A method, equipment, and medium for assessing peak-shaving of high-energy-consuming flexible loads in power distribution networks.
By constructing paired descriptions of peak-shaving execution paths and recovery paths, the problem of failing to balance process recoverability and distribution network safety constraints in existing technologies is solved, thus achieving accuracy and security in the assessment of peak-shaving for high-energy-consuming flexible loads.
Patent Information
- Application Number
- CN202611629616.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-21
- Publication Date
- 2026-11-17
AI Technical Summary
Existing assessment methods for high-energy-consuming flexible load peak shaving fail to effectively balance process recoverability, recovery power timing occupancy, and distribution network safety constraints, which may cause peak shaving schemes to exceed network boundaries during the recovery phase.
By constructing paired descriptions of peak shaving execution paths and recovery paths, and combining them with process state transition relationships, state transitions that meet the conditions are screened to form a joint evaluation record. Furthermore, by reducing the power change amplitude, adjusting the transition time, and replacing the recovery path, network conflicts are eliminated, and a peak shaving evaluation record is generated.
It improves the accuracy and safety of peak shaving assessment, reduces the risk of capacity overestimation caused by ignoring production process continuity, and enables paired descriptions of load adjustment and process recovery processes.
Smart Images

Figure CN123121599A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of power dispatching technology, and in particular to a method, equipment and medium for assessing peak load shaving of high-energy-consuming flexible loads in distribution networks. Background Technology
[0002] With the high proportion of new energy integration and the transformation of distribution network operation from unidirectional power supply to coordinated regulation of source, grid, and load, high-energy-consuming industrial loads, due to their large power scale, phased production processes, and time-adjustable characteristics of some process states, are gradually becoming important regulatory resources for demand response and distribution network peak shaving. Existing high-energy-consuming flexible load peak shaving assessment technologies typically combine historical load curves, equipment rated power, production plans, and distribution network power flow status to estimate the power that the load can increase or decrease within a given period, and determine the feasibility of peak shaving tasks through process constraints, duration constraints, and branch capacity constraints. As the data integration of energy management platforms, production control platforms, and distribution automation platforms improves, related assessment methods are beginning to evolve from static adjustable capacity statistics to a combination of process state identification, load path analysis, and network security verification, enabling high-energy-consuming loads to participate in peak shaving, power balancing, and new energy consumption without disrupting normal production processes and distribution network safety boundaries.
[0003] Existing technologies still have certain shortcomings. Some peak-shaving assessment methods mainly determine adjustable capacity based on the current operating power and the allowable power range of equipment, or only verify the single power change during the peak-shaving execution phase, without organizing the process state transition sequence, holding time, recovery interval, and recovery period into a complete path that can be continuously executed and return to a stable process state. Existing assessment methods usually handle load regulation capacity and distribution network security constraints separately, and do not adequately consider the newly added recovery power occupation after the peak-shaving task is completed, the recovery power occupation of historical peak-shaving tasks that have not yet been completed, and the superimposed impact of different recovery processes in the same network range and adjacent time periods. When the peak-shaving execution path and the recovery path are mapped to the distribution network, the recovery power may coincide with the subsequent peak-shaving power in the same branch or node at the same time period, causing the peak-shaving scheme that originally met the current power flow constraints to exceed the branch load boundary or node voltage boundary during the recovery phase. Summary of the Invention
[0004] In view of the aforementioned existing problems, the present invention is proposed.
[0005] Therefore, this invention provides a method for assessing the peak load of high-energy-consuming flexible loads in distribution networks to solve the problem that peak load assessment is difficult to balance process recoverability, recovery power timing occupancy, and distribution network safety constraints.
[0006] To solve the above-mentioned technical problems, the present invention provides the following technical solution: In a first aspect, the present invention provides a method for assessing high-energy-consuming flexible load peak shaving in a distribution network, comprising: acquiring load peak shaving data, distribution network operation data, and historical peak shaving records; determining the current process state, network association range, distribution network operation state, and historical recovery power occupancy according to the assessment time; extracting process state transition relationships and peak shaving duration to form a joint assessment record; based on the process state transition relationships in the joint assessment record, starting from the current process state, screening state transitions that meet power change conditions, holding time, and recovery intervals; constructing peak shaving execution paths according to the transition order; and tracing recovery paths that meet process recovery conditions for each process state traversed by the peak shaving execution path to form paired peak shaving path records; and comparing the states in the paired peak shaving path records. The power changes before and after the state transition, combined with the power change conditions and recovery period corresponding to the recovery path, determine the newly added recovery power occupation and recovery period. The newly added recovery power occupation and the historical recovery power occupation are merged according to the network association range and time sequence to form a recovery undertaking ledger. The peak shaving execution path and recovery path in the recovery undertaking ledger are mapped to the network association range. The network undertaking margin for each period is determined according to the distribution network operation status and the recovery power occupation is deducted. Network conflicts are eliminated by reducing the power change amplitude, adjusting the state transition time and replacing the recovery path to form a recoverable peak shaving core. The recoverable peak shaving core is divided according to the peak shaving duration. The upward adjustment capacity, downward adjustment capacity and the corresponding peak shaving execution path, recovery path and network location of the peak shaving capacity restriction are extracted to generate a peak shaving assessment record.
[0007] As a preferred embodiment of the high-energy-consuming flexible load peak-shaving assessment method for distribution networks described in this invention, the specific steps for forming a joint assessment record are as follows: The current process status is determined based on the load operation status and process status judgment conditions in the load peak shaving data. The process status transition relationship and peak shaving duration are extracted. Based on the load access location and the topological relationship in the distribution network operation data, the network association range affected by the power change of high energy-consuming flexible load is determined. The distribution network operation status of the network association range at the evaluation time is extracted. The network operation boundary is constructed based on the branch allowable load range and node allowable voltage range in the distribution network operation data. The historical peak-shaving records are used to screen out recovery processes that have not yet been completed at the time of assessment. Based on the planned recovery amount, the completed recovery amount, and the remaining recovery period of the recovery process, the historical recovery power occupancy for the subsequent assessment period is determined to form a joint assessment record.
[0008] As a preferred embodiment of the high-energy-consuming flexible load peak-shaving assessment method for distribution networks described in this invention, the specific steps for forming paired peak-shaving path records are as follows: Extract the power change conditions, holding time and recovery interval corresponding to each state transition from the process state transition relationship, and determine the candidate state transition starting from the current process state. Verify the power change before and after the candidate state transition, the duration of the process state involved, and the time interval between adjacent candidate state transitions. Retain the state transitions that meet the requirements of each verification, and connect them according to the order of state transitions to form the peak shaving execution path. For each process state traversed by the peak shaving execution path, trace the state transitions that meet the process recovery conditions along the process state transition relationship, and connect them according to the order of state transitions to form a recovery path. Delete peak shaving execution paths that cannot form a recovery path due to any process state, and write the retained peak shaving execution paths and corresponding recovery paths into a pair of peak shaving path records.
[0009] As a preferred embodiment of the high-energy-consuming flexible load peak-shaving assessment method for distribution networks described in this invention, the specific steps for determining the newly added restored power occupancy and restoration time period are as follows: According to the state transition sequence of the peak shaving execution path, compare the load power of each process state with the load power corresponding to the process state before peak shaving execution, and combine the duration of each process state to determine the accumulated power to be restored formed by each state transition. The power to be restored is allocated within the power change conditions corresponding to each state transition according to the state transition sequence. The power to be restored in each recovery period is determined by limiting the end time of the allocation through the recovery period. The power to be restored in each recovery period is then determined as the newly added power to be restored.
[0010] As a preferred embodiment of the high-energy-consuming flexible load peak-shaving assessment method for distribution networks described in this invention, the specific steps for forming the recovery undertaking ledger are as follows: The newly added recovery power occupancy and the historical recovery power occupancy are respectively mapped to the network association range. The continuous time intervals are divided according to the start and end times of the recovery period corresponding to the newly added recovery power occupancy and the historical recovery power occupancy. The recovery power occupancy acting on the same network association range in each continuous time interval is determined. The newly added recovery power usage and historical recovery power usage within the same network association range and the same continuous time interval are accumulated. The recovery power usage with different network association ranges and recovery periods that do not overlap is retained. The corresponding recovery power usage is no longer included in the continuous time interval after the recovery period ends. The paired peak-shaving path records and recovery periods corresponding to each recovery power usage are retained to form a recovery undertaking ledger.
[0011] As a preferred embodiment of the high-energy-consuming flexible load peak-shaving assessment method for distribution networks described in this invention, the specific steps for determining the network capacity capacity for each time period and deducting the recovery power usage are as follows: According to the time periods of each state transition in the peak shaving execution path and recovery path, the corresponding power changes are mapped to the load access location. The branch power flow changes and node voltage changes caused by the power changes are tracked along the network association range, and the correspondence between each state transition, the affected network location and the affected time period is established. Based on the distribution network operation status and network operation boundary, determine the branch load margin and node voltage margin of each affected network location, and convert them into the allowable power variation range of the load access location. The network capacity margin for the corresponding time period is determined by the power variation range corresponding to each affected network location, and the correspondence between the network capacity margin and the affected network location is retained. Based on the network association scope and recovery period in the recovery ledger, the recovery power occupancy is mapped to the affected network location, and the recovery power occupancy is deducted from the network capacity reserve of the affected network location within the corresponding recovery period to determine the remaining network capacity reserve of each affected network location in each period.
[0012] As a preferred embodiment of the high-energy-consuming flexible load peak-shaving assessment method for distribution networks described in this invention, the specific steps for forming a recoverable peak-shaving core are as follows: Along the state transition sequence of the peak shaving execution path and the recovery path, the power change amplitude of each state transition is compared with the remaining network capacity at the same time and network location. When the power change amplitude exceeds the remaining network capacity, the peak shaving execution path, recovery path, state transition time and network location corresponding to the network conflict are determined according to the correspondence between the remaining network capacity and the affected network location. To address network conflicts arising during the peak shaving execution phase, the power change amplitude of the corresponding state transition is reduced. For network conflicts arising from the overlap of path power change and recovery power occupation time periods, the state transition time is adjusted under the conditions of holding time, recovery interval and recovery period. For network conflicts that still exist during the recovery phase, recovery paths that meet the process recovery conditions and have different recovery periods are replaced along the process state transition relationship. The adjusted peak shaving execution path and recovery path are remapped to the network association range. The remaining network capacity for each time period is re-determined and network conflicts are identified. Peak shaving execution paths, recovery paths and corresponding power change ranges that do not have network conflicts in both the peak shaving execution phase and the recovery phase are included in the recoverable peak shaving core, and paired peak shaving paths that still have network conflicts are removed.
[0013] As a preferred embodiment of the high-energy-consuming flexible load peak-shaving assessment method for distribution networks described in this invention, the generation of peak-shaving assessment records includes: Based on the continuous maintenance duration of each peak shaving execution path in the recoverable peak shaving core, peak shaving execution paths with a continuous maintenance duration of not less than the corresponding peak shaving duration are selected according to the peak shaving duration, and the corresponding recovery path, power change range and remaining network capacity in each time period are retained. According to the direction of load power increase and load power decrease, the selected power change ranges are compared respectively. The maximum power increase that can be sustained for each peak shaving duration is determined as the upward adjustment capability, and the maximum power decrease that can be sustained is determined as the downward adjustment capability. For the peak shaving execution path and recovery path corresponding to the upward and downward adjustment capabilities, the network location with the smallest allowable power change amplitude is tracked along the network association range and used as the network location that limits the corresponding peak shaving capability. The peak shaving duration, upward adjustment capability, downward adjustment capability, peak shaving execution path, recovery path and network location that limits the peak shaving capability are associated to generate a peak shaving assessment record.
[0014] In a second aspect, the present invention provides a computer device, including a memory and a processor, wherein the memory stores a computer program, wherein when the computer program is executed by the processor, it implements any step of the high-energy-consuming flexible load peak-shaving assessment method for distribution networks as described in the first aspect of the present invention.
[0015] Thirdly, the present invention provides a computer-readable storage medium having a computer program stored thereon, wherein: when the computer program is executed by a processor, it implements any step of the high-energy-consuming flexible load peak-shaving assessment method for distribution networks as described in the first aspect of the present invention.
[0016] The beneficial effects of this invention are as follows: By constructing peak-shaving execution paths based on process state transition relationships and synchronously tracing recovery paths that meet recovery conditions for each process state, a paired description of the load adjustment process, state maintenance requirements, and post-peak-shaving process recovery process is achieved. This ensures that peak-shaving capacity is no longer limited to instantaneous power change judgments, reducing the risk of overestimating capacity due to neglecting production process continuity relationships. By merging newly added recovery power occupancy with historical recovery power occupancy according to network association range and time sequence, and combining the network capacity margin for each time period, the power amplitude of peak-shaving execution paths and recovery paths is reduced, transition times are adjusted, and recovery paths are replaced. This achieves joint identification and elimination of network conflicts during the peak-shaving and recovery phases, improving the accuracy of peak-shaving assessment, execution security, and result traceability. Attached Figure Description
[0017] To more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the following description of the embodiments will be briefly introduced. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0018] Figure 1 This is a flowchart of the assessment method for peak shaving of high-energy-consuming flexible loads in distribution networks.
[0019] Figure 2 This diagram illustrates the paired peak-shaving paths and the recovery power occupancy.
[0020] Figure 3 A schematic diagram illustrating the linkage between the restored ledger and the network's remaining capacity.
[0021] Figure 4 This is a schematic diagram for assessing network conflict resolution and peak shaving capabilities. Detailed Implementation
[0022] To make the above-mentioned objects, features and advantages of the present invention more apparent and understandable, the specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings.
[0023] Many specific details are set forth in the following description in order to provide a full understanding of the invention. However, the invention may also be practiced in other ways different from those described herein, and those skilled in the art can make similar extensions without departing from the spirit of the invention. Therefore, the invention is not limited to the specific embodiments disclosed below.
[0024] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure, or characteristic that may be included in at least one implementation of the present invention. The phrase "in one embodiment" appearing in different places in this specification does not necessarily refer to the same embodiment, nor is it a single or selective embodiment that is mutually exclusive with other embodiments.
[0025] Reference Figures 1-4 As one embodiment of the present invention, this embodiment provides a method for assessing peak-shaving of high-energy-consuming flexible loads in a distribution network, comprising the following steps: S1. Obtain load peak shaving data, distribution network operation data and historical peak shaving records, and determine the current process status, network association range, distribution network operation status and historical recovery power occupancy according to the assessment time. Extract the process status transition relationship and peak shaving duration to form a joint assessment record.
[0026] S1.1 Determine the current process status based on the load operation status and process status judgment conditions in the load peak shaving data, extract the process status transition relationship and peak shaving duration, and determine the network association range affected by the power change of high energy consumption flexible loads based on the load access location and the topological relationship in the distribution network operation data. Extract the distribution network operation status of the network association range at the evaluation time, and construct the network operation boundary based on the branch allowable load range and node allowable voltage range in the distribution network operation data.
[0027] It should be noted that the load peak shaving data is obtained from the production control platform and energy management platform corresponding to the high-energy-consuming flexible load. This includes load power, equipment operating parameters, production progress, process control instructions, load access location, load power corresponding to each process state, process state determination conditions, process state transition relationships, and peak shaving duration with the data acquisition time. The process state determination conditions record the range of equipment operating parameters, production progress range, and process control instructions corresponding to different process states. The process state transition relationships record the allowed transition directions between each process state, as well as the power change conditions, holding time, recovery interval, process recovery conditions, and recovery period corresponding to each state transition. The peak shaving duration is determined by the duration recorded in the peak shaving task and the time domain to be evaluated, and can be set to one or more duration levels.
[0028] Specifically, based on the evaluation time, the equipment operating parameters, production progress, and process control instructions corresponding to the load operation status are extracted and matched with the process status determination conditions. The process status that meets all the conditions is determined as the current process status. When the high-energy-consuming flexible load is undergoing a state transition, the current process status is determined according to the state transition indicated by the process control instructions, the start time of the transition, and the progress of the completed transition, and the state transition that is being performed is retained.
[0029] Distribution network operation data is obtained from distribution automation platforms, electricity consumption information collection platforms, and equipment operation archives. This includes distribution network topology, switch status, branch power flow, node voltage, branch allowable load range, node allowable voltage range, and network response samples. The network response samples record the direction and magnitude of power change of high-energy-consuming flexible loads under the corresponding distribution network topology and switch status, as well as the power flow change of each branch and the voltage change of each node before and after the power change. Starting from the load access location, feeders, transformers, buses, branches, and nodes are traced along the actual power supply path according to the switch status at the evaluation time. The network locations that can accept the power change of high-energy-consuming flexible loads and generate branch power flow changes and node voltage changes are determined as the network association range.
[0030] The power flow and switching status of each branch within the network association range at the assessment time, as well as the node voltage of each node at the assessment time, are extracted from the distribution network operation data to form the distribution network operation status. The allowable load range of the branch and the allowable voltage range of the node are respectively mapped to the branch and node within the network association range to construct the network operation boundary. The allowable load range of the branch is determined in combination with the rated capacity of the branch, the current operating mode and the derating status of the equipment, and the allowable voltage range of the node is determined in combination with the corresponding voltage level and voltage control requirements.
[0031] S1.2. Screen the recovery processes that have not yet been completed at the time of evaluation from the historical peak shaving records. Determine the historical recovery power occupancy for the subsequent evaluation period based on the planned recovery amount, the completed recovery amount and the remaining recovery period of the recovery process, and form a joint evaluation record.
[0032] It should be noted that historical peak shaving records are obtained from the energy management platform and peak shaving task execution records, including the load identifier corresponding to the historical peak shaving task, peak shaving execution period, planned restoration amount, restoration power direction, restoration period, restoration period, actual restoration power, and restoration completion status; the planned restoration amount represents the amount of electricity required for high-energy-consuming flexible loads to restore to their pre-peak shaving operating state according to the corresponding process after the historical peak shaving task ends.
[0033] Specifically, using the assessment time as the screening criterion, historical peak shaving records with an incomplete recovery status and a recovery period later than the assessment time are selected; the completed recovery amount is determined based on the actual recovery power and corresponding duration already executed during the recovery phase; the difference between the planned recovery amount and the completed recovery amount is determined as the remaining recovery amount; and the time range between the recovery period and the assessment time is determined as the remaining recovery period.
[0034] The remaining recovery period is divided into subsequent assessment periods according to the time interval used in the peak shaving assessment. Based on the recovery period arrangement in the historical peak shaving records, the remaining recovery amount is allocated to the corresponding subsequent assessment period, and the recovery power is determined in combination with the duration of each subsequent assessment period. The recovery power and the direction of the recovery power are determined as the historical recovery power occupancy of the corresponding subsequent assessment period. At the same time, the load identifier, recovery period, remaining recovery amount and recovery period corresponding to the historical recovery power occupancy are retained. When there are multiple incomplete recovery processes, the historical recovery power occupancy corresponding to each recovery process is determined separately and is not accumulated in this step.
[0035] The current process status, process status transition relationships, peak shaving duration, network association range, distribution network operation status, network operation boundary, and historical recovery power occupancy are associated according to the assessment time to form a joint assessment record.
[0036] S2. Based on the process state transition relationship in the joint evaluation record, starting from the current process state, screen the state transitions that meet the power change conditions, holding time and recovery interval, construct the peak shaving execution path according to the transition order, and trace the recovery path that meets the process recovery conditions for each process state passed through by the peak shaving execution path to form a pair of peak shaving path records.
[0037] S2.1 Extract the power change conditions, holding time and recovery interval corresponding to each state transition from the process state transition relationship, and determine the candidate state transitions starting from the current process state. Verify the power change before and after the candidate state transition, the duration of the process state involved, and the time interval between adjacent candidate state transitions. Retain the state transitions that meet the requirements of each verification, and connect them according to the order of state transitions to form the peak shaving execution path.
[0038] It should be noted that the current process status, process status transition relationship, load operation status and peak shaving duration are read from the joint assessment record. The current process status is used as the starting process status to find the state transition that can be transferred from the current process status to other process statuses. Then, the search continues to find the state transition that can be taken over by the reached process status, forming candidate state transitions within the coverage of the peak shaving duration.
[0039] For each candidate state transition, the direction and magnitude of power change before and after the transition are determined based on the load power corresponding to the initial process state and the arrival process state, and compared with the corresponding power change conditions; the duration of the initial process state before the evaluation time is determined based on the load operation state, and compared with the corresponding holding time in combination with the arrangement duration of the arrival process state in the candidate state transition; the time interval is determined based on the end time and start time of adjacent candidate state transitions, and compared with the recovery interval corresponding to the next candidate state transition.
[0040] State transitions that meet the power change conditions in terms of direction and magnitude, duration of process states, and time interval between adjacent state transitions are considered to be in accordance with the recovery interval. These transitions are then connected sequentially according to the starting process state, the arriving process state, and the order of occurrence to form a peak-shaving execution path starting from the current process state. When multiple transition directions meet the requirements, corresponding peak-shaving execution paths are formed, and the process states traversed by each peak-shaving execution path, the load power corresponding to each process state, the state transition time, the state duration, and the power change are recorded.
[0041] S2.2 For each process state traversed by the peak shaving execution path, trace the state transitions that meet the process recovery conditions along the process state transition relationship, and connect them according to the order of state transitions to form a recovery path. Delete peak shaving execution paths that cannot form a recovery path due to any process state, and write the retained peak shaving execution paths and corresponding recovery paths into the peak shaving path record.
[0042] It should be noted that, according to the state transition order in the peak shaving execution path, each process state traversed by the peak shaving execution path is extracted sequentially, and each process state is used as the recovery traceability starting point; based on the process state transition relationship, the state transition that can transition from the corresponding process state to the sustainable operation process state is found, and the equipment operating parameters, production progress and process control requirements corresponding to the state transition are compared with the process recovery conditions, and the state transition that meets the process recovery conditions is retained.
[0043] The process state that has been retained as the starting point for recovery tracing is used to repeatedly search for process state transitions that meet the process recovery conditions and can be successively accepted until the process state before peak shaving is executed, or the process state that can continue to operate according to the original production process is reached; the process state, the process state, and the order of acceptance of each process state transition are connected to form the recovery path of the corresponding process state, and the process state, the order of state transition, and the recovery period are recorded.
[0044] Each process state traversed by the peak shaving execution path is checked to ensure that a corresponding recovery path is formed. If no recovery path that meets the process recovery conditions exists for any process state, the peak shaving execution path traversing the corresponding process state is deleted. If a recovery path can be formed for each process state, the peak shaving execution path is retained, and each process state traversed by the peak shaving execution path is associated with a recovery path formed from the corresponding process state, and written into a pair of peak shaving path records. The pair of peak shaving path records also retain the entry time and duration of each process state in the peak shaving execution path, which are used to determine the process state corresponding to the end of peak shaving and its associated recovery path when evaluating according to the peak shaving duration.
[0045] S3. Compare the power changes before and after each state transition in the paired peak-shaving path records. Combine the power change conditions and recovery period corresponding to the recovery path to determine the newly added recovery power occupation and recovery period. Merge the newly added recovery power occupation with the historical recovery power occupation according to the network association range and time order to form a recovery undertaking ledger.
[0046] S3.1 According to the state transition sequence of the peak shaving execution path, compare the load power of each process state with the load power corresponding to the process state before peak shaving execution, and determine the power to be restored accumulated by each state transition in combination with the duration of each process state.
[0047] It should be noted that the process states traversed by the peak shaving execution path, the load power corresponding to each process state, the state duration, and the state transition sequence are extracted from the paired peak shaving path records, and the load power corresponding to the process state before peak shaving execution is used as the power comparison benchmark.
[0048] For each peak shaving duration, the actual process states experienced during the peak shaving duration are determined along the peak shaving execution path according to the state transition order at the self-assessment time. When the original duration of a process state is entirely within the peak shaving duration, the original duration is determined as the actual duration. When the end time of the peak shaving duration is within the duration of a certain process state, the time between entering that process state and the end time of the peak shaving duration is determined as the actual duration of that process state.
[0049] For each process state actually experienced during the corresponding peak shaving duration, the power difference between the corresponding load power and the power comparison benchmark is determined. When the load power is higher than the power comparison benchmark, the power difference is recorded as a positive value, and when the load power is lower than the power comparison benchmark, the power difference is recorded as a negative value.
[0050] The expression for calculating the cumulative power offset is: ; in, Indicates the peak shaving execution path The cumulative power offset generated during the current peak shaving period Indicates the peak shaving execution path within the current peak shaving duration. Number of process states passed through Indicates the peak shaving execution path The load power corresponding to the process state before peak shaving execution; Indicates the peak shaving execution path The Middle The load power corresponding to each process state Indicates the peak shaving execution path The Middle The actual duration of each process state within the current peak shaving duration.
[0051] When the same process state appears multiple times in the peak shaving execution path, it is counted according to the load power after entering the process state each time and the actual duration within the corresponding peak shaving duration. When the power difference direction corresponding to different process states is the same, it is accumulated through the same-sign item; when the power difference direction is opposite, it is deducted through the opposite-sign item.
[0052] When the cumulative power offset is less than zero, it means that the power consumption was reduced during the peak shaving period compared to the process state before the peak shaving. The absolute value of the cumulative power offset is determined as the power to be restored that needs to be restored by increasing the load power. When the cumulative power offset is greater than zero, it means that the power consumption was increased during the peak shaving period. The cumulative power offset is determined as the power to be restored that needs to be restored by reducing the load power. When the cumulative power offset is equal to zero, no new power to be restored is generated.
[0053] The power to be restored is associated with the corresponding peak shaving duration, peak shaving execution path, process status that generates the power to be restored, actual status duration, and power restoration direction.
[0054] S3.2. Along the state transition sequence of the recovery path, allocate the power to be restored within the power change condition limit corresponding to each state transition, and determine the restoration power of each recovery period by limiting the end time of allocation through the restoration period, and determine the restoration power of each recovery period as the newly added restoration power occupancy.
[0055] It should be noted that, based on the peak shaving duration and peak shaving execution path associated with the power to be restored, the process state of the peak shaving execution path at the end of the corresponding peak shaving duration is determined, and the recovery path associated with the process state is extracted from the paired peak shaving path records. The order of occurrence of each state transition, power change conditions, and recovery period in the recovery path are read. The moment when the recovery path can be entered after the end of the corresponding peak shaving duration is taken as the recovery starting point. The recovery period is divided according to the evaluation time interval, and the recovery period that can be covered by each state transition and whose end time is no later than the recovery period is determined according to the state transition order of the recovery path.
[0056] The direction of power restoration is determined based on the cumulative power offset. When the cumulative power offset is less than zero, the direction of increasing load power is determined as the direction of power restoration; when the cumulative power offset is greater than zero, the direction of decreasing load power is determined as the direction of power restoration. Based on the power change conditions corresponding to the state transitions in each restoration period, the allowable power restoration amplitude along the power restoration direction for each restoration period is determined.
[0057] The expression for calculating the recovery power allocated during the recovery period is: ; in, Indicates the peak shaving execution path Recovery path corresponding to the process state at the end of the current peak shaving duration. In the The recovery power allocated to each recovery period. Indicates the peak shaving execution path The amount of electricity to be restored during the current peak shaving period Indicates the recovery path In the The allowable recovery power amplitude for each recovery period corresponding to the state transition. Indicates the recovery path In the The duration of each recovery period, Indicates the recovery path The number of recovery periods that can be used to restore power distribution within the recovery period. Indicates the recovery path In the The recovery power amplitude during each recovery period.
[0058] The denominator of the formula represents the total restored power that the recovery path can handle within the recovery period. When the total restored power is not less than the power to be restored, the power to be restored is allocated according to the proportion of the allowable restoration power amplitude in each recovery period to the total restoration capacity of the recovery path, so that the sum of the restored power allocated in each recovery period equals the power to be restored. When the power to be restored is zero, no restoration power allocation is performed; when the power to be restored is greater than zero and the total restoration capacity corresponding to the recovery path is greater than zero, restoration power is allocated according to the expression.
[0059] When the total restored electricity that the recovery path can handle within the recovery period is less than the electricity to be restored, it is determined that the corresponding recovery path cannot complete the allocation of the electricity to be restored formed during the peak shaving duration. The combination of the corresponding peak shaving execution path and the peak shaving duration is marked as not meeting the recovery requirements and is not included in the subsequent peak shaving capacity assessment for the corresponding peak shaving duration.
[0060] The recovery power, recovery power direction, recovery period, corresponding peak shaving duration, peak shaving execution path, recovery path and recovery period allocated for each recovery period are associated to form the newly added recovery power occupancy.
[0061] S3.3. Assign the newly added recovery power usage and the historical recovery power usage to the network association range respectively. Divide the continuous time intervals according to the start and end times of the recovery period corresponding to the newly added recovery power usage and the historical recovery power usage, and determine the recovery power usage that acts on the same network association range in each continuous time interval.
[0062] It should be noted that, based on the newly added restored power occupancy and corresponding paired peak-shaving path records of the completed power allocation, the load access location of high-energy-consuming flexible loads is extracted, and the network association range corresponding to the load access location is found from the joint assessment record. The newly added restored power occupancy is then mapped to the network association range. Based on the load identifiers retained in the historical restored power occupancy, the load access location of the corresponding high-energy-consuming flexible load is found from the joint assessment record, and the network association range corresponding to the historical restored power occupancy is determined based on the load access location. The newly added restored power occupancy formed by different peak-shaving execution paths or different peak-shaving durations is processed separately and is not accumulated in the same restored power occupancy result.
[0063] For the current peak shaving execution path and its corresponding peak shaving duration, extract the start and end times of the recovery periods corresponding to the newly added recovery power occupancy and the historical recovery power occupancy. Arrange the different start and end times in chronological order and divide the time range between adjacent times into continuous time intervals. When the recovery period of the recovery power occupancy spans multiple continuous time intervals, assign the corresponding recovery power occupancy to each of the continuous time intervals it spans, but keep the recovery power, recovery power direction and network association range unchanged.
[0064] For each continuous time interval, the newly added recovery power usage and historical recovery power usage that cover the recovery period are filtered, and corresponding to the network association range are determined to determine the recovery power usage that simultaneously affects the same network association range within the continuous time interval.
[0065] S3.4. Accumulate the newly added recovery power usage and historical recovery power usage within the same network association range and the same continuous time interval, and retain the recovery power usage with different network association ranges and recovery periods that do not overlap. In the continuous time interval after the end of the recovery period, the corresponding recovery power usage will no longer be included, and the paired peak-shaving path records and recovery periods corresponding to each recovery power usage will be retained to form a recovery undertaking ledger.
[0066] It should be noted that, for the current peak shaving execution path and corresponding peak shaving duration, the newly added recovery power occupancy and historical recovery power occupancy are processed according to the order of continuous time intervals. For recovery power occupancy that acts on the same network association range and whose recovery period covers the same continuous time interval, the corresponding recovery power is accumulated according to the recovery power direction, and the load access location, recovery power source, recovery path, and recovery period corresponding to each recovery power occupancy that constitutes the accumulated result are retained. When the recovery power direction is opposite, the accumulated results of different directions are retained to avoid direct cancellation before analyzing branch power flow changes and node voltage changes. New recovery power occupancy formed by different peak shaving execution paths or different peak shaving durations is not added to the current processing result. The accumulated results in the recovery undertaking ledger are used to characterize the recovery task occupancy of the corresponding network association range and continuous time interval. The details of each recovery power occupancy are retained, and the subsequent network impact is calculated separately according to their respective load access locations.
[0067] For recovery power usage affecting different network association ranges, it is recorded separately according to the corresponding network association range; for recovery power usage that does not overlap during recovery periods, it is recorded separately according to the continuous time intervals it covers, without accumulating across time intervals; if the start time of the current continuous time interval is not earlier than the end time of a certain recovery power usage, that recovery power usage will no longer be counted from the current continuous time interval, so that each continuous time interval only retains the recovery tasks that still need to be executed.
[0068] The recovery power occupancy formed by each network association range in each continuous time interval is associated with the corresponding load access location, recovery power direction, recovery time period and recovery period; for newly added recovery power occupancy, the corresponding peak shaving duration and paired peak shaving path record are retained at the same time; for historical recovery power occupancy, the corresponding historical peak shaving task identifier is retained; the above contents are arranged according to the current paired peak shaving path, network association range and continuous time interval to form a recovery undertaking ledger.
[0069] S4. Map the peak shaving execution path and recovery path in the recovery undertaking ledger to the network association range. Determine the network undertaking capacity of each time period based on the distribution network operation status and deduct the recovery power occupation. Eliminate network conflicts by reducing the power change range, adjusting the state transition time and replacing the recovery path to form a recoverable peak shaving core. Divide the recoverable peak shaving core according to the peak shaving duration. Extract the upward adjustment capacity, downward adjustment capacity and the corresponding peak shaving execution path, recovery path and network location that limits the peak shaving capacity, and generate a peak shaving assessment record.
[0070] S4.1 According to the time periods of each state transition in the peak shaving execution path and recovery path, map the corresponding power changes to the load access location, track the branch power flow changes and node voltage changes caused by power changes along the network association range, and establish the correspondence between each state transition, the location of the affected network, and the time period of the impact.
[0071] It should be noted that the peak shaving execution path, recovery path, and the occurrence time and power change corresponding to each state transition are extracted from the recovery and acceptance ledger, and the load access location, network association range, distribution network operation status and network response samples are read from the joint assessment record.
[0072] Network response samples record the historical power change direction and magnitude of high-energy-consuming flexible loads under the corresponding distribution network topology and switching states, as well as the power flow changes of each branch and the voltage changes of each node before and after the power change. Network response samples are screened according to the distribution network topology and switching states at the evaluation time, and network response sample sets are formed according to the direction of load power increase and load power decrease, respectively, and network response samples with zero load power change magnitude are filtered out.
[0073] The expression for calculating the response coefficients of a directional network is: ; in, Indicates the load connection location along the direction of power variation. Location of affected network when unit power changes The resulting changes in operating volume; This represents a set of network response samples that match the distribution network topology, switching states, and power change direction at the time of evaluation. Represents network response samples Medium and high energy-consuming flexible loads along the power variation direction The magnitude of the power change that occurred; Indicates the corresponding network response sample Affected network locations Changes in operating volume.
[0074] When the affected network location is a branch, the change in operating volume represents the change in branch power flow; when the affected network location is a node, the change in operating volume represents the change in node voltage. A positive value for the directional network response coefficient indicates that the operating volume at the affected network location increases after the load connection location changes along the corresponding direction; a negative value for the directional network response coefficient indicates that the corresponding operating volume decreases.
[0075] According to the time period of each state transition, the load power of the corresponding process state is mapped to the load access location; the load power corresponding to the process state before peak shaving is used as the network verification power benchmark, and the net power offset between the load power of the corresponding process state after the state transition and the network verification power benchmark is determined. The direction and magnitude of the net power offset are used as the power change of the state transition in the corresponding period of influence. The net power offset magnitude is combined with the directional network response coefficient of the corresponding direction to determine the power flow change of each branch and the voltage change of each node.
[0076] Branches and nodes that are associated with the load access location and have changes in operating volume are identified as affected network locations. The state transition, affected period, affected network location, directional network response coefficient and changes in operating volume are associated to establish a corresponding relationship. The recovery path adopts the same method, using the load power corresponding to the process state before peak shaving as the network verification power benchmark, and determining the net power offset of the corresponding affected period based on the load power of each process state during the recovery process.
[0077] S4.2. Based on the operating status of the distribution network and the network operating boundary, determine the branch load margin and node voltage margin of each affected network location, and convert them into the allowable power variation range of the load access location. The network capacity margin for the corresponding time period is jointly limited by the power variation range corresponding to each affected network location, and the correspondence between the network capacity margin and the affected network location is retained.
[0078] It should be noted that, based on the correspondence between each state transition, the location of the affected network, and the affected time period, the baseline operating quantity, directional network response coefficient, and corresponding network operating boundary for the affected network location within each affected time period are extracted. When the affected network location is a branch, the branch power flow is used as the baseline operating quantity, and the allowable load range of the branch is used as the allowable range of the corresponding operating quantity; when the affected network location is a node, the node voltage is used as the baseline operating quantity, and the allowable voltage range of the node is used as the allowable range of the corresponding operating quantity.
[0079] The expression for calculating the allowable power variation at each affected network location and the overall network capacity margin is as follows: ; in, Indicates the affected network location During the period of impact and the direction of power change Below, the power range that allows the load connection location to continue to change; This indicates all affected network locations during the affected period. and the direction of power change The network capacity is sufficient; Indicates the period of influence Inner edge power change direction The set of network locations affected Indicates the affected network location During the period of impact The baseline operating volume, And indicates the affected network location. The upper boundary of the corresponding runtime, Indicates the affected network location The lower boundary of the corresponding runtime.
[0080] When the directional network response coefficient is greater than zero, the allowable power change range is determined based on the difference between the baseline operating quantity and the upper operating boundary. When the directional network response coefficient is less than zero, the difference between the baseline operating quantity and the lower operating boundary is obtained, and the allowable power change range is determined based on the absolute value of the ratio of the current difference to the directional network response coefficient. When the directional network response coefficient is equal to zero, it means that the power change along the corresponding direction at the load access location will not cause an identifiable change in the operating quantity at that network location, and the network location is not included in the comparison of the network capacity capacity in the corresponding direction.
[0081] Calculate the allowable power change range for each affected branch and each affected node, then compare the allowable power change ranges for each affected network location under the same period of influence and the same direction of power change, and determine the minimum power change range as the network capacity margin for the corresponding period.
[0082] The allowable power variation range for each affected network location, the overall network capacity margin, the affected network locations that form the network capacity margin boundary, the affected time period, and the direction of power variation are retained.
[0083] S4.3 According to the network association scope and recovery period in the recovery ledger, the recovery power occupancy is mapped to the affected network location, and the recovery power occupancy is deducted from the network capacity reserve of the affected network location within the corresponding recovery period to determine the remaining network capacity reserve of each affected network location in each period.
[0084] It should be noted that, for the current paired peak-shaving paths, the network association range, recovery power occupancy, recovery power direction, load access location, recovery power occupancy source, and recovery period corresponding to each continuous time interval are extracted from the recovery undertaking ledger. Based on the topological correspondence between the network association range and the affected network location, the branches and nodes affected by each recovery power occupancy are determined. When the network association range corresponding to the recovery power occupancy only overlaps with some of the affected network locations, the network impact of the corresponding recovery power is analyzed only for the overlapping affected network locations.
[0085] For the recovery power occupancy originating from historical peak shaving tasks, the directional network response coefficients of the load access location to each affected network location under the corresponding power change direction are extracted based on the corresponding load access location, recovery power direction, and network association range. The historical recovery power occupancy is then combined with the corresponding directional network response coefficients to determine the power flow change and voltage change generated by each historical recovery process in the affected branch and the affected node, respectively. When multiple historical recovery processes act on the same affected network location within the same continuous time interval, the power flow change or voltage change is superimposed according to the change direction of the corresponding operating quantity, instead of directly adding or subtracting the recovery power values corresponding to different load access locations.
[0086] The power flow changes or voltage changes generated during the historical recovery process in each continuous time interval are superimposed onto the baseline operating volume of the corresponding affected network location. The operating margin after deducting the historical recovery task occupation is determined based on the difference between the superimposed operating volume and the network operating boundary. Then, based on the directional network response coefficient of the load access location corresponding to the current paired peak-shaving path, the operating margin is converted into the allowable residual power change amplitude along the corresponding power change direction of the load access location. The remaining network capacity capacity of each affected network location in the corresponding continuous time interval is determined.
[0087] It should also be noted that the newly added recovery power occupancy associated with the current paired peak shaving path in the recovery ledger is used to characterize the recovery power and recovery period required for the subsequent recovery phase of the current peak shaving execution path, and is not deducted repeatedly in this step as the network occupancy already existing when assessing the current paired peak shaving path; the network impact of the recovery process corresponding to the current paired peak shaving path is included when performing network conflict verification along the recovery path; the remaining network capacity is associated with the location of the affected network, continuous time interval, power change direction, corresponding historical recovery power occupancy, and recovery period.
[0088] S4.4. Along the state transition sequence of the peak shaving execution path and the recovery path, compare the power change amplitude of each state transition with the remaining network capacity at the same time and network location. When the power change amplitude exceeds the remaining network capacity, determine the peak shaving execution path, recovery path, state transition time and network location corresponding to the network conflict based on the correspondence between the remaining network capacity and the affected network location.
[0089] It should be noted that, according to the order of state transitions in the peak shaving execution path and recovery path, the state transition time and duration corresponding to each state transition are extracted. The load power corresponding to the process state before peak shaving is used as the network verification power benchmark. The net power offset direction and net power offset magnitude formed by the process state after the state transition within the corresponding impact period are determined. The net power offset magnitude is used as the power change magnitude for network capacity verification of the corresponding state transition. Based on the correspondence between each state transition, the location of the affected network, and the impact period, the branches and nodes affected by the corresponding power change are determined. When the duration of the state transition spans multiple continuous time intervals, comparisons are made separately for each continuous time interval to ensure that the remaining network capacity used for comparison is consistent with the recovery power occupancy of the corresponding period.
[0090] For each affected network location, the direction of net power offset is correlated with the direction of power change in the remaining network capacity. When the remaining network capacity is greater than zero, the net power offset amplitude is compared with the remaining network capacity corresponding to the same affected network location within the same continuous time interval. When the net power offset amplitude does not exceed the remaining network capacity, it is determined that there is no network conflict at that network location for the corresponding process state. When the net power offset amplitude exceeds the remaining network capacity, the excess portion is determined as the capacity gap at the corresponding network location. When the remaining network capacity is not greater than zero, it is determined that there is a network conflict at that network location for the corresponding power change.
[0091] Based on the attribution of the state transition of the network conflict in the paired peak shaving path records, the network conflicts generated during the peak shaving execution phase and the recovery phase are distinguished, and the corresponding peak shaving execution path, recovery path, state transition time, conflict duration and affected network location are traced. At the same time, the corresponding power change magnitude, remaining network capacity and capacity gap are retained. When a state transition generates network conflicts at multiple affected network locations, the conflict results of each network location are retained respectively.
[0092] S4.5. For network conflicts generated during the peak shaving execution phase, reduce the power change amplitude of the corresponding state transition. For network conflicts caused by the overlap of path power change and recovery power occupation time periods, adjust the state transition time under the conditions of holding time, recovery interval and recovery period. For network conflicts that still exist in the recovery phase, replace the recovery path that meets the process recovery conditions and has a different recovery period along the process state transition relationship.
[0093] It should be noted that, for network conflicts generated during the peak shaving execution phase, the state transition, power change direction, power change amplitude, conflict duration, affected network location, and remaining network capacity are extracted. Based on the power change amplitude that each conflict location can handle in the corresponding time period, the power change amplitude corresponding to the state transition is reduced, ensuring that the adjusted power change amplitude is within the corresponding power change condition limit and does not exceed the remaining network capacity of each conflict location in the same power change direction. When reducing the power change amplitude, the state transition direction, process state acceptance order, and state transition time remain unchanged, and the load power corresponding to each process state after the state transition is updated synchronously. Based on the updated load power and state duration, the cumulative power offset is recalculated, the power to be restored and the direction of power restoration are redefined, and the power to be restored is redistributed according to the allowed power restoration amplitude in each restoration period, and the newly added power restoration occupancy in each restoration period is updated.
[0094] For network conflicts arising from the overlap of path power changes and historical recovery power occupancy in the recovery undertaking ledger within the same affected network location and the same continuous time interval, adjustable time periods are searched before and after the original state transition time. The duration of the initial process state is compared with the holding time to determine the time range within which the state transition can be brought forward. Based on the time interval between the current state transition and adjacent state transitions, the recovery interval, and the state transition undertaking order, the time range within which the state transition can be delayed is determined. Finally, the end time of the state transition in the recovery path is limited by the recovery period.
[0095] The state transition is moved to a period that does not overlap with the corresponding recovery power occupancy and where the remaining network capacity can accommodate the corresponding power change. The duration of the state constrained by the state transition relationship is adjusted accordingly, while keeping the order of state transitions in the peak shaving execution path and the recovery path unchanged. The cumulative power offset is recalculated based on the adjusted state duration, and the power to be restored is redistributed according to the adjusted recovery start point, recovery period, and allowable recovery power amplitude. The newly added recovery power occupancy in each recovery period is updated.
[0096] For network conflicts that persist after the power change amplitude has been reduced and the state transition time has been adjusted during the recovery phase, the starting process state of the recovery path that caused the conflict is taken as the starting point for tracing. Other state transition combinations that can reach the same recovery target process state are found from the process state transition relationship. The process recovery conditions, power change conditions, holding time, recovery interval and recovery period corresponding to other state transition combinations are verified. State transition combinations that can complete the power allocation to be restored and whose recovery period does not overlap with the conflict period are retained. Alternative recovery paths are formed according to the state transition succession order.
[0097] The alternative recovery path is re-associated with the corresponding peak-shaving execution path, and the recovery power, recovery power usage, and recovery period are updated for each recovery period.
[0098] S4.6 Remap the adjusted peak shaving execution path and recovery path to the network association range, redetermine the remaining network capacity for each time period and identify network conflicts, include the peak shaving execution path, recovery path and corresponding power change range that have no network conflicts in both the peak shaving execution phase and the recovery phase into the recoverable peak shaving core, and remove the paired peak shaving paths that still have network conflicts.
[0099] It should be noted that the adjusted peak-shaving execution path, recovery path, state transition sequence, state transition time, power change amplitude, and recovery power occupancy are extracted. Based on the occurrence time of each state transition, the power changes are re-corresponded to the load access location, and the branches, nodes, and affected time periods of the power changes are re-determined along the network's associated range. When the state transition time is adjusted, the continuous time interval is re-corresponded according to the adjusted occurrence time period; when the recovery path is replaced, the recovery power occupancy for each recovery time period is re-determined according to the alternative recovery path.
[0100] Based on the adjusted state transition power change direction and affected time period, the directional network response coefficients of the corresponding directions are invoked to redetermine the branch power flow changes and node voltage changes caused by each state transition. Then, based on the baseline operating volume, network operating boundary, and directional network response coefficients of each affected network location, the network capacity margins in the direction of load power increase and load power decrease are redetermined. According to the historical recovery power occupancy and its corresponding network impact in the recovery capacity ledger that is unrelated to the current paired peak shaving path, the remaining network capacity margins of each affected network location in each continuous time interval are redetermined. The newly added recovery power occupancy after the current paired peak shaving path update continues to be associated with the corresponding recovery path, and its executability is determined through network conflict verification of the recovery path.
[0101] If any state transition exceeds the remaining network capacity of the affected network location during the corresponding time period, the corresponding peak shaving execution path and recovery path are marked as having network conflicts and removed from the paired peak shaving path records. If there are no network conflicts in either the peak shaving execution phase or the recovery phase, the power change conditions corresponding to each state transition are overlapped with the allowable power change range of each affected network location to determine the power change range that can be executed for the corresponding state transition, and the power change range corresponding to the peak shaving execution path is formed along the state transition sequence.
[0102] The peak shaving execution path without network conflict, the corresponding recovery path, the state transition time, the power change range, the recovery period, and the remaining network capacity in each time period are associated and included in the recoverable peak shaving core.
[0103] S4.7. Based on the continuous maintenance duration of each peak-shaving execution path in the recoverable peak-shaving core, select peak-shaving execution paths with a continuous maintenance duration of not less than the corresponding peak-shaving duration according to the peak-shaving duration, and retain the corresponding recovery path, power change range and remaining network capacity for each time period.
[0104] It should be noted that, according to the state transition sequence of each peak-shaving execution path, the start time, end time, power change direction, and power change range of each process state are extracted, and the time range between adjacent state transitions is determined as the maintenance period of the corresponding process state; the power change range corresponding to the process state is overlapped with the remaining network capacity of each affected network location within the same maintenance period to determine the power change range that can be continuously executed within the maintenance period.
[0105] When the power change direction of adjacent maintenance periods is consistent and the power change range that can be continuously executed overlaps, the adjacent maintenance periods are continuously connected, and the overlapping part of the power change range of each maintenance period is determined as the power change range that can be continuously maintained during the connection; when the power change direction changes and there is no common power change range between adjacent maintenance periods, the current connection is terminated; the continuous maintenance duration of the peak shaving execution path is determined according to the start time and end time of the continuous connection.
[0106] For each peak shaving duration, peak shaving execution paths with a continuous maintenance duration of not less than the peak shaving duration and a continuously maintained power change range that is not empty are selected, and the corresponding process status at the end of the peak shaving duration is determined. Recovery paths associated with this process status and for which the power allocation to be restored has been completed are extracted from the paired peak shaving path records. The correspondence between the recovery paths and the peak shaving execution paths is verified, while retaining the power change range during the continuous maintenance period and the remaining network capacity corresponding to each time period and each affected network location. Peak shaving execution paths with a continuous maintenance duration of less than the peak shaving duration are not included in the capacity assessment for the corresponding peak shaving duration.
[0107] S4.8. According to the direction of load power increase and load power decrease, compare the selected power change ranges respectively, and determine the maximum power increase that can be sustained for each peak shaving duration as the upward adjustment capability, and determine the maximum power decrease that can be sustained as the downward adjustment capability.
[0108] It should be noted that the selected peak-shaving execution paths are grouped according to their peak-shaving duration, and the power change range that each peak-shaving execution path can continuously maintain within the corresponding peak-shaving duration is extracted. The portion of the power change range that is greater than zero is classified into the direction of increasing load power, and the corresponding positive value is determined as the power increase magnitude; the portion of the power change range that is less than zero is classified into the direction of decreasing load power, and the absolute value of the corresponding negative value is determined as the power decrease magnitude; when the same power change range contains both positive and negative values, it is split into two power change ranges in two directions with zero as the boundary.
[0109] For the same peak shaving duration, determine the power increase that can be continuously maintained in the direction of increasing load power and the power decrease that can be continuously maintained in the direction of decreasing load power for each peak shaving execution path; compare the power increase corresponding to each peak shaving execution path, and determine the largest power increase as the upward adjustment capability for the peak shaving duration; compare the power decrease corresponding to each peak shaving execution path, and determine the largest power decrease as the downward adjustment capability for the peak shaving duration.
[0110] The upward and downward adjustment capabilities are respectively associated with the peak shaving execution path, recovery path, power change range, and remaining network capacity in each time period to achieve the corresponding capabilities; when multiple peak shaving execution paths form the same upward or downward adjustment capability, all corresponding paths are retained and not merged in this step.
[0111] S4.9 For the peak shaving execution path and recovery path corresponding to the upward and downward adjustment capabilities, track the network location with the smallest allowable power change along the network association range, and use it as the network location that limits the corresponding peak shaving capability. Then associate the peak shaving duration, upward adjustment capability, downward adjustment capability, peak shaving execution path, recovery path and the network location that limits the peak shaving capability to generate a peak shaving assessment record.
[0112] It should be noted that the peak shaving execution path, recovery path, state transition period, power change direction, and remaining network capacity of each affected network location are extracted for each peak shaving duration, corresponding to the upward and downward adjustment capacity. According to the state transition sequence of the peak shaving execution path and recovery path, branches and nodes are traced step by step from the load access location along the network association range, and the allowable increase and decrease in power change of the load access location during the corresponding state transition period for each affected network location is determined.
[0113] For the upward adjustment capability, compare the allowable power increase at each affected network location when the load power increases during the peak shaving execution phase, and combine the allowable power change in the corresponding direction of each state transition during the recovery phase to determine the power change range that can fully absorb the upward adjustment execution and recovery processes; for the downward adjustment capability, compare the allowable power change in the direction of load power reduction in the same way, and verify the network absorption status in the corresponding power change direction during the recovery phase.
[0114] The affected network location with the smallest allowable power change during the entire peak shaving process is determined as the network location that limits the corresponding peak shaving capacity. The state transition period during which the limitation occurs, the direction of the limitation, the branch load margin, and the node voltage margin are retained. When multiple affected network locations form the same limitation range, the corresponding network locations are retained respectively.
[0115] Based on the duration of peak shaving, the upward and downward adjustment capabilities are associated with the corresponding peak shaving execution path, recovery path, network location limiting peak shaving capabilities, and the time period during which the limitation occurs, respectively, to generate a peak shaving assessment record.
[0116] This embodiment also provides a computer device applicable to the assessment method of high energy consumption flexible load peak shaving in distribution networks, including: a memory and a processor; the memory is used to store computer-executable instructions, and the processor is used to execute the computer-executable instructions to realize the assessment method of high energy consumption flexible load peak shaving in distribution networks as proposed in the above embodiment.
[0117] The computer device can be a terminal, comprising a processor, memory, communication interface, display screen, and input devices connected via a system bus. The processor provides computing and control capabilities. The memory includes non-volatile storage media and internal memory. The non-volatile storage media stores the operating system and computer programs. The internal memory provides an environment for the operation of the operating system and computer programs stored in the non-volatile storage media. The communication interface is used for wired or wireless communication with external terminals; wireless communication can be achieved through Wi-Fi, carrier networks, NFC (Near Field Communication), or other technologies. The display screen can be an LCD screen or an e-ink screen. The input devices can be a touch layer covering the display screen, buttons, a trackball, or a touchpad on the computer device's casing, or an external keyboard, touchpad, or mouse.
[0118] This embodiment also provides a storage medium storing a computer program. When executed by a processor, the program implements the method for assessing high-energy-consuming flexible load peak shaving in a distribution network as proposed in the above embodiments. The storage medium can be implemented by any type of volatile or non-volatile storage device or a combination thereof, such as Static Random Access Memory (SRAM), Electrically Erasable Programmable Read-Only Memory (EEPROM), Erasable Programmable Read Only Memory (EPROM), Programmable Read-Only Memory (PROM), Read-Only Memory (ROM), magnetic storage, flash memory, magnetic disk, or optical disk.
[0119] In summary, this invention constructs peak-shaving execution paths based on process state transition relationships and synchronously traces recovery paths that meet recovery conditions for each process state. This achieves paired descriptions of the load adjustment process, state maintenance requirements, and post-peak-shaving process recovery process, ensuring that peak-shaving capacity is no longer limited to instantaneous power changes and reducing the risk of overestimating capacity due to neglecting production process continuity. By merging newly added recovery power occupancy with historical recovery power occupancy according to network association range and time sequence, and combining this with network capacity margin in each time period, the invention performs power amplitude contraction, transition time adjustment, and recovery path replacement on peak-shaving execution paths and recovery paths. This enables joint identification and elimination of network conflicts during the peak-shaving and recovery phases, improving the accuracy of peak-shaving assessment, execution security, and result traceability.
[0120] It should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and are not intended to limit it. Although the present invention has been described in detail with reference to preferred embodiments, those skilled in the art should understand that modifications or equivalent substitutions can be made to the technical solutions of the present invention without departing from the spirit and scope of the technical solutions of the present invention, and all such modifications or substitutions should be covered within the scope of the claims of the present invention.
Claims
1. A method for assessing peak-shaving of high-energy-consuming flexible loads in a distribution network, characterized in that, include: Obtain load peak shaving data, distribution network operation data and historical peak shaving records, and determine the current process status, network association range, distribution network operation status and historical recovery power occupancy according to the assessment time, extract process status transition relationships and peak shaving duration, and form a joint assessment record; Based on the process state transition relationship in the joint evaluation record, starting from the current process state, we screen the state transitions that meet the power change conditions, holding time and recovery interval, construct the peak shaving execution path according to the transition order, and trace the recovery path that meets the process recovery conditions for each process state traversed by the peak shaving execution path to form a pair of peak shaving path records. By comparing the power changes before and after each state transition in the paired peak-shaving path records, and combining the power change conditions and recovery period corresponding to the recovery path, the newly added recovery power occupation and recovery period are determined. The newly added recovery power occupation and the historical recovery power occupation are merged according to the network association range and time order to form a recovery undertaking ledger. Map the peak shaving execution paths and recovery paths in the recovery ledger to the network association range, determine the network capacity of each time period based on the distribution network operation status and deduct the recovery power occupation, eliminate network conflicts by reducing the power change range, adjusting the state transition time and replacing the recovery path, form a recoverable peak shaving core, divide the recoverable peak shaving core according to the peak shaving duration, extract the upward adjustment capacity, downward adjustment capacity and the corresponding peak shaving execution path, recovery path and network location of the peak shaving capacity limitation, and generate a peak shaving assessment record.
2. The method for assessing peak-shaving of high-energy-consuming flexible loads in a distribution network as described in claim 1, characterized in that, The specific steps for forming the joint evaluation record are as follows: The current process status is determined based on the load operation status and process status judgment conditions in the load peak shaving data. The process status transition relationship and peak shaving duration are extracted. Based on the load access location and the topological relationship in the distribution network operation data, the network association range affected by the power change of high energy-consuming flexible load is determined. The distribution network operation status of the network association range at the evaluation time is extracted. The network operation boundary is constructed based on the branch allowable load range and node allowable voltage range in the distribution network operation data. The historical peak-shaving records are used to screen out recovery processes that have not yet been completed at the time of assessment. Based on the planned recovery amount, the completed recovery amount, and the remaining recovery period of the recovery process, the historical recovery power occupancy for the subsequent assessment period is determined to form a joint assessment record.
3. The method for assessing peak-shaving of high-energy-consuming flexible loads in a distribution network as described in claim 2, characterized in that, The specific steps for forming paired peak-shaving path records are as follows: Extract the power change conditions, holding time and recovery interval corresponding to each state transition from the process state transition relationship, and determine the candidate state transition starting from the current process state. Verify the power change before and after the candidate state transition, the duration of the process state involved, and the time interval between adjacent candidate state transitions. Retain the state transitions that meet the requirements of each verification, and connect them according to the order of state transitions to form the peak shaving execution path. For each process state traversed by the peak shaving execution path, trace the state transitions that meet the process recovery conditions along the process state transition relationship, and connect them according to the order of state transitions to form a recovery path. Delete peak shaving execution paths that cannot form a recovery path due to any process state, and write the retained peak shaving execution paths and corresponding recovery paths into a pair of peak shaving path records.
4. The method for assessing peak-shaving of high-energy-consuming flexible loads in a distribution network as described in claim 3, characterized in that, The specific steps for determining the newly added recovery power usage and recovery period are as follows: According to the state transition sequence of the peak shaving execution path, compare the load power of each process state with the load power corresponding to the process state before peak shaving execution, and combine the duration of each process state to determine the accumulated power to be restored formed by each state transition. The power to be restored is allocated within the power change conditions corresponding to each state transition according to the state transition sequence. The power to be restored in each recovery period is determined by limiting the end time of the allocation through the recovery period. The power to be restored in each recovery period is then determined as the newly added power to be restored.
5. The method for assessing peak-shaving of high-energy-consuming flexible loads in a distribution network as described in claim 4, characterized in that, The specific steps for forming the restored ledger are as follows: The newly added recovery power occupancy and the historical recovery power occupancy are respectively mapped to the network association range. The continuous time intervals are divided according to the start and end times of the recovery period corresponding to the newly added recovery power occupancy and the historical recovery power occupancy. The recovery power occupancy acting on the same network association range in each continuous time interval is determined. The newly added recovery power usage and historical recovery power usage within the same network association range and the same continuous time interval are accumulated. The recovery power usage with different network association ranges and recovery periods that do not overlap is retained. The corresponding recovery power usage is no longer included in the continuous time interval after the recovery period ends. The paired peak-shaving path records and recovery periods corresponding to each recovery power usage are retained to form a recovery undertaking ledger.
6. The method for assessing peak-shaving of high-energy-consuming flexible loads in a distribution network as described in claim 5, characterized in that, The specific steps for determining the network capacity margin for each time period and deducting the recovery power usage are as follows: According to the time periods of each state transition in the peak shaving execution path and recovery path, the corresponding power changes are mapped to the load access location. The branch power flow changes and node voltage changes caused by the power changes are tracked along the network association range, and the correspondence between each state transition, the affected network location and the affected time period is established. Based on the distribution network operation status and network operation boundary, determine the branch load margin and node voltage margin of each affected network location, and convert them into the allowable power variation range of the load access location. The network capacity margin for the corresponding time period is determined by the power variation range corresponding to each affected network location, and the correspondence between the network capacity margin and the affected network location is retained. Based on the network association scope and recovery period in the recovery ledger, the recovery power occupancy is mapped to the affected network location, and the recovery power occupancy is deducted from the network capacity reserve of the affected network location within the corresponding recovery period to determine the remaining network capacity reserve of each affected network location in each period.
7. The method for assessing peak-shaving of high-energy-consuming flexible loads in a distribution network as described in claim 6, characterized in that, The specific steps for forming a recoverable peak-tuning core are as follows: Along the state transition sequence of the peak shaving execution path and the recovery path, the power change amplitude of each state transition is compared with the remaining network capacity at the same time and network location. When the power change amplitude exceeds the remaining network capacity, the peak shaving execution path, recovery path, state transition time and network location corresponding to the network conflict are determined according to the correspondence between the remaining network capacity and the affected network location. To address network conflicts arising during the peak shaving execution phase, the power change amplitude of the corresponding state transition is reduced. For network conflicts arising from the overlap of path power change and recovery power occupation time periods, the state transition time is adjusted under the conditions of holding time, recovery interval and recovery period. For network conflicts that still exist during the recovery phase, recovery paths that meet the process recovery conditions and have different recovery periods are replaced along the process state transition relationship. The adjusted peak shaving execution path and recovery path are remapped to the network association range. The remaining network capacity of each time period is re-determined and network conflicts are identified. Peak shaving execution paths, recovery paths and corresponding power change ranges that do not have network conflicts in both the peak shaving execution phase and the recovery phase are included in the recoverable peak shaving core, and paired peak shaving paths that still have network conflicts are removed.
8. The method for assessing peak-shaving of high-energy-consuming flexible loads in a distribution network as described in claim 7, characterized in that, The generated peak-shaving assessment record includes: Based on the continuous maintenance duration of each peak shaving execution path in the recoverable peak shaving core, peak shaving execution paths with a continuous maintenance duration of not less than the corresponding peak shaving duration are selected according to the peak shaving duration, and the corresponding recovery path, power change range and remaining network capacity in each time period are retained. According to the direction of load power increase and load power decrease, the selected power change ranges are compared respectively. The maximum power increase that can be sustained for each peak shaving duration is determined as the upward adjustment capability, and the maximum power decrease that can be sustained is determined as the downward adjustment capability. For the peak shaving execution path and recovery path corresponding to the upward and downward adjustment capabilities, the network location with the smallest allowable power change amplitude is tracked along the network association range and used as the network location that limits the corresponding peak shaving capability. The peak shaving duration, upward adjustment capability, downward adjustment capability, peak shaving execution path, recovery path and network location that limits the peak shaving capability are associated to generate a peak shaving assessment record.
9. A computer device comprising a memory and a processor, wherein the memory stores a computer program, characterized in that: When the processor executes the computer program, it implements the steps of the high-energy-consuming flexible load peak-shaving assessment method for distribution networks as described in any one of claims 1 to 8.
10. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by the processor, it implements the steps of the high-energy-consuming flexible load peak-shaving assessment method for distribution networks as described in any one of claims 1 to 8.