Butadiene gas phase condensation recovery device

By designing a butadiene gas phase condensation recovery device, the unloading compressor and cooler are used to cool and recover butadiene, and the recovery of butadiene is realized through nitrogen injection, which solves the problem of waste in the gas phase pressure relief of butadiene storage tanks. problem, reducing storage losses and improving the efficiency of storage security management.

CN221788207UActive Publication Date: 2024-10-01振华新材料(东营)有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420301963.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-19
Publication Date
2024-10-01
Estimated Expiration
2034-02-19

AI Technical Summary

Technical Problem

During the gas phase pressure relief process of butadiene storage tanks, there is a large amount of butadiene gas phase waste, resulting in material loss. Existing technology cannot effectively recover and affects storage safety management.

Method used

A butadiene gas-phase condensation recovery device is designed. The unloading compressor is used to send the butadiene in the butadiene storage tank to the tank truck unloading crane. It is cooled and recovered through the cooler, and the butadiene material pump and Nitrogen injection pressure realizes the recovery of butadiene, and finally the recovered butadiene is returned to the storage tank.

Benefits of technology

It effectively reduces the material waste of butadiene, reduces storage losses, and improves the efficiency of storage safety management.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221788207U_ABST
    Figure CN221788207U_ABST
Patent Text Reader

Abstract

The utility model discloses a butadiene gas phase condensation recovery device, which belongs to the technical field of butadiene gas phase condensation and comprises a butadiene storage tank, an unloading compressor is arranged on one side of the butadiene storage tank, and an unloading compressor gas outlet pipeline I is arranged on one side of the unloading compressor. A butadiene tank car unloading crane position is arranged at one end of a first gas outlet pipeline of the unloading compressor, a cooler is arranged on one side of the unloading compressor, a liquid separation tank is arranged on one side of the cooler, an eighth pipeline is arranged on one side of the liquid separation tank, and a butadiene gas phase balance pipeline is arranged at one end of the eighth pipeline. The device solves the problems that in the butadiene gas phase pressure relief process of the butadiene storage tank, the released gas phase contains nitrogen, a large amount of butadiene gas phase exists, and butadiene materials are wasted in the daily butadiene storage safety management process, and is provided with various condensation recovery routes.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of butadiene gas phase condensation, in particular to a butadiene gas phase condensation recovery device. Background Art

[0002] Butadiene, as a chemical raw material, is an important component in the chemical industry. However, as a chemical raw material, butadiene itself is an extremely flammable gas, which can easily form an explosive mixture when mixed with air, and can burn and explode when exposed to high heat, open flames or oxidants; it can easily polymerize when exposed to heat or catalysts, and is a key regulated hazardous chemical.

[0003] Related research shows that butadiene will react to form explosive peroxide polymers when the oxygen content in the gas phase is greater than 1.2%. The peroxide polymers will rapidly decompose and spontaneously combust when impacted or heated, causing explosions. They can also break into active free radicals under high temperature or the catalysis of metal ion catalysts such as Fe2+. The active free radicals will polymerize with butadiene molecules again to form end-group polymers, causing the polymer molecules to rapidly increase in size and expand in volume, blocking or bursting equipment pipelines, and ultimately causing accidents.

[0004] At present, the country has put forward strict management requirements for the storage of butadiene and has issued specific documents, requiring that storage tanks involved in butadiene storage should be equipped with a nitrogen sealing system; at the same time, different control measures should be taken for the butadiene liquid phase in different storage cycles.

[0005] The main function of the butadiene gas phase nitrogen sealing system is to automatically add nitrogen to the butadiene storage tank when the pressure in the butadiene storage tank decreases and reaches the set value. At the same time, the gas phase in the tank needs to be depressurized regularly to prevent the butadiene gas phase from self-polymerizing.

[0006] During the butadiene gas phase pressure relief process in the butadiene storage tank, although there is nitrogen in the released gas phase, there is still a large amount of butadiene gas phase. Therefore, there is a phenomenon of butadiene material waste in the daily butadiene storage safety management process.

[0007] In summary, the existing process technology has the defect of material waste, which needs to be improved. In order to achieve the purpose of butadiene recovery and reduce butadiene loss, we propose a butadiene gas phase condensation recovery device. Utility Model Content

[0008] The utility model is to solve the shortcomings in the prior art and propose a butadiene gas phase condensation recovery device. The butadiene gas phase condensation recovery device solves the problem that in the process of butadiene gas phase pressure relief of butadiene in a butadiene storage tank, there is nitrogen component in the released gas phase, but there is still a large amount of butadiene gas phase, so there is a phenomenon of butadiene material waste in the daily butadiene storage safety management process.

[0009] In order to achieve the above purpose, the utility model adopts the following technical solutions:

[0010] A butadiene gas phase condensation recovery device comprises a butadiene storage tank, wherein the number of the butadiene storage tanks is at least two, a truck unloading compressor is arranged on one side of the butadiene storage tank, a truck unloading compressor air outlet pipeline 1 is arranged on one side of the truck unloading compressor, a butadiene tank truck unloading crane position is arranged on one end of the truck unloading compressor air outlet pipeline 1, a cooler is arranged on one side of the truck unloading compressor, a liquid separator tank is arranged on one side of the cooler, a pipeline 8 is arranged on one side of the liquid separator tank, a butadiene gas phase balance pipeline is arranged on one end of the pipeline 8, one end of the butadiene gas phase balance pipeline is connected to one side of the butadiene storage tank, a pipeline 2 is arranged on one end of the pipeline 1, and a butadiene material pump is arranged on one end of the pipeline 2.

[0011] Through the above technical scheme, the butadiene in the butadiene storage tank is sent to the butadiene tank unloading crane position by using the unloading compressor, and the butadiene generated in the transportation process is cooled and recovered by the cooler and sent to the liquid separation tank. According to the situation, the butadiene is recovered by using the butadiene material pump, and sent to the butadiene gas phase balance pipeline through pipeline 8, and finally sent to the butadiene storage tank by the butadiene gas phase balance pipeline, thereby providing a butadiene recovery function.

[0012] Preferably, an unloading compressor air outlet pipeline 1 is arranged between the unloading crane position of the butadiene tank truck and the unloading compressor, a pipeline 4 is arranged on one side of the unloading compressor air outlet pipeline 1, an unloading compressor air outlet pipeline 2 is arranged at one end of the pipeline 4, and one end of the unloading compressor air outlet pipeline 2 is connected to one side of the cooler.

[0013] Through the above technical scheme, the unloading compressor air outlet pipeline 1 is used to provide an air guide function between the butadiene tank unloading crane and the unloading compressor. The pipeline 4 cooperates with the unloading compressor air outlet pipeline 2. When the butadiene storage tank is feeding the butadiene tank unloading crane, the generated dibutylene can flow into the unloading compressor air outlet pipeline 2 through the pipeline 4, and finally flow into the cooler for cooling and recovery.

[0014] Preferably, an unloading compressor air intake pipeline 1 is provided on one side of the unloading compressor, an unloading compressor air intake pipeline 2 is provided at one end of the unloading compressor air intake pipeline 1, and one end of the unloading compressor air intake pipeline 2 is connected to one side of the butadiene storage tank.

[0015] Through the above technical solution, the unloading compressor air intake pipeline 1 cooperates with the unloading compressor air intake pipeline 2 to provide an air guiding function between the butadiene storage tank and the unloading compressor.

[0016] Preferably, a pipeline seven is provided between the cooler and the liquid separation tank, and a nitrogen pipe is provided on one side of the liquid separation tank.

[0017] Preferably, pipeline one is provided on one side of the liquid separation tank, pipeline three is provided at one end of pipeline one, a butadiene storage tank material pipeline is provided at one end of pipeline three, and one end of the butadiene storage tank material pipeline is connected to one side of the butadiene storage tank.

[0018] Through the above technical scheme, the nitrogen pipe can provide a pressure injection function for the liquid separation tank, the pressure in the liquid separation tank is increased, and it flows to pipeline three through pipeline one, and then flows into the butadiene storage tank material pipeline from pipeline three, and then flows into the butadiene storage tank from the butadiene storage tank material pipeline for recovery, so that dibutylene can be recovered without a butadiene material pump.

[0019] Preferably, a pipeline six is ​​provided on one side of the cooler, and a chilled water return inlet area is provided at one end of the pipeline six.

[0020] Preferably, a pipeline five is provided on one side of the cooler, and a chilled water inlet boundary is provided at one end of the pipeline five.

[0021] Through the above technical solution, the chilled water inlet boundary area injects cooling water into the cooler through pipeline five, and then the cooling water flows into the chilled water return water inlet boundary area through pipeline six, providing a cooling function for the cooler.

[0022] In summary, the utility model uses an unloading compressor to transport the butadiene in a butadiene storage tank to a butadiene tank truck unloading position for unloading. The butadiene generated during the transportation process is cooled and recovered by a cooler and sent to a liquid separation tank. According to the situation, a butadiene material pump is used to recover the butadiene, and the butadiene is sent to a butadiene gas phase balance pipeline through pipeline 8. Finally, the butadiene gas phase balance pipeline is sent to a butadiene storage tank, thereby providing a butadiene recovery function.

[0023] The utility model provides a nitrogen pipe with a pressure injection function for the liquid separation tank. The pressure in the liquid separation tank is increased, and the nitrogen pipe flows to the pipeline three through the pipeline one, and then flows into the material pipeline of the butadiene storage tank from the pipeline three, and then flows into the butadiene storage tank from the material pipeline of the butadiene storage tank for recovery, so that dibutylene is recovered without a butadiene material pump.

[0024] In the utility model, the chilled water inlet boundary area injects cooling water into the cooler through pipeline five, and then the cooling water flows into the chilled water return water inlet boundary area through pipeline six, thereby providing a cooling function for the cooler. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 The utility model is a schematic diagram of the process structure of the butadiene gas phase condensation recovery device.

[0026] In the figure: 1. butadiene tank truck unloading crane position; 2. unloading compressor outlet pipeline 1; 3. unloading compressor; 4. unloading compressor air inlet pipeline 1; 5. unloading compressor air inlet pipeline 2; 6. butadiene storage tank; 7. chilled water inlet boundary area; 8. chilled water return water inlet boundary area; 9. cooler; 10. separator tank; 11. pipeline 1; 12. pipeline 2; 13. pipeline 3; 14. pipeline 4; 15. unloading compressor air outlet pipeline 2; 16. pipeline 5; 17. pipeline 6; 18. pipeline 7; 19. nitrogen pipe; 20. pipeline 8; 21. butadiene gas phase balance pipeline; 22. control valve; 23. butadiene material pump; 24. butadiene storage tank material pipeline. DETAILED DESCRIPTION

[0027] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments.

[0028] like Figure 1 As shown, a butadiene gas phase condensation recovery device includes a butadiene storage tank 6, the number of butadiene storage tanks 6 is at least two, a truck unloading compressor 3 is arranged on one side of the butadiene storage tank 6, a truck unloading compressor outlet pipeline 1 2 is arranged on one side of the truck unloading compressor 3, a truck unloading compressor inlet pipeline 1 4 is arranged on one side of the truck unloading compressor 3, a truck unloading compressor inlet pipeline 2 5 is arranged at one end of the truck unloading compressor inlet pipeline 1 4, and one end of the truck unloading compressor inlet pipeline 2 5 is connected to one side of the butadiene storage tank 6,

[0029] One end of the unloading compressor air outlet pipeline 1 is provided with a butadiene tank truck unloading crane 1, one side of the unloading compressor 3 is provided with a cooler 9, an unloading compressor air outlet pipeline 1 is provided between the butadiene tank truck unloading crane 1 and the unloading compressor 3, a pipeline 4 14 is provided on one side of the unloading compressor air outlet pipeline 1, one end of the pipeline 4 14 is provided with an unloading compressor air outlet pipeline 2 15, and one end of the unloading compressor air outlet pipeline 2 15 is connected to one side of the cooler 9,

[0030] A liquid separator 10 is provided on one side of the cooler 9, a pipeline 8 20 is provided on one side of the liquid separator 10, a butadiene gas phase equilibrium pipeline 21 is provided at one end of the pipeline 8 20, one end of the butadiene gas phase equilibrium pipeline 21 is connected to one side of the butadiene storage tank 6, a pipeline 2 12 is provided at one end of the pipeline 1 11, and a butadiene material pump 23 is provided at one end of the pipeline 2 12.

[0031] A pipeline 11 is provided on one side of the liquid separator 10, a pipeline 3 13 is provided on one end of the pipeline 11, a butadiene storage tank material pipeline 24 is provided on one end of the pipeline 3 13, one end of the butadiene storage tank material pipeline 24 is connected to one side of the butadiene storage tank 6, a pipeline 7 18 is provided between the cooler 9 and the liquid separator 10, and a nitrogen pipe 19 is provided on one side of the liquid separator 10.

[0032] A pipeline 6 17 is provided on one side of the cooler 9, and a chilled water return boundary area 8 is provided at one end of the pipeline 6 17. A pipeline 5 16 is provided on one side of the cooler 9, and a chilled water inlet boundary area 7 is provided at one end of the pipeline 5 16. Control valves 22 are sleeved on the outside of all pipelines.

[0033] When the utility model is used, when a task vehicle is loading, the task vehicle stops in the butadiene tank truck unloading crane position 1, one end of the unloading compressor outlet pipeline 2 is connected to the task vehicle, the unloading compressor 3 works, and the unloading compressor inlet pipeline 4 is used to guide air between the butadiene storage tank 6 and the unloading compressor 3. This process is for the butadiene storage tank 6 to transport butadiene to the task vehicle.

[0034] When the utility model is used, when a task vehicle unloads, the task vehicle stops in the butadiene tank truck unloading crane position 1, one end of the unloading compressor outlet pipeline 1 2 is connected to the task vehicle, and the control valve 22 controls the flow rate. The butadiene gas phase flows to the unloading compressor outlet pipeline 2 15 through the pipeline 4 14, and then flows to the cooler 9 from the unloading compressor outlet pipeline 2 15 for condensation operation. After the condensation is completed, the condensed butadiene flows into the liquid separation tank 10 through the pipeline 7 18. The butadiene cooled in the liquid separation tank 10 flows into the butadiene storage tank 6. There are three situations:

[0035] Case 1: The butadiene cooled in the separator 10 can also flow directly into the butadiene gas phase equilibrium pipeline 21 through the pipeline 8 20, and finally flow into the butadiene storage tank 6;

[0036] Case 2: When there is a butadiene material pump 23, the butadiene cooled in the separator 10 flows into the pipeline 1 11, then flows from the pipeline 11 to the pipeline 2 12, and finally flows into the butadiene storage tank 6 from the pipeline 2 12 in cooperation with the butadiene material pump 23;

[0037] Case three: When there is no butadiene material pump 23, nitrogen will be injected into the separator tank 10 through the nitrogen pipe 19 to pressurize it. Then, after the separator tank 10 is pressurized, gas will be introduced into pipeline one 11, and then flow into pipeline three 13, and finally sent from pipeline three 13 to the butadiene storage tank material pipeline 24 and flow into the butadiene storage tank 6.

[0038] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes within the technical scope disclosed by the present invention according to the technical scheme and the utility model concept of the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A butadiene gas phase condensation recovery device, comprising a butadiene storage tank (6), characterized in that: The number of the butadiene storage tanks (6) is at least two. A truck unloading compressor (3) is arranged on one side of the butadiene storage tank (6). A truck unloading compressor outlet pipeline (2) is arranged on one side of the truck unloading compressor (3). A butadiene tank truck unloading crane (1) is arranged at one end of the truck unloading compressor outlet pipeline (2). A cooler (9) is arranged on one side of the truck unloading compressor (3). A liquid separator (10) is arranged on one side of the cooler (9). A pipeline (20) is arranged on one side of the liquid separator (10). A butadiene gas phase equilibrium pipeline (21) is arranged at one end of the pipeline (20). One end of the butadiene gas phase equilibrium pipeline (21) is connected to one side of the butadiene storage tank (6). A pipeline (12) is arranged at one end of the pipeline (11). A butadiene material pump (23) is arranged at one end of the pipeline (12).

2. A butadiene gas phase condensation recovery device according to claim 1, characterized in that: An unloading compressor air outlet pipeline 1 (2) is provided between the unloading crane position (1) of the butadiene tank truck and the unloading compressor (3); a pipeline 4 (14) is provided on one side of the unloading compressor air outlet pipeline 1 (2); an unloading compressor air outlet pipeline 2 (15) is provided at one end of the pipeline 4 (14); and one end of the unloading compressor air outlet pipeline 2 (15) is connected to one side of the cooler (9).

3. A butadiene gas phase condensation recovery device according to claim 1, characterized in that: A first unloading compressor air intake pipeline (4) is provided on one side of the unloading compressor (3), a second unloading compressor air intake pipeline (5) is provided at one end of the first unloading compressor air intake pipeline (4), and one end of the second unloading compressor air intake pipeline (5) is connected to one side of the butadiene storage tank (6).

4. A butadiene gas phase condensation recovery device according to claim 1, characterized in that: A pipeline seven (18) is provided between the cooler (9) and the liquid separation tank (10), and a nitrogen pipe (19) is provided on one side of the liquid separation tank (10).

5. A butadiene gas phase condensation recovery device according to claim 1, characterized in that: A pipeline one (11) is provided on one side of the liquid separation tank (10), a pipeline three (13) is provided at one end of the pipeline one (11), a butadiene storage tank material pipeline (24) is provided at one end of the pipeline three (13), and one end of the butadiene storage tank material pipeline (24) is connected to one side of the butadiene storage tank (6).

6. A butadiene gas phase condensation recovery device according to claim 1, characterized in that: A pipeline six (17) is provided on one side of the cooler (9), and a chilled water return inlet area (8) is provided at one end of the pipeline six (17).

7. A butadiene gas phase condensation recovery device according to claim 6, characterized in that: A pipeline five (16) is provided on one side of the cooler (9), and a chilled water inlet boundary area (7) is provided at one end of the pipeline five (16).