn will cause uneven stress distribution and reduce the overall stress uniformity of the steel-concrete composite structure.

[0042] Combination Figure 2 Step S4 involves the pouring and curing of high-performance crack-resistant concrete. High-performance crack-resistant concrete incorporating polypropylene fibers and an expansive agent is prepared. The polypropylene fibers are uniformly distributed within the concrete matrix, providing fiber bridging during early concrete shrinkage and inhibiting the propagation of microcracks. The expansive agent generates micro-expansion during concrete hydration, compensating for volume changes caused by concrete hydration shrinkage, thereby reducing the formation of shrinkage cracks.

[0043] A layered pouring process was used to pour high-performance crack-resistant concrete into the space between the steel shell and the reinforcing cage. After each layer was poured, high-frequency vibration was applied to ensure that the concrete fully filled the area around the shear studs and the grooves in the reinforcing cage, guaranteeing a dense and defect-free mechanical interlocking interface between the concrete and the shear studs. After pouring, a composite curing method combining membrane moisturizing and steam curing was adopted. The membrane moisturizing prevented the concrete surface moisture from evaporating too quickly, while steam curing provided a constant temperature and humidity environment to promote the continuous growth of concrete strength.

[0044] In some embodiments, in step S4, the polypropylene fiber content of the high-performance crack-resistant concrete is 0.8 to 1.2 kg / m³, the expansive agent content accounts for 8% to 10% of the mass of the cementitious material, the water-binder ratio is controlled at 0.3 to 0.35, and the slump is 180 to 220 mm; the thickness of each layer in layered pouring is 300 to 500 mm, the composite curing temperature is controlled at 20 to 30 °C, and the curing duration is no less than 28 days. A low water-binder ratio ensures the compactness and strength of the concrete, and the slump range ensures the pumpability and filling performance of the concrete; constant-temperature composite curing enables the concrete to complete the hydration reaction under controlled conditions, greatly improving the crack resistance and compactness of the concrete, and enhancing the structural reliability of the steel-concrete connection part.

[0045] Step S5 is the installation and commissioning of the buoyancy regulation system. Water filling and draining pumps and pressure sensors are installed in the divided sealed buoyancy regulation tanks welded to the bottom of the steel shell in step S1. The water filling and draining pumps communicate with each divided tank chamber of the buoyancy regulation tank through water filling and draining interfaces, and the pressure sensors are installed at the reserved interfaces of each chamber for real-time monitoring of the internal pressure of the chambers. After the installation is completed, a sealing test is performed on the buoyancy regulation tanks to verify the sealing performance of each chamber. After the sealing test is qualified, the buoyancy regulation system is commissioned, and water filling and draining operations under different draft depths are simulated to verify the response capability of the system under different working conditions.

[0046] In some embodiments, in step S5, the water filling pressure for the sealing test of the buoyancy regulation tank is 1.2 times the design pressure, and a 24-hour pressure holding period without leakage is deemed qualified, with the system response time not exceeding 10 seconds. Performing the sealing pressure holding test at a water filling pressure exceeding the design pressure can verify the pressure and seepage resistance performance of the buoyancy regulation tank under extreme working conditions; the system response time not exceeding 10 seconds ensures that the buoyancy regulation system can respond in time when the typhoon, wave and current loads change rapidly, and change the foundation draft depth by actively adjusting the water filling and draining volume of each chamber to maintain the floating attitude stability of the foundation.

[0047] Step S6 is the construction of the overall anti-corrosion and wave-resistant coating. The outer surface of the steel shell is subjected to sand blasting and rust removal treatment to completely remove rust, oxide scale and various contaminants on the surface of the steel shell, so that the surface of the steel shell reaches the specified cleanliness, providing a basis for the subsequent coating to form a firm adhesion with the surface of the steel shell. After the sand blasting and rust removal is completed, three layers of anti-corrosion coatings are sprayed in sequence, and interlayer adhesion is formed between the bottom layer, the middle layer and the surface layer to constitute a continuous anti-corrosion coating system. A polyurethane arc-shaped wave-resistant fender is installed at the bottom edge of the foundation. The fender is fixedly connected to the bottom edge of the foundation through mounting connectors, and its arc-shaped cross section can disperse the wave impact force along the arc surface, reducing the concentrated impact damage of waves to the bottom edge of the foundation.

[0048] In some embodiments, the sandblasting and rust removal grade of the outer surface of the steel shell in step S6 reaches Sa2.5; the three-layer anti-corrosion coating consists of a bottom epoxy zinc-rich primer, a middle epoxy micaceous iron oxide intermediate paint, and a top polyurea anti-wave and wear-resistant topcoat, with a total coating thickness of not less than 300μm, and the polyurea topcoat having a Shore hardness of not less than D80, and a seawater immersion performance of 5000 hours without powdering or peeling. The bottom epoxy zinc-rich primer provides electrochemical protection to the steel shell through the sacrificial anode effect of zinc powder; the lamellar micaceous iron oxide filler in the middle epoxy micaceous iron oxide intermediate paint forms a shielding layer, preventing corrosive media from penetrating into the steel shell; the top polyurea coating has high hardness and high elasticity, and can resist the impact and abrasion of typhoon waves; the three layers together constitute a dual protection system combining physical barriers and electrochemical corrosion protection.

[0049] Step S7 involves maritime transport and positioning installation. The prefabricated steel-concrete floating foundation is transported to the designated aircraft position via a semi-submersible barge. The barge uses ballast adjustment to submerge the deck below the waterline, allowing the steel-concrete floating foundation to rise from the deck using its own buoyancy, completing the loading and unloading operation. Tugboats are used to assist in the foundation's relocation, while a satellite positioning system monitors the foundation's position in real time, precisely guiding it to the designated aircraft position coordinates. The buoyancy adjustment system is activated, and the foundation's draft is adjusted to the design value by filling and deflating each compartment, achieving the designed floating attitude. The mooring system is installed, securing one end of the mooring cable to the mooring connection point on the foundation and the other end to the seabed anchor, completing the anchoring and positioning of the foundation.

[0050] In some implementations, the foundation positioning deviation in step S7 is controlled within ±50cm, the mooring system adopts a catenary arrangement, and the mooring cables are made of polyester fiber with a safety factor of not less than 6. The catenary mooring arrangement allows the mooring cables to hang in the water in a catenary shape under normal operating conditions. When typhoon waves generate impact loads, the cables absorb the impact energy by changing their catenary shape, effectively buffering the impact force of the typhoon waves. The polyester fiber cables combine high strength with seawater corrosion resistance, and the safety factor of not less than 6 ensures that the mooring system has sufficient load-bearing capacity under super typhoon conditions, preventing foundation displacement.

[0051] Without altering the core construction process mechanism described above, the fiber reinforcement material used in the high-performance crack-resistant concrete in step S4 is not limited to polypropylene fibers; other fiber materials such as steel fibers and basalt fibers can also be used, as long as they can inhibit crack propagation within the concrete matrix. Similarly, the surface anti-corrosion coating in step S6 is not limited to polyurea coatings; other anti-corrosion topcoat materials with high hardness, high wear resistance, and seawater corrosion resistance can also be used, as long as they can form a strong adhesion with the intermediate coating and meet the requirements for wave impact resistance. Where there is no conflict, the technical features of the aforementioned embodiments can be combined with each other.

Claims

1. A construction process for a typhoon-resistant floating wind turbine steel-concrete floating foundation, characterized in that, The construction process method for the typhoon-resistant floating steel-concrete foundation of a wind turbine includes: Prefabrication and reinforcement treatment of steel shell: prefabricate the main body of the annular steel shell, weld grid-shaped shear studs and reinforcing rib plates on the inner wall of the steel shell, weld separate sealed buoyancy adjustment tanks at the bottom of the steel shell, and reserve interfaces for pressure sensors and water filling and draining; Binding and pre-embedding of the reinforcement cage for the concrete cap: bind a steel truss type reinforcement cage, fix pre-embedded sleeves for tower barrel connection at the top of the reinforcement cage, reserve grooves matching the shear studs of the steel shell at the bottom, and pre-embed multiple sets of stress monitoring sensors inside; Matching and positioning of the steel shell and the reinforcement cage: hoist the steel shell to the pouring area and level it, lift the reinforcement cage into the steel shell, make the grooves of the reinforcement cage butt with the shear studs of the steel shell, fix them with temporary supports, and install detachable steel formwork in the gap between the steel shell and the reinforcement cage.

2. The construction process of the steel-concrete floating foundation for a typhoon-resistant floating wind turbine according to claim 1, characterized in that, After the step of matching and positioning the steel shell and the reinforcement cage, the method further includes: Pouring and curing of high-performance crack-resistant concrete: prepare high-performance crack-resistant concrete mixed with polypropylene fibers and expansion agent, adopt a layered pouring process for pouring, and after pouring, adopt a composite curing method of film covering for moisture retention and steam curing for curing; Installation and commissioning of the buoyancy adjustment system: install water filling and draining pumps and pressure sensors in the buoyancy adjustment tanks, conduct sealing tests, commission the buoyancy adjustment system, and simulate water filling and draining operations under different draft depths; Construction of overall anti-corrosion and wave-resistant coating: perform sand blasting and rust removal on the outer surface of the steel shell, spray three layers of anti-corrosion coating, and install polyurethane arc-shaped wave-resistant fenders at the bottom edge of the foundation; Marine transportation, positioning and installation: transport the prefabricated steel-concrete floating foundation to the designated machine position via a semi-submersible barge, use tugboats and a satellite positioning system to assist positioning, start the buoyancy adjustment system to adjust the draft depth, install the mooring system and connect it to the seabed anchor.

3. The construction process of the steel-concrete floating foundation for a typhoon-resistant floating wind turbine according to claim 2, characterized in that, The steel shell is made of high-strength weathering steel with a thickness of 80-120mm, the spacing of shear studs is 150-200mm, and the reinforcing rib plates are H-shaped steel and are fully welded to the inner wall of the steel shell.

4. The construction process of the steel-concrete floating foundation for a typhoon-resistant floating wind turbine according to claim 3, characterized in that, The arrangement direction of the reinforcing rib plates forms a 45° included angle with the dominant typhoon direction.

5. The construction process of the steel-concrete floating foundation for a typhoon-resistant floating wind turbine according to claim 4, characterized in that, The main reinforcements of the reinforcement cage are high-strength threaded steel with a diameter of 40-50mm, the spacing of stirrups is 100-150mm, and the stress monitoring sensors are wirelessly connected to an external data acquisition terminal.

6. The construction process of the steel-concrete floating foundation for a typhoon-resistant floating wind turbine according to claim 5, characterized in that, In the high-performance crack-resistant concrete, the polypropylene fiber content is 0.8-1.2kg / m³, the expansion agent content is 8%-10% of the mass of the cementitious material, the water-binder ratio is controlled at 0.3-0.35, and the slump is 180-220mm; the thickness of each layer in layered pouring is 300-500mm, the composite curing temperature is controlled at 20-30°C, and the curing time is no less than 28 days.

7. The construction process of the steel-concrete floating foundation for a typhoon-resistant floating wind turbine according to claim 6, characterized in that, The water filling pressure for the sealing test of the buoyancy adjustment tank is 1.2 times the design pressure, and it is qualified if there is no leakage after 24 hours of pressure holding, and the system response time does not exceed 10 seconds.

8. The construction process of the steel-concrete floating foundation for a typhoon-resistant floating wind turbine according to claim 7, characterized in that, The sand blasting and rust removal grade of the outer surface of the steel shell reaches Sa2.5; the three anti-corrosion coating layers consist of a bottom epoxy zinc-rich primer, a middle epoxy micaceous iron intermediate paint, and a surface polyurea wave-resistant wear-resistant finish, the total coating thickness is no less than 300μm, the Shore hardness of the polyurea finish is not lower than D80, and the seawater immersion resistance performance reaches 5000 hours without pulverization or shedding.

9. The construction process of the steel-concrete floating foundation for a typhoon-resistant floating wind turbine according to claim 8, characterized in that, The basic positioning deviation is controlled within ±50cm. The mooring system adopts a catenary arrangement, and the mooring cables are made of polyester fiber with a safety factor of not less than 6.

10. The construction process of the steel-concrete floating foundation for a typhoon-resistant floating wind turbine according to claim 9, characterized in that, The detachable steel formwork is made of Q355 steel plate with a thickness of not less than 6mm. The installation gap between the formwork and the inner wall of the steel shell and the reinforcing cage is controlled within ±3mm. The joints of the formwork are filled with sealing strips to prevent grout leakage. The formwork can only be removed after the concrete strength reaches more than 75% of the design strength.