A modularly designed integrated photovoltaic, energy storage, and charging pile and its control method

By adopting a modular design for the integrated photovoltaic-storage-charging pile control method, real-time acquisition and analysis of photovoltaic power generation, energy storage battery and grid data are obtained and analyzed to optimize reverse power transmission decisions. This solves the problems of equipment life, grid stability and user experience in the reverse power transmission control of the integrated photovoltaic-storage-charging pile, and realizes efficient and safe reverse power transmission operation.

CN123104447APending Publication Date: 2026-11-17SHENZHEN JIANUO IND CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611404553.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-10
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

Existing integrated photovoltaic-storage-charging piles fail to effectively combine photovoltaic output, energy storage battery status, and grid demand in reverse power transmission control, resulting in shortened equipment lifespan, grid instability, and poor user experience.

Method used

By using a modularly designed integrated photovoltaic-storage-charging pile control method, the system can acquire real-time data on photovoltaic power generation, energy storage battery status, charging vehicle demand, and grid data. It can then calculate the power supply suitability coefficient, reverse power supply margin, discharge risk value, and risk-reward ratio to optimize reverse power supply decisions.

Benefits of technology

It achieves efficient, safe, and economical reverse power supply control for charging piles, ensuring equipment lifespan, improving user experience, stabilizing the power grid, and optimizing the coordinated operation of photovoltaics, energy storage, charging, and the power grid.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123104447A_ABST
    Figure CN123104447A_ABST
Patent Text Reader

Abstract

This application relates to the field of charging pile technology, specifically to a modularly designed integrated photovoltaic-storage-charging charging pile and its control method. The method includes: real-time acquisition of the photovoltaic power generation of a single charging pile, the state of charge and surface temperature of the energy storage battery, the charging duration of each vehicle in the charging station, and the electricity price and voltage data on the grid side; extracting reverse power transmission events that occurred at the charging pile in historical periods; quantifying the power transmission suitability coefficient of the charging pile's physical power transmission potential; assessing the charging demand degree of the overall urgency of electricity use for vehicles in the station; determining the reverse power transmission margin characterizing the charging pile's reverse power transmission capability; calculating the discharge risk value and discharge benefit-risk ratio; obtaining the decision coefficient for the charging pile to transmit power to the grid in reverse, and controlling the reverse power transmission operation of the charging pile accordingly. This application improves the accuracy and scientific scheduling of the control over the reverse power transmission behavior of integrated photovoltaic-storage-charging charging piles.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of charging pile technology, specifically to a modularly designed integrated photovoltaic, energy storage, and charging pile and its control method. Background Technology

[0002] In microgrid and vehicle-to-grid (V2G) scenarios, integrated photovoltaic-storage-charging piles, by combining photovoltaic power generation, energy storage batteries, and smart charging modules, have become an important means of mitigating the impact of high-power charging on the power grid. These charging piles provide green electricity to electric vehicles through photovoltaic power generation and store surplus electricity in energy storage batteries. This surplus electricity can be sold back to the grid during peak electricity price periods or when the grid experiences peak-shaving demand, thereby assisting the grid in peak shaving and valley filling and profiting from the price difference.

[0003] Existing reverse power supply control strategies typically make discharge decisions based on a single electricity price difference, severing the inherent coupling relationship between the multiple modules of photovoltaic, energy storage, and charging. For example, they fail to consider the volatility of photovoltaic output and the real-time temperature and charge status of the batteries. Blindly discharging when the underlying energy redundancy is insufficient or the battery health is poor will severely shorten the equipment lifespan. Secondly, they ignore the rigid demand of local vehicle charging load. Forcibly supplying power to external sources when the power supply at the station is tight will affect the charging experience of car owners. In addition, they disregard the cumulative damage to the energy storage batteries caused by frequent high-rate reverse power supply and the physical safety hazards caused by grid voltage oscillations. They only follow the temptation of electricity price to connect to the grid and supply power, which may exacerbate the unstable operation of the grid and even cause equipment damage, thereby reducing the decision-making ability of the charging pile's reverse power supply control. Summary of the Invention

[0004] To address the aforementioned technical issues, a modularly designed integrated photovoltaic, energy storage, and charging pile and its control method are provided to resolve existing problems.

[0005] The solution to the technical problem addressed in this application is to provide a modularly designed integrated photovoltaic, energy storage, and charging pile and its control method, including the following steps: In a first aspect, embodiments of this application provide a control method for an integrated photovoltaic-storage-charging pile based on modular design, the method comprising the following steps: Real-time acquisition of photovoltaic power generation, state of charge and surface temperature of energy storage batteries, charging time of each vehicle in the charging station, electricity price and voltage data on the grid side of a single charging pile, and extraction of reverse power transmission events that occurred at the charging pile in historical periods. For the current moment, based on the photovoltaic power generation intensity reflected by the photovoltaic power generation, and the energy storage margin and healthy operation status reflected by the state of charge of the energy storage battery and the surface temperature of the battery, the power supply suitability coefficient of the charging pile is used to quantify the physical power supply potential of the charging pile; the charging demand is assessed by the number of charging vehicles and their charging time to evaluate the overall urgency of power consumption of vehicles in the station, and combined with the power supply suitability coefficient, the reverse power supply margin, which characterizes the reverse power supply capability of the charging pile, is determined. The volatility of voltage data on the grid side and the frequency of reverse power transmission events are analyzed to characterize the discharge risk value superimposed by cumulative discharge damage and unstable grid operation. Combined with the trend of electricity price changes on the grid side, the discharge benefit risk ratio of the charging pile is calculated. Based on the reverse power supply margin and the discharge benefit-risk ratio, the decision coefficient for the charging pile to reverse power supply to the grid is obtained, and the reverse power supply operation of the charging pile is controlled accordingly.

[0006] Preferably, the calculation process for the power supply suitability factor is as follows: The average photovoltaic power generation of a single charging pile over all historical periods is calculated as the benchmark power generation; the ratio of the photovoltaic power generation of a single charging pile at the current moment to the benchmark power generation is used as the power generation intensity factor. The state of charge (SOC) of the energy storage battery and the degree of deviation of the battery surface temperature are used to calculate the SOC. The power supply suitability coefficient is positively correlated with the power generation intensity factor and the energy storage state prevalence.

[0007] Preferably, the calculation of the state of energy storage superiority includes: for a single charging pile, defining the time when each reverse power supply event occurs within a historical period as the historical power supply time; taking the average of the battery surface temperatures at all historical power supply times as the average temperature; calculating the difference between the current battery surface temperature and the average temperature as the temperature deviation; and taking the ratio of the current state of charge of the energy storage battery to the temperature deviation as the state of energy storage superiority.

[0008] Preferably, the calculation process for the charging demand is as follows: extract all completed charging order records within the historical period, and take the average charging duration of all charging order records as the historical average duration; take the average charging duration of all charging vehicles at the current moment as the average charging duration; take the ratio of the average charging duration to the historical average duration as the charging progress ratio; count the total number of all charging vehicles in the charging station at the current moment, and take the ratio of this number to the charging progress ratio as the charging demand of a single charging pile at the current moment.

[0009] Preferably, the reverse power supply margin is positively correlated with the power supply suitability coefficient, and negatively correlated with the charging demand.

[0010] Preferably, the process for obtaining the discharge risk value is as follows: For the current moment, extract the previously preset short time period; count the number of reverse power supply events that occur in a single charging pile within the short time period, and record it as the single pile discharge frequency; calculate the average single pile discharge frequency of all charging piles in the charging station, and use it as the average discharge frequency; use the ratio of the single pile discharge frequency to the average discharge frequency as the discharge fatigue degree. Calculate the dispersion of voltage data on the grid side at all times within a short period of time; The discharge risk value is positively correlated with both discharge fatigue degree and dispersion.

[0011] Preferably, the calculation process for the discharge benefit-risk ratio is as follows: A linear fit is performed on all electricity prices within a short period, and the slope of the fitted line is calculated. The electricity price on the grid side at the current moment is positively integrated with this slope to obtain the electricity price trend height at the current moment. The discharge benefit-risk ratio is highly positively correlated with electricity price, but negatively correlated with discharge risk value.

[0012] Preferably, the decision coefficient is positively correlated with both the reverse power supply margin and the discharge benefit-risk ratio.

[0013] Preferably, controlling the reverse power supply operation of the charging pile includes: if the decision coefficient of a single charging pile is greater than a preset threshold at multiple consecutive times, then the charging pile performs a reverse power supply operation to the power grid; otherwise, the reverse power supply operation is not performed.

[0014] Secondly, this application also provides a modularly designed integrated photovoltaic-storage-charging pile, including a photovoltaic power generation module, an energy storage battery module, a charging sensor module, a power grid monitoring module, and a main control unit that communicates with the above modules. The main control unit is equipped with a computer program, and when the main control unit executes the computer program, it implements the steps of any of the above-described modularly designed integrated photovoltaic-storage-charging pile control methods.

[0015] This application has at least the following beneficial effects: This application calculates the power supply suitability factor, which has the beneficial effect of fully quantifying the redundant power generation capacity of the photovoltaic side and the healthy backup power status of the energy storage side. This ensures that the underlying hardware of the charging pile has sufficient power reserves and excellent thermal stability at any given moment, effectively avoiding the inefficiency and irreversible damage to battery life caused by blind discharge when battery temperature deteriorates or the battery storage is low. This guarantees the feasibility and economy of reverse power supply operations from the source. Calculating the charging demand also has the beneficial effect of accurately reflecting the real-time vehicle scale and the urgency of overall energy replenishment needs within the charging station, dynamically... By sensing the pressure status of local power load, it effectively prevents situations that severely degrade the basic service experience at the station, such as vehicles having no power to charge or limited charging rates due to ignoring local load. Determining the reverse power supply margin has the beneficial effect of comprehensively characterizing the availability of reverse power supply for charging piles under the dual constraints of physical power supply capacity and local charging conflicts, accurately identifying and calculating the net remaining available power after deducting the rigid demand for local electricity, and eliminating ineffective scheduling by robbing Peter to pay Paul. Calculating the discharge risk value has the beneficial effect of deeply superimposing the internal risks generated by the battery due to high-frequency discharge. The system addresses the risks of fatigue accumulation and external grid collapse caused by severe grid voltage oscillations, preventing power injection during vulnerable grid periods from damaging equipment or interfering with grid recovery, thus achieving dual protection for both equipment and grid safety. Calculating the discharge benefit-risk ratio effectively balances the high profits driven by soaring external market electricity prices with the risks of internal and external physical damage, suppressing the impulse to connect charging piles to the grid during periods of battery fatigue or severe grid oscillations, and completely preventing safety accidents caused by blindly pursuing high electricity prices. Obtaining the decision coefficient for charging piles to reverse power supply to the grid allows for control of reverse power supply operations. This breaks down information silos between the four modules of photovoltaic, energy storage, charging, and grid, integrating the final net physical output capacity with external peak-shaving arbitrage drivers. This ensures that charging piles only trigger reverse power supply operations during optimal windows of abundant power, extremely light local load, stable grid, and high profits, achieving synergistic optimization of economic benefits, equipment lifespan, user experience, and grid safety. This improves the accuracy and scientific nature of controlling and scheduling the reverse power supply behavior of integrated photovoltaic-energy storage-charging piles. Attached Figure Description

[0016] Figure 1 A flowchart illustrating the steps of a modularly designed integrated photovoltaic-storage-charging pile control method provided in this application embodiment; Figure 2 A flowchart illustrating the steps of the method for obtaining the power supply suitability factor provided in this application embodiment. Detailed Implementation

[0017] The following, in conjunction with the accompanying drawings and implementation examples, provides a more detailed description of the modularly designed integrated photovoltaic, energy storage, and charging pile and its control method proposed in this application.

[0018] Please see Figure 1 The diagram illustrates a flowchart of a control method for an integrated photovoltaic-storage-charging pile based on modular design, according to an embodiment of this application. The method includes the following steps: Step 1: In real time, acquire the photovoltaic power generation of a single charging pile, the state of charge and surface temperature of the energy storage battery, the charging time of each charging vehicle in the charging station, and the electricity price and voltage data on the grid side, and extract the reverse power transmission events that occurred at the charging pile in the historical period.

[0019] In actual operation, integrated photovoltaic-storage-charging piles not only serve the basic function of powering electric vehicles, but also need to use energy storage batteries to feed power back to the grid when there is photovoltaic power redundancy or when the grid experiences peak-shaving demand. If discharge control is solely based on the peak-valley electricity price difference, it is highly likely to lead to severe battery damage due to excessive pursuit of electricity price gains, power depletion during peak charging periods, and grid connection safety hazards under extreme grid fluctuations. Therefore, it is necessary to control integrated photovoltaic-storage-charging piles to balance the station's energy replenishment needs, battery health status, and grid interaction benefits.

[0020] Based on the above analysis, the photovoltaic power generation module connected to a single charging pile is used to obtain the photovoltaic power generation in real time; the state of charge and surface temperature of the energy storage battery are obtained in real time in the energy storage battery module; and the charging sensing module is used to extract the charging time of each electric vehicle in the charging station to which a single charging pile belongs from the start of plug-in charging in real time. The power grid monitoring module can obtain real-time electricity price and voltage data from the power grid side. It should be noted that since the electricity price is updated every 15 minutes, the data collection interval for the electricity price is 15 minutes, while the data collection frequency for other data is 1 second. As other implementation methods, implementers can set them according to their actual situation. The collected data is time-aligned. The time alignment process is a well-known technique and will not be described in detail here.

[0021] The behavior of a single charging pile's energy storage battery outputting electrical energy to the grid is defined as a reverse power transmission event; the reverse power transmission events that occurred in a single charging pile within a historical period are retrieved from the locally stored historical interaction logs. In this embodiment, the historical period is set to the time period included in the past six months. As for other implementation methods, the implementer can set it according to the actual situation.

[0022] At this point, real-time photovoltaic power generation, state of charge and surface temperature of energy storage batteries, charging time of each charging vehicle, and electricity price and voltage data on the grid side are obtained, and reverse power transmission events that occurred at the charging pile in historical periods are extracted.

[0023] Step 2: For the current moment, based on the photovoltaic power generation intensity reflected by the photovoltaic power generation, and the energy storage margin and healthy operation status reflected by the state of charge of the energy storage battery and the surface temperature of the battery, the power supply suitability coefficient of the charging pile's physical power supply potential is quantified; the charging demand is assessed by the number of charging vehicles and their charging time to evaluate the overall urgency of power consumption of vehicles in the station, and combined with the power supply suitability coefficient, the reverse power supply margin, which characterizes the reverse power supply capability of the charging pile, is determined.

[0024] In microgrid operation scenarios, the main challenge faced by the distribution network is the excessive peak-to-valley difference. When the real-time photovoltaic power generation of the charging station increases, the photovoltaic modules continuously inject power into the energy storage modules. At this time, the energy storage batteries are more likely to accumulate redundant power exceeding the local charging demand. This part of the power provides a physical basis for responding to the grid's peak shaving needs. At the same time, the state of charge and surface temperature of the energy storage batteries directly affect the feasibility and economy of reverse power transmission. If the battery has sufficient remaining power and the surface temperature is in a suitable state, it means that there is enough redundant power available for dispatch. The smaller the energy loss and lifespan reduction caused by forced discharge, the higher the overall feasibility of reverse power transmission to the grid. However, if the battery surface temperature is too high, forced discharge is not only less efficient but also severely reduces battery life. Therefore, based on the photovoltaic power generation intensity assessment, combined with the state of charge and surface temperature of the energy storage batteries, a power transmission suitability coefficient is calculated. This serves as a benchmark for judging whether the underlying physical state of the charging pile supports reverse power transmission. The flowchart of the method for obtaining the power transmission suitability coefficient provided in this application embodiment is as follows. Figure 2 As shown, specifically: Calculate the average photovoltaic power generation of a single charging pile at all times in the historical period as the benchmark power generation; The ratio of the photovoltaic power generation of a single charging pile at the current moment to the benchmark power generation is used as the power generation intensity factor. It should be noted that, in order to avoid the denominator being 0 when calculating the ratio, a parameter adjustment factor is added to the denominator. In this embodiment, the parameter adjustment factor is set to 1. As for other implementation methods, the implementer can set it according to the actual situation. Secondly, the larger the power generation intensity factor, the more abundant the photovoltaic power generation at the current moment is compared with the historical average level. The stronger the photovoltaic power generation performance, the more redundant power may be, thus providing sufficient underlying support for responding to the grid's reverse peak shaving and power transmission.

[0025] For a single charging pile, the time when each reverse power supply event occurs within a historical period is defined as the historical power supply time; the average value of the battery surface temperature at all historical power supply times is taken as the average temperature. Calculate the difference between the current battery surface temperature and the average temperature, and use it as the temperature deviation; In this embodiment, the absolute value of the difference between the current battery surface temperature and the average temperature is calculated, and the ratio of this value to the average temperature is taken as the temperature deviation. In order to avoid the denominator being 0 when calculating the ratio, a parameter adjustment factor is added to the denominator. This parameter adjustment factor is set to 0.01. In other implementation methods, the implementer can set it according to the actual situation.

[0026] The ratio of the current state of charge of the energy storage battery to the temperature deviation is used as the state of charge preference. It should be noted that, in calculating the ratio, to avoid a temperature deviation of 0, a parameter adjustment factor is added to the denominator. This parameter adjustment factor is set to 0.1. As another implementation method, the implementer can set it according to the actual situation. The smaller the temperature deviation, the more stable the battery surface temperature is at the time of successful power transmission in the past, and the more stable the battery state is. The larger the state of charge, the more sufficient the remaining usable power of the energy storage battery is. The greater the obtained state of charge dominance, the more the battery is not only fully charged but also has good thermal stability, and can safely and efficiently support high-power reverse power transmission to the grid without causing serious lifespan degradation.

[0027] The power supply suitability coefficient of a single charging pile at the current moment is positively correlated with the power generation intensity factor and the energy storage state prevalence. It should be noted that a positive correlation means that the dependent variable increases as the independent variable increases and decreases as the independent variable decreases.

[0028] In this embodiment, the product of the power generation intensity factor and the energy storage state of preference is used as the power transmission suitability coefficient.

[0029] It should be noted that the larger the power supply suitability coefficient, the stronger the comprehensive ability of the charging pile to support reverse power supply from the "photovoltaic + energy storage" side, and the more inherent the conditions for discharging into the grid.

[0030] The core service function of charging stations is to prioritize the charging needs of electric vehicles, not to sell electricity to the grid. Forcibly feeding electricity back into the grid during peak charging times at the station would not only crowd out energy storage resources intended for vehicle charging but could also lead to reduced charging power, longer waiting times for users, and ultimately negatively impact user experience. Therefore, it is essential to quantify the priority conflict between "charging vehicles" and "selling electricity to the grid."

[0031] Secondly, the number of electric vehicles at the charging station and their charging progress jointly determine the urgency of the charging demand. A large number of vehicles charging at a station indicates a high overall electricity demand; simultaneously, if these vehicles have generally had short charging times, it suggests they are mostly in the initial charging stage and will require a considerable amount of time to fully charge, continuing to absorb significant amounts of energy. The combination of these two factors reflects an extremely urgent need for local power dissipation from charging stations in the short term. If electricity were then fed back to the grid, it would create a significant disconnect between local charging demand and the actual charging needs.

[0032] Based on the above analysis, the charging demand is calculated by measuring the number of vehicles charging at the charging station in real time and the degree of deviation of the charging time of these vehicles from the historical average level. Specifically: Extract all completed charging order records within the historical period, and use the average charging duration of all charging order records as the historical average duration; The average charging time is the average charging time of all charging vehicles at the current moment. The ratio of the average charging time to the historical average charging time is used as the charging progress ratio; The total number of all vehicles charging at the current charging station is counted, and the ratio of this number to the charging progress is used as the charging demand. It should be noted that, when calculating the ratio, to avoid the denominator being 0, a parameter adjustment factor is added to the denominator. This parameter adjustment factor is set to 0.01. As another implementation method, the implementer can set it according to the actual situation. If the total number of all charging vehicles in the charging station at the current moment is 0, then the charging demand is assigned a value of 0. Secondly, the smaller the charging progress ratio, the more the average charging time of the vehicles in the station is far lower than the average time required to complete charging in the past, reflecting that most vehicles have just been parked and have a huge power shortage, and are in a state of high demand for power output from the charging piles. The larger the total number, the more dense the equipment load of the current grid-connected charging. The larger the obtained charging demand, the more vehicles there are in the station, and the vast majority of them are in a state of extreme power shortage, reflecting that the rigid demand for internal power supply at the current moment is extremely high. At this time, the deviation risk of sending power back to the grid increases sharply.

[0033] Furthermore, based on the charging demand and power supply suitability coefficient, the reverse power supply margin is determined as follows: The reverse power supply margin of a single charging pile at the current moment is positively correlated with the power supply suitability coefficient, but negatively correlated with the charging demand. It should be noted that a negative correlation means that the dependent variable decreases as the independent variable increases, and increases as the independent variable decreases; in this embodiment, the ratio of the power supply suitability coefficient to the charging demand is used as the reverse power supply margin. It should be noted that, in order to avoid the denominator being 0 when calculating the ratio, a parameter adjustment factor is added to the denominator. This parameter adjustment factor is set to 0.1. As another implementation method, the implementer can set it according to the actual situation. The larger the reverse power supply margin, the more abundant the photovoltaic output, the better the energy storage status, and the lower the charging load pressure in the station. This reflects that the charging pile at this moment has an absolute surplus capacity to participate in external interaction while fully taking into account internal services. It should tend to transmit the redundant power back to the grid to participate in peak-valley arbitrage.

[0034] Thus, the reverse power supply margin of a single charging pile at the current moment is obtained.

[0035] Step 3: Analyze the voltage fluctuations on the grid side and the frequency of reverse power transmission events to characterize the discharge risk value resulting from the superposition of cumulative discharge damage and unstable grid operation. Combined with the trend of electricity price changes on the grid side, calculate the discharge benefit-risk ratio of the charging pile.

[0036] The core driving force behind the interaction between photovoltaic, energy storage, and charging piles and the grid lies in economic benefits and peak-shaving value. By storing electricity during off-peak hours and discharging during peak hours, peak-valley price arbitrage is achieved. Therefore, when the grid experiences peak demand leading to soaring electricity prices, it not only signifies an urgent power shortage on the grid side but also maximizes the economic return of charging piles feeding electricity back into the grid. Thus, if real-time electricity prices are high and recent price trends show a significant and continuous upward trend, the necessity for charging piles to feed electricity back into the grid increases. Based on this, the trend of electricity price changes is analyzed, and the price trend height is calculated, specifically: For the current moment, extract its previously preset short time period; In this embodiment, the duration of the short period is 2 hours. As for other implementation methods, the implementer can set the duration according to the actual situation. Perform a linear fit on all electricity prices over a short period and calculate the slope of the fitted line; In this embodiment, the least squares method is used for linear fitting. The least squares method and the calculation of the slope are well-known techniques and will not be described in detail here. The current electricity price on the grid side is positively integrated with this slope to obtain the current electricity price trend height. It should be noted that forward fusion specifically refers to a multiplicative relationship, an additive relationship, etc. In this embodiment, the product of the current electricity price on the grid side and the slope is calculated and recorded as the first product. This product is then normalized to represent the electricity price trend height. The normalization process is as follows: the first product of all times in the past day is normalized using the maximum value normalization method. The maximum value normalization method is a well-known technique and will not be described in detail here.

[0037] It should be noted that the greater the slope, the faster the recent electricity price has risen, reflecting that the grid is in a critical stage of rapid increase in electricity load. The higher the current electricity price on the grid side, the more lucrative the instantaneous unit price revenue can be obtained from selling electricity to the grid. The greater the trend of the obtained electricity price, the more it indicates that not only is the unit price of electricity sold high, but it is also in an upward channel of rapid demand growth, reflecting the dual superposition of economic arbitrage space for sending electricity back to the grid and the urgency of peak shaving, with extremely strong external driving force.

[0038] There are significant differences in power characteristics between charging piles supplying power to the grid and charging vehicles. Selling electricity to the grid typically requires a high power throughput capacity, meaning that energy storage batteries need to release energy at a high discharge rate. If the same charging pile repeatedly performs high-rate discharge operations to the grid within a short period, the battery will frequently be under high stress conditions, which can easily lead to imbalance in lithium-ion diffusion and accelerated side reactions within the battery, resulting in severe lifespan reduction. Therefore, if a charging pile frequently supplies power to the grid in a short period, the necessity of reverse power supply should be appropriately reduced to lower the hidden maintenance costs of high-frequency, high-rate discharge. The discharge fatigue degree is calculated based on the frequency of reverse power supply by the charging pile in a short period of time. The number of reverse power supply events that occur in a single charging pile within a short period of time is counted and recorded as the single-pile discharge frequency. Calculate the average discharge frequency of each charging pile in the charging station as the average discharge frequency. The ratio of the discharge frequency of a single pile to the average discharge frequency is used as the discharge fatigue degree. It should be noted that if the average discharge frequency is 0, then the discharge fatigue value is set to 0. The higher the discharge frequency of a single charging pile, the greater the discharge fatigue value, indicating that the discharge load of the charging pile recently has seriously exceeded the average level of the equipment in the station. This reflects that the charging pile has recently been performing high-rate discharge operations very frequently, and the internal battery is in a state of high fatigue and high stress. The risk of battery life loss has increased sharply. At this time, the discharge priority of the charging pile should be forcibly reduced.

[0039] Secondly, when evaluating the reverse power transmission strategy, if the grid-side voltage changes extremely rapidly and fluctuates significantly in the short term, it indicates that the grid inertia is insufficient, its anti-interference capability is weak, and it is in a highly unstable critical state. Under such highly unstable critical conditions, if the energy storage of the charging pile continues to forcibly inject asynchronous or weakly synchronous power into the grid, it will not only easily trigger resonance leading to a complete grid collapse, but will also suffer voltage surge backflow that burns out the charging pile's own converter and battery. Therefore, by analyzing the volatility of the grid-side voltage data and combining it with discharge fatigue, the discharge risk value is calculated as follows: Calculate the dispersion of voltage data on the grid side at all times within a short period of time; In this embodiment, the degree of dispersion is measured by calculating the coefficient of variation of voltage data at all times within a short period of time on the grid side. The calculation of the coefficient of variation is a well-known technique and will not be described in detail here. In order to avoid the denominator being 0 when calculating the coefficient of variation, a parameter adjustment factor is added to the denominator. This parameter adjustment factor is set to 0.001. As another implementation method, the implementer can set it according to the actual situation.

[0040] The discharge risk value of a single charging pile at the current moment is positively correlated with the discharge fatigue degree and the degree of dispersion. In this embodiment, the sum of the discharge fatigue degree and the degree of dispersion is used as the discharge risk value; It should be noted that the greater the degree of dispersion, the more severe the voltage oscillation on the grid side in the short term, the less inertia the grid has, the weaker its anti-interference ability, and the more unstable it is in a critical state. At this time, if the charging pile forcibly injects grid-connected power in pursuit of profit, it will not only easily cause resonance and aggravate grid collapse, but also may suffer voltage surge back and burn out the equipment hardware. The obtained discharge risk value characterizes the superposition degree of fatigue risk caused by high-frequency discharge of the charging pile and grid connection safety risk caused by grid instability. The larger the value, the greater the potential risk of the charging pile's battery being in a high-frequency overwork state and the external grid voltage oscillating violently and on the verge of collapse. At this time, the potential risk of the charging pile performing grid-connected reverse power transmission is greater.

[0041] Furthermore, based on the trend of electricity prices and the risk value of discharge, the risk-reward ratio of discharge is determined as follows: The discharge benefit-risk ratio of a single charging pile at the current moment is highly positively correlated with the electricity price, but negatively correlated with the discharge risk value; In this embodiment, the ratio of the electricity price trend height to the discharge risk value is used as the discharge benefit risk ratio. In order to avoid the discharge risk value being 0 when calculating the ratio, a parameter adjustment factor is added to the denominator. In this embodiment, the parameter adjustment factor is set to 0.1. As for other implementation methods, the implementer can set it according to the actual situation.

[0042] It should be noted that the higher the discharge benefit-risk ratio, the higher the grid electricity price is and the upward trend it is. At the same time, the lower the potential risk of grid-connected discharge, the more appropriate and suitable it is to participate in reverse power transmission to the grid.

[0043] Thus, the discharge benefit-risk ratio of a single charging pile at the current moment is obtained.

[0044] Step 4: Based on the reverse power supply margin and the discharge benefit-risk ratio, obtain the decision coefficient for the charging pile to reverse power supply to the grid, and control the reverse power supply operation of the charging pile accordingly.

[0045] Furthermore, based on the reverse power transmission margin and the discharge benefit-risk ratio, the decision coefficients are determined as follows: The decision coefficient of a single charging pile at the current moment is positively correlated with the reverse power supply margin and the discharge benefit-risk ratio. In this embodiment, the product of the reverse power supply margin and the discharge benefit-risk ratio is calculated and denoted as the second product. The normalized result is used as the decision coefficient. The normalization process is as follows: the second product at all times in the historical period is normalized using the maximum-minimum normalization method. The maximum-minimum normalization method is a well-known technique and will not be described in detail here.

[0046] It should be noted that the larger the decision coefficient, the more sufficient the photovoltaic redundancy inside the charging pile is and the local charging load inside the station is extremely light. At the same time, the external power grid is in a high premium peak-shaving gap and the physical environment of grid connection is absolutely safe. This reflects that the underlying foundation for external power transmission is fully available, and the economic benefits of grid connection can be obtained with minimal hardware damage risk. In this case, reverse power transmission operation should be performed.

[0047] Secondly, the reverse power supply operation of the charging pile is regulated using decision coefficients, specifically as follows: If the decision coefficient of a single charging pile is greater than the preset threshold at multiple consecutive times, the charging pile will perform a reverse power supply operation to the grid; otherwise, it will not perform a reverse power supply operation. In this embodiment, the process of obtaining the preset threshold is as follows: calculate the average of the decision coefficients of the charging pile at all historical power supply moments in the historical period, and use it as the preset threshold. In this embodiment, the preset threshold is set to 0.85. As for other implementation methods, the implementer can set it according to the actual situation. Secondly, when the decision coefficient of the charging pile is greater than the preset threshold for 5 consecutive minutes, the charging pile performs a reverse power supply operation to the grid. As for other implementation methods, the implementer can set it according to the actual situation.

[0048] If the decision coefficient of a single charging pile is greater than the preset threshold at multiple consecutive times, it indicates that the grid connection and power supply conditions are met. At this time, a reverse grid connection control command is generated to control the bidirectional converter of the charging pile to switch from pure vehicle charging mode to bidirectional hybrid discharge mode, so that the energy storage battery can discharge energy to the vehicle while also transmitting energy back to the distribution network. Otherwise, the reverse power supply operation is not performed, and the original pure vehicle charging mode of the charging pile is maintained.

[0049] Based on the same inventive concept as the above method, this application embodiment also provides a photovoltaic-storage-charging integrated charging pile based on modular design, including a photovoltaic power generation module, an energy storage battery module, a charging sensing module, a power grid monitoring module, and a main control unit that communicates with the above multiple modules. The main control unit is equipped with a computer program, and when the main control unit executes the computer program, it implements any of the steps of the above-described method for controlling a photovoltaic-storage-charging integrated charging pile based on modular design.

[0050] The photovoltaic power generation module consists of several photovoltaic modules connected in series or in parallel. It is installed on the roof of the charging station or the roof of an adjacent building and is used to convert solar energy into DC power. Its output end is connected to the DC bus through a DC / DC converter and is also electrically connected to the energy storage battery module to charge the energy storage battery or directly provide power to the electric vehicle. The energy storage battery module adopts a lithium iron phosphate or ternary lithium battery pack and integrates a battery management system (BMS) to monitor the battery's state of charge and surface temperature in real time. The charging sensing module is installed at each charging gun interface and interacts with the vehicle's BMS via CAN bus or PLC power line carrier communication to read information such as the unique identifier of the connected vehicle, charging time, required power and battery status in real time. The power grid monitoring module is installed at the grid connection point of the charging pile and includes a voltage transformer, a current transformer, and an energy metering chip. It is used to collect the voltage amplitude, frequency, and real-time electricity price on the power grid side in real time. The main control unit adopts an industrial-grade ARM / DSP embedded processor, which integrates memory, communication interface and multiple I / O ports. The main control unit communicates with the photovoltaic power generation module, energy storage battery module, charging sensor module and power grid monitoring module through CAN bus, RS485 or Ethernet respectively, forming a centralized control architecture. It receives monitoring data from the above multiple modules in real time by executing the internally configured computer program, and uses it to regulate the reverse power supply operation of the charging pile.

Claims

1. A control method for an integrated photovoltaic-energy storage-charging pile based on modular design, characterized in that, The method includes the following steps: Real-time acquisition of photovoltaic power generation, state of charge and surface temperature of energy storage batteries, charging time of each vehicle in the charging station, electricity price and voltage data on the grid side of a single charging pile, and extraction of reverse power transmission events that occurred at the charging pile in historical periods. For the current moment, based on the photovoltaic power generation intensity reflected by the photovoltaic power generation, and the energy storage margin and healthy operation status reflected by the state of charge of the energy storage battery and the surface temperature of the battery, the power supply suitability coefficient of the charging pile is used to quantify the physical power supply potential of the charging pile; the charging demand is assessed by the number of charging vehicles and their charging time to evaluate the overall urgency of power consumption of vehicles in the station, and combined with the power supply suitability coefficient, the reverse power supply margin, which characterizes the reverse power supply capability of the charging pile, is determined. The volatility of voltage data on the grid side and the frequency of reverse power transmission events are analyzed to characterize the discharge risk value superimposed by cumulative discharge damage and unstable grid operation. Combined with the trend of electricity price changes on the grid side, the discharge benefit risk ratio of the charging pile is calculated. Based on the reverse power supply margin and the discharge benefit-risk ratio, the decision coefficient for the charging pile to reverse power supply to the grid is obtained, and the reverse power supply operation of the charging pile is controlled accordingly.

2. The control method for an integrated photovoltaic-energy storage-charging pile based on modular design as described in claim 1, characterized in that, The calculation process for the power supply suitability factor is as follows: The average photovoltaic power generation of a single charging pile over all historical periods is calculated as the benchmark power generation; the ratio of the photovoltaic power generation of a single charging pile at the current moment to the benchmark power generation is used as the power generation intensity factor. The state of charge (SOC) of the energy storage battery and the degree of deviation of the battery surface temperature are used to calculate the SOC. The power supply suitability coefficient is positively correlated with the power generation intensity factor and the energy storage state prevalence.

3. The control method for an integrated photovoltaic-energy storage-charging pile based on modular design as described in claim 2, characterized in that, The calculation of the energy storage state of priority includes: for a single charging pile, defining the time when each reverse power supply event occurs within a historical period as the historical power supply time; taking the average of the battery surface temperature at all historical power supply times as the average temperature; calculating the difference between the battery surface temperature at the current time and the average temperature as the temperature deviation; and taking the ratio of the state of charge of the energy storage battery at the current time to the temperature deviation as the energy storage state of priority.

4. The control method for an integrated photovoltaic-energy storage-charging pile based on modular design as described in claim 1, characterized in that, The calculation process for the charging demand is as follows: extract all completed charging order records within the historical period, and take the average charging duration of all charging order records as the historical average duration; take the average charging duration of all charging vehicles at the current moment as the average charging duration. The ratio of the average charging time to the historical average charging time is used as the charging progress ratio; the total number of all charging vehicles in the charging station at the current moment is counted, and the ratio of this number to the charging progress ratio is used as the charging demand of a single charging pile at the current moment.

5. The control method for an integrated photovoltaic-energy storage-charging pile based on modular design as described in claim 1, characterized in that, The reverse power supply margin is positively correlated with the power supply suitability coefficient, but negatively correlated with the charging demand.

6. The control method for an integrated photovoltaic-energy storage-charging pile based on modular design as described in claim 1, characterized in that, The process for obtaining the discharge risk value is as follows: For the current moment, extract the previously preset short time period; count the number of reverse power supply events that occur in a single charging pile within the short time period, and record it as the single pile discharge frequency; Calculate the average discharge frequency of each charging pile in the charging station as the average discharge frequency; the ratio of the discharge frequency of each charging pile to the average discharge frequency is used as the discharge fatigue degree. Calculate the dispersion of voltage data on the grid side at all times within a short period of time; The discharge risk value is positively correlated with both discharge fatigue degree and dispersion.

7. The control method for an integrated photovoltaic-energy storage-charging pile based on modular design as described in claim 6, characterized in that, The calculation process for the discharge benefit-risk ratio is as follows: A linear fit is performed on all electricity prices within a short period, and the slope of the fitted line is calculated. The electricity price on the grid side at the current moment is positively integrated with this slope to obtain the electricity price trend height at the current moment. The discharge benefit-risk ratio is highly positively correlated with electricity price, but negatively correlated with discharge risk value.

8. The control method for an integrated photovoltaic-energy storage-charging pile based on modular design as described in claim 1, characterized in that, The decision coefficient is positively correlated with both the reverse power supply margin and the discharge benefit-risk ratio.

9. The control method for an integrated photovoltaic-energy storage-charging pile based on modular design as described in claim 1, characterized in that, The control of the reverse power supply operation of the charging pile includes: if the decision coefficient of a single charging pile is greater than a preset threshold at multiple consecutive times, then the charging pile performs a reverse power supply operation to the power grid; otherwise, the reverse power supply operation is not performed.

10. A modularly designed integrated photovoltaic-storage-charging pile, comprising a photovoltaic power generation module, an energy storage battery module, a charging sensor module, a power grid monitoring module, and a main control unit communicating with the above modules, characterized in that, The main control unit is equipped with a computer program, and when the main control unit executes the computer program, it implements the steps of the control method for an integrated photovoltaic, energy storage and charging pile based on modular design as described in any one of claims 1-9.