Green Power Direct Supply Line Power Optimization Control Method and System for Export-Oriented Enterprises

By optimizing the power control of green electricity direct supply lines for export-oriented enterprises, and comprehensively considering time-of-use pricing, carbon emission factors, and carbon cost parameters, the power of green electricity direct supply and the power purchased from the upstream grid are determined in a coordinated manner. This solves the problem of matching electricity costs and carbon emission costs for high-energy-consuming export enterprises, and achieves a reduction in total electricity carbon costs and an improvement in green electricity utilization efficiency.

CN123073794APending Publication Date: 2026-11-10STATE GRID HUNAN ELECTRIC POWER CO LTD ELECTRIC POWER SCI RES INST +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611103299.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-07-23
Publication Date
2026-11-10

AI Technical Summary

Technical Problem

Existing technologies have several drawbacks when dealing with the electricity costs, carbon emission costs, and green electricity utilization of high-energy-consuming export enterprises. These include incomplete cost accounting dimensions, insufficient matching between production load regulation and green electricity supply, and low precision in coordinated control between different power supply methods. As a result, it is difficult to effectively reduce the overall electricity and carbon costs of enterprises while meeting production needs.

Method used

This paper presents a method for optimizing the power control of green electricity direct supply lines for export-oriented enterprises. By acquiring production batch control parameters, time-of-use electricity prices, grid carbon emission factors, and carbon cost parameters, the method determines the power of green electricity direct supply and the power purchased from the upstream grid, forming a coordinated control scheme to reduce the total carbon cost of electricity during the dispatch cycle.

Benefits of technology

While meeting the electricity demand of production batches and the constraints of direct green electricity supply, the total carbon cost of electricity during the dispatch cycle was reduced, the efficiency of green electricity utilization was improved, and the adaptability of the power control scheme to the carbon cost of export orders was enhanced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123073794A_ABST
    Figure CN123073794A_ABST
Patent Text Reader

Abstract

This invention discloses a method and system for optimizing the power control of green electricity direct supply lines for export-oriented enterprises. The method includes: S1, obtaining production batch control parameters and the proportion of export orders, and dividing the production cycle into multiple continuous control periods; S2, determining the load power demand and the unit net cost difference between green electricity direct supply and supply from the upper-level grid; S3, dividing the green electricity priority period and the period to be optimized, and determining the green electricity direct supply power and the power purchased from the upper-level grid to form the current power control scheme; S4, calculating the total carbon cost of electricity, constructing load transfer combinations in the period to be optimized, and updating the power when the load transfer constraints are met and the total carbon cost of electricity in the scheduling cycle after the transfer decreases; S5, repeating step S4 until there are no load transfer combinations that reduce the total carbon cost of electricity in the scheduling cycle, and summarizing the updated power to form the final power control scheme. This invention can reduce the carbon cost of electricity and improve the efficiency of green electricity utilization.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the fields of electricity market trading and carbon emission management technology, specifically to a method and system for optimizing the power control of green electricity direct supply lines for export-oriented enterprises. Background Technology

[0002] Against the backdrop of a global effort to address climate change, carbon market trading mechanisms are used to constrain greenhouse gas emissions from key emitting enterprises. International trade rules are gradually moving towards green and low-carbon development, and some overseas markets have established border adjustment mechanisms and carbon cost constraints related to carbon emissions. This means that energy-intensive export enterprises such as cement, steel, and electrolytic aluminum need to pay attention not only to conventional electricity costs but also to the carbon emission costs of their production processes and their impact on export competitiveness.

[0003] Currently, high-energy-consuming enterprises typically reduce their overall energy costs through time-of-use pricing, demand-side load adjustment, green electricity procurement, and carbon emission accounting. Specifically, in terms of electricity dispatch, enterprises generally adjust a portion of their adjustable production load according to peak-valley time-of-use pricing, shifting electricity demand from high-price periods to low-price periods to reduce electricity purchase costs. Regarding green electricity utilization, enterprises typically increase the proportion of green electricity used through green electricity trading, green certificate trading, or renewable energy supply methods to reduce indirect carbon emissions corresponding to purchased electricity. In terms of carbon cost management, enterprises typically calculate carbon emissions and carbon compliance costs based on purchased electricity volume, emission factors, carbon quotas, and carbon prices, and manage these costs as part of their operating expenses.

[0004] However, most existing electricity optimization schemes focus on minimizing electricity costs, typically adjusting production load based solely on time-of-use pricing, without fully considering the carbon emission differences associated with different power sources. This can easily lead to a situation where electricity purchase costs decrease, but overall carbon costs do not decrease simultaneously. While existing low-carbon dispatch schemes incorporate carbon emission costs into their optimization objectives, they primarily target general industrial users or park loads, usually only considering carbon emission accounting and carbon compliance costs under the domestic carbon market. This makes them unsuitable for the actual operating scenarios of export-oriented enterprises, which are simultaneously constrained by domestic and international carbon costs. Existing green electricity utilization schemes focus more on the green electricity consumption ratio or green electricity procurement cost, lacking a synergistic analysis of production batch electricity demand, adjustable load boundaries, green electricity availability, and external power purchase costs. This results in insufficient matching between green electricity usage periods and production load arrangements.

[0005] Therefore, existing technologies still have problems when dealing with the relationship between electricity costs, carbon emission costs and green electricity utilization of high-energy-consuming export enterprises. These problems include incomplete cost accounting dimensions, insufficient matching between production load regulation and green electricity supply, and low precision of coordinated control between different power supply methods. As a result, it is difficult to effectively reduce the comprehensive carbon cost of enterprises while meeting production needs. Summary of the Invention

[0006] The technical problem this invention aims to solve is to provide a method and system for optimizing the power control of green electricity direct supply lines for export-oriented enterprises, addressing the aforementioned problems in the prior art. This method comprehensively considers the impact of time-of-use pricing, carbon emission factors, domestic and international carbon costs, and the proportion of export orders on power supply costs, while meeting the electricity demand of export-oriented enterprises' production batches and the constraints of green electricity direct supply. It collaboratively determines the green electricity direct supply power and the power purchased from the upstream power grid for each control period, thereby reducing the total carbon cost of electricity during the dispatch cycle and improving the efficiency of green electricity utilization.

[0007] To solve the above-mentioned technical problems, the technical solution adopted by the present invention is as follows: A method for optimizing and controlling the power of green electricity direct supply lines for export-oriented enterprises, comprising: S1: Obtain the production batch control parameters and export order ratio corresponding to the export orders of export-oriented enterprises, and divide the production cycle corresponding to the production batch into multiple continuous control periods. S2, obtain the time-of-use electricity price parameters, grid carbon emission factor, carbon cost parameters and green electricity direct supply constraints for each control period, determine the load power demand for each control period based on the time-of-use electricity price parameters and production batch control parameters, and determine the unit net cost difference of green electricity direct supply replacing the supply from the upper-level grid for each control period based on the time-of-use electricity price parameters, grid carbon emission factor, carbon cost parameters and export order ratio; S3, based on the unit net cost difference, divide each control period into green electricity priority period and period to be optimized, and based on the load power demand and green electricity direct supply constraints, determine the green electricity direct supply power and the power purchased by the upper-level grid for each control period to form the current power control scheme; S4, calculate the total carbon cost of the scheduling cycle corresponding to the current power control scheme, construct a load transfer combination in the period to be optimized, and update the green electricity direct supply power and the power purchased by the upper grid for the corresponding control period when the load transfer constraints are met and the total carbon cost of the scheduling cycle after the transfer is reduced. S5. Repeat step S4 until there is no load transfer combination in the time period to be optimized that reduces the total carbon cost of the scheduling cycle. Then, summarize the updated green electricity direct supply power and the power purchased by the upper-level grid for each control period to form the final power control scheme.

[0008] Further, in step S2, the load power demand for each control period is determined based on the time-of-use electricity price parameters and production batch control parameters. The production batch control parameters include the total electricity consumption of the production batch, the base load, and the number of control periods within the scheduling cycle, including: First, compare the time-of-use electricity price of the upper-level power grid and the time-of-use electricity price of green electricity within the same control period to determine the minimum electricity price for the current control period. Then, according to the principle that the lower the minimum electricity price, the higher the allocated load, allocate the remaining electricity consumption of the production batch on the base load to obtain the load power demand for each control period, expressed as:

[0009]

[0010] In the above formula, For the first The lowest electricity price for each time period; For the first The time-of-use electricity price of the superior power grid for each time period; For the first Time-of-use pricing for green electricity during specific time periods; For the first Load power demand for each time period; For each time period within the scheduling cycle The maximum value; T τ represents the total number of control periods in the production cycle of the current batch of products; τ is the control period sequence number. This represents the total electricity consumption required for the production of the current batch of products. It is the base load.

[0011] Further, in step S2, the unit net cost difference between direct green electricity supply and supply from the upper-level power grid for each control period is determined, including: The difference in electricity cost per unit of green electricity directly supplied compared to the cost per unit of electricity purchased from the upstream power grid is calculated. This difference is then deducted from the reduction in domestic carbon costs due to reduced purchases from the upstream grid and the foreign carbon costs related to the proportion of export orders. The resulting net cost difference is expressed as follows:

[0012] In the above formula, For the first The marginal net cost of replacing power from the upstream power grid with green electricity per unit time period; For the first The time-of-use electricity price of the superior power grid for each time period; For the first Time-of-use pricing for green electricity during specific time periods; For the first Carbon emission factor of the power grid in the region where the enterprise is located during a specific time period; For domestic carbon market carbon prices; The proportion of export orders; The carbon price in the international carbon market.

[0013] Further, in step S3, each control period is divided into a green electricity priority period and a period to be optimized based on the unit net cost difference, including: Control periods with a unit net cost difference of less than or equal to zero are designated as green electricity priority periods, while control periods with a unit net cost difference of greater than zero are designated as periods to be optimized. Based on the aforementioned load power demand and green electricity direct supply constraints, the green electricity direct supply power and the upstream grid power purchase power for each control period are determined, including: For green electricity priority periods, the green electricity direct supply power is determined within the range jointly limited by load power demand, the maximum transmittable power of green electricity direct supply lines, and the maximum available green electricity power on the renewable energy generation side, and the remaining load is supplemented by the power purchased by the upstream grid; for periods to be optimized, the green electricity direct supply power is initially set to zero, and the power purchased by the upstream grid undertakes all the load of the corresponding period, as expressed in the following expression:

[0014] In the above formula, For the first Green electricity direct supply power during each time period; For the first The power purchased by the upstream power grid during each time period; The maximum transmittable power for green electricity direct supply lines; For the first The maximum available green electricity power from the new energy generation side during each time period; For the first Load power demand for each time period; , These are the green electricity priority time periods and the time periods to be optimized, respectively.

[0015] Further, in step S4, the total carbon cost of the scheduling cycle corresponding to the current power control scheme is calculated, including: The total carbon cost is obtained by adding the domestic carbon market compliance cost to the foreign carbon cost. The total electricity cost is obtained by adding the green electricity direct supply cost to the upstream grid purchase cost for each control period. Finally, the total carbon cost is added to the total electricity cost to obtain the total electricity carbon cost for the dispatch cycle. The specific expression is as follows:

[0016]

[0017]

[0018]

[0019]

[0020] In the above formula, Total carbon cost; The carbon costs for enterprises to comply with domestic carbon market regulations; Carbon costs for companies exporting overseas; Carbon quotas for enterprises; This represents the total carbon emissions during the scheduling cycle. The proportion of export orders; For domestic carbon market carbon prices; Carbon prices in foreign carbon markets; Total electricity cost; For the first Green electricity direct supply power during each time period; For the first The power purchased by the upstream power grid during each time period; For the first The time-of-use electricity price of the superior power grid for each time period; For the first Time-of-use pricing for green electricity during specific time periods; As a dispatching unit; T This represents the total number of control periods in the production cycle of the current batch of products. This represents the total cost of electricity in carbon.

[0021] Furthermore, the total carbon emissions during the scheduling cycle The calculation method is as follows: The historical direct carbon emission intensity per unit of purchased electricity is determined based on the direct carbon emissions of historical production batches and the total historical electricity purchases. Then, the total carbon emissions for the dispatch cycle are calculated by combining the purchased electricity from the upstream grid and the grid carbon emission factor in the current power control scheme. The expression is:

[0022] In the above formula, This represents the total carbon emissions during the scheduling cycle. For the first j Direct carbon emissions from a historical batch; For the first j Total electricity purchased in each historical batch; The scheduling unit is N; the historical production batch quantity is E; ... For the first Carbon emission factor of the power grid in the region where the enterprise is located during a specific time period; For the first The amount of electricity purchased by the upstream power grid during each time period.

[0023] Furthermore, in step S4, when constructing the load transfer combination during the period to be optimized, the constraints for load transfer include: The load transfer step size is greater than zero, and the load transfer step size does not exceed the minimum value among the power purchased by the upper-level power grid during the load transfer-out period, the remaining transmittable power of the green electricity direct supply line during the load transfer-in period, and the remaining available green electricity power on the new energy generation side during the load transfer-in period. The expression is:

[0024] In the above formula, , These are the periods for load transfer in and transfer out, respectively. This is the load transfer step size; For time period The maximum available green electricity capacity on the new energy generation side; , Time periods Power purchase capacity and time period of the upstream power grid Green electricity direct supply power; The maximum transmittable power for green electricity direct supply lines.

[0025] Further, in step S4, when the load transfer constraints are met and the total carbon cost of electricity in the dispatch cycle decreases after the transfer, the green electricity direct supply power and the upstream grid purchase power for the corresponding control period are updated, including: The expression for increasing the load transfer step size for direct green electricity supply during load transfer-in periods and decreasing the load transfer step size for power purchased from the upper-level grid during load transfer-out periods, while keeping the power output unchanged during other control periods besides load transfer-in and load transfer-out periods, is as follows:

[0026] In the above formula, , These are the periods for load transfer in and transfer out, respectively. , These are the periods after load transfer. The direct green electricity supply capacity and the electricity purchased from the upstream power grid; Before load transfer Green electricity direct supply power during each time period; Before load transfer The amount of electricity purchased by the upstream power grid during each time period. This is the load transfer step size.

[0027] A green electricity direct supply line power optimization control system for export-oriented enterprises includes a microprocessor and a memory interconnected, wherein the microprocessor is programmed or configured to execute the steps of a green electricity direct supply line power optimization control method for export-oriented enterprises.

[0028] A computer-readable storage medium storing a computer program / instructions programmed or configured to execute, via a processor, the steps of a green electricity direct supply line power optimization control method for export-oriented enterprises.

[0029] Compared with the prior art, the advantages of the present invention are as follows: This invention incorporates export order proportions, time-of-use electricity price parameters, grid carbon emission factors, carbon cost parameters, and green electricity direct supply constraints into the power control process within the production cycle. Based on the determined load power demand for each control period, it distinguishes between green electricity priority periods and periods requiring optimization, and coordinates and iteratively updates the green electricity direct supply power with the power purchased from the upper-level grid. This prioritizes the limited green electricity direct supply capacity for periods more conducive to reducing overall costs. Thus, while meeting the electricity demand of export-oriented enterprises' production batches and the green electricity direct supply constraints, it reduces the total carbon cost of electricity during the dispatch cycle, improves green electricity utilization efficiency, and enhances the adaptability of the power control scheme to the impact of export order carbon costs. Attached Figure Description

[0030] Figure 1 This is a flowchart of a green electricity direct supply line power optimization control method for export-oriented enterprises, according to an embodiment of the present invention.

[0031] Figure 2 This is a schematic diagram of the external operating parameter curves for a typical export-oriented enterprise.

[0032] Figure 3 The diagram shows the enterprise load power curves in Scheme 1 and Scheme 2 in specific application examples.

[0033] Figure 4 This is a schematic diagram of the green electricity direct supply power and the power purchased by the upstream power grid under Scheme 2 in a specific application example.

[0034] Figure 5 This is a comparative diagram of the carbon cost composition in Scheme 1 and Scheme 2 in a specific application example. Detailed Implementation

[0035] To better understand the above technical solutions, the following will provide a detailed explanation of the technical solutions in conjunction with the accompanying drawings and specific implementation methods.

[0036] This embodiment provides a method for optimizing the power control of green electricity direct supply lines for export-oriented enterprises. This method is applicable to export-oriented enterprises with export orders, adjustable production loads within a certain range, and the conditions for accessing green electricity direct supply lines, such as high-energy-consuming export-oriented enterprises like cement, steel, and electrolytic aluminum. This method incorporates the proportion of export orders, differences in domestic and international carbon costs, time-of-use electricity pricing parameters, grid carbon emission factors, and green electricity direct supply constraints into the power control process within the production cycle. While meeting the electricity demand of each production batch, it determines the green electricity direct supply power and the power purchased from the upstream grid for each control period, thereby reducing the total carbon cost of electricity during the scheduling cycle. This invention can reduce carbon costs of electricity while meeting production order demands, providing export-oriented enterprises with green electricity direct supply line power control that adapts to differentiated carbon accounting rules both domestically and internationally.

[0037] like Figure 1 As shown, the method in this embodiment includes the following steps: S1: Obtain the production batch control parameters and export order ratio corresponding to the export orders of export-oriented enterprises, and divide the production cycle corresponding to the production batch into multiple continuous control periods.

[0038] Specifically, the internal parameters for export-oriented enterprises include production planning information, export order information, historical electricity consumption data, and historical carbon emission data. Production planning information and export order information are used to determine production batches, production cycles, total electricity consumption, and the proportion of export orders. Historical electricity consumption data and historical carbon emission data are used to determine the historical carbon emission intensity corresponding to the enterprise's production energy consumption, in order to subsequently calculate load power demand, unit net cost difference, and total carbon cost per dispatch cycle. Among these, the production batch control parameters include the total electricity consumption of the production batch. The base load and the number of control periods within the scheduling cycle are used to subsequently determine the load power demand for each control period. Export order percentage. s This represents the proportion of export orders to the total output of the corresponding production batch. This is used to subsequently calculate the foreign carbon costs associated with exported products, ensuring that the power control results for green electricity direct supply lines simultaneously reflect both domestic carbon market compliance costs and the impact of foreign carbon costs. The production cycle corresponding to a production batch can be divided into multiple continuous control periods according to a preset time scale. For example, using one hour as a control period, a T-hour scheduling cycle (the production cycle of a batch of products) can be divided into T continuous control periods.

[0039] S2, obtain the time-of-use electricity price parameters, grid carbon emission factor, carbon cost parameters and green electricity direct supply constraints for each control period, determine the load power demand for each control period based on the time-of-use electricity price parameters and production batch control parameters, and determine the unit net cost difference of green electricity direct supply replacing the supply from the upper-level grid for each control period based on the time-of-use electricity price parameters, grid carbon emission factor, carbon cost parameters and export order ratio.

[0040] Specifically, the time-of-use pricing parameters include the time-of-use pricing of the upstream power grid and the time-of-use pricing of green electricity for each control period; the carbon cost parameters include the carbon price in the domestic carbon market and the carbon price in the foreign carbon market; and the constraints on direct green electricity supply include the maximum transmittable power of the direct green electricity supply line and the maximum available green electricity power on the renewable energy generation side for each control period.

[0041] 1. Determining Load Power Demand: To guide load distribution to lower-cost time periods while meeting the total electricity consumption of the production batch, this embodiment first compares the time-of-use electricity price of the upstream grid and the time-of-use electricity price of green electricity within the same control period to determine the minimum electricity price for the current control period. Then, according to the principle that the lower the minimum electricity price, the higher the allocated load, the remaining electricity consumption of the production batch is allocated on the base load to obtain the load power demand for each control period. The expression for load power demand is:

[0042]

[0043] In the above formula, For the first The lowest electricity price for each time period; For the first The time-of-use electricity price of the superior power grid for each time period; For the first Time-of-use pricing for green electricity during specific time periods; For the first Load power demand for each time period; For each time period within the scheduling cycle The maximum value; T τ represents the total number of control periods in the production cycle of the current batch of products; τ is the control period sequence number. This represents the total electricity consumption required for the production of the current batch of products. It is the base load.

[0044] By using the above method, while ensuring that the load is not lower than the baseline load in each control period, more of the remaining electricity consumption is allocated to the control period with the lowest electricity price, thereby forming a load power demand curve that matches the time-of-use electricity price parameters.

[0045] 2. Determination of Unit Net Cost Difference: After determining the load power demand, this embodiment further evaluates whether replacing upstream grid power supply with direct green electricity supply during each control period can reduce overall costs. Specifically, the difference in electricity cost per unit of direct green electricity supply compared to per unit of upstream grid power purchase is first calculated. Then, the reduction in domestic carbon costs due to reduced upstream grid power purchases and the foreign carbon costs related to the proportion of export orders are deducted to obtain the unit net cost difference. This unit net cost difference is used to determine whether direct green electricity supply should be prioritized during a given control period. The expression for the unit net cost difference is:

[0046] In the above formula, For the first The marginal net cost of replacing power from the upstream power grid with green electricity per unit time period; For the first The time-of-use electricity price of the superior power grid for each time period; For the first Time-of-use pricing for green electricity during specific time periods; For the first Carbon emission factor of the power grid in the region where the enterprise is located during a specific time period; For domestic carbon market carbon prices; The proportion of export orders; This refers to carbon prices in international carbon markets. Among them, This represents the difference in electricity costs between a unit of directly supplied green electricity and a unit of electricity purchased from the upstream power grid. This indicates a reduction in domestic carbon costs corresponding to a decrease in the amount of electricity purchased from the upstream power grid. This indicates the impact of the difference in foreign carbon costs related to the proportion of export orders. Therefore, the unit net cost difference reflects the economic viability of export-oriented enterprises adopting direct green electricity supply under the combined effects of domestic and international carbon costs.

[0047] S3 divides each control period into green electricity priority periods and periods to be optimized based on the unit net cost difference. Based on the load power demand and green electricity direct supply constraints, the green electricity direct supply power and the power purchased by the upper-level grid for each control period are determined to form the current power control scheme.

[0048] 1. Division of Green Energy Priority Periods and Periods to be Optimized: When the unit net cost difference is less than or equal to zero, it indicates that the increase in unit electricity cost after replacing the upstream grid supply with direct green energy supply during this control period can be offset by the reduction in carbon costs, or that direct green energy supply itself has a cost advantage. Therefore, this control period is classified as a green energy priority period. When the unit net cost difference is greater than zero, it indicates that directly using direct green energy supply during this control period will increase the overall cost. Therefore, this control period is classified as a period to be optimized. Specifically, select... The time period forms a set of green electricity priority time periods. Select The time periods are used to form a set of time periods to be optimized. .

[0049] 2. Formation of the Current Power Control Scheme: For green electricity priority periods, this embodiment determines the green electricity direct supply power within the range jointly limited by load power demand, the maximum transmittable power of the green electricity direct supply line, and the maximum available green electricity power on the renewable energy generation side, and the remaining load is supplemented by the power purchased by the upstream grid; for periods to be optimized, this embodiment initially sets the green electricity direct supply power to zero, and the power purchased by the upstream grid undertakes all the load of the corresponding period. This allows for the formation of a current power control scheme that satisfies the production load and green electricity direct supply constraints. The expression for the current power control scheme is:

[0050] In the above formula, For the first Green electricity direct supply power during each time period; For the first The power purchased by the upstream power grid during each time period; The maximum transmittable power for green electricity direct supply lines; For the first The maximum available green electricity power from the new energy generation side during each time period; For the first Load power demand for each time period; , These are the green electricity priority time periods and the time periods to be optimized, respectively.

[0051] Specifically, readable collections and set Determine the direct green electricity supply capacity for each time period. Power purchased from the upper-level power grid :for Under the condition of meeting the constraints of direct green electricity supply, priority will be given to direct green electricity supply to cover the load during this period, and the remaining load will be supplemented by electricity purchased from the upper-level power grid; for Initially, the entire load for that period is borne by the upstream power grid; furthermore, the power control results for each period are aggregated. ,in To form an initial power control scheme within the production cycle. .

[0052] S4. Calculate the total carbon cost of electricity in the current power control scheme during the scheduling period. Construct load transfer combinations in the period to be optimized. When the load transfer constraints are met and the total carbon cost of electricity in the scheduling period after the transfer is reduced, update the green electricity direct supply power and the power purchased by the upper-level grid for the corresponding control period.

[0053] 1. Calculation of total carbon emissions during the dispatch cycle: This embodiment first determines the historical direct carbon emission intensity corresponding to each unit of purchased electricity based on the direct carbon emissions of historical production batches and the historical total purchased electricity. Then, it combines the purchased electricity power from the upstream grid and the grid carbon emission factor in the current power control scheme to calculate the total carbon emissions during the dispatch cycle. This allows for the simultaneous consideration of direct carbon emissions from the enterprise's production process and indirect carbon emissions caused by the upstream grid's electricity purchases.

[0054] Specifically, it can be seen from the plan The system reads power control results based on historical electricity consumption data, historical carbon emission data, and the power purchased from the upstream power grid. Calculate the total carbon emissions during the scheduling cycle. Taking into account the compliance costs of the domestic carbon market, international carbon cost accounting rules, and relevant carbon parameters, the total carbon cost for the period is calculated. Total electricity cost The sum of the two yields the total carbon cost of the scheduling cycle under the initial power control scheme. .

[0055] The specific expression for the total carbon emissions during the scheduling cycle is as follows:

[0056] In the above formula, This represents the total carbon emissions during the scheduling cycle. For the first j Direct carbon emissions from a historical batch; For the first j Total electricity purchased in each historical batch; The scheduling unit is N; the historical production batch quantity is E; ... For the first Carbon emission factor of the power grid in the region where the enterprise is located during a specific time period; For the first The amount of electricity purchased by the upstream power grid during each time period.

[0057] 2. Calculation of total carbon cost of electricity during the dispatch cycle: In this embodiment, the total carbon cost is obtained by adding the compliance cost of the domestic carbon market to the carbon cost abroad, the total electricity cost is obtained by adding the cost of direct green electricity supply during each control period to the cost of electricity purchased from the upper-level power grid, and the total carbon cost is added to the total electricity cost to obtain the total carbon cost of electricity during the dispatch cycle.

[0058] The specific expression for the total carbon cost of the scheduling cycle is:

[0059]

[0060]

[0061]

[0062]

[0063] In the above formula, Total carbon cost; The carbon costs for enterprises to comply with domestic carbon market regulations; Carbon costs for companies exporting overseas; Carbon quotas for enterprises; This represents the total carbon emissions during the scheduling cycle. The proportion of export orders; For domestic carbon market carbon prices; Carbon prices in foreign carbon markets; Total electricity cost; For the first Green electricity direct supply power during each time period; For the first The power purchased by the upstream power grid during each time period; For the first The time-of-use electricity price of the superior power grid for each time period; For the first Time-of-use pricing for green electricity during specific time periods; As a dispatching unit; T This represents the total number of control periods in the production cycle of the current batch of products. This represents the total carbon cost. Domestic carbon market compliance costs are incurred only when total carbon emissions exceed a company's carbon allowance during the scheduling cycle. International carbon costs are calculated based on the proportion of export orders, the difference between domestic and international carbon prices, and total carbon emissions during the scheduling cycle, to reflect the cost impact of export orders on products under international carbon cost accounting rules.

[0064] 3. Construction of Load Transfer Combinations and Load Transfer Constraints: In the current power control scheme, the upstream power grid initially undertakes all the load of the period to be optimized. To further reduce the total carbon cost of electricity during the dispatch cycle, this embodiment constructs load transfer combinations in the period to be optimized, selecting load transfer-in and load transfer-out periods. A portion of the load carried by the upstream power grid during the load transfer-out period is transferred to the load transfer-in period and undertaken by direct green electricity supply. To ensure that the power control results meet electrical constraints and green electricity supply constraints, the load transfer step size needs to be simultaneously limited by the transferable power during the load transfer-out period, the remaining transmittable power of the direct green electricity supply lines during the load transfer-in period, and the remaining available green electricity power on the renewable energy generation side during the load transfer-in period. The load transfer constraint expression is:

[0065] In the above formula, , These are the periods for load transfer in and transfer out, respectively. This is the load transfer step size; For time period The maximum available green electricity capacity on the new energy generation side; , Time periods Power purchase capacity and time period of the upstream power grid Green electricity direct supply power; This refers to the maximum transmittable power of a direct green electricity supply line. Among them, It limits the maximum load that can be transferred out from the power purchased from the upper-level power grid during the load transfer period; The remaining transmittable power of green electricity direct supply lines is limited during the load transfer period; It limits the remaining available green electricity power on the renewable energy generation side during the load transfer period.

[0066] 4. Power Update After Load Transfer: When the load transfer combination meets the load transfer constraints, this embodiment increases the green electricity direct supply power during the load transfer-in period by the load transfer step size, decreases the upstream grid purchased power during the load transfer-out period by the load transfer step size, and keeps the power of other control periods unchanged except for the load transfer-in and load transfer-out periods. Then, the total carbon cost of the dispatch cycle after the transfer is recalculated; if the total carbon cost of the dispatch cycle after the transfer is lower than the total carbon cost of the current dispatch cycle, the load transfer is accepted and the current power control scheme is updated; otherwise, the current power control scheme remains unchanged. The power update expression after load transfer is:

[0067] In the above formula, , These are the periods for load transfer in and transfer out, respectively. , These are the periods after load transfer. The direct green electricity supply capacity and the electricity purchased from the upstream power grid; Before load transfer Green electricity direct supply power during each time period; Before load transfer The amount of electricity purchased by the upstream power grid during each time period. This is the load transfer step size.

[0068] Specifically, it can be derived from the set to be optimized. Traversing two different time periods and ,in This is the period of load transfer. This refers to the load transfer period; under the condition of satisfying load transfer constraints, the load transfer step size is used. Divide the time period into units. The portion of the load borne by the upper-level power grid Transfer to time period The cost will be borne by direct green electricity supply; the total carbon cost of electricity under the corresponding power control scheme after load transfer will be recalculated. Compared with the current total carbon cost of electricity Compare; if Perform this load transfer and update the corresponding time period. and At the same time Update to the new current total carbon cost; otherwise, keep the current power and total carbon cost unchanged.

[0069] S5, Output the final power control scheme: Repeat step S4 until there are no factors that reduce the total carbon cost of the scheduling cycle in the period to be optimized. The load transfer combination combines the updated green electricity direct supply power and the power purchased by the upper-level grid in each control period to form the final power control scheme within the production cycle. .

[0070] To verify the effectiveness of the method in this embodiment, a case study was conducted using an export-oriented enterprise. The scheduling cycle was set to 24 hours, and the total daily electricity consumption was 360 MWh. Figure 2 As shown, typical external operating parameters for export-oriented enterprises include the time-of-use tariff of the upstream power grid, the time-of-use tariff for green electricity, the grid carbon emission factor, the maximum available green electricity power from the renewable energy generation side, and the maximum transmittable power of the green electricity direct supply line. The time-of-use tariff of the upstream power grid and the time-of-use tariff for green electricity are used to determine the load power demand and the cost difference between direct green electricity supply and supply from the upstream power grid; the grid carbon emission factor is used to calculate the carbon emissions corresponding to the purchase of electricity from the upstream power grid; the maximum available green electricity power from the renewable energy generation side and the maximum transmittable power of the green electricity direct supply line together constitute the constraints for direct green electricity supply.

[0071] Table 1 shows the production and carbon dioxide parameters for export-oriented enterprises: Table 1 Production and Carbon Dioxide Parameters of Export-Oriented Enterprises Parameter name numerical values unit Scheduling cycle 24 h Daily electricity consumption 360 MWh Export order percentage 60 % base load 9000 kW Load transfer step size 500 kW Domestic carbon price 70 <![CDATA[Yuan per ton of CO2]]> Foreign carbon cost prices 600 <![CDATA[Yuan per ton of CO2]]> Two schemes were selected for comparison and calculation in this example: Option 1: Prioritize the power supply method with the lower electricity price during each time period to form a power control scheme; Option 2: A power control scheme is formed by comprehensively considering the carbon cost of electricity and the constraints of direct green electricity supply in each time period (the method of this embodiment).

[0072] The enterprise load power curves under the two schemes are as follows: Figure 3 As shown, there are significant differences in the enterprise load power curves under the two schemes. Compared to Scheme 1, Scheme 2 shifts part of the load to periods with higher available green electricity and lower unit net cost, thereby improving the level of direct green electricity supply utilization.

[0073] The curves of green electricity direct supply power and upstream grid power purchase power under Option 2 are as follows: Figure 4 As shown, under Scheme 2, the direct green electricity supply and the electricity purchased from the upstream grid are complementary. Scheme 2 prioritizes increasing the direct green electricity supply during periods of green electricity surplus and correspondingly reduces the electricity purchased from the upstream grid.

[0074] Comparison of the cost structure of the two carbon emission schemes Figure 5 As shown, Option 2 reduces the amount of electricity purchased from the upstream power grid and its corresponding carbon emissions, thereby lowering both domestic and international carbon costs.

[0075] Calculations show that, after adopting the method of this invention (Scheme 2), the green electricity consumption increased from 132 MWh to 226 MWh, and the proportion of green electricity increased from 36.67% to 62.78%; the electricity purchased from the upstream grid decreased from 228 MWh to 134 MWh, and carbon emissions decreased from 202.72t to 110.83t; the total carbon cost decreased from 253,300 yuan to 229,700 yuan, a reduction of 9.29%. Therefore, this invention can achieve coordinated control of direct green electricity supply and upstream grid electricity purchases, while meeting the electricity needs of export-oriented enterprises, thereby reducing the overall carbon cost of electricity for these enterprises.

[0076] Compared with the prior art, the present invention has the following beneficial effects: By acquiring production plan information, export order information, historical electricity consumption data, and historical carbon emission data of export-oriented enterprises, the production batches corresponding to export orders, total electricity consumption, and the proportion of export orders can be incorporated into the power control process, enabling the power control scheme to adapt to the actual needs of export-oriented enterprises' production batches and the differentiated carbon accounting rules at home and abroad.

[0077] When determining the load power demand for each control period, the time-of-use electricity price of the upper-level power grid and the time-of-use electricity price of green electricity are comprehensively compared. The remaining load is allocated according to the principle that the lower the minimum electricity price, the higher the allocated load. This can distribute the production load to the time period with lower electricity cost while meeting the electricity demand of production orders, thereby improving the economy of load arrangement within the production cycle.

[0078] Based on time-of-use pricing, grid carbon emission factors, and domestic and international carbon price parameters, the unit net cost difference between direct green electricity supply and supply from the upstream grid is calculated, and the control period is divided into green electricity priority periods and periods to be optimized accordingly. This method can simultaneously consider the changes in green electricity consumption costs and the carbon cost reduction effect, so that the direct green electricity supply power is prioritized in periods with more favorable overall electricity carbon costs, avoiding simple scheduling based solely on electricity prices or solely on the available green electricity power.

[0079] When formulating a power control scheme, the green electricity direct supply power is determined by combining the load power demand, the maximum transmittable power of the green electricity direct supply line, and the maximum available green electricity power on the renewable energy generation side. The remaining load is supplemented by the power purchased by the upper-level power grid. This enables coordinated control of the green electricity direct supply power and the power purchased by the upper-level power grid without exceeding the transmission capacity of the direct supply line and the availability of renewable energy.

[0080] By calculating the total carbon cost of electricity during the scheduling cycle, load transfer comparisons are performed between the time periods to be optimized, and the power control scheme is updated when the total carbon cost decreases after the transfer, until there are no more time period combinations that can further reduce costs. This allows for further optimization of green electricity utilization and power purchase and allocation from the upper-level grid based on the initial power control scheme, thereby reducing the total carbon cost of electricity during the production cycle.

[0081] The present invention further provides a green electricity direct supply line power optimization control system for export-oriented enterprises, including a microprocessor and a memory interconnected thereto, wherein the microprocessor is programmed or configured to execute the steps of the green electricity direct supply line power optimization control method for export-oriented enterprises.

[0082] The present invention further provides a computer-readable storage medium storing a computer program / instructions, the computer program / instructions being programmed or configured to execute, via a processor, the steps of a green electricity direct supply line power optimization control method for export-oriented enterprises.

[0083] The system and medium of the present invention, corresponding to the methods described above, also have the advantages described above.

[0084] The present invention can implement all or part of the processes in the methods of the above embodiments, or it can be implemented by a computer program instructing related hardware. The computer program can be stored in a computer-readable storage medium. When the computer program is executed by a processor, it can implement the steps of the above method embodiments. The computer program includes computer program code, which can be in the form of source code, object code, executable file, or some intermediate form. Computer-readable media include: any entity or device capable of carrying computer program code, recording media, USB flash drives, portable hard drives, magnetic disks, optical disks, computer memory, read-only memory (ROM), random access memory (RAM), electrical carrier signals, telecommunication signals, and software distribution media, etc. The memory is used to store computer programs and / or modules. The processor implements various functions by running or executing the computer programs and / or modules stored in the memory, and by calling data stored in the memory. The memory may include high-speed random access memory, as well as non-volatile memory, such as hard disks, RAM, plug-in hard disks, smart media cards (SMC), secure digital (SD) cards, flash cards, at least one disk storage device, flash memory device, or other volatile solid-state storage devices.

[0085] The above description is merely a preferred embodiment of the present invention. The scope of protection of the present invention is not limited to the above embodiments. All technical solutions falling within the scope of the present invention's concept are within the scope of protection of the present invention. It should be noted that for those skilled in the art, any improvements and modifications made without departing from the principles of the present invention should also be considered within the scope of protection of the present invention.

Claims

1. A method for optimizing and controlling the power of green electricity direct supply lines for export-oriented enterprises, characterized in that, include: S1: Obtain the production batch control parameters and export order ratio corresponding to the export orders of export-oriented enterprises, and divide the production cycle corresponding to the production batch into multiple continuous control periods. S2, obtain the time-of-use electricity price parameters, grid carbon emission factor, carbon cost parameters and green electricity direct supply constraints for each control period, determine the load power demand for each control period based on the time-of-use electricity price parameters and production batch control parameters, and determine the unit net cost difference of green electricity direct supply replacing the supply from the upper-level grid for each control period based on the time-of-use electricity price parameters, grid carbon emission factor, carbon cost parameters and export order ratio; S3, based on the unit net cost difference, divide each control period into green electricity priority period and period to be optimized, and based on the load power demand and green electricity direct supply constraints, determine the green electricity direct supply power and the power purchased by the upper-level grid for each control period to form the current power control scheme; S4, calculate the total carbon cost of the scheduling cycle corresponding to the current power control scheme, construct a load transfer combination in the period to be optimized, and update the green electricity direct supply power and the power purchased by the upper grid for the corresponding control period when the load transfer constraints are met and the total carbon cost of the scheduling cycle after the transfer is reduced. S5. Repeat step S4 until there is no load transfer combination in the time period to be optimized that reduces the total carbon cost of the scheduling cycle. Then, summarize the updated green electricity direct supply power and the power purchased by the upper-level grid for each control period to form the final power control scheme.

2. The green electricity direct supply line power optimization control method for export-oriented enterprises according to claim 1, characterized in that, In step S2, the load power demand for each control period is determined based on the time-of-use electricity price parameters and production batch control parameters. The production batch control parameters include the total electricity consumption of the production batch, the base load, and the number of control periods within the scheduling cycle, including: First, compare the time-of-use electricity price of the upper-level power grid and the time-of-use electricity price of green electricity within the same control period to determine the minimum electricity price for the current control period. Then, according to the principle that the lower the minimum electricity price, the higher the allocated load, allocate the remaining electricity consumption of the production batch on the base load to obtain the load power demand for each control period, expressed as: In the above formula, For the first The lowest electricity price for each time period; For the first The time-of-use electricity price of the superior power grid for each time period; For the first Time-of-use pricing for green electricity during specific time periods; For the first Load power demand for each time period; For each time period within the scheduling cycle The maximum value; T τ represents the total number of control periods in the production cycle of the current batch of products; τ is the control period sequence number. This represents the total electricity consumption required for the production of the current batch of products. It is the base load.

3. The green electricity direct supply line power optimization control method for export-oriented enterprises according to claim 1, characterized in that, In step S2, the unit net cost difference between direct green electricity supply and supply from the upper-level power grid for each control period is determined, including: The difference in electricity cost per unit of green electricity directly supplied compared to the cost per unit of electricity purchased from the upstream power grid is calculated. This difference is then deducted from the reduction in domestic carbon costs due to reduced purchases from the upstream grid and the foreign carbon costs related to the proportion of export orders. The resulting net cost difference is expressed as follows: In the above formula, For the first The marginal net cost of replacing power from the upstream power grid with green electricity per unit time period; For the first The time-of-use electricity price of the superior power grid for each time period; For the first Time-of-use pricing for green electricity during specific time periods; For the first Carbon emission factor of the power grid in the region where the enterprise is located during a specific time period; For domestic carbon market carbon prices; The proportion of export orders; The carbon price in the international carbon market.

4. The green electricity direct supply line power optimization control method for export-oriented enterprises according to claim 1, characterized in that, In step S3, each control period is divided into a green electricity priority period and a period to be optimized based on the unit net cost difference, including: Control periods with a unit net cost difference of less than or equal to zero are designated as green electricity priority periods, while control periods with a unit net cost difference of greater than zero are designated as periods to be optimized. Based on the aforementioned load power demand and green electricity direct supply constraints, the green electricity direct supply power and the upstream grid power purchase power for each control period are determined, including: For green electricity priority periods, the green electricity direct supply power is determined within the range jointly limited by load power demand, the maximum transmittable power of green electricity direct supply lines, and the maximum available green electricity power on the renewable energy generation side, and the remaining load is supplemented by the power purchased by the upstream grid; for periods to be optimized, the green electricity direct supply power is initially set to zero, and the power purchased by the upstream grid undertakes all the load of the corresponding period, as expressed in the following expression: In the above formula, For the first Green electricity direct supply power during each time period; For the first The power purchased by the upstream power grid during each time period; The maximum transmittable power for green electricity direct supply lines; For the first The maximum available green electricity power from the new energy generation side during each time period; For the first Load power demand for each time period; , These are the green electricity priority time periods and the time periods to be optimized, respectively.

5. The green electricity direct supply line power optimization control method for export-oriented enterprises according to claim 1, characterized in that, In step S4, the total carbon cost of the scheduling cycle corresponding to the current power control scheme is calculated, including: The total carbon cost is obtained by adding the domestic carbon market compliance cost to the foreign carbon cost. The total electricity cost is obtained by adding the green electricity direct supply cost to the upstream grid purchase cost for each control period. Finally, the total carbon cost is added to the total electricity cost to obtain the total electricity carbon cost for the dispatch cycle. The specific expression is as follows: In the above formula, Total carbon cost; The carbon costs for enterprises to comply with domestic carbon market regulations; Carbon costs for companies exporting overseas; Carbon quotas for enterprises; This represents the total carbon emissions during the scheduling cycle. The proportion of export orders; For domestic carbon market carbon prices; Carbon prices in foreign carbon markets; Total electricity cost; For the first Green electricity direct supply power during each time period; For the first The power purchased by the upstream power grid during each time period; For the first The time-of-use electricity price of the superior power grid for each time period; For the first Time-of-use pricing for green electricity during specific time periods; As a dispatching unit; T This represents the total number of control periods in the production cycle of the current batch of products. This represents the total cost of electricity in carbon.

6. The green electricity direct supply line power optimization control method for export-oriented enterprises according to claim 5, characterized in that, Total carbon emissions during the scheduling cycle The calculation method is as follows: The historical direct carbon emission intensity per unit of purchased electricity is determined based on the direct carbon emissions of historical production batches and the total historical electricity purchases. Then, the total carbon emissions for the dispatch cycle are calculated by combining the purchased power from the upstream grid and the grid carbon emission factor in the current power control scheme. The expression is: In the above formula, This represents the total carbon emissions during the scheduling cycle. For the first j Direct carbon emissions from a historical batch; For the first j Total electricity purchased in each historical batch; The scheduling unit is N; the historical production batch quantity is E; ... For the first Carbon emission factor of the power grid in the region where the enterprise is located during a specific time period; For the first The amount of electricity purchased by the upstream power grid during each time period.

7. The green electricity direct supply line power optimization control method for export-oriented enterprises according to claim 1, characterized in that, In step S4, when constructing load transfer combinations during the time period to be optimized, the constraints for load transfer include: The load transfer step size is greater than zero, and the load transfer step size does not exceed the minimum value among the power purchased by the upper-level power grid during the load transfer-out period, the remaining transmittable power of the green electricity direct supply line during the load transfer-in period, and the remaining available green electricity power on the new energy generation side during the load transfer-in period. The expression is: In the above formula, , These are the periods for load transfer in and transfer out, respectively. This is the load transfer step size; For time period The maximum available green electricity capacity on the new energy generation side; , Time periods Power purchase capacity and time period of the upstream power grid Green electricity direct supply power; The maximum transmittable power for green electricity direct supply lines.

8. The green electricity direct supply line power optimization control method for export-oriented enterprises according to claim 1, characterized in that, In step S4, when the load transfer constraints are met and the total carbon cost of electricity in the dispatch cycle decreases after the transfer, the green electricity direct supply power and the power purchased by the upstream grid for the corresponding control period are updated, including: The expression for increasing the load transfer step size for direct green electricity supply during load transfer-in periods and decreasing the load transfer step size for power purchased from the upper-level grid during load transfer-out periods, while keeping the power output unchanged during other control periods besides load transfer-in and load transfer-out periods, is as follows: In the above formula, , These are the periods for load transfer in and transfer out, respectively. , These are the periods after load transfer. The direct green electricity supply capacity and the electricity purchased from the upstream power grid; Before load transfer Green electricity direct supply power during each time period; Before load transfer The amount of electricity purchased by the upstream power grid during each time period. This is the load transfer step size.

9. A green electricity direct supply line power optimization control system for export-oriented enterprises, comprising a microprocessor and a memory interconnected, characterized in that, The microprocessor is programmed or configured to perform the steps of the green electricity direct supply line power optimization control method for export-oriented enterprises as described in any one of claims 1 to 8.

10. A computer-readable storage medium storing a computer program / instructions, characterized in that, The computer program / instructions are programmed or configured to execute, via a processor, the steps of the green electricity direct supply line power optimization control method for export-oriented enterprises as described in any one of claims 1 to 8.