Cement clinker silo bottom discharging structure

Through the cooperation between the adjusting plate and the ejector rod and the screw structure, combined with the motor and pulley transmission, the control of the discharge flow of the cement clinker warehouse is simplified, solving the problems of cumbersome operation and high cost in the existing technology, and achieving convenience and efficiency. flow regulation.

CN221796280UActive Publication Date: 2024-10-01XINXIANG PINGAN CEMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323646606.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-29
Publication Date
2024-10-01
Estimated Expiration
2033-12-29

AI Technical Summary

Technical Problem

During the discharging process of the existing cement clinker warehouse, the adjustment of the baffle plate position by the adjusting equipment is cumbersome and costly, and lacks a convenient flow control method.

Method used

Through the matching setting of the adjusting plate and the ejector, the screw structure is used to realize the self-locking adjustment of the baffle plate position, and combined with the motor, pulley and screw drive, the discharge flow control is simplified and the operation complexity is reduced.

Benefits of technology

It achieves flexible control of the discharge flow of the cement clinker warehouse, facilitates operation, reduces costs, simplifies the equipment structure, and improves the efficiency of the discharge process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221796280U_ABST
    Figure CN221796280U_ABST
Patent Text Reader

Abstract

The utility model discloses a cement clinker silo bottom discharging structure which comprises a discharging pipe and an adjusting assembly. A collecting hopper is arranged in a connecting opening formed in the upper end of the discharging pipe, a limiting plate is arranged on the upper side of the right wall of the discharging pipe, and a cavity is formed in the right side of the interior of the discharging pipe; the adjusting assembly comprises a connecting rod and a striker plate, the connecting rod is rotationally connected to the left side of the interior of the discharging pipe through a bearing, the striker plate is arranged in the middle of the outer arc face of the connecting rod and located on the lower side of the limiting plate, the adjusting assembly further comprises a control switch, the control switch is located outside the discharging pipe, and the input end of the control switch is electrically connected with an external power source. According to the cement clinker silo bottom discharging structure, the position of the material blocking plate can be adjusted, so that the discharging flow of a cement clinker silo is controlled, the structure is simple, meanwhile, self-locking can be achieved through a lead screw structure after the position of the material blocking plate is adjusted, and operation is convenient and fast.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of cement clinker storage equipment, in particular to a cement clinker silo bottom discharge structure. Background Art

[0002] The cement clinker silo is the storage and mixing center of cement clinker in the cement production line. It is usually composed of a cylindrical warehouse and can store a large amount of cement clinker. The temperature of cement clinker is still very high after it leaves the cooler. One of the functions of the cement clinker silo is to cool the clinker to a temperature range acceptable to subsequent production.

[0003] During the discharge process of the cement clinker silo, the cement clinker in the cement clinker silo usually enters the inside of the discharge pipe through the collecting hopper. After that, the staff adjusts the discharge flow of the cement clinker silo through the electric valve according to the actual situation;

[0004] In the process of discharging, the existing cement clinker silo can adjust the discharge flow of the cement clinker silo through electric valves, but the cost of installing electric valves is relatively high. Some cement clinker silos adjust the position of the baffle plate through the internal adjustment device of the discharge pipe, thereby controlling the discharge flow of the cement clinker silo, which replaces the traditional control method through electric valves. However, after the adjustment device adjusts the position of the baffle plate, it is often necessary to add an additional self-locking unit to lock and fix the baffle plate, and the operation is relatively cumbersome. For this reason, we propose a cement clinker silo bottom discharge structure. Utility Model Content

[0005] The technical problem to be solved by the utility model is to overcome the existing defects and provide a cement clinker silo bottom discharge structure. Through the coordinated arrangement of the adjusting plate and the top rod, the position of the baffle plate can be adjusted, thereby realizing the control of the discharge flow rate of the cement clinker silo. The structure is simple, and after the position of the baffle plate is adjusted, it can be self-locked by the screw structure, and the operation is also relatively convenient, which can effectively solve the problems in the background technology.

[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a cement clinker silo bottom discharge structure, comprising a discharge pipe and an adjustment component;

[0007] Discharge pipe: a collecting hopper is arranged in the connection port opened at the upper end thereof, a limit plate is arranged on the upper side of the right wall of the discharge pipe, and a cavity is arranged on the right side inside the discharge pipe;

[0008] Adjustment component: It includes a connecting rod and a baffle plate. The connecting rod is rotatably connected to the left side of the discharge pipe through a bearing. A baffle plate is arranged in the middle of the outer arc surface of the connecting rod. The baffle plate is located on the lower side of the limit plate. The position of the baffle plate can be adjusted by cooperating with the adjustment plate and the top rod, so as to realize the control of the discharge flow rate of the cement clinker bin. The structure is simple. At the same time, after the position of the baffle plate is adjusted, it can be self-locked by the screw structure, and the operation is also relatively convenient.

[0009] Furthermore, it also includes a control switch, which is located outside the discharge pipe. The input end of the control switch is electrically connected to the external power supply and can regulate the electrical components inside the equipment.

[0010] Furthermore, the adjustment component also includes a guide slot, an adjustment plate and a push rod. The guide slots are respectively arranged on the lower sides of the front and rear walls of the discharge pipe. An adjustment plate is slidably connected between the two guide slots. A push rod is arranged on the upper end of the adjustment plate. The upper end of the push rod contacts the lower surface of the baffle plate, thereby adjusting the position of the baffle plate.

[0011] Furthermore, the adjustment assembly also includes a screw rod, which is rotatably connected to the inside of the guide slot through a bearing. The screw rod is threadedly connected to the threaded holes corresponding to the right end of the adjustment plate, and the position of the push rod can be adjusted through the adjustment plate.

[0012] Furthermore, it also includes a mounting rod, a pulley and a double-layer pulley. The mounting rod is rotatably connected to the middle of the left wall of the cavity through a bearing, the double-layer pulley is arranged in the middle of the outer arc surface of the mounting rod, and the pulleys are respectively arranged on the right side of the outer arc surface of the screw. The pulleys are connected to the double-layer pulley through belts, and can drive the screw to rotate through the pulley.

[0013] Furthermore, it also includes a motor, which is arranged at the right end of the discharge pipe, the left end of the motor output shaft is fixedly connected to the right end of the mounting rod, the input end of the motor is electrically connected to the output end of the control switch, and can drive the double-layer pulley to rotate through the mounting rod.

[0014] Furthermore, it also includes mounting holes, which are respectively arranged at the upper end of the collecting bucket to support and fix the discharge pipe and internal equipment.

[0015] Compared with the prior art, the beneficial effects of the utility model are: the cement clinker silo bottom discharge structure has the following advantages:

[0016] In the subsequent use process, the cement clinker in the cement clinker silo passes through the collecting hopper and enters the inside of the discharge pipe. Then, through the regulation of the control switch, the motor starts to run, and the output shaft of the motor drives the mounting rod to rotate, and the mounting rod drives the double-layer pulley to rotate. The double-layer pulley drives the two pulleys to rotate through the belt, thereby driving the two screws to rotate. In the process of the screw rotation, the screw drives the adjustment plate to move to the right through the threaded connection, and the adjustment plate drives the top rod to move to the right. In the process of the top rod moving to the right, the baffle plate begins to rotate upward due to the upward thrust of the top rod. At this time, the distance between the right end of the baffle plate and the inner wall of the discharge pipe is reduced, reducing the flow in the discharge pipe. After adjusting the position of the top rod through the adjusting plate, it can be self-locked through the screw structure, and finally the baffle plate is locked and fixed, thereby realizing the regulation of the discharge flow of the cement clinker silo. Through the coordinated setting of the adjusting plate and the top rod, the position of the baffle plate can be adjusted, thereby realizing the control of the discharge flow of the cement clinker silo. The structure is simple, and at the same time, the position of the baffle plate can be self-locked through the screw structure after adjustment, and the operation is also relatively convenient. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a schematic diagram of the structure of the utility model;

[0018] Figure 2 It is a structural schematic diagram of the adjustment component of the utility model;

[0019] Figure 3 It is a schematic diagram of the upper side sectional structure of the utility model.

[0020] In the figure: 1 discharge pipe, 2 control switch, 3 collection bucket, 4 adjustment component, 41 connecting rod, 42 baffle plate, 43 guide slide, 44 adjustment plate, 45 push rod, 46 screw, 5 mounting rod, 6 pulley, 7 double pulley, 8 motor, 9 limit plate, 10 mounting hole, 11 cavity. DETAILED DESCRIPTION

[0021] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0022] See also Figure 1-3 , This embodiment provides a technical solution: a cement clinker silo bottom discharge structure, including a discharge pipe 1 and an adjustment component 4;

[0023] Discharge pipe 1: A collecting hopper 3 is arranged in the connection port opened at the upper end thereof, a limiting plate 9 is arranged on the upper side of the right wall of the discharge pipe 1, and a cavity 11 is arranged on the right side inside the discharge pipe 1. In the subsequent use process, the cement clinker in the cement clinker silo passes through the collecting hopper 3 and enters the inside of the discharge pipe 1, and then the discharge flow rate of the cement clinker silo is adjusted by the regulating device;

[0024] The adjusting assembly 4 includes a connecting rod 41 and a baffle plate 42. The connecting rod 41 is rotatably connected to the left side of the inside of the discharge pipe 1 through a bearing. A baffle plate 42 is provided in the middle of the outer arc surface of the connecting rod 41. The baffle plate 42 is located at the lower side of the limit plate 9. The adjusting assembly 4 also includes a guide slot 43, an adjusting plate 44 and a push rod 45. The guide slots 43 are respectively arranged on the lower sides of the front and rear walls of the discharge pipe 1. An adjusting plate 44 is slidably connected between the two guide slots 43. A push rod 45 is provided at the upper end of the adjusting plate 44. The upper end of the push rod 45 contacts the lower surface of the baffle plate 42. The adjusting assembly 4 also includes a screw 46. The screw 46 is rotatably connected to the inside of the guide slot 43 through a bearing. The screw 46 is threadedly connected to the threaded holes corresponding to the right end of the adjusting plate 44. In the subsequent use process, the cement clinker in the cement clinker warehouse passes through the collecting bucket 3. After entering the interior of the discharge pipe 1, the driving device starts to operate through the regulation of the control device, and the driving device drives the two screws 46 to rotate. During the rotation of the screw 46, the screw 46 drives the adjusting plate 44 to move to the right through the threaded connection, and the adjusting plate 44 drives the push rod 45 to move to the right. During the movement of the push rod 45 to the right, the baffle plate 42 is pushed upward by the push rod 45 and starts to rotate upward. At this time, the distance between the right end of the baffle plate 42 and the inner wall of the discharge pipe 1 is reduced, reducing the flow rate in the discharge pipe 1, thereby adjusting the discharge flow rate of the cement clinker bin. Through the coordinated setting of the adjusting plate 44 and the push rod 45, the position of the baffle plate 42 can be adjusted, thereby realizing the control of the discharge flow rate of the cement clinker bin. At the same time, after the position of the baffle plate 42 is adjusted, it can be self-locked through the screw structure, and the operation is also relatively convenient.

[0025] Among them: it also includes a control switch 2, which is located outside the discharge pipe 1, and the input end of the control switch 2 is electrically connected to the external power supply, which can regulate the electrical components inside the equipment.

[0026] Wherein: it also includes a mounting rod 5, a pulley 6 and a double-layer pulley 7, the mounting rod 5 is rotatably connected to the middle part of the left wall of the cavity 11 through a bearing, the double-layer pulley 7 is arranged in the middle part of the outer arc surface of the mounting rod 5, the pulleys 6 are respectively arranged on the right side of the outer arc surface of the screw rod 46, the pulleys 6 are connected to the double-layer pulley 7 through a belt, the mounting rod 5 drives the double-layer pulley 7 to rotate, the double-layer pulley 7 drives the two pulleys 6 to rotate through the belt, thereby driving the two screw rods 46 to rotate, during the rotation of the screw rod 46, the screw 46 drives the adjustment plate 44 to move to the right through a threaded connection, the adjustment plate 44 drives the push rod 45 to move to the right, during the movement of the push rod 45 to the right, the baffle plate 42 is pushed upward by the push rod 45 and starts to rotate upward, thereby adjusting the position of the baffle plate 42.

[0027] Wherein: it also includes a motor 8, which is arranged at the right end of the discharge pipe 1, the left end of the output shaft of the motor 8 is fixedly connected to the right end of the mounting rod 5, the input end of the motor 8 is electrically connected to the output end of the control switch 2, and the cement clinker in the cement clinker bin passes through the collecting bucket 3 and enters the inside of the discharge pipe 1, and then the motor 8 starts to run through the regulation of the control switch 2, the output shaft of the motor 8 drives the mounting rod 5 to rotate, the mounting rod 5 drives the double-layer pulley 7 to rotate, and the double-layer pulley 7 drives the two pulleys 6 to rotate through the belt, thereby driving the two screws 46 to rotate.

[0028] Among them: it also includes mounting holes 10, which are respectively arranged at the upper end of the collecting bucket 3. Before use, the cement clinker silo bottom discharge structure is moved to the designated work location through external traction equipment, and the fastening bolts are passed through the mounting holes 10 to connect with the corresponding cement clinker silo, thereby realizing the support and fixation of the discharge pipe 1 and the internal equipment.

[0029] The working principle of the cement clinker silo bottom discharge structure provided by the utility model is as follows: before use, the cement clinker silo bottom discharge structure is moved to the designated work location by an external traction device, and the fastening bolts are passed through the mounting holes 10 to connect with the corresponding cement clinker silo, thereby realizing the support and fixation of the discharge pipe 1 and the internal equipment. In the subsequent use process, the cement clinker in the cement clinker silo passes through the collecting bucket 3 and enters the inside of the discharge pipe 1. Then, through the regulation of the control switch 2, the motor 8 starts to run, and the output shaft of the motor 8 drives the mounting rod 5 to rotate, and the mounting rod 5 drives the double-layer pulley 7 to rotate, and the double-layer pulley 7 is driven by the belt The two pulleys 6 are driven to rotate, thereby driving the two screw rods 46 to rotate. During the rotation of the screw rod 46, the screw rod 46 drives the adjusting plate 44 to move to the right through the threaded connection, and the adjusting plate 44 drives the ejector rod 45 to move to the right. During the movement of the ejector rod 45 to the right, the baffle plate 42 begins to rotate upward due to the thrust of the ejector rod 45. At this time, the distance between the right end of the baffle plate 42 and the inner wall of the discharge pipe 1 is reduced, reducing the flow rate in the discharge pipe 1. After the position of the ejector rod 45 is adjusted by the adjusting plate 44, it can be self-locked through the screw rod structure, and finally the baffle plate 42 is locked and fixed, thereby realizing the regulation of the discharge flow of the cement clinker bin.

[0030] It is worth noting that the motor 8 disclosed in the above embodiment can be selected as 5IK200A-AF, and the control switch 2 is provided with a control button corresponding to the motor 8 for controlling its switch.

[0031] The above description is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the specification and drawings of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A cement clinker silo bottom discharge structure, characterized in that: It comprises a discharge pipe (1) and an adjustment component (4); A discharge pipe (1): a collecting hopper (3) is arranged in a connection opening at the upper end thereof, a limiting plate (9) is arranged on the upper side of the right wall of the discharge pipe (1), and a cavity (11) is arranged on the right side inside the discharge pipe (1); An adjustment assembly (4): comprising a connecting rod (41) and a material baffle plate (42); the connecting rod (41) is rotatably connected to the left side of the discharge pipe (1) via a bearing; a material baffle plate (42) is provided in the middle of the outer arc surface of the connecting rod (41); the material baffle plate (42) is located on the lower side of the limit plate (9).

2. A cement clinker silo bottom discharge structure according to claim 1, characterized in that: It also comprises a control switch (2), wherein the control switch (2) is located outside the discharge pipe (1), and an input end of the control switch (2) is electrically connected to an external power supply.

3. A cement clinker silo bottom discharge structure according to claim 2, characterized in that: The adjustment assembly (4) further comprises a guide slot (43), an adjustment plate (44) and a push rod (45); the guide slot (43) is respectively arranged at the lower side of the front and rear walls of the discharge pipe (1); an adjustment plate (44) is slidably connected between the two guide slots (43); a push rod (45) is arranged at the upper end of the adjustment plate (44); and the upper end of the push rod (45) contacts the lower surface of the baffle plate (42).

4. A cement clinker silo bottom discharge structure according to claim 3, characterized in that: The adjustment assembly (4) further comprises a screw rod (46), wherein the screw rod (46) is rotatably connected to the inside of the guide slide groove (43) via a bearing, and the screw rod (46) is threadedly connected to a corresponding threaded hole arranged at the right end of the adjustment plate (44).

5. A cement clinker silo bottom discharge structure according to claim 4, characterized in that: It also includes a mounting rod (5), a pulley (6) and a double-layer pulley (7), wherein the mounting rod (5) is rotatably connected to the middle of the left wall of the cavity (11) via a bearing, the double-layer pulley (7) is arranged in the middle of the outer arc surface of the mounting rod (5), the pulleys (6) are respectively arranged on the right side of the outer arc surface of the screw rod (46), and the pulleys (6) are connected to the double-layer pulley (7) through a belt.

6. A cement clinker silo bottom discharge structure according to claim 5, characterized in that: It also includes a motor (8), which is arranged at the right end of the discharge pipe (1), the left end of the output shaft of the motor (8) is fixedly connected to the right end of the mounting rod (5), and the input end of the motor (8) is electrically connected to the output end of the control switch (2).

7. A cement clinker silo bottom discharge structure according to claim 1, characterized in that: It also includes mounting holes (10), wherein the mounting holes (10) are respectively arranged at the upper end of the collecting bucket (3).