Optimal Selection Method for Strengthening Critical Power Grid Lines under Typhoon Disasters

By constructing a set of extreme fault scenarios for power grid lines and equipment under typhoon disasters, and combining a deep collaborative method of meteorological, topological, and engineering multi-dimensional data, the problem of complex fault combinations and difficulty in risk quantification of critical power grid lines under typhoon disasters was solved. This enabled efficient reinforcement optimization through simultaneous operations by multiple construction teams, improving the cost-effectiveness and safety of power grid emergency response.

CN123116604APending Publication Date: 2026-11-17NANJING UNIV OF SCI & TECH +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611362064.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-03
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

Existing technologies face complex fault combinations and difficulties in risk quantification for critical power grid lines during typhoon disasters. They also lack precision in optimization and fail to effectively consider the combined effects of multiple construction teams working simultaneously, resulting in low cost-effectiveness of emergency response.

Method used

By constructing a set of extreme fault scenarios for power grid line equipment under typhoon disasters, and combining a deep collaborative method of meteorological-topology-engineering multidimensional data, risk quantification and cost accounting are carried out, and the reinforcement combination of critical lines is optimized. This includes an improved Rankine typhoon circulation wind speed model, Monte Carlo simulation, Hamming distance and K-means clustering algorithm, and dynamic optimization of power grid topology and cost model.

Benefits of technology

It significantly improves the accuracy and cost-effectiveness of decision-making for reinforcing critical power grid lines during typhoon disasters, is compatible with simultaneous operations by multiple construction teams, enhances the economy and efficiency of emergency response, and ensures power grid safety and load stability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123116604A_ABST
    Figure CN123116604A_ABST
Patent Text Reader

Abstract

This invention discloses a method for optimizing the reinforcement combination of critical power grid lines under typhoon disasters, specifically including the following steps: First, constructing a set of extreme fault scenarios for power grid line equipment under typhoon disasters; second, calculating the load loss and scenario risk corresponding to each scenario, and selecting the highest-risk scenario as a representative extreme fault scenario; subsequently, implementing reinforcement treatment on each line combination in the highest-risk scenario, calculating the load loss and risk changes after treatment; finally, calculating the cost-effectiveness of treatment for each line combination, ranking the critical lines accordingly, and outputting an optimal list of critical line combinations. This invention is adaptable to the equipment combination treatment mode of multiple construction teams operating simultaneously, and constructs a cost accounting system combined with typhoon characteristics. It effectively solves the problems of complex power grid line equipment fault combinations, difficulty in risk quantification, and insufficient optimization accuracy under typhoon disaster conditions, improving the pertinence and effectiveness of power grid emergency response, and ensuring the rapid restoration of stable operation of the power grid.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of power system emergency response technology, and in particular, it is a preferred method for strengthening critical power grid lines under typhoon disasters. Background Technology

[0002] In recent years, typhoon disasters have occurred frequently, causing severe damage to power grids in coastal areas and typhoon-affected regions. The strong winds generated by typhoons can easily lead to faults such as the collapse of transmission line towers and conductor galloping, and often cause extreme failures of multiple line devices, resulting in significant system load losses and posing a huge challenge to the emergency response of power grids during typhoon disasters.

[0003] To address the emergency response of critical power grid lines during typhoon disasters, existing research primarily focuses on fault scenario modeling and emergency response scheme optimization. However, research on the risk variations caused by equipment combinations and the economic efficiency and effectiveness of emergency response plans remains scarce. Practice shows that simultaneously reinforcing equipment combinations through multiple construction teams can improve resource utilization efficiency, thereby enhancing the cost-effectiveness of emergency response. Therefore, when conducting emergency response work on power grid lines during typhoon disasters, it is necessary to fully consider the combined effects of line equipment to achieve optimal combination of critical lines. Summary of the Invention

[0004] The purpose of this invention is to address the shortcomings of the prior art by proposing an optimal method for strengthening and combining critical power grid lines under typhoon disasters. This method aims to solve technical problems such as the complexity of power grid line equipment fault combinations, difficulty in risk quantification, and insufficient optimization accuracy under typhoon disaster conditions.

[0005] The technical solution to achieve the purpose of this invention is: a preferred method for strengthening critical power grid lines under typhoon disasters, the method comprising the following steps:

[0006] Step 1: Obtain historical typhoon evolution characteristics and the physical attributes of the power grid lines to be evaluated. Generate multiple typhoon disaster scenarios through spatiotemporal evolution simulation. Combine the failure probability of each line under the corresponding wind speed to construct the extreme failure scenario set of the power grid line equipment under the typhoon disaster, which is denoted as the representative failure scenario set.

[0007] Step 2: Establish a power flow constraint model based on the power grid operation status, calculate the load loss and scenario occurrence risk corresponding to each fault scenario in the representative fault scenario set, and sort the fault scenarios in descending order according to the scenario occurrence risk, and select the scenario with the highest risk value as the representative extreme fault scenario.

[0008] Step 3: In the representative extreme fault scenario, match the preset operation resource constraints and construct multiple combinations of line equipment to be reinforced; simulate the reinforcement treatment of each of the line equipment combinations, update the power grid topology state, and recalculate the change in load loss and scenario risk of the power system after the reinforcement treatment.

[0009] Step 4: Based on the characteristics of the typhoon environment and the operating conditions, establish a multi-dimensional cost accounting system to calculate the comprehensive handling cost of each line equipment combination. Then, use the ratio of the change in the scenario risk to the comprehensive handling cost as the handling cost-effectiveness. Based on this, prioritize each line equipment combination and output a preferred list of key line combinations for reinforcement.

[0010] Furthermore, step 1 specifically includes:

[0011] Step 1-1: Calculate the actual wind speed at any point in space from the typhoon center using the improved Rankine typhoon circulation wind speed model;

[0012] Steps 1-2: The transmission lines in the power grid are discretized into multiple segments according to a preset length threshold, and the geographical coordinates of the center point of each segment are calculated using linear interpolation.

[0013] Steps 1-3: Calculate the spherical distance from the typhoon center to the center point of each transmission line segment, and use the improved Rankine typhoon circulation wind speed model to calculate the maximum wind speed at the center point of each transmission line segment during the typhoon's life cycle, thereby determining the overall failure probability of each transmission line.

[0014] Steps 1-4: A high-dimensional global scene pool is generated through Monte Carlo simulation. Based on the geometric similarity between scenes, a clustering algorithm is used to reduce the dimensionality of the global scene pool and output a representative set of fault scenes containing the probability of scene occurrence and line state vectors.

[0015] Furthermore, the improved Rankine typhoon circulation wind speed model is as follows:

[0016]

[0017] In the formula, R is the maximum wind speed of the typhoon; R is the radius of the eye; r is the distance from the calculation point to the center of the typhoon. This represents the current actual wind speed.

[0018] Furthermore, in steps 1-3, the formula for calculating the overall fault probability of each transmission line is as follows:

[0019]

[0020] In the formula, For a specific typhoon disaster scenario, the power line The probability of failure, The maximum wind speed designed to withstand the wind load of the line.

[0021] Furthermore, in steps 1-4, when reducing the dimensionality of the global scene pool, Hamming distance metric combined with K-means clustering algorithm is used:

[0022] The formula for the Hamming distance between any two fault scenarios is:

[0023]

[0024] In the formula, and These represent the routes in scene a and scene b, respectively. The 0-1 fault states, where L is the total number of lines. The Hamming distance between scene a and scene b;

[0025] The global scene pool is clustered into K clusters. From each cluster, the sample closest to the cluster center Hamming is selected as the representative fault scene. The probability of the scene occurring is the proportion of the number of samples in that cluster to the total number of samples.

[0026] Furthermore, step 2 calculates the load loss corresponding to each fault scenario, specifically including:

[0027] Step 2-1: Based on the line state vector under the fault scenario, disconnect and clear the physical admittance or susceptance parameters corresponding to the faulty transmission line, and correct the node susceptance matrix.

[0028] Step 2-2: With the objective function of minimizing the generator output cost within the system and the load reduction loss of the entire network, construct a DC optimal power flow model, namely the power flow constraint model, which takes into account line power flow constraints, Kirchhoff current node constraints, line transmission capacity constraints, generator output upper and lower limits constraints, and slack node phase angle constraints.

[0029] Steps 2-3: Solve the DC optimal power flow model to calculate the total active power load loss of the entire network under each fault scenario.

[0030] Furthermore, the objective function described in step 2-2 is:

[0031]

[0032] In the formula, These are the weighting coefficients; All are cost coefficients for the i-th generator; The active power output of the i-th generator; This represents the load loss at the k-th node. For generator sets; It is a set of nodes.

[0033] Furthermore, the formula for calculating the risk of the scenario occurring in step 2 is as follows:

[0034]

[0035] In the formula, This represents the risk value of the c-th failure scenario. This represents the probability of the c-th failure scenario occurring. This represents the total active power load loss of the power system corresponding to the c-th fault scenario. This represents a set of representative failure scenarios.

[0036] Furthermore, step 3 calculates the changes in load loss and scenario risk of the power system after the reinforcement treatment, specifically including:

[0037] Using the number of assigned construction teams as constraint variables, arbitrary combinations are performed on the set of faulty lines to obtain multiple sets of equipment combinations for the lines to be reinforced. ;

[0038] During the simulated reinforcement, the set The probability of line faults included in the set is forcibly adjusted to 0, and its operating state variable is forcibly restored to the normal state. For lines not included in the set... The faulty circuit within remains physically disconnected.

[0039] The power flow constraint model is updated using the corrected state data. The active load loss of each node after the treatment is obtained, and the total remaining active load loss of the power system after the hardening treatment is accumulated. The change in scenario risk caused by equipment hardening treatment is calculated using the following formula:

[0040]

[0041] In the formula, This represents the scenario risk value for the c-th failure scenario after reinforcement treatment is completed. This represents the risk value of the c-th failure scenario before reinforcement treatment. This represents the change in scenario risk for the c-th failure scenario. This represents a set of representative failure scenarios.

[0042] Furthermore, in the multi-dimensional cost accounting system of step 4, the comprehensive disposal cost includes material costs, labor costs, and additional costs for typhoon-specific operations. The calculation model is expressed as follows:

[0043]

[0044] In the formula, For material costs, For labor costs, Additional costs for typhoon-specific operations; The comprehensive handling cost for each line combination h;

[0045] The cost of materials Human resource costs Additional costs for typhoon-specific operations They are represented as follows:

[0046]

[0047]

[0048]

[0049] in,

[0050]

[0051] In the formula, This is a collection of equipment for the line to be reinforced. For line transmission capacity, for Number of internal lines The average transmission capacity of the line combination. The basic material unit price per unit of transmission capacity. This is a voltage level correction factor. The wind resistance coefficient of the line. This is a correction factor for the scale effect of batch processing; The basic working hours for single-line processing, This is the current line length. The average length of the line. For random disturbance coefficients; The number of personnel required for handling a single line. The hourly rate for the workers. This is the typhoon wind speed correction factor. This is a terrain correction factor for the work area; Additional costs are incurred for typhoon-specific operations on a single route. This is the working distance correction factor; the cost unit is 10,000 yuan.

[0052] Compared with the prior art, the significant advantages of this invention are:

[0053] (1) It can adapt to the "combined treatment" mode of multiple construction teams working simultaneously, breaking through the limitations of traditional single-point independent emergency repair. Existing technologies usually only plan for emergency repair or reinforcement of a single piece of equipment, without considering the complex combined effect of multiple equipment failures during typhoons. This invention is directly aimed at the actual engineering conditions of multiple construction teams working simultaneously, and can collaboratively evaluate the system-level technical performance response when multiple equipment are reinforced at the same time, significantly improving the practicality of decision-making and macro-coordination capabilities.

[0054] (2) This invention innovatively proposes a cross-disciplinary deep collaboration and risk quantification method for multi-dimensional data of "meteorology-topology-engineering economics", which significantly improves the accuracy of optimization. This invention deeply integrates the spatiotemporal evolution characteristics of the entire life cycle of typhoons (meteorological dimension), the physical constraints of the optimal DC power flow of the power grid (topology dimension), and the refined cost accounting system (engineering economic dimension). The meteorological field directly and collaboratively corrects the network node topology matrix, thereby driving the collaborative operation of the cost model, effectively solving the technical pain points of complex fault combinations and difficulty in accurate risk quantification under typhoon disasters.

[0055] (3) Considering the “spatial discretization segmentation” of long transmission lines, the realism of typhoon wind field simulation is significantly improved. Given that the length of large-scale cross-regional transmission lines is extremely long and the wind speed and direction of typhoons vary significantly at different parts of the line, this invention discretizes and divides the ultra-long line by setting a preset threshold (such as a 30km interval), and calculates the real-time maximum wind speed at the center of each segment using linear interpolation and the Haversine spherical distance formula. This effectively avoids the problem of distortion in failure rate analysis caused by the traditional method of “treating the entire long line as a single mass point”.

[0056] (4) A "multi-dimensional refined cost accounting system" was established to take into account the special environment of typhoon disasters, so as to ensure the economic rationality and cost-effectiveness of planning decisions. This invention does not simply pursue the stability of the grid structure at the technical level, but innovatively deconstructs the cost composition into material costs, labor costs, and additional costs for typhoon-specific operations. The model comprehensively incorporates physical parameters and working condition correction coefficients such as voltage level, wind resistance coefficient, scale effect of batch disposal, terrain conditions, real-time wind speed, and round-trip distance for emergency repairs, so that the final output of "disposal cost-effectiveness" has extremely strong engineering implementation value.

[0057] (5) Dynamically reduce the cost of power generation output and fully tilt the focus towards the emergency defense essence of "ensuring grid safety and reducing load loss". In solving the objective function of the DC optimal power flow model, this invention innovatively introduces weight coefficients applicable to emergency response scenarios. By reducing the consideration of the economic cost of conventional generator output, the defense model is fully focused on the core objective of "minimizing the load reduction loss of the entire grid", which is highly consistent with the primary emergency principle of "ensuring safety and power supply" when the power grid responds to extreme typhoon disasters.

[0058] (6) High-dimensional scenarios are effectively reduced using a clustering dimensionality reduction algorithm (Hamming distance + K-means), balancing computational efficiency with scenario representativeness. For the large-scale, massive, and uncertain fault combinations caused by typhoons, this invention first constructs a high-dimensional global scenario pool through Monte Carlo simulation, and then performs K-means clustering screening based on the Hamming distance of the line state vector features. While ensuring no extreme core scenarios (highest risk scenarios) are overlooked, the computational dimensionality is significantly reduced, guaranteeing the system's rapid online decision-making response speed.

[0059] The present invention will now be described in further detail with reference to the accompanying drawings. Attached Figure Description

[0060] Figure 1 This is a flowchart of the preferred method for strengthening critical power grid lines under typhoon disasters according to the present invention.

[0061] Figure 2 This is a schematic diagram of an IEEE-39 node test system in one embodiment. Detailed Implementation

[0062] To make the objectives, technical solutions, and advantages of this application clearer, the following detailed description is provided in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative and not intended to limit the scope of this application.

[0063] It should be noted that if the embodiments of the present invention involve descriptions such as "first" and "second," these descriptions are for descriptive purposes only and should not be construed as indicating or implying their relative importance or implicitly specifying the number of technical features indicated. Therefore, a feature defined with "first" and "second" may explicitly or implicitly include at least one of those features. Furthermore, the technical solutions of the various embodiments can be combined with each other, but this must be based on the ability of those skilled in the art to implement them. When the combination of technical solutions is contradictory or impossible to implement, it should be considered that such a combination of technical solutions does not exist and is not within the scope of protection claimed by the present invention.

[0064] In one embodiment, combined Figure 1 A method for optimizing reinforcement combinations for critical power grid lines under typhoon disasters is provided, the method comprising the following steps:

[0065] Step 1: Obtain historical typhoon evolution characteristics and the physical attributes of the power grid lines to be evaluated. Generate multiple typhoon disaster scenarios through spatiotemporal evolution simulation. Combine the failure probability of each line under the corresponding wind speed to construct the extreme failure scenario set of the power grid line equipment under the typhoon disaster, which is denoted as the representative failure scenario set.

[0066] Step 2: Establish a power flow constraint model based on the power grid operation status, calculate the load loss and scenario occurrence risk corresponding to each fault scenario in the representative fault scenario set, and sort the fault scenarios in descending order according to the scenario occurrence risk, and select the scenario with the highest risk value as the representative extreme fault scenario.

[0067] Step 3: In the representative extreme fault scenario, match the preset operation resource constraints and construct multiple combinations of line equipment to be reinforced; simulate the reinforcement treatment of each of the line equipment combinations, update the power grid topology state, and recalculate the change in load loss and scenario risk of the power system after the reinforcement treatment.

[0068] Step 4: Based on the characteristics of the typhoon environment and the operating conditions, establish a multi-dimensional cost accounting system to calculate the comprehensive handling cost of each line equipment combination. Then, use the ratio of the change in the scenario risk to the comprehensive handling cost as the handling cost-effectiveness. Based on this, prioritize each line equipment combination and output a preferred list of key line combinations for reinforcement.

[0069] Furthermore, in one embodiment, step 1 specifically includes:

[0070] Step 1-1: Calculate the actual wind speed at any point in space from the typhoon center using the improved Rankine typhoon circulation wind speed model;

[0071] Steps 1-2: The transmission lines in the power grid are discretized into multiple segments according to a preset length threshold, and the geographical coordinates of the center point of each segment are calculated using linear interpolation.

[0072] Here, because excessively long lines may lead to distorted fault analysis, each line is discretized.

[0073] Steps 1-3: Calculate the spherical distance from the typhoon center to the center point of each transmission line segment, and use the improved Rankine typhoon circulation wind speed model to calculate the maximum wind speed at the center point of each transmission line segment during the typhoon's life cycle, thereby determining the overall failure probability of each transmission line.

[0074] Steps 1-4: A high-dimensional global scene pool is generated through Monte Carlo simulation. Based on the geometric similarity between scenes, a clustering algorithm is used to reduce the dimensionality of the global scene pool and output a representative set of fault scenes containing the probability of scene occurrence and line state vectors.

[0075] Preferably, in some embodiments, the improved Rankine typhoon circulation wind speed model is as follows:

[0076]

[0077] In the formula, R is the maximum wind speed of the typhoon; R is the radius of the eye; r is the distance from the calculation point to the center of the typhoon. This represents the current actual wind speed.

[0078] Preferably, in some embodiments, the formula for calculating the overall fault probability of each transmission line in steps 1-3 is as follows:

[0079]

[0080] In the formula, For a specific typhoon disaster scenario, the power line The probability of failure, The maximum wind speed designed for the line (based on GB 50545-2010 "Design Code for 110kV~750kV Overhead Transmission Lines", taken as 24.66m / s with a return period of 30 years). , This refers to the collection of all power grid lines.

[0081] Here, each line The attributes include:

[0082]

[0083] In the formula, For line length, These are the longitudes of the starting and ending points, respectively. These are the latitudes of the starting and ending points, respectively. The maximum wind speed designed to withstand the wind load of the line.

[0084] Preferably, in some embodiments, step 1-2 discretizes each line, specifically including:

[0085] For each line Divided into equal intervals of 30km part:

[0086]

[0087] Calculate the first one using linear interpolation Segment center point coordinates:

[0088]

[0089] In the formula, , The first The latitude and longitude coordinates of the center point of the segment The lines are respectively The longitude of the starting and ending points, The lines are respectively The latitude of the starting and ending points, For the line The total number of segments.

[0090] Considering the full life cycle evolution characteristics of typhoons, from formation and development to maturity and weakening upon landfall, we set... These are representative typhoons, each corresponding to a different intensity level and spatial location. Each typhoon is represented by a quaternion: In the formula, Longitude of the typhoon center Latitude of the typhoon center At maximum wind speed, The radius of the eye of the storm.

[0091] Preferably, in some embodiments, steps 1-3 specifically include:

[0092] Calculation of line segment centers based on Haversine formula To the center of the typhoon spherical distance :

[0093]

[0094] In the formula, For the Earth's radius, The difference in latitude and longitude between two points after converting from degrees to radians;

[0095] The maximum wind speed at the center of each line segment was calculated based on the improved Rankine typhoon circulation wind speed model.

[0096]

[0097] In the formula, For the first Line under the influence of typhoon The Wind speed at the center point of the segment For the first The maximum wind speed of each typhoon For the first The radius of the eye of a typhoon. For the first Typhoon to the line The Spherical distance between the center points of the segments;

[0098] line The maximum wind speed is:

[0099]

[0100] Based on this, the power line under a certain typhoon disaster scenario is calculated. Failure probability .

[0101] For each typhoon conduct Monte Carlo simulation (total number of samples) ): No. In this simulation, a uniformly random number is generated for each line. ,when At that time, the line A malfunction occurred. Otherwise the line No malfunction occurred. ; This indicates a line fault condition.

[0102] Therefore, we obtain the first... Line fault vectors for each scenario: Global scene pool: .

[0103] Furthermore, in one embodiment, steps 1-4, when reducing the dimensionality of the global scene pool, employ a Hamming distance metric combined with a K-means clustering algorithm:

[0104] The formula for the Hamming distance between any two fault scenarios is:

[0105]

[0106] In the formula, and These represent the routes in scene a and scene b, respectively. The 0-1 fault states, where L is the total number of lines. The Hamming distance between scene a and scene b;

[0107] The global scene pool is clustered into K clusters. From each cluster, the sample closest to the cluster center Hamming is selected as the representative fault scene. The probability of the scene occurring is the proportion of the number of samples in that cluster to the total number of samples.

[0108] Preferably, in some embodiments, Clustering Cluster , minimize: ,in, For the first Class center;

[0109] From each category The sample closest to the center Hamming was selected as the representative scene. :

[0110]

[0111] The probability of a scenario occurring is the proportion of that type of sample to the total sample: ;

[0112] The final output is a set of representative failure scenarios. Corresponding probability and the line state vector for each scenario .

[0113] Furthermore, in one embodiment, step 2, calculating the load loss corresponding to each fault scenario, specifically includes:

[0114] Step 2-1: Based on the line state vector under the fault scenario, disconnect and clear the physical admittance or susceptance parameters corresponding to the faulty transmission line, and correct the node susceptance matrix.

[0115] Step 2-2: With the objective function of minimizing the generator output cost within the system and the load reduction loss of the entire network, construct a DC optimal power flow model, namely the power flow constraint model, which takes into account line power flow constraints, Kirchhoff current node constraints, line transmission capacity constraints, generator output upper and lower limits constraints, and slack node phase angle constraints.

[0116] Steps 2-3: Solve the DC optimal power flow model to calculate the total active power load loss of the entire network under each fault scenario.

[0117] Preferably, in some embodiments, step 2-1 specifically includes:

[0118] Calculate the load loss for a single fault scenario; Input: fault scenario Line state vector System raw parameters: number of nodes Number of lines Branch parameters Generator parameters, load parameters, slack line Reference power .

[0119] When there is no fault The order-order nodal susceptance matrix has diagonal and off-diagonal elements as follows:

[0120]

[0121] For the nodes connected to the faulty line, let:

[0122] ,

[0123] In the formula, , The diagonal elements are respectively equal to the nodes. , The sum of the susceptance of all connected lines. , For nodes , The non-diagonal elements between them are equal to the node. With nodes The negative value of the line susceptance between them. For the line ( The reactance of ) , These are the nodes after the fault. , The diagonal elements, , For the node after the fault , Non-diagonal elements between These are the elements of the original susceptance matrix under fault-free conditions. Faulty line Reactance, By defining a set of faulty lines, we can obtain the fault scenarios. The modified nodal susceptance matrix below The equivalent faulty line is physically disconnected.

[0124] Preferably, in some embodiments, the objective function in step 2-2 is:

[0125]

[0126] In the formula, These are the weighting coefficients; All are cost coefficients for the i-th generator; The active power output of the i-th generator; This represents the load loss at the k-th node. For generator sets; It is a set of nodes.

[0127] The constraints of the power flow constraint model include:

[0128] Power flow constraints:

[0129]

[0130] The active power flow of the line is proportional to the phase angle difference between its two ends;

[0131] In the formula, For the line The meritorious trend, For the line susceptivity, For line reactance, , They are nodes , voltage phase angle, For the line Reactive power flow (set to 0 in the DC optimal power flow model); Kirchhoff current node constraints;

[0132] For nodes Applying Kirchhoff's laws, we can obtain:

[0133]

[0134] In the formula, For fault scenarios Next node Net active power injection, For the line The positive trend on the frontier;

[0135] for The node network can be written in matrix form as follows:

[0136]

[0137] In the formula, It is a fault scenario The net active power injection phasor of the next node, For fault scenarios The corrected nodal susceptance matrix below, The node voltage phase angle vector;

[0138] Upper and lower limits of load loss constraints:

[0139]

[0140] In the formula, For the first The load loss of each node. For the first The baseline load of each node. It is the set of all load nodes in the power grid;

[0141] Line operation status constraints:

[0142]

[0143] In the formula, Variables are 0-1, representing nodes. Inter-line The running status, This indicates a line fault. This indicates that the line is normal. It is the set of all lines in the power grid;

[0144] Line capacity constraints:

[0145]

[0146] In the formula, For the line The maximum permissible active power;

[0147] Generator output constraints:

[0148]

[0149] In the formula, For the first Lower limit of active power output of the generator; For the first The maximum active power output of the generator; For generator sets;

[0150] Phase angle constraint at equilibrium node:

[0151]

[0152] In the formula, The phase angle is the reference node.

[0153] Furthermore, in one embodiment, the formula for calculating the risk of scenario occurrence in step 2 is:

[0154]

[0155] In the formula, This represents the risk value of the c-th failure scenario. This represents the probability of the c-th failure scenario occurring. This represents the total active power load loss of the power system corresponding to the c-th fault scenario. This represents a set of representative failure scenarios.

[0156] The formula for calculating the total active power load loss of the power system is as follows:

[0157]

[0158] In the formula, For the first In the scenario, the first The active load loss of each node.

[0159] Furthermore, in one embodiment, step 3, calculating the change in load loss and the change in scenario risk of the power system after the reinforcement treatment, specifically includes:

[0160] Step 3-1: Using the number of assigned construction teams as constraint variables, perform arbitrary simultaneous combinations on the set of faulty lines to obtain multiple sets of equipment combinations for the lines to be reinforced. ;

[0161] Here, the number of construction teams is set to... They set off from the warehouse carrying supplies and assembled along the faulty route. Simultaneously select any Each line of equipment undergoes reinforcement treatment; the combination of faulty lines treated in a single instance is denoted as a set. .

[0162] Step 3-2, during the simulated reinforcement, the assembly The probability of line faults included in the set is forcibly adjusted to 0, and its operating state variable is forcibly restored to the normal state. For lines not included in the set... The faulty circuit within remains physically disconnected.

[0163] Here, the collection The included line fault probability is forcibly corrected to 0, represented as:

[0164]

[0165] In the formula, For reinforced equipment; For the first time after emergency response Probability of equipment failure; The maximum value is the number of equipment combinations. ;

[0166] Constraints on the line operation status after reinforcement:

[0167]

[0168] This constraint means that the reinforced line is forced to return to normal operation, while the unreinforced faulty line remains unchanged. constant.

[0169] Step 3-3: Update the power flow constraint model using the corrected state data, solve for the active load loss of each node after the treatment, and sum them up to obtain the remaining total active load loss of the power system after the reinforcement treatment. Then, calculate the change in scenario risk caused by the equipment reinforcement treatment using the following formula:

[0170]

[0171] In the formula, This represents the scenario risk value for the c-th failure scenario after reinforcement treatment is completed. This represents the risk value of the c-th failure scenario before reinforcement treatment. This represents the change in scenario risk for the c-th failure scenario. This represents a set of representative failure scenarios.

[0172] Here, the risk value of the scenario after reinforcement is completed is:

[0173]

[0174] Among them, the total active power load loss of the power system after treatment The calculation formula is:

[0175]

[0176] In the formula, The first result calculated using the updated power flow constraint model In the scenario, the first The active load loss of each node.

[0177] Furthermore, in one embodiment, in the multi-dimensional cost accounting system of step 4, the comprehensive disposal cost includes material costs, labor costs, and additional costs for typhoon-specific operations, and the calculation model is expressed as follows:

[0178]

[0179] In the formula, For material costs, For labor costs, Additional costs for typhoon-specific operations; The comprehensive handling cost for each line combination h;

[0180] The cost of materials Human resource costs Additional costs for typhoon-specific operations They are represented as follows:

[0181]

[0182]

[0183]

[0184] in,

[0185]

[0186] In the formula, This is a collection of equipment for the line to be reinforced. For line transmission capacity, for Number of internal lines The average transmission capacity of the line combination. The basic material unit price per unit of transmission capacity. This is a voltage level correction factor. The wind resistance coefficient of the line. This is a correction factor for the scale effect of batch processing; The basic working hours for single-line processing, This is the current line length. The average length of the line. For random disturbance coefficients; The number of personnel required for handling a single line. The hourly rate for the workers. This is the typhoon wind speed correction factor. This is a terrain correction factor for the work area; Additional costs are incurred for typhoon-specific operations on a single route. This is the working distance correction factor; the cost unit is 10,000 yuan.

[0187] Furthermore, in one embodiment, step 4 outputs a preferred list of reinforcement combinations for critical power grid lines, specifically including:

[0188] The change in scenario risk is monetized according to a preset load value standard to obtain the monetized change in risk. ;

[0189] The following formula is used to calculate the cost-effectiveness of handling each line equipment combination. :

[0190] .

[0191] Calculate the cost-effectiveness of each reinforcement line equipment combination and sort them in descending order. The combination with the higher cost-effectiveness has the higher reinforcement priority. Based on this, output the preferred reinforcement list of critical line combinations.

[0192] In one embodiment, a preferred system for reinforcing critical power grid lines under typhoon disasters is provided, the system comprising:

[0193] The first module is used to: acquire historical typhoon evolution characteristics and the physical attributes of the power grid lines to be evaluated, generate multiple typhoon disaster scenarios through spatiotemporal evolution simulation, and construct a set of extreme fault scenarios for power grid line equipment under typhoon disasters by combining the fault probability of each line under the corresponding wind speed, which is denoted as the representative fault scenario set.

[0194] The second module is used to: establish a power flow constraint model based on the power grid operation status, calculate the load loss and scenario occurrence risk corresponding to each fault scenario in the representative fault scenario set, sort the fault scenarios in descending order according to the scenario occurrence risk, and select the scenario with the highest risk value as the representative extreme fault scenario.

[0195] The third module is used to: match preset operational resource constraints in the representative extreme fault scenarios, construct multiple combinations of line equipment to be reinforced; simulate reinforcement treatment for each of the line equipment combinations, update the power grid topology state, and recalculate the change in load loss and scenario risk of the power system after reinforcement treatment;

[0196] The fourth module is used to: establish a multi-dimensional cost accounting system based on the characteristics of the typhoon environment and the operating conditions to calculate the comprehensive handling cost of each line equipment combination; then use the ratio of the change in the scenario risk to the comprehensive handling cost as the handling cost-effectiveness; prioritize each line equipment combination accordingly; and output a preferred list of key line combinations for reinforcement.

[0197] Specific limitations regarding the optimal reinforcement combination system for critical power grid lines under typhoon disasters can be found in the limitations of the optimal reinforcement combination method for critical power grid lines under typhoon disasters mentioned above, and will not be repeated here. Each module in the aforementioned optimal reinforcement combination system for critical power grid lines under typhoon disasters can be implemented entirely or partially through software, hardware, or a combination thereof. These modules can be embedded in or independent of the processor in a computer device, or stored in the memory of a computer device as software, so that the processor can call and execute the corresponding operations of each module.

[0198] In one embodiment, a computer device is provided, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor, when executing the computer program, implements:

[0199] Step 1: Obtain historical typhoon evolution characteristics and the physical attributes of the power grid lines to be evaluated. Generate multiple typhoon disaster scenarios through spatiotemporal evolution simulation. Combine the failure probability of each line under the corresponding wind speed to construct the extreme failure scenario set of the power grid line equipment under the typhoon disaster, which is denoted as the representative failure scenario set.

[0200] Step 2: Establish a power flow constraint model based on the power grid operation status, calculate the load loss and scenario occurrence risk corresponding to each fault scenario in the representative fault scenario set, and sort the fault scenarios in descending order according to the scenario occurrence risk, and select the scenario with the highest risk value as the representative extreme fault scenario.

[0201] Step 3: In the representative extreme fault scenario, match the preset operation resource constraints and construct multiple combinations of line equipment to be reinforced; simulate the reinforcement treatment of each of the line equipment combinations, update the power grid topology state, and recalculate the change in load loss and scenario risk of the power system after the reinforcement treatment.

[0202] Step 4: Based on the characteristics of the typhoon environment and the operating conditions, establish a multi-dimensional cost accounting system to calculate the comprehensive handling cost of each line equipment combination. Then, use the ratio of the change in the scenario risk to the comprehensive handling cost as the handling cost-effectiveness. Based on this, prioritize each line equipment combination and output a preferred list of key line combinations for reinforcement.

[0203] For specific limitations on each step, please refer to the limitations on the optimal combination of reinforcement methods for critical power grid lines under typhoon disasters mentioned above, which will not be repeated here.

[0204] In one embodiment, a computer-readable storage medium is provided having a computer program stored thereon, the computer program being implemented when executed by a processor:

[0205] Step 1: Obtain historical typhoon evolution characteristics and the physical attributes of the power grid lines to be evaluated. Generate multiple typhoon disaster scenarios through spatiotemporal evolution simulation. Combine the failure probability of each line under the corresponding wind speed to construct the extreme failure scenario set of the power grid line equipment under the typhoon disaster, which is denoted as the representative failure scenario set.

[0206] Step 2: Establish a power flow constraint model based on the power grid operation status, calculate the load loss and scenario occurrence risk corresponding to each fault scenario in the representative fault scenario set, and sort the fault scenarios in descending order according to the scenario occurrence risk, and select the scenario with the highest risk value as the representative extreme fault scenario.

[0207] Step 3: In the representative extreme fault scenario, match the preset operation resource constraints and construct multiple combinations of line equipment to be reinforced; simulate the reinforcement treatment of each of the line equipment combinations, update the power grid topology state, and recalculate the change in load loss and scenario risk of the power system after the reinforcement treatment.

[0208] Step 4: Based on the characteristics of the typhoon environment and the operating conditions, establish a multi-dimensional cost accounting system to calculate the comprehensive handling cost of each line equipment combination. Then, use the ratio of the change in the scenario risk to the comprehensive handling cost as the handling cost-effectiveness. Based on this, prioritize each line equipment combination and output a preferred list of key line combinations for reinforcement.

[0209] For specific limitations on each step, please refer to the limitations on the optimal combination of reinforcement methods for critical power grid lines under typhoon disasters mentioned above, which will not be repeated here.

[0210] As a specific example, the invention is further illustrated in one embodiment.

[0211] The effectiveness of the proposed method for selecting key power grid equipment is verified using an improved IEEE 39-bus test system as an example. The power grid topology is as follows: Figure 2 As shown.

[0212] Assume that the power grid experiences partial equipment failure due to a typhoon. The power grid system comprises 39 nodes, 34 transmission lines, and 10 generators, including 29 PQ nodes, 9 PV nodes, and 1 balancing node (node ​​39). The system's base capacity is 100 MVA, the base voltage is 500 kV, the total system load is 6154.13 MW, and the power outage loss per unit time is 0.5 million yuan / MW.

[0213] The parameters of the transmission lines are shown in Table 1.

[0214] Table 1 Transmission Line Parameters

[0215] Line number Starting point node End point Length (km) Capacity (MVA) L1 1 2 275.5 600.0 L2 1 39 167.6 1000.0 L3 2 3 101.2 500.0 L4 2 25 57.6 500.0 L5 3 4 142.8 500.0 L6 3 18 89.1 500.0 L7 4 5 85.8 600.0 L8 4 14 86.5 500.0 L9 5 6 17.4 1200.0 L10 5 8 75.1 900.0 L11 6 7 61.7 900.0 L12 6 11 55.0 480.0 L13 7 8 30.8 900.0 L14 8 9 243.3 900.0 L15 9 39 167.6 900.0 L16 10 11 28.8 600.0 L17 10 13 28.8 600.0 L18 13 14 67.7 600.0 L19 14 15 142.8 600.0 L20 15 16 63.0 600.0 L21 16 17 59.7 600.0 L22 16 19 130.7 600.0 L23 16 21 90.5 600.0 L24 16 24 39.5 600.0 L25 17 18 55.0 600.0 L26 17 27 116.0 600.0 L27 21 22 93.8 900.0 L28 22 23 64.3 600.0 L29 23 24 234.6 600.0 L30 25 26 216.5 600.0 L31 26 27 98.5 600.0 L32 26 28 317.7 600.0 L33 26 29 418.9 600.0 L34 28 29 101.2 600.0

[0216] Considering the full life cycle evolution characteristics of typhoons, from formation and development to maturity and weakening upon landfall, four representative typhoons were selected, each corresponding to a different intensity level and spatial location, as shown in Table 2.

[0217] Table 2 Typhoon Disaster Parameters

[0218] Typhoon number Central latitude (°N) Central longitude (°W) Maximum wind speed (m / s) Eye radius (km) Intensity level 1 42.20 69.70 45 30 Strong typhoon level 2 42.35 70.60 55 20 Super Typhoon 3 42.55 70.80 48 25 Strong typhoon level 4 42.30 71.60 40 35 Typhoon level

[0219] Each typhoon underwent 1500 Monte Carlo simulations, resulting in a total sample size of 6000. K-means clustering based on Hamming distance was used to cluster the scenarios into 5 classes. The sample closest to the center Hamming distance from each class was selected as the representative scenario, and the probability of a scenario occurring was the proportion of samples in that class. The clustering results are shown in Table 3.

[0220] Table 3. Clustering results for representative scenarios

[0221] Scene Number Scenario Probability Number of faulty lines Faulty line number Load loss (MW) 1 0.251 7 L20, L21, L22, L23, L24, L33, L34 335.48 2 0.309 11 L6,L18,L19,L20,L21,L25,L26,L30,L31,L32,L33 898.71 3 0.192 10 L4,L6,L19,L20,L25,L26,L30,L31,L32,L33 898.00 4 0.107 6 L1, L3, L4, L11, L15, L18 9.77 5 0.141 7 L1, L2, L3, L6, L8, L10, L15 104.85

[0222] Calculations show that scenario 2 is the highest risk scenario, with a total of 11 faulty lines.

[0223] Cost parameters are set as follows: Material cost coefficient =0.05 million yuan / MVA =1.0, =1.2; Base working hours for labor costs =8 hours, each team has n=4 people working. =0.05 million yuan / person·h, additional cost for typhoon operations =20,000 yuan / hour =1.1.

[0224] The handling information for a single faulty line is shown in Table 4.

[0225] Table 4. Information on faulty lines in the highest-risk scenario

[0226] Ranking reinforce the line Recovery (MW) recover(%) disposal costs Cost-effectiveness 1 15-16 238.37 26.52 40.39 2.9508 2 14-15 235.93 26.25 40.63 2.9034 3 3-18 156.42 17.40 34.48 2.2681 4 25-26 139.00 15.47 40.96 1.6968 5 26-28 139.00 15.47 41.09 1.6912 6 26-29 139.00 15.47 42.40 1.6392 7 13-14 0.71 0.08 40.46 0.0088 8 16-17 0.00 0.00 40.29 0.0000 9 17-18 0.00 0.00 40.06 0.0000 10 17-27 0.00 0.00 40.55 0.0000

[0227] Considering the combined effect of emergency response to power grid lines during typhoon disasters and the repair capacity with a certain amount of material reserves, two construction teams were dispatched to simultaneously repair the two line combinations. The relevant information on the handling of the equipment combinations is shown in Table 5.

[0228] Table 5 Information on Line Combination Handling

[0229] Ranking reinforce the line Recovery (MW) recover(%) disposal costs Cost-effectiveness 1 3-18,15-16 475.58 52.92 71.13 3.3430 2 3-18,14-15 473.58 52.70 71.79 3.2985 3 15-16,25-26 458.16 50.98 77.39 2.9601 4 15-16,26-28 458.16 50.98 78.26 2.9270 5 14-15,25-26 456.16 50.76 78.44 2.9078 6 14-15,26-28 456.16 50.76 78.54 2.9038 7 15-16,26-29 458.16 50.98 78.91 2.9029 8 14-15,26-29 456.16 50.76 78.81 2.8941 9 25-26,26-27 419.76 46.71 78.25 2.6821 10 26-27,26-28 418.30 46.54 78.46 2.6656

[0230] The results show that, in the event of this typhoon disaster, the priority should be given to L20 and L6, rather than simply L20 and L19, which are ranked from highest to lowest cost-effectiveness.

[0231] In summary, the method of this invention, through its multi-team line reinforcement strategy, accurate load loss calculation, and cost-effectiveness calculation system that takes into account the characteristics of typhoon environments, has significant advantages in terms of adaptability, system recovery efficiency, and accuracy in selecting key equipment. It can effectively reduce power grid load loss under typhoon disasters, improve the cost-effectiveness of emergency response strategies, and ensure the power supply stability and rapid recovery capability of the power grid under typhoon disasters. This fully verifies the engineering practicality, effectiveness, and targeted emergency response of the method.

[0232] The foregoing has shown and described the basic principles, main features, and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The embodiments and descriptions in the specification are merely illustrative of the principles of the invention. Any modifications, equivalent substitutions, or improvements made within the spirit and principles of the present invention without departing from its spirit and scope should be included within the protection scope of the present invention.

Claims

1. A method for optimizing the reinforcement combination of critical power grid lines under typhoon disasters, characterized in that, The method includes the following steps: Step 1: Obtain historical typhoon evolution characteristics and the physical attributes of the power grid lines to be evaluated. Generate multiple typhoon disaster scenarios through spatiotemporal evolution simulation. Combine the failure probability of each line under the corresponding wind speed to construct the extreme failure scenario set of the power grid line equipment under the typhoon disaster, which is denoted as the representative failure scenario set. Step 2: Establish a power flow constraint model based on the power grid operation status, calculate the load loss and scenario occurrence risk corresponding to each fault scenario in the representative fault scenario set, and sort the fault scenarios in descending order according to the scenario occurrence risk, and select the scenario with the highest risk value as the representative extreme fault scenario. Step 3: In the representative extreme fault scenario, match the preset operation resource constraints and construct multiple combinations of line equipment to be reinforced; simulate the reinforcement treatment of each of the line equipment combinations, update the power grid topology state, and recalculate the change in load loss and scenario risk of the power system after the reinforcement treatment. Step 4: Based on the characteristics of the typhoon environment and the operating conditions, establish a multi-dimensional cost accounting system to calculate the comprehensive handling cost of each line equipment combination. Then, use the ratio of the change in the scenario risk to the comprehensive handling cost as the handling cost-effectiveness. Based on this, prioritize each line equipment combination and output a preferred list of key line combinations for reinforcement.

2. The method for optimizing the reinforcement combination of critical power grid lines under typhoon disasters according to claim 1, characterized in that, Step 1 specifically includes: Step 1-1: Calculate the actual wind speed at any point in space from the typhoon center using the improved Rankine typhoon circulation wind speed model; Steps 1-2: The transmission lines in the power grid are discretized into multiple segments according to a preset length threshold, and the geographical coordinates of the center point of each segment are calculated using linear interpolation. Steps 1-3: Calculate the spherical distance from the typhoon center to the center point of each transmission line segment, and use the improved Rankine typhoon circulation wind speed model to calculate the maximum wind speed at the center point of each transmission line segment during the typhoon's life cycle, thereby determining the overall failure probability of each transmission line. Steps 1-4: A high-dimensional global scene pool is generated through Monte Carlo simulation. Based on the geometric similarity between scenes, a clustering algorithm is used to reduce the dimensionality of the global scene pool and output a representative set of fault scenes containing the probability of scene occurrence and line state vectors.

3. The preferred method for strengthening critical power grid lines under typhoon disasters according to claim 2, characterized in that, The improved Rankine typhoon circulation wind speed model is as follows: In the formula, This is the maximum wind speed of the typhoon; The radius of the eye of the storm; To calculate the distance from the point of origin to the center of the typhoon, This represents the current actual wind speed.

4. The method for optimizing the reinforcement combination of critical power grid lines under typhoon disasters according to claim 2, characterized in that, In steps 1-3, the formula for calculating the overall fault probability of each transmission line is as follows: In the formula, For a specific typhoon disaster scenario, the power line The probability of failure, The maximum wind speed designed to withstand the wind load of the line.

5. The preferred method for strengthening critical power grid lines under typhoon disasters according to claim 2, characterized in that, Steps 1-4 involve reducing the dimensionality of the global scene pool using Hamming distance metric combined with the K-means clustering algorithm. The formula for the Hamming distance between any two fault scenarios is: In the formula, and These represent the routes in scene a and scene b, respectively. The 0-1 fault states, where L is the total number of lines. The Hamming distance between scene a and scene b; The global scene pool is clustered into K clusters. From each cluster, the sample closest to the cluster center Hamming is selected as the representative fault scene. The probability of the scene occurring is the proportion of the number of samples in that cluster to the total number of samples.

6. The method for optimizing the reinforcement combination of critical power grid lines under typhoon disasters according to claim 1, characterized in that, Step 2 calculates the load loss corresponding to each fault scenario, specifically including: Step 2-1: Based on the line state vector under the fault scenario, disconnect and clear the physical admittance or susceptance parameters corresponding to the faulty transmission line, and correct the node susceptance matrix. Step 2-2: With the objective function of minimizing the generator output cost within the system and the load reduction loss of the entire network, construct a DC optimal power flow model, namely the power flow constraint model, which takes into account line power flow constraints, Kirchhoff current node constraints, line transmission capacity constraints, generator output upper and lower limits constraints, and slack node phase angle constraints. Steps 2-3: Solve the DC optimal power flow model to calculate the total active power load loss of the entire network under each fault scenario.

7. The method for optimizing the reinforcement combination of critical power grid lines under typhoon disasters according to claim 6, characterized in that, The objective function mentioned in step 2-2 is: In the formula, These are the weighting coefficients; All are cost coefficients for the i-th generator; The active power output of the i-th generator; This represents the load loss at the k-th node. For generator sets; It is a set of nodes.

8. The preferred method for strengthening critical power grid lines under typhoon disasters according to claim 1, characterized in that, The formula for calculating the risk of the scenario in step 2 is: In the formula, This represents the risk value of the c-th failure scenario. This represents the probability of the c-th failure scenario occurring. This represents the total active power load loss of the power system corresponding to the c-th fault scenario. This represents a set of representative failure scenarios.

9. The method for optimizing the reinforcement combination of critical power grid lines under typhoon disasters according to claim 1, characterized in that, Step 3 calculates the changes in load loss and scenario risk of the power system after reinforcement treatment, specifically including: Using the number of assigned construction teams as constraint variables, arbitrary combinations are performed on the set of faulty lines to obtain multiple sets of equipment combinations for the lines to be reinforced. ; During the simulated reinforcement, the set The probability of line faults included in the set is forcibly adjusted to 0, and its operating state variable is forcibly restored to the normal state. For lines not included in the set... The faulty circuit within remains physically disconnected. The power flow constraint model is updated using the corrected state data. The active load loss of each node after the treatment is obtained, and the summation is used to obtain the remaining total active load loss of the power system after the hardening treatment. The change in scenario risk caused by equipment hardening treatment is calculated using the following formula: In the formula, This represents the scenario risk value for the c-th failure scenario after reinforcement treatment is completed. This represents the risk value of the c-th failure scenario before reinforcement treatment. This represents the change in scenario risk for the c-th failure scenario. This represents a set of representative failure scenarios.

10. The preferred method for strengthening critical power grid lines under typhoon disasters according to claim 1, characterized in that, In the multi-dimensional cost accounting system of step 4, the comprehensive disposal cost includes material costs, labor costs, and additional costs for typhoon-specific operations. The calculation model is expressed as follows: In the formula, For material costs, For labor costs, Additional costs for typhoon-specific operations; The comprehensive handling cost for each line combination h; The cost of materials Human resource costs Additional costs for typhoon-specific operations They are represented as follows: in, In the formula, This is a collection of equipment for the line to be reinforced. Let k be the line transmission capacity. Number of internal lines The average transmission capacity of the line combination. The basic material unit price per unit of transmission capacity. This is a voltage level correction factor. The wind resistance coefficient of the line. This is a correction factor for the scale effect of batch processing; The basic working hours for single-line processing, This is the current line length. The average length of the line. is the random disturbance coefficient; n is the number of personnel required for handling a single line. The hourly rate for the workers. This is the typhoon wind speed correction factor. This is a terrain correction factor for the work area; Additional costs are incurred for typhoon-specific operations on a single route. This is the working distance correction factor; the cost unit is 10,000 yuan.