Distribution network fault recovery method and system considering backup power margin of computing center
By determining the minimum power supply requirements and surplus energy of the computing center's backup power, an optimized model for power distribution network fault recovery was constructed. This coordinated internal and external support, solving the problem of insufficient surplus capacity in backup power management and improving the utilization efficiency of backup power and the recovery efficiency of the power distribution network.
Patent Information
- Application Number
- CN202611295513.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-25
- Publication Date
- 2026-11-17
AI Technical Summary
In existing technologies, the management method of backup power supply in computing centers is fixed, resulting in insufficient utilization of surplus capacity and difficulty in playing a full role in the recovery of power distribution network faults. Furthermore, the capacity release of backup power supply is too conservative or the duration of external support is insufficient, which affects the power supply security of computing centers and the recovery efficiency of power distribution networks.
By acquiring the estimated time for fault repair and the critical load demand data of the computing center, the minimum supply guarantee demand is determined, the surplus energy and output of the backup power supply are calculated, and an optimization model for distribution network fault recovery is constructed to coordinate internal supply guarantee and external recovery support, thereby optimizing the utilization efficiency of the backup power supply.
It improves the utilization efficiency of backup power and the fault recovery capability of the distribution network, ensures continuous power supply for the critical business of the computing center, reduces the risk of external support interruption, and enhances the recovery level of important loads and the resilience of the distribution network.
Smart Images

Figure CN123121600A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of power system automation technology, specifically relating to a method and system for distribution network fault recovery that takes into account the backup power margin of the computing center. Background Technology
[0002] With the development of the digital economy, artificial intelligence, and cloud computing industries, computing centers have gradually become crucial infrastructure for data processing, model training, business computing, and information storage. Computing centers typically include server clusters, storage devices, network communication equipment, cooling equipment, and power supply and distribution equipment, placing high demands on power continuity and quality. When a power distribution network failure causes an external power outage, computing centers need to rely on backup power sources such as energy storage devices, uninterruptible power supplies (UPS), and backup generators to maintain critical business operations.
[0003] Existing backup power supplies for computing centers are typically configured with capacity based on preset independent support durations and worst-case operating conditions, with the primary control objective being to ensure the critical load of the computing center itself. However, in actual fault scenarios, fault types, repair conditions, and recovery schedules vary, and the actual support requirements of backup power supplies may be lower than those corresponding to fixed contingency plans. If backup power supplies are still managed using a fixed retention method, some available energy and output capacity may remain idle for extended periods, making it difficult to fully leverage the support role of backup power supplies in restoring the surrounding power distribution network.
[0004] Furthermore, when backup power supplies participate in distribution network fault recovery, they must simultaneously meet conditions such as continuous power supply to critical loads of the computing center, backup power supply power and energy boundaries, continuous power supply requirements of the loads to be restored, and power flow and voltage safety of the distribution network. Existing technologies do not adequately address the coordination between these conditions, which can easily lead to problems such as overly conservative release of backup capacity, insufficient duration of external support, or external support affecting the power supply security of the computing center itself.
[0005] Therefore, there is an urgent need for a power distribution network fault recovery method that takes into account the backup power margin of computing centers, so as to improve the utilization efficiency of backup power and the fault recovery capability of power distribution networks. Summary of the Invention
[0006] This invention provides a power distribution network fault recovery method that considers the backup power margin of computing centers. The solution of this invention determines the minimum power supply requirements of computing centers based on the estimated fault repair time, incorporates the surplus support capacity of backup power into the optimization of power distribution network fault recovery, and solves the problems of fixed backup power retention methods, insufficient utilization of surplus capacity, and difficulty in coordinating internal power supply and external recovery support.
[0007] A first aspect of the present invention provides a method for distribution network fault recovery that considers the backup power margin of computing centers, the method comprising: Acquire data on distribution network faults, estimated time for fault repair, critical load demand data for the computing center, backup power status data, and distribution network operation constraints. Based on the estimated fault repair time and the critical load demand data of the computing center, determine the minimum backup power support requirement required to maintain continuous power supply to the critical load of the computing center during the estimated fault repair time, and generate minimum power supply requirement data. Based on the backup power status data and the minimum supply requirement data, determine the surplus energy and surplus output of the backup power after meeting the critical load of the computing center, and generate backup power surplus support capacity data. Using the backup power surplus support capacity data as a recovery resource, and combining the distribution network fault data and the distribution network operation constraint data, a distribution network fault recovery optimization model is constructed. Solve the aforementioned distribution network fault recovery optimization model to generate a coordinated power output strategy for backup power supply between critical load protection in the computing center and distribution network fault recovery support.
[0008] By adopting the above scheme, the present invention provides a power distribution network fault recovery method that considers the backup power margin of the computing center. This method uses the estimated fault repair time as the time boundary for backup power supply requirements, matching the minimum supply requirements with the actual fault duration. By comparing the backup power status with the minimum supply requirements, surplus energy and output that do not affect the continuous power supply to critical loads in the computing center are obtained. Furthermore, by incorporating surplus support capacity as a recovery resource into the power distribution network fault recovery optimization, coordinated allocation is made between internal power supply requirements in the computing center and external recovery support in the power distribution network, thereby improving the utilization efficiency of backup power and the recovery level of critical loads.
[0009] In some embodiments of the present invention, determining the minimum backup power support requirement based on the estimated fault repair time and the critical load demand data of the computing center includes: Obtain the critical load power sequence of the computing center within the estimated timeframe for fault repair; Integrating the power sequence of the critical loads of the computing center within the estimated time of the fault repair, the minimum energy required for power supply is obtained:
[0010] in, This indicates the minimum energy required to maintain the critical load of the computing center within the estimated timeframe for fault repair. Indicates the estimated time for emergency repairs; Indicates time The critical load power of the computing center.
[0011] In some embodiments of the present invention, determining the surplus energy and the surplus output includes: Based on the current remaining available energy of the backup power supply, the safety reserve energy, and the minimum guaranteed energy, the surplus energy is calculated according to the following formula:
[0012] Determine the time based on the power distribution network fault data. Power supplied to the computing center after the power distribution network is restored The internal power supply capacity and surplus output of the backup power supply for critical load protection in the computing center are determined according to the following formula:
[0013]
[0014] in, This indicates the surplus energy of the backup power supply that can be used for power distribution network fault recovery after meeting the continuous power supply requirements of the critical loads of the computing center. This indicates the current remaining available energy of the backup power supply; This indicates that energy is being safely preserved; Indicates time The power supply provided to the computing center after the power distribution network is restored; Indicates time Backup power supplies are used for the internal power supply of critical loads in the computing center; Indicates time Backup power supplies can be used as surplus output for power distribution network fault recovery; This indicates the maximum output power of the backup power supply.
[0015] In some embodiments of the present invention, generating backup power surplus support capacity data further includes: When the critical load power of the computing center is approximately constant, the sustainable support time of the backup power supply is calculated based on the current remaining available energy of the backup power supply, the safety reserve energy, and the average power of the critical load of the computing center:
[0016] Compare the sustainable support time of the backup power supply with the estimated time for fault repair; When satisfied At that time, it is determined that the backup power supply has the basic supply capability to cover the estimated time of fault repair; where Tb represents the sustainable support time of the backup power supply, Eres represents the current remaining available energy of the backup power supply, Esafe represents the energy reserved for safety, Pdccrit represents the average power of the critical load of the computing center, and Tr represents the estimated time of fault repair.
[0017] In some embodiments of the present invention, the distribution network fault recovery optimization model aims to minimize the overall system loss, which includes the load loss due to unrestored distribution network loads and the service loss due to insufficient power supply to the computing center. The objective function is:
[0018] in, Indicates the overall system loss; This represents the set of load nodes to be restored; Represents a node The importance weight of the load awaiting restoration; Indicates time node Unrestored load power at the location; Indicates time The weight of business loss corresponding to the unit power deficit of the computing power center; Indicates time The computing center has not met the critical load power requirements; Represents a discrete time interval.
[0019] In some embodiments of the present invention, the power distribution network fault recovery optimization model includes backup power allocation constraints:
[0020]
[0021]
[0022] in, t Indicates a point in time during the fault recovery process; Indicates time t Backup power supplies are used for the internal power supply of critical loads in the computing center; Indicates time t Backup power supply is used as external support power for distribution network fault recovery. This indicates the maximum output power of the backup power supply; Indicates time t Power requirements of critical loads in computing centers; Indicates time t The power supply provided by the power distribution network to the computing center; Indicates time t After meeting the power supply needs of the critical loads of the computing center, the backup power supply can be used for the surplus output of the power distribution network fault recovery.
[0023] In some embodiments of the present invention, the power distribution network fault recovery optimization model includes backup power energy constraints:
[0024]
[0025]
[0026] in, Indicates time The remaining energy of the backup power supply; This indicates the initial remaining available energy of the backup power supply at the moment the fault occurs; This indicates that energy is being safely preserved; Represents a discrete time interval.
[0027] In some embodiments of the present invention, the distribution network fault recovery optimization model further includes external load recovery constraints and distribution network operation constraints, wherein the external load recovery constraints are:
[0028]
[0029] The distribution network operation constraints include at least node power balance constraints, line power flow constraints, and node voltage constraints, wherein the node power balance constraints are:
[0030] The line power flow constraint and the node voltage constraint are:
[0031]
[0032] in, Indicates time node Actual restored load power; Indicates time node A binary variable determining whether power has been restored to the load; Represents a node The load demand, Indicates time node Load demand; Indicates time node The power supply power includes the power supply provided by the power distribution network and the backup power supply of the computing center. Represents nodes A set of connected nodes; Indicates time line Uploaded power; Indicates the line The upper limit of transmission power; Indicates time node The voltage; and Representing nodes respectively The lower and upper voltage limits.
[0033] In some embodiments of the present invention, the method further includes: acquiring fault repair progress data and remaining backup power energy according to a preset rolling cycle; updating the fault repair progress data according to the fault repair progress data. The estimated remaining fault repair time for each rolling cycle Update the number according to the following formula Minimum guaranteed energy and surplus energy for each rolling cycle:
[0034]
[0035] The distribution network fault recovery optimization model is re-solved based on the updated minimum guaranteed energy and surplus energy, and the coordinated output strategy is adjusted accordingly. in, Indicates the first The start time of each rolling cycle; Indicates the first The estimated remaining fault repair time for each rolling cycle; Indicates the first Minimum guaranteed energy supply for each rolling cycle; Indicates the first The surplus energy of each rolling cycle; Indicates time The remaining energy of the backup power supply; This represents the time variable for integration.
[0036] Compared with the prior art, the beneficial effects of the present invention are as follows: This invention determines the minimum power supply requirement by estimating fault repair time and the critical load demand of the computing center, quantifying the backup power supply boundary as the fault duration and critical load change. It determines surplus energy and surplus output by the difference between the backup power status and the minimum power supply requirement, enabling the backup power to release available support capacity while ensuring the continuous operation of critical computing center services. By matching the power demand for restored loads with the required continuous power supply time, it reduces the risk of external support interruption. Furthermore, by jointly considering the unrestored load loss in the distribution network, the computing center's service loss, the power and energy boundaries of the backup power supply, and the distribution network's operational constraints, it generates a power output strategy that coordinates internal power supply and external restoration support, improving the level of critical load restoration, fault recovery efficiency, and the resilience of the distribution network.
[0037] A second aspect of the present invention provides a power distribution network fault recovery system that considers the backup power margin of a computing center, comprising: The data acquisition module is used to acquire data on distribution network faults, estimated time for fault repair, critical load demand data of the computing center, status data of backup power supply, and operational constraints of the distribution network. The minimum power supply requirement determination module is used to determine the minimum backup power support requirement required to maintain continuous power supply to the critical load of the computing center during the estimated time of fault repair based on the estimated time of fault repair and the critical load requirement data of the computing center, and generate minimum power supply requirement data. The surplus support capacity determination module is used to determine the surplus energy and surplus output of the backup power supply after meeting the critical load of the computing center, based on the backup power status data and the minimum supply requirement data, and generate backup power surplus support capacity data. The optimization model building module is used to construct a distribution network fault recovery optimization model by using the backup power surplus support capacity data as a recovery resource and combining it with the distribution network fault data and the distribution network operation constraint data. The coordinated output strategy generation module is used to solve the distribution network fault recovery optimization model and generate a coordinated output strategy for backup power between critical load supply in the computing center and distribution network fault recovery support.
[0038] A third aspect of the present invention provides a power distribution network fault recovery device that considers the backup power margin of a computing center. The device includes a computer device, which includes a processor and a memory. The memory stores computer instructions. When the computer instructions are executed, the device implements the power distribution network fault recovery method that considers the backup power margin of a computing center.
[0039] Additional advantages, objects, and features of the invention will be set forth in part in the description which follows, and will also become apparent in part to those skilled in the art upon studying the text, or may be learned by practice of the invention. The objects and other advantages of the invention will become apparent from the description and the accompanying drawings.
[0040] Those skilled in the art will understand that the objectives and advantages achievable with the present invention are not limited to those specifically described above, and that the above and other objectives achievable with the present invention will become clearer from the following detailed description. Attached Figure Description
[0041] The accompanying drawings, which form part of this application, are used to provide a further understanding of the invention. The illustrative embodiments of the invention and their descriptions are used to explain the invention and do not constitute an improper limitation of the invention.
[0042] In the attached diagram: Figure 1 This is a flowchart illustrating a power distribution network fault recovery method that considers the backup power margin of a computing center, as provided in an embodiment of the present invention.
[0043] Figure 2 This is a schematic diagram of a power distribution network fault recovery system that takes into account the backup power margin of the computing center, provided as an embodiment of the present invention.
[0044] Figure 3 This is a schematic diagram of the structure of an electronic device provided in an embodiment of the present invention. Detailed Implementation
[0045] The present invention will now be described in detail with reference to the accompanying drawings and embodiments. It should be noted that, unless otherwise specified, the embodiments and features described in this application can be combined with each other.
[0046] The following detailed description is exemplary and intended to provide further detailed explanation of the invention. Unless otherwise specified, all technical terms used in this invention have the same meaning as commonly understood by one of ordinary skill in the art to which this application pertains. The terminology used in this invention is for the purpose of describing particular embodiments only and is not intended to limit the scope of exemplary embodiments according to the invention.
[0047] In this invention, the backup power supply for the computing center may include at least one of the following: energy storage devices, uninterruptible power supplies (UPS), backup generators, and other power supply equipment capable of providing power support when external power is interrupted. The computing center load mainly includes IT systems, cooling systems, and power distribution and security systems, among which servers, storage devices, and network equipment within the IT system are the core components determining the overall energy consumption level of the computing center. Because the intensity of computing tasks undertaken by the computing center varies under different business scenarios, its load demand exhibits certain dynamic changes. To accurately assess the emergency power supply needs of the computing center during a fault, this invention divides the computing center load into critical loads and non-critical loads. Critical loads mainly include server clusters, storage devices, network communication equipment, and related auxiliary support equipment necessary to maintain the continuous operation of core computing services; these loads require priority for continuous power supply during fault repair. Non-critical loads can be appropriately reduced or delayed in power supply based on the status of the backup power supply and recovery needs. Distribution network fault data may include fault location, fault type, isolation range, power outage nodes, available tie switches, and recoverable power supply paths. Distribution network operation constraint data may include node load, line capacity, node voltage allowable range, network topology, and available power supply status.
[0048] Figure 1 This is a flowchart illustrating a power distribution network fault recovery method that considers the backup power margin of a computing center, according to an embodiment of the present invention.
[0049] Example 1, as Figure 1 As shown, the present invention provides a power distribution network fault recovery method that considers the backup power margin of the computing center, the method comprising the following steps.
[0050] Step S1: Obtain data on distribution network faults, estimated time for fault repair, critical load demand data of the computing center, status data of backup power supply, and operational constraints of the distribution network.
[0051] Step S2: Based on the estimated fault repair time and the critical load demand data of the computing center, determine the minimum backup power support requirement required to maintain continuous power supply to the critical load of the computing center during the estimated fault repair time, and generate minimum power supply requirement data.
[0052] Step S3: Based on the backup power status data and minimum supply requirement data, determine the surplus energy and surplus output of the backup power after meeting the critical load requirements of the computing center, and generate backup power surplus support capacity data.
[0053] Step S4: Using the backup power surplus support capacity data as a recovery resource, and combining it with distribution network fault data and distribution network operation constraint data, construct a distribution network fault recovery optimization model.
[0054] Step S5: Solve the distribution network fault recovery optimization model to generate a coordinated power output strategy for backup power supply between critical load supply in the computing center and distribution network fault recovery support.
[0055] By adopting the above scheme, the present invention provides a power distribution network fault recovery method that considers the backup power margin of the computing center. This method limits the time range during which critical loads of the computing center need to be continuously supported by the backup power supply by defining the estimated fault repair time, thereby matching the minimum power supply requirement with the actual fault recovery process. Furthermore, by comparing the minimum power supply requirement with the current state of the backup power supply, it achieves quantitative identification of surplus energy and surplus output. Further, by incorporating surplus support capacity into the power distribution network fault recovery optimization, it achieves coordinated allocation of internal backup power supply and external support power, avoiding external support impacting the continuous operation of critical services in the computing center and improving the recovery level of surrounding important loads.
[0056] Specifically, in step S1, the estimated fault repair time represents the expected duration from the current fault recovery decision time to the completion of fault repair and restoration of stable external power supply. The estimated fault repair time can be determined based on at least one of the following: fault type, fault location, on-site repair resources, historical repair times for similar faults, and on-site feedback information. The critical load demand data for the computing center can be a continuous-time power curve or a power sequence formed according to discrete time intervals. Backup power status data can include current remaining available energy, safety reserve energy, maximum output power, and current operating status; the specific data can be selected based on the actual backup power type.
[0057] The load of a computing center can be divided into critical loads and non-critical loads. Critical loads may include server clusters, storage devices, network communication equipment, cooling equipment, and power supply and distribution equipment required to maintain the continuous operation of core computing services; non-critical loads may have their power supply reduced or delayed depending on the availability of backup power and the need for fault recovery. For non-critical tasks and non-critical cooling loads that can be reduced during a fault, the power consumption may be excluded from the critical load calculation, or it may be included according to a preset minimum operating power.
[0058] Specifically, to determine the emergency power supply capability of the computing center's backup power supply during a failure, the sustainable support time of the backup power supply is introduced, denoted as... The support time This indicates the longest time that the backup power supply of the computing center can maintain power supply while meeting the continuous power supply requirements of critical loads under the condition of external power interruption.
[0059] Assume the remaining available energy of the backup power supply at the computing center is... Safely retain energy as The critical load power requirement of the computing center is :
[0060] in, This indicates the sustainable support time for the backup power supply to maintain power to the critical loads of the computing center under the condition of external power outage; This represents the effective energy available for power supply after deducting the safety reserve energy.
[0061] When the critical load power of the computing center varies over time, the backup power supply can sustain operation for the maximum duration that satisfies the following formula:
[0062] Using the above methods, we can determine the minimum support capacity required for the backup power supply of the computing center to maintain continuous power supply to critical loads under the condition of known emergency repair time, which provides a basis for subsequent identification of surplus energy and participation in distribution network fault recovery decision-making.
[0063] when This indicates that the backup power supply, under its current energy condition, has the basic capacity to cover the estimated time for fault repair; when In such cases, priority should be given to reducing non-critical loads, migrating computing tasks, or calling up other backup power sources, without releasing external support capabilities to the distribution network.
[0064] By calculating the sustainable support time of backup power The backup power supply can sustainably support the power supply for a certain period of time. Estimated time for emergency repair By comparing the two, we can determine whether the backup power supply has the basic ability to cover the entire process of fault repair.
[0065] In step S2, when the critical load power of the computing center is approximately constant within the estimated time for fault repair, the minimum energy supply is:
[0066] in, This represents the average power of critical loads in the computing center during the estimated time for fault repair. This indicates the estimated time for fault repair. The minimum energy reserve is as follows: [Indicates the estimated time for fault repair].
[0067] Under discrete-time conditions, the above equation can be written as:
[0068] in, This represents the set of discrete time periods corresponding to the estimated time for fault repair; Represents a discrete time interval.
[0069] Minimum backup power requirements may include a minimum output power, which is determined based on the peak power of critical loads during the estimated time for fault repair, using the following formula:
[0070] This indicates the minimum output power required by the backup power supply during the estimated time for fault repair. By jointly determining the minimum backup energy and the minimum output power, the backup power supply can simultaneously meet the cumulative energy demand and instantaneous power demand during fault repair.
[0071] When the backup power supply can sustainably support the time And the maximum output power of the backup power supply is not less than At that time, the backup power supply has the basic supply guarantee capability to cover the estimated time for fault repair; on this basis, according to the current remaining available energy, safe reserve energy and minimum supply guarantee energy of the backup power supply, the surplus support capacity of the backup power supply that can be used for distribution network fault restoration is further determined.
[0072] In step S3, the surplus energy is first determined based on the minimum guaranteed energy supply:
[0073] Among them, E sur This refers to the surplus energy available for distribution network fault restoration after the backup power supply meets the continuous power supply requirements of the computing center's critical loads within the estimated timeframe for fault repair. Currently, the remaining available energy consists of safety reserve energy, minimum guaranteed supply energy, and surplus energy; when... At that time, the backup power supply is only used for internal power supply within the computing center; when At that time, continue to calculate the surplus output that can be used for distribution network fault restoration.
[0074] If the distribution network has already been able to provide partial restored power to the computing center during the fault recovery process, then the internal power supply capacity of the backup power source is:
[0075] The spare output of the backup power supply is:
[0076] Where Pgrid,dc(t) represents the power supply provided by the distribution network to the computing center at time t; Pin(t) represents the internal power supply of the backup power supply for critical load protection of the computing center at time t; Presmax represents the maximum output power of the backup power supply; and Psur(t) represents the surplus output of the backup power supply at time t that can be used for distribution network fault recovery.
[0077] Therefore, fault recovery optimization involves preserving the minimum power supply requirements of the computing center and ensuring sufficient energy reserves, and then allocating surplus energy... and spare efforts As a backup power source, it serves as a supporting boundary for distribution network fault recovery.
[0078] Through the above processing, the surplus energy and surplus output of the backup power supply that can be used for distribution network fault recovery after meeting the critical load supply requirements of the computing center are obtained. The surplus energy and surplus output are used as the recovery resource boundary for subsequent distribution network fault recovery optimization.
[0079] In step S4, the surplus energy Surplus labor Based on the energy and power boundaries of the backup power source for the computing center participating in distribution network fault recovery, and combining distribution network fault data, load data to be restored, and distribution network operation constraint data, an optimization model for distribution network fault recovery is constructed. The decision variables of the model can include the internal power supply power of the backup power source in each time period. External support power Remaining energy of backup power supply Load recovery status of each node Line transmission power And at least one of the following: distribution network switch status.
[0080] The distribution network fault recovery optimization model aims to reduce power outage losses caused by unrestored loads in the distribution network and business losses caused by insufficient power supply to the computing center. It includes backup power allocation constraints, backup power energy constraints, external load recovery constraints, and distribution network operation constraints.
[0081] The distribution network fault recovery optimization model aims to minimize the overall system loss.
[0082] Where L represents the overall system loss; t represents the discrete time period during the fault recovery process; N represents the set of load nodes to be restored; and i represents the load node to be restored. ω i This represents the importance weight of the load to be restored at node i; P i loss (t) This represents the unrecovered load power at node i at time t; λ dc (t) This represents the business loss weight corresponding to the unit power deficit of the computing center at time t. P dc loss (t)This indicates the critical load power that the computing center has not met at time t; Δt Represents a discrete time interval.
[0083] Importance weight Used to differentiate the importance of different loads to be restored (e.g., medical, telecommunications, traffic control, public safety, and general residential loads); service loss weighting. The parameters can be determined based on the computing center's business type, task priority, unit power outage loss, and service level requirements. By simultaneously setting external load loss items and computing center business loss items, the critical load supply capacity of the computing center can be prevented from being weakened in order to restore external load.
[0084] Backup power allocation meets the following requirements:
[0085]
[0086]
[0087] in, P in (t) This represents the power supplied by the backup power supply to the critical loads inside the computing center at time t. P out (t) This indicates the external support power of the backup power supply at time t for distribution network fault recovery. This indicates the maximum output power of the backup power supply; This represents the critical load power of the computing center at time t; This represents the power supplied by the distribution network to the computing center at time t; The value at time t represents the surplus output of the backup power supply available for distribution network fault recovery. The above constraints respectively limit the total output of the backup power supply, ensure priority power supply to critical loads in the computing center, and limit the external support power to not exceed the surplus output.
[0088] Of the three formulas above, the first term limits the sum of the internal power supply and external support power of the backup power supply to no more than the maximum output power; the second term ensures that the critical loads of the computing center are given priority; and the third term limits the external support power to no more than the surplus output calculated based on the current internal power supply status.
[0089] The backup power supply energy state meets the following requirements:
[0090]
[0091]
[0092] Where E(t) represents the remaining energy of the backup power supply at time t; E(0) represents the initial remaining energy of the backup power supply at the time of the fault; E res E represents the initial remaining available energy of the backup power supply. safe Indicates safe energy retention; P in (t) represents the internal power supply capacity of the backup power supply; P out (t) represents the external support power of the backup power supply; Δt represents the discrete time interval; E sur This indicates that the backup power supply is surplus energy that can be used for power distribution network fault recovery.
[0093] The aforementioned energy constraints ensure that the remaining energy of the backup power supply is not less than the safe reserve energy throughout the entire fault recovery process, and that the cumulative energy consumed for external support does not exceed the surplus energy determined according to the estimated fault repair time.
[0094] For the load to be restored at node i, the external load restoration satisfies:
[0095]
[0096] in, P i rec (t) This represents the actual restored load power at node i at time t; P i load This represents the load power demand of node i; x i (t) A binary variable representing whether the load at node i has resumed power supply at time t. x i (t) =1, otherwise x i (t) =0; N represents the set of load nodes to be restored; P out (t) This represents the external support power of the backup power supply for distribution network fault restoration at time t. The constraint ensures that the actual restored load power does not exceed the corresponding load demand and that the external support power of the backup power supply does not exceed the total actual restored load power.
[0097] Power balance at distribution network nodes must satisfy:
[0098] in, This represents the power supplied to node i at time t; This represents the load demand of node i at time t; This represents the power transmitted on line ij at time t; Ω i This represents the set of nodes connected to node i.
[0099] When the backup power supply of the computing center provides external support power to the distribution network, the node power supply includes the power supplied by the original power supply of the distribution network and the power supplied by the backup power supply of the computing center. In addition to node power balance constraints, distribution network operation constraints also include line power flow constraints and node voltage constraints, which are used to ensure that the fault recovery process meets the basic physical operation requirements of the distribution network.
[0100] Line power flow and node voltage meet the following requirements:
[0101]
[0102] in, Indicates the line The upper limit of transmission power; Indicates time node The voltage; and Representing nodes respectively The lower and upper voltage limits.
[0103] Depending on the accuracy requirements of the distribution network model, AC power flow constraints, linearized power flow constraints, or second-order cone relaxation power flow constraints can also be used.
[0104] In step S5, the distribution network fault recovery optimization model is solved to obtain the internal power supply, external support power, and recovery status of the loads to be restored for each time period. A coordinated output strategy is formed based on the solution results. This coordinated output strategy controls the backup power supply to prioritize powering critical loads at the computing center, and provides external support to the loads to be restored in the distribution network within the allowable range of surplus energy and output. The distribution network fault recovery optimization model can be solved using mixed-integer linear programming, mixed-integer second-order cone programming, dynamic programming, or heuristic optimization algorithms to obtain the internal power supply, external support power, load restoration sequence, switching operation sequence, and expected restoration time for each time period. The coordinated output strategy is formed from the above solution results and corresponding control commands are sent to the backup power supply control device and the distribution network fault recovery control device.
[0105] In a specific application example, the backup power supply currently has remaining available energy. 10 megawatt-hours, safely retaining energy The average power of critical loads in a computing center is 1 megawatt-hour. The power capacity is 2 megawatts, and the estimated time for emergency repairs is [not specified]. For a period of 3 hours, the minimum guaranteed energy supply is... 6 megawatt-hours, surplus energy It is 3 megawatt-hours. If the maximum output power of the backup power supply... The power supply capacity is 4 MW. During the fault, the distribution network has not yet restored power to the computing center, so the internal power supply capacity is 2 MW, and the surplus output is 2 MW. The distribution network fault recovery optimization model can choose to restore a critical load with a power of 1 MW and a continuous power supply time requirement of 3 hours within the boundary formed by the surplus energy of 3 MW and the surplus output of 2 MW, or choose other load combinations that meet the power and duration conditions. The above values are only used to illustrate the calculation process and do not constitute a limitation on the backup power capacity, critical load power, or the estimated fault repair time.
[0106] Furthermore, the estimated time for fault repair can be updated on a rolling basis during the fault recovery process. At the start of each rolling cycle, acquire information on the on-site repair progress, fault isolation status, estimated completion time, and current remaining energy of the backup power supply. And determine the estimated time for the remaining fault repair. , No. The minimum energy supply for each rolling cycle is:
[0107] No. The surplus energy for each rolling cycle is:
[0108] After obtaining the minimum guaranteed energy and surplus energy for the (k)th rolling cycle, the internal guaranteed energy demand of the backup power supply during the remaining fault repair time is updated according to the minimum guaranteed energy, and the energy boundary for the backup power supply to participate in the distribution network fault recovery is updated according to the surplus energy.
[0109] Substitute the updated minimum guaranteed energy and surplus energy into the distribution network fault recovery optimization model, and re-solve the internal power supply, external support power and recovery status of the load to be restored in the (k)th rolling cycle. Adjust the coordinated output strategy based on the re-solved results.
[0110] When the estimated time for remaining fault repair is shortened, the minimum power supply capacity decreases accordingly, and the surplus energy available for distribution network fault recovery from the backup power supply increases accordingly. The re-solved coordinated output strategy can increase the external support power of the backup power supply. When the estimated time for remaining fault repair is extended, the demand for critical loads in the computing center increases, or the remaining energy of the backup power supply decreases, the minimum power supply capacity increases accordingly or the surplus energy decreases accordingly. The re-solved coordinated output strategy reduces the external support power of the backup power supply and prioritizes maintaining the continuous power supply to critical loads in the computing center.
[0111] When the estimated time for repairing remaining faults is shortened after the update, the minimum energy supply will decrease accordingly, allowing for the release of additional surplus energy to restore more load. When the estimated time for repairing remaining faults is extended after the update, or when the demand for critical loads in the computing center increases, the minimum energy supply will increase accordingly, and the surplus energy will decrease accordingly. The model will reduce external support power or withdraw some external recovery loads to maintain continuous power supply to critical loads in the computing center and ensure the safe supply boundary of the computing center.
[0112] Through the aforementioned rolling updates, the coordinated power output strategy can be adjusted according to the progress of fault repair and changes in the status of backup power.
[0113] Compared with the prior art, the beneficial effects of the present invention are as follows: This invention determines the minimum power supply requirements needed to maintain continuous power supply to critical loads in the computing center during the estimated fault repair time by acquiring data on the estimated fault repair time, critical load demand data of the computing center, and backup power status data. Based on meeting safety retention requirements, it determines the surplus energy and surplus output of the backup power supply. This allows the assessment of backup power supply support capacity to no longer be limited to fixed backup duration or static state of charge, but to match with the actual fault duration and computing center load demand, thereby improving the accuracy and usability of backup power margin assessment results.
[0114] This invention incorporates the surplus support capacity of backup power as a recovery resource into the distribution network fault recovery optimization model. It comprehensively considers the load loss of the distribution network that has not been restored, the service loss due to insufficient power supply to the computing center, and the power and energy boundaries of the backup power. It coordinates and allocates power between ensuring the supply of critical loads inside the computing center and supporting fault recovery outside the distribution network. This allows the backup power to provide power support for the loads waiting to be restored in the distribution network while prioritizing the continuous operation of the critical services of the computing center, thereby improving the utilization efficiency of the backup power and the recovery level of important loads in the distribution network.
[0115] This invention limits the power and energy usage range of the backup power supply during external support by jointly constraining the internal power supply power, external support power, remaining energy and external load recovery power of the backup power supply, and combining it with distribution network operation constraints such as node power balance, line power flow and node voltage. This avoids the impact of external fault recovery support on the safe supply of the computing center itself, and improves the safety and engineering feasibility of the coordinated output strategy.
[0116] Furthermore, this invention updates the minimum supply requirements, surplus support capacity, and coordinated output strategies based on the progress of fault repair, remaining repair time, critical load demand of the computing center, and the remaining status of backup power. This allows the external support capacity of the backup power to be dynamically adjusted according to the fault recovery status. When the repair time is extended or the critical load demand increases, external support is contracted in a timely manner, and more recovery capacity is released when the supply margin increases. This improves the dynamic adaptability of the distribution network during fault recovery, reduces the overall power outage loss of the system, and enhances the resilience and emergency support capability of the distribution network in the event of a sudden fault.
[0117] Figure 2 This is a schematic diagram of a power distribution network fault recovery system that takes into account the backup power margin of the computing center, according to an embodiment of the present invention.
[0118] Example 2, as Figure 2 As shown, the present invention also provides a power distribution network fault recovery system that considers the backup power margin of the computing center, including: a data acquisition module, a minimum power supply requirement determination module, a surplus support capacity determination module, an optimization model construction module, and a coordinated output strategy generation module.
[0119] The data acquisition module is used to acquire data on distribution network faults, estimated fault repair times, critical load demand data from the computing center, backup power status data, and distribution network operational constraints. The data acquisition module can communicate with the distribution network dispatching system, fault repair management system, computing center energy management system, and backup power control device.
[0120] The minimum power supply requirement determination module is used to determine the minimum backup power support required to maintain continuous power supply to the critical loads of the computing center during the estimated time of fault repair, based on the estimated fault repair time and the critical load demand data of the computing center, and generates minimum power supply requirement data. The minimum power supply requirement determination module can calculate the minimum power supply energy using either a continuous integration method or a discrete accumulation method.
[0121] The redundancy support capacity determination module is used to determine the surplus energy and surplus output of the backup power supply after meeting the critical load requirements of the computing center, based on backup power status data and minimum supply guarantee data, and generates backup power supply surplus support capacity data. The redundancy support capacity determination module can also determine the set of recoverable loads based on the power requirements and continuous power supply time requirements of candidate recovery loads.
[0122] The optimization model construction module is used to construct a distribution network fault recovery optimization model by combining backup power surplus support capacity data as a recovery resource with distribution network fault data and distribution network operation constraint data. The distribution network fault recovery optimization model may include a system comprehensive loss objective function, backup power supply power constraints, backup power supply energy constraints, external load recovery constraints, node power balance constraints, line power flow constraints, and node voltage constraints.
[0123] The coordinated output strategy generation module is used to solve the distribution network fault recovery optimization model and generate a coordinated output strategy for backup power sources between critical load supply in the computing center and distribution network fault recovery support. The module can output the internal power supply sequence of the backup power source, the external support power sequence, the recovery sequence of the loads to be restored, and the distribution network switch operation sequence.
[0124] In one optional implementation, the system further includes a rolling correction module, which is used to acquire fault repair progress data and remaining backup power energy according to a preset rolling cycle, update the remaining fault repair estimated time, minimum power supply energy and surplus energy, and trigger the optimization model building module and the coordinated output strategy generation module to re-execute the model building and solving operations.
[0125] Example 3: The present invention also provides a power distribution network fault recovery device that considers the backup power margin of the computing center. The device includes a computer device, which includes a processor and a memory. The memory stores computer instructions. When the computer instructions are executed, the device implements the power distribution network fault recovery method that considers the backup power margin of the computing center.
[0126] Example 4, as Figure 3 As shown, the present invention also provides an electronic device 100 for implementing a power distribution network fault recovery method that takes into account the backup power margin of the computing center.
[0127] The electronic device 100 includes a memory 101, at least one processor 102, a computer program 103 stored in the memory 101 and executable on at least one processor 102, and at least one communication bus 104.
[0128] The memory 101 can be used to store the computer program 103. The processor 102 implements the steps of the power grid fault recovery method considering the backup power margin of the computing center as described in the first aspect of the present invention by running or executing the computer program stored in the memory 101 and calling the data stored in the memory 101.
[0129] The memory 101 may primarily include a program storage area and a data storage area. The program storage area may store the operating system, application programs required for at least one function (such as sound playback function, image playback function, etc.), etc.; the data storage area may store data created based on the use of the electronic device 100 (such as audio data), etc. In addition, the memory 101 may include non-volatile memory, such as hard disk, RAM, plug-in hard disk, smart media card (SMC), secure digital (SD) card, flash card, at least one disk storage device, flash memory device, or other non-volatile solid-state storage device.
[0130] At least one processor 102 may be a Central Processing Unit (CPU), or other general-purpose processors, digital signal processors (DSPs), application-specific integrated circuits (ASICs), field-programmable gate arrays (FPGAs), or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. Processor 102 may be a microprocessor or any conventional processor. Processor 102 is the control center of electronic device 100, connecting various parts of electronic device 100 via various interfaces and lines.
[0131] The memory 101 in the electronic device 100 stores multiple instructions to implement a power distribution network fault recovery method that takes into account the backup power margin of the computing center. The processor 102 can execute multiple instructions to achieve the following: Acquire data on distribution network faults, estimated time for fault repair, critical load demand data for the computing center, backup power status data, and distribution network operation constraints. Based on the estimated fault repair time and the critical load demand data of the computing center, determine the minimum backup power support requirement required to maintain continuous power supply to the critical load of the computing center during the estimated fault repair time, and generate minimum power supply requirement data. Based on the backup power status data and the minimum supply requirement data, determine the surplus energy and surplus output of the backup power after meeting the critical load of the computing center, and generate backup power surplus support capacity data. Using the backup power surplus support capacity data as a recovery resource, and combining the distribution network fault data and the distribution network operation constraint data, a distribution network fault recovery optimization model is constructed. Solve the aforementioned distribution network fault recovery optimization model to generate a coordinated power output strategy for backup power supply between critical load protection in the computing center and distribution network fault recovery support.
[0132] Example 5: If the modules / units integrated in the electronic device 100 are implemented as software functional units and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on this understanding, all or part of the processes in the methods of the above embodiments of the present invention can also be implemented by a computer program instructing related hardware. The computer program can be stored in a computer-readable storage medium, and when executed by a processor, it can implement the steps of the various method embodiments described above. The computer program includes computer program code, which can be in the form of source code, object code, executable files, or certain intermediate forms. The computer-readable medium can include: any entity or device capable of carrying computer program code, recording media, USB flash drives, portable hard drives, magnetic disks, optical disks, computer memory, and read-only memory (ROM).
[0133] Those skilled in the art will understand that embodiments of the present invention can be provided as methods, systems, or computer program products. Therefore, the present invention can take the form of a completely hardware embodiment, a completely software embodiment, or an embodiment combining software and hardware aspects. Furthermore, the present invention can take the form of a computer program product embodied on one or more computer-usable storage media (including, but not limited to, disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.
[0134] This invention is described with reference to flowchart illustrations and / or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of the invention. It will be understood that each block of the flowchart illustrations and / or block diagrams, and combinations of blocks in the flowchart illustrations and / or block diagrams, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, special-purpose computer, embedded processor, or other programmable data processing apparatus to produce a machine, such that the instructions, which execute via the processor of the computer or other programmable data processing apparatus, generate instructions for implementing the flowchart illustrations and / or block diagrams. Figure 1 One or more processes and / or boxes Figure 1 A device that provides the functions specified in one or more boxes.
[0135] These computer program instructions may also be stored in a computer-readable storage medium that can direct a computer or other programmable data processing device to function in a particular manner, such that the instructions stored in the computer-readable storage medium produce an article of manufacture including instruction means, which are implemented in a process Figure 1 One or more processes and / or boxes Figure 1 The function specified in one or more boxes.
[0136] These computer program instructions may also be loaded onto a computer or other programmable data processing equipment to cause a series of operational steps to be performed on the computer or other programmable equipment to produce a computer-implemented process, thereby providing instructions that execute on the computer or other programmable equipment for implementing the process. Figure 1 One or more processes and / or boxes Figure 1 The steps of the function specified in one or more boxes.
[0137] In the description of this specification, references to terms such as "an embodiment," "example," "specific example," etc., indicate that a specific feature, structure, material, or characteristic described in connection with that embodiment or example is included in at least one embodiment or example of the invention. In this specification, illustrative expressions of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the specific features, structures, materials, or characteristics described may be combined in any suitable manner in one or more embodiments or examples.
[0138] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and not to limit it. Although the present invention has been described in detail with reference to the above embodiments, those skilled in the art should understand that modifications or equivalent substitutions can still be made to the specific implementation of the present invention. Any modifications or equivalent substitutions that do not depart from the spirit and scope of the present invention should be covered within the scope of protection of the claims of the present invention.
Claims
1. A method for distribution network fault recovery that considers the backup power margin of computing centers, characterized in that, The method includes: Acquire data on distribution network faults, estimated time for fault repair, critical load demand data for the computing center, backup power status data, and distribution network operation constraints. Based on the estimated fault repair time and the critical load demand data of the computing center, determine the minimum backup power support requirement required to maintain continuous power supply to the critical load of the computing center during the estimated repair time, and generate minimum power supply requirement data. Based on the backup power status data and the minimum supply requirement data, determine the surplus energy and surplus output of the backup power after meeting the critical load of the computing center, and generate backup power surplus support capacity data. Using the backup power surplus support capacity data as a recovery resource, and combining the distribution network fault data and the distribution network operation constraint data, a distribution network fault recovery optimization model is constructed. Solve the aforementioned distribution network fault recovery optimization model to generate a coordinated power output strategy for backup power supply between critical load protection in the computing center and distribution network fault recovery support.
2. The power distribution network fault recovery method considering the backup power margin of the computing center according to claim 1, characterized in that, The step of determining the minimum backup power support requirement based on the estimated fault repair time and the critical load demand data of the computing center includes: Obtain the critical load power sequence of the computing center within the estimated timeframe for fault repair; Integrating the power sequence of the critical loads of the computing center within the estimated time of the fault repair, the minimum energy required for power supply is obtained: in, This indicates the minimum energy required to maintain critical loads at the computing center within the estimated timeframe for fault repair. Indicates the estimated time for emergency repairs. Indicates time The critical load power of the computing center.
3. The power distribution network fault recovery method considering the backup power margin of the computing center according to claim 2, characterized in that, Determining the surplus energy and the surplus output includes: Based on the current remaining available energy of the backup power supply, the safety reserve energy, and the minimum guaranteed energy, the surplus energy is calculated according to the following formula: Determine the time based on the power distribution network fault data. Power supplied to the computing center after the power distribution network is restored The internal power supply capacity and surplus output of the backup power supply for critical load protection in the computing center are determined according to the following formula: in, This indicates the surplus energy available from the backup power supply after meeting the continuous power supply requirements of the critical loads in the computing center, which can be used for power distribution network fault recovery. This indicates the current remaining available energy of the backup power supply. This indicates that energy is being safely conserved. Indicates time The power supply provided to the computing center after the power distribution network is restored. Indicates time Backup power supplies are used for the internal power supply of critical loads in the computing center. Indicates time Backup power supplies can be used as surplus output for power distribution network fault recovery. This indicates the maximum output power of the backup power supply.
4. The power distribution network fault recovery method considering the backup power margin of the computing center according to claim 3, characterized in that, The generation of backup power surplus support capacity data also includes: When the critical load power of the computing center is approximately constant, the sustainable support time of the backup power supply is calculated based on the current remaining available energy of the backup power supply, the safety reserve energy, and the average power of the critical load of the computing center: Compare the sustainable support time of the backup power supply with the estimated time for fault repair; When satisfied At that time, it is determined that the backup power supply has the basic supply capacity to cover the estimated time for the emergency repair of the aforementioned fault; Where Tb represents the sustainable operating time of the backup power supply, Eres represents the current remaining available energy of the backup power supply, and Esafe represents the energy reserved for safety. Tr represents the average power of critical loads in the computing center, and Tr represents the estimated time for fault repair.
5. The power distribution network fault recovery method considering the backup power margin of the computing center according to claim 1, characterized in that, The distribution network fault recovery optimization model aims to minimize the overall system loss, which includes load loss due to unrestored distribution network loads and service losses due to insufficient power supply to the computing center. The objective function is: in, Indicates the overall system loss; This represents the set of load nodes to be restored. Represents a node The importance weight of the load to be restored Indicates time node Unrestored load power at the location, Indicates time The weight of business loss corresponding to the unit power deficit of the computing power center. Indicates time The critical load power not met by the computing center Represents a discrete time interval.
6. The power distribution network fault recovery method considering the backup power margin of the computing center according to claim 5, characterized in that, The power distribution network fault recovery optimization model includes backup power allocation constraints: in, t Indicates the time point in the fault recovery process. Indicates time t Backup power supplies are used for the internal power supply of critical loads in the computing center. Indicates time t Backup power supplies serve as external support for power distribution network fault recovery. This indicates the maximum output power of the backup power supply. Indicates time t Power requirements of critical loads in computing centers Indicates time t The power supply provided by the distribution network to the computing center Indicates time t After meeting the power supply needs of the critical loads of the computing center, the backup power supply can be used for the surplus output of the power distribution network fault recovery.
7. The power distribution network fault recovery method considering the backup power margin of the computing center according to claim 6, characterized in that, The power distribution network fault recovery optimization model includes backup power energy constraints: Where t represents the time during the fault recovery process, E(t) represents the remaining energy of the backup power supply at time t, and E(0) represents the initial remaining energy of the backup power supply at the time the fault occurred. res E represents the initial remaining available energy of the backup power supply. safe P indicates the safe retention of energy. in (t) represents the power supplied by the backup power supply to the critical loads inside the computing center at time t, P out (t) represents the external support power of the standby power supply to the distribution network at time t, Δt represents the discrete time interval, and E sur This indicates that the backup power supply is surplus energy that can be used for power distribution network fault recovery.
8. The power distribution network fault recovery method considering the backup power margin of the computing center according to claim 7, characterized in that, The distribution network fault recovery optimization model also includes external load recovery constraints and distribution network operation constraints. The external load recovery constraints are as follows: The distribution network operation constraints include at least node power balance constraints, line power flow constraints, and node voltage constraints, wherein the node power balance constraints are: The line power flow constraint and the node voltage constraint are: in, Indicates time node Actual restored load power, Indicates time node A binary variable determining whether power has been restored to the load. Represents a node The load demand, Indicates time node The load demand, Indicates time node The power supply power includes the power supply provided by the power distribution network and the backup power supply of the computing center. Represents nodes A set of connected nodes. Indicates time line Upload power, Indicates the line The upper limit of transmission power, Indicates time node voltage, and Representing nodes respectively The lower and upper voltage limits.
9. The power distribution network fault recovery method considering the backup power margin of the computing center according to claim 1, characterized in that, The method further includes: Data on the progress of fault repair and the remaining energy of the backup power supply are obtained according to a preset rolling cycle. Update the fault repair progress data according to the above. The estimated remaining fault repair time for each rolling cycle Update the first according to the following formula Minimum guaranteed energy and surplus energy for each rolling cycle: The distribution network fault recovery optimization model is re-solved based on the updated minimum guaranteed energy and surplus energy, and the coordinated output strategy is adjusted accordingly. in, Indicates the first The start time of each rolling cycle Indicates the first The estimated remaining fault repair time for each rolling cycle. Indicates time The critical load power of the computing center Indicates the first Minimum guaranteed energy supply for each rolling cycle Indicates the first The surplus energy of each rolling cycle Indicates time The remaining energy of the backup power supply This indicates that energy is being safely conserved. This represents the time variable for integration.
10. A power distribution network fault recovery system considering the backup power margin of a computing center, characterized in that, The system includes: The data acquisition module is used to acquire data on distribution network faults, estimated time for fault repair, critical load demand data of the computing center, status data of backup power supply, and operational constraints of the distribution network. The minimum power supply requirement determination module is used to determine the minimum backup power support requirement required to maintain continuous power supply to the critical load of the computing center during the estimated time of fault repair based on the estimated time of fault repair and the critical load requirement data of the computing center, and generate minimum power supply requirement data. The surplus support capacity determination module is used to determine the surplus energy and surplus output of the backup power supply after meeting the critical load of the computing center, based on the backup power status data and the minimum supply requirement data, and generate backup power surplus support capacity data. The optimization model building module is used to construct a distribution network fault recovery optimization model by using the backup power surplus support capacity data as a recovery resource and combining it with the distribution network fault data and the distribution network operation constraint data. The coordinated output strategy generation module is used to solve the distribution network fault recovery optimization model and generate a coordinated output strategy for backup power between critical load supply in the computing center and distribution network fault recovery support.