Hydropower station water inlet trash holding device
By using a combined design of a rigid grid structure and a sliding tensioning device at the water inlet of the hydropower station, the problems of insufficient structural strength and complex installation of the existing pollution-blocking devices are solved, achieving efficient pollution-blocking effects and a simple installation process.
Patent Information
- Application Number
- CN202420279160.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-05
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2034-02-05
AI Technical Summary
The structure of the pollution-blocking net of the existing pollution-blocking device at the water inlet of the hydropower station is insufficient. Debris is easily stuck and the flow of water causes the pollution-blocking net to bulge and the gaps to become larger, resulting in poor pollution-blocking effect. At the same time, the installation process is complicated and inconvenient.
The blocking net uses a rigid grid structure and is connected to the traction rope through a sliding tensioning device. The sliding seat is designed to prevent debris from escaping. The installation adopts a simple structure of shackles or wire rope clamps. The buoy design provides active buoyancy and balance.
It makes it difficult for debris to get stuck and improves the pollution blocking effect. The installation process is simple and efficient. It is suitable for the later installation of dam pollution blocking devices and is easy to maintain.
Smart Images

Figure CN221855440U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of sewage interception at a water inlet of a hydropower station, in particular to a sewage interception device at a water inlet of a hydropower station. Background Art
[0002] A power station is located in the upper reaches of Longjiang River. In recent years, during the rainy season, the river surface is full of debris. At most, branches, wood, bamboo branches and other debris floating on the river surface are dozens of meters long. The half-rotten wood piled up in front of the trash rack is two meters high, which seriously affects the power generation of the unit and even threatens the safety of the dam. In order to improve the production efficiency of the power station and completely eliminate the potential safety hazards, it is planned to install a set of debris interception device at the water inlet of the power station.
[0003] Although Chinese patent document CN111926783B, published / announced on November 13, 2020, discloses a floating trash-blocking and drainage device for a hydropower station, including two slide rails, which are respectively fixed on the walls on both sides of the water inlet of the dam, and pulleys are slidably connected to the two slide rails, and the pulleys are hinged to the two ends of the truss structure. The truss structure is formed by the end-to-end hinge of the float unit, and a trash-blocking net is fixed to the bottom side of the truss structure, and the lower side of the trash-blocking net is fixed to a heavy object. However, due to the relatively low structural strength of the trash-blocking net, when in use, it is necessary to hang a heavy object to ensure that the trash-blocking net is perpendicular to the flow direction of the water body, so as to intercept the debris in the water body. The shortcomings are that the debris is easily stuck on the trash-blocking net and is not easy to remove, such as tree branches and bamboo branches. Secondly, under the drive of the water flow, the debris will squeeze the trash-blocking net, causing the trash-blocking net to bulge in the direction of the water flow, resulting in a larger gap between the two ends of the trash-blocking net and the dam body, and the debris escapes from the gaps at both ends, and the trash-blocking effect is poor. In addition, when installing the float in the device, LLDPE foam must be filled into the float, and then a connecting rod is inserted into the central axis of the float to form a float unit, and then the float units are connected. The installation structure is relatively complicated. At the same time, when installing the trash net under the float, it is necessary to install it underwater, or lift the float out of the water and then install the trash net. The installation of the trash net is very inconvenient. Utility Model Content
[0004] The technical problem to be solved by the utility model is: to solve the problems existing in the above-mentioned background technology, and provide a sewage intercepting device for the water inlet of a hydropower station, in which the blocking net is a grid net structure with a rigid structure, and debris is not easily stuck on the sewage intercepting net, and adjacent blocking nets are connected, and the blocking nets at both ends are respectively connected to the sliding tensioning devices on both sides, so that when debris squeezes the blocking net, the gap between the two ends of the blocking net will not become larger, and the top of the sliding seat exceeds the blocking net, and the bottom is flush with the lower end of the blocking net or extends out of the blocking net, so that the sliding seat can also block debris.
[0005] In order to solve the above technical problems, the technical solution adopted by the utility model is: a sewage intercepting device at the water inlet of a hydropower station, comprising a main buoy, a blocking net, a traction rope and a sliding tensioning device, wherein a plurality of main buoys are arranged, each of which is connected in a row in sequence, a blocking net is installed on the main buoy, and the two ends of the traction rope are respectively connected to the sliding tensioning devices on both sides, and each main buoy is respectively connected to the traction rope, and is characterized in that: the blocking net is a grid net structure, adjacent main buoys are movably connected, each blocking net is respectively suspended and installed on one side of the water-facing surface of each main buoy, each main buoy is respectively connected to the traction rope, and adjacent blocking nets are movably connected; the sliding tensioning devices on both sides respectively include a sliding seat, a guide column and a fixed seat, and the two ends of the guide column are respectively installed with a fixed seat, the fixed seat is used to be installed and fixed with a concrete foundation, the sliding seat is slidably clamped and installed on the guide column, and the two ends of the traction rope and the blocking net close to the sliding tensioning device are respectively connected to the sliding seats on both sides.
[0006] A plurality of first ear seats are axially arranged on one side of the outer wall of the main buoy, a plurality of second ear seats are axially arranged on the top of the outer wall of the main buoy, a third ear seat is arranged on the end of the main buoy, the third ear seats between adjacent main buoys are connected by a first connecting piece, each barrier net is respectively suspended on one side of the water-facing surface of each main buoy through the first ear seat, a second connecting piece is installed on the first ear seat to limit the barrier net, the second ear seat of each main buoy is connected to the traction rope through the third connecting piece, and adjacent barrier nets are connected through a fourth connecting piece, and at least two connecting seats are arranged on the side of the sliding seat close to the barrier net, the uppermost connecting seat is connected to the traction rope, and the remaining connecting seats are connected to the barrier net through the fifth connecting piece.
[0007] The outer wall of the sliding seat is provided with a buoyancy box.
[0008] The main buoy is also provided with a balancing buoy on the side away from the barrier net, and the balancing buoy is connected and fixed to the main buoy through a steel frame.
[0009] A walkway is installed on the top of the steel frame.
[0010] The sliding seat includes side plates, arc wheels and a central shaft. At least two arc wheels are arranged between the two side plates and on both sides of the guide column. The arc wheels are rotatably connected to the central shaft through bearings. Threaded sections are arranged at both ends of the central shaft, and the threaded sections at both ends extend out of the side plates on both sides respectively. The first nut is screwed and installed on the threaded section of the central shaft and presses and fixes the side plates.
[0011] The connecting seat includes a fixed shaft and a connecting plate, the fixed shaft is vertically connected and fixed to the connecting plate, threaded sections are respectively provided at both ends of the fixed shaft, the threaded sections at both ends of the fixed shaft respectively extend out of the side plates on both sides, the second nut is screwed and installed on the threaded section of the fixed shaft, and the fixed shaft is connected and fixed to the side plates on both sides; the traction rope and the barrier net are respectively connected to the corresponding connecting plates on the connecting seat.
[0012] Scrapers are fixedly installed on the opposite sides of the side plates at both sides and on the upper and lower sides of the arc wheel respectively, and the scrapers are provided with scraping parts adapted to the outer walls of the guide pillars.
[0013] The guide column of the sliding tensioning device comprises two longitudinally arranged rods, a plurality of supporting rods are arranged between the two longitudinally arranged rods, and the plurality of supporting rods connect the two longitudinally arranged rods into a whole.
[0014] Positioning plates are respectively arranged at the upper and lower ends of the guide column, a rotating shaft is fixedly arranged on the positioning plate at a side away from the guide column, a rotating hole is arranged at one end of the fixing seat connected to the guide column, and the rotating shaft extends into the rotating hole.
[0015] The utility model has the following beneficial effects:
[0016] 1. The barrier net of the utility model is a rigid grid net structure, and debris is not easy to get stuck on the dirt net. There are connections between adjacent barrier nets, and the barrier nets at both ends are respectively connected to the sliding tensioning devices on both sides. When debris squeezes the barrier net, the gap between the two ends of the barrier net will not become larger. Moreover, the top of the sliding seat exceeds the barrier net, and the bottom is flush with the lower end of the barrier net or extends out of the barrier net, so that the sliding seat can also block debris. When installing the main buoy and barrier net of the present application, shackles or wire rope clamps are used for on-site installation, which has a simple structure and is easy to install.
[0017] 2. The installation of the utility model does not require welding, and the connection of each component adopts the assembly method of shackles or wire rope buckles, which is simple and convenient to install and has high installation and construction efficiency.
[0018] 3. When installing the sliding tensioning device of the utility model, it is only necessary to install and fix the fixing seat, which is easy to install and suitable for the later installation of the pollution-blocking device on the dam of the power station.
[0019] 4. The outer wall of the sliding seat of the utility model is provided with a buoyancy box to provide buoyancy for the sliding seat to actively rise and fall.
[0020] A balancing buoy is installed on the side of the main buoy away from the barrier net to keep the main buoy balanced and not flipped. A walkway is installed on the top of the steel frame to facilitate the maintenance of the device and the walking and slag removal of personnel.
[0021] 5. The sliding seat of the utility model is provided with a scraper. During each up and down movement of the sliding seat, the scraper scrapes off the debris on the surface of the guide column, thereby cleaning the walking area of the arc wheel on the guide column, so that the sliding seat can keep moving flexibly up and down.
[0022] 6. The guide column of the utility model can rotate, so that the sliding seat can swing along the deformation of the traction rope, so that the sliding seat follows the force direction of the traction rope, preventing the sliding seat from being deformed by the traction rope. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] The utility model is further described below in conjunction with the accompanying drawings and embodiments:
[0024] Figure 1 It is a schematic diagram of the main structure of the utility model.
[0025] Figure 2 This is a schematic diagram of the structure of the utility model from a top view, in which the sliding tensioning device is not shown.
[0026] Figure 3 for Figure 2 Schematic diagram of the right view structure.
[0027] Figure 4 It is a schematic diagram of the main structure of the sliding tensioning device of the utility model.
[0028] Figure 5 for Figure 4 Schematic diagram of the K-axis structure.
[0029] Figure 6 This is a schematic structural diagram of the utility model in which the guide column is composed of two rods.
[0030] Figure 7 for Figure 4 Schematic diagram of the AA section structure.
[0031] Figure 8 for Figure 4 Schematic diagram of the BB cross-section structure.
[0032] Fig. 9 for Figure 4 Schematic diagram of the CC cross-section structure.
[0033] Fig.10 It is a schematic diagram of the status of the utility model during on-site installation.
[0034] In the figure, a main buoy 10, a first ear seat 11, a second connecting piece 111, a second ear seat 12, a third connecting piece 121, a third ear seat 13, a first connecting piece 14, a balancing buoy 15, a steel frame 16, a barrier net 20, a fourth connecting piece 21, a traction rope 30, a sliding tensioning device 40, a sliding seat 41, a side plate 411, an arc wheel 412, a central shaft 413, a first nut 414, an end cover 415, a sealing ring 416, a scraper 417, a scraping part 418, a guide column 42, a positioning plate 421, a rotating shaft 422, a supporting rod 423, a fixing seat 43, a connecting seat 44, a fixing shaft 441, a second nut 442, a connecting plate 443, a pontoon 45, a dam body 50, and a rock mass 60. DETAILED DESCRIPTION
[0035] See also Figure 1-10 A sewage interception device for a water inlet of a hydropower station comprises a main buoy 10, a barrier net 20, a traction rope 30 and a sliding tensioning device 40, wherein a plurality of main buoys 10 are provided, and each main buoy 10 is sequentially connected in a row, and a barrier net 20 is installed on the main buoy 10, and both ends of the traction rope 30 are respectively connected to the sliding tensioning devices 40 on both sides, and each main buoy 10 is respectively connected to the traction rope 30, and the barrier net 20 is a grid net structure, and a plurality of first ear seats 11 are axially provided on one side of the outer wall of the main buoy 10, and a plurality of second ear seats 12 are axially provided on the top of the outer wall of the main buoy 10, and a third ear seat 13 is provided at the end of the main buoy 10, and the third ear seats 13 between adjacent main buoys 10 are connected by a first connecting member 14, and each barrier net 20 is respectively suspended by the first ear seat 11 Hanging on the side of the water-facing surface of each main buoy 10, a second connecting member 111 is installed on the first ear seat 11 to limit the barrier net 20, the second ear seat 12 of each main buoy 10 is connected to the traction rope 30 through the third connecting member 121, and the adjacent barrier nets 20 are connected through the fourth connecting member 21. The sliding tensioning devices 40 on both sides respectively include a sliding seat 41, a guide column 42 and a fixed seat 43. Fixed seats 43 are respectively installed at both ends of the guide column 42. The fixed seat 43 is used to be installed and fixed to the concrete foundation. The sliding seat 41 is slidably clamped on the guide column 42. At least two connecting seats 44 are provided on the side of the sliding seat 41 close to the barrier net 20. The uppermost connecting seat 44 is connected to the traction rope 30, and the remaining connecting seats 44 are connected to the barrier net 20 through the fifth connecting member 22.
[0036] Preferably, the first connecting member 14, the second connecting member 111, the third connecting member 121, the fourth connecting member 21 and the fifth connecting member 22 are U-shaped shackles or U-shaped wire rope clamps.
[0037] The blocking net 20 is a rigid grid net structure, and debris is not easily stuck on the blocking net. There are connections between adjacent blocking nets, and the blocking nets at both ends are respectively connected to the sliding tensioning devices 40 on both sides. When debris squeezes the blocking net, the gap between the two ends of the blocking net will not increase. In addition, the top of the sliding seat exceeds the blocking net, and the bottom is flush with the lower end of the blocking net or extends out of the blocking net, so that the sliding seat can also block debris. When installing the main buoy and the blocking net of the present application, a shackle or a wire rope is used for on-site installation, which has a simple structure and is easy to install.
[0038] For further information, see Figure 4-9 As shown, a buoyancy box 45 is provided on the outer wall of the sliding seat 41. When the buoyancy box 45 is not provided, the sliding seat 41 slides up and down by the buoyancy of the main buoy 10, but because the sliding seat 41 has a certain weight, the ends of the main buoy 10 near the sliding seat 41 on both sides will tilt downward. Therefore, after the buoyancy box 45 is provided on the outer wall of the sliding seat 41, the buoyancy of the active lifting is provided for the sliding seat 41.
[0039] For further information, see Figure 2 , 3 The main buoy 10 is also provided with a balancing buoy 15 on the side away from the barrier net 20, and the balancing buoy 15 is connected and fixed to the main buoy 10 by a steel frame 16. Since the barrier net 20 is arranged on the side of the main buoy 10, the main buoy 10 will be subjected to unbalanced force and the barrier net 20 will tilt. Therefore, the balancing buoy 15 is arranged on the side of the main buoy 10 away from the barrier net 20 to keep the main buoy 10 balanced and not flip over.
[0040] It should be noted that the grille structure of the barrier net 20 has a plurality of grille holes. When installed, the first ear seat 11 passes through the grille holes on the barrier net 20, the grille holes cooperate with the first ear seat 11, and the barrier net 20 is connected and fixed to the main buoy 10 under the action of the second connecting member 111. Specifically, a through hole is transversely arranged at the end of the first ear seat 11, and the second connecting member 111 passes through the through hole to form a lock, which locks the barrier net 20 on the first ear seat 11 and fixes it.
[0041] Furthermore, a walkway is installed on the top of the steel frame 16, which is not shown in the figure. The function of the walkway is to maintain the device and for personnel to walk and remove slag. Specifically, the walkway is installed in sections on the steel frame 16. The length of the walkway is slightly shorter than the length of the main buoy 10. The walkway can be a metal frame and a patterned plate. The metal frame is welded on the steel frame 16, and the patterned plate is laid on the metal frame.
[0042] See also Figure 4-9The sliding seat 41 includes a side plate 411, an arc wheel 412 and a central shaft 413. At least two arc wheels 412 are respectively arranged between the two side plates 411 and on both sides of the guide column 42. The arc wheels 412 are rotatably connected to the central shaft 413 through bearings. The two ends of the central shaft 413 are respectively provided with threaded sections, which extend out of the side plates 411 on both sides. The first nut 414 is screwed and installed on the threaded sections of the central shaft 413 and presses and fixes the side plates 411. Through the above structure, the structure of the sliding seat 41 is simple, and the on-site assembly of the sliding seat 41 is convenient.
[0043] Specifically, the four upper and lower arc wheels 412 clamp the guide pillar 42 from both sides respectively, so that the sliding seat 41 can slide flexibly up and down on the guide pillar 42. The buoyancy box 45 is installed on the outer side of the side plate 411.
[0044] For further information, see Figure 7 Because the lower arc wheel 412 is immersed in water, mud and other debris are easy to enter the bearing of the arc wheel 412, causing the bearing to be stuck. Therefore, end covers 415 are installed at both ends of the arc wheel 412, and the end covers 415 and the ends of the arc wheel 412 are sealed by sealant or sealing gaskets. The inner circle of the end cover 415 is installed with a sealing ring 416, and the sealing ring 416 cooperates with the outer wall of the central shaft 413 to form a seal, thereby preventing mud and other debris from entering the bearing.
[0045] For details, see Figure 8 The connecting seat 44 includes a fixed shaft 441 and a connecting plate 443. The fixed shaft 441 is vertically connected and fixed to the connecting plate 443. The two ends of the fixed shaft 441 are respectively provided with threaded sections. The threaded sections at both ends of the fixed shaft 441 extend out of the side plates 411 on both sides. The second nut 442 is screwed and installed on the threaded sections of the fixed shaft 441 to connect and fix the fixed shaft 441 to the side plates 411 on both sides. The traction rope 30 and the blocking net 20 are respectively connected to the corresponding connecting plates 443 on the connecting seat 44. The connecting seat 44 is installed by the second nut 442, which has a simple structure and is convenient for the installation of the connecting seat 44 and the assembly of the entire sliding seat 41.
[0046] Furthermore, two fixing shafts 441 are disposed on each connecting plate 443 .
[0047] See also Figure 5 , 9 , on the opposite side of the side plates 411 on both sides, scrapers 417 are fixedly installed on the upper and lower sides of the arc wheel 412, and the scrapers 417 are provided with scraper parts 418 adapted to the outer wall of the guide column 42. Figure 5 In FIG. 4 , it is shown that scrapers 417 are respectively installed on the upper and lower sides of the arc wheel 412. Fig. 9In the figure, it is shown that the scrapers 417 are respectively installed on the side plates 411 on both sides, and the scrapers 417 on the side plates 411 on both sides are combined to scrape off the debris attached to the walking area of the arc wheel 412 on the guide column 42, so as to facilitate the up and down movement of the sliding seat 41. During each up and down movement of the sliding seat 41, the scraper 418 scrapes off the debris on the surface of the guide column 42, thereby cleaning the walking area of the arc wheel 412 on the guide column 42, so that the sliding seat 41 can keep moving up and down flexibly.
[0048] Specifically, when the guide column 42 is a round tube, the scraping portion 418 of the scraper 417 is a semicircle, and the scraping portions 418 of the scrapers 417 on the left and right sides surround the guide column 42, thereby scraping the outer wall of the entire guide column 42.
[0049] When the guide pillars 42 are two round tubes, a support rod 423 is provided between the two round tubes to connect them. Fig. 9 Each layer of scrapers 417 has four pieces, and the scraping portion 418 of each scraper 417 is a quarter circle, so as to scrape away the debris on the outside of the two round tubes, that is, the walking area of the arc wheel 412.
[0050] See also Figure 4 , 6 Since the distance of the sliding seat 41 floating up and down is about 6 meters, the guide column 42 adopts a single round tube, and the structural strength is low. During the flood period, due to the rapid flow of the flood water and the large amount of debris carried, the guide column 42 may be deformed. Therefore, the guide column 42 of the sliding tensioning device 40 includes two longitudinally arranged rods, and a plurality of supporting rods 423 are arranged between the two longitudinally arranged rods. The plurality of supporting rods 423 connect the two longitudinally arranged rods into a whole, thereby enhancing the structural strength of the guide column 42.
[0051] For further information, see Figure 5 , 6 The upper and lower ends of the guide column 42 are respectively provided with positioning plates 421, and a rotating shaft 422 is fixedly provided on the positioning plate 421 on the side away from the guide column 42. The end of the fixed seat 43 connected to the guide column 42 is provided with a rotating hole, and the rotating shaft 422 extends into the rotating hole. The guide column 42 can rotate, so that the sliding seat 41 can swing along the deformation of the traction rope 30, so that the sliding seat 41 follows the force direction of the traction rope 30, and prevents the sliding seat 41 from being pulled and deformed by the traction rope 30.
[0052] Specifically, when the water inlet of the hydropower station is filled with water for power generation, the water flow carries debris and squeezes the barrier net 20, so that the traction rope 30 forms an arc convex downstream, especially on the side of the dam body 50. At this time, if the sliding seat 41 does not rotate, the traction rope 30 not only exerts a pulling force on the sliding seat 41, but also exerts a thrust on the sliding seat 41 toward the water inlet of the hydropower station, and this thrust will cause the sliding seat 41 to deform. After the sliding seat 41 can rotate, it can adjust its direction by itself, so that the traction rope 30 only exerts a pulling force on the sliding seat 41, thereby preventing the sliding seat 41 from deforming.
[0053] Preferably, the traction rope 30 is a steel wire rope. Of course, a chain can also be used.
[0054] The installation steps of this utility model are as follows:
[0055] Step 1: Install two sliding tensioning devices 40 on the dam body 50 and the rock mass 60 opposite to the dam body 50 respectively.
[0056] For details, see Figure 1 , 4 , 10, the fixing seat 43 of the sliding tensioning device 40 on the side of the dam body 50 is fixed to the dam body by anchor bolts. The rock body 60 needs to be cast with a concrete column first, and the concrete column is fixed to the rock body 60 by anchor bolts during casting. The fixing seat 43 of the sliding tensioning device 40 on the side of the rock body 60 is installed on the concrete column by anchor bolts, and the guide columns 42 of the sliding tensioning devices 40 on both sides are installed perpendicular to the horizontal plane.
[0057] The sliding seat 41 is installed on the guide column 42 in advance. Specifically, the central shaft 413 and the arc wheel 412 are assembled first, the arc wheels 412 on both sides are against the two sides of the guide column 42, and then the side plates 411 on both sides are installed to the two ends of the central shaft 413, and the connecting seat 44 is also synchronously installed and connected with the side plates on both sides.
[0058] When the two sliding tensioning devices 40 are installed, a lifting vessel is used for lifting.
[0059] Step 2: Connect and fix the two ends of the traction rope 30 to the uppermost connection seats 44 of the sliding tensioning devices 40 on both sides respectively.
[0060] See also Figure 1 During installation, the traction rope 30 passes through the hole on the connecting seat 44, then folds back, and fixes the traction rope 30 with the wire rope buckle. Alternatively, a shackle is installed on the connecting seat 44, and the traction rope 30 passes through the shackle and then folds back, and then fixes the traction rope 30 with the wire rope buckle.
[0061] Step three, transport the main buoy 10 by a lifting ship. After the main buoy 10 is transported to one end of the dam body 50 or one end of the rock mass 60, lift the main buoy 10 to the water surface, adjust the position between the end of the main buoy 10 and the sliding seat 41, connect the second ear seat 12 of the main buoy 10 to the traction rope 30 through the third connecting piece 121, and fix the main buoy 10 in position.
[0062] Step 4: Place the next main buoy 10 at the end of the previous main buoy 10, adjust the distance between the main buoy 10 and the previous main buoy 10, flexibly connect the third ear seat 13 between the two main buoys 10 through the first connecting member 14, and then connect and fix the second ear seat 12 of this main buoy 10 to the traction rope 30 through the third connecting member 121; in this way, install the remaining main buoys 10.
[0063] Step five, then install the barrier net 20 in sequence. The barrier net 20 is a grille net structure. The barrier net 20 is transported by a lifting ship and installed starting from the main buoy 10 at one end. The lifting ship lifts the barrier net 20 to the side of the main buoy 10 where the first ear seat 11 is provided. The hole formed by the grille on the barrier net 20 is aligned with the first ear seat 11. Then the barrier net 20 is pushed into the first ear seat 11. The first ear seat 11 extends from the hole formed by the grille on the barrier net 20. The second connecting piece 111 is installed at the protruding end of the first ear seat 11 to limit the barrier net 20 on the first ear seat 11.
[0064] Step 6: Use the method in step 5 to install the barrier net 20 on the next main buoy 10, and movably connect this barrier net 20 with the previous barrier net 20 through the fourth connecting member 21.
[0065] Step 7: Repeat steps 5 and 6 to complete the installation of the barrier nets 20 on all main buoys 10 and the connection between adjacent barrier nets 20.
[0066] Step 8: Connect the barrier nets 20 at both ends to the connection seats 44 located below the traction ropes 30 on the sliding tensioning devices 40 on both sides through the fifth connecting pieces 22, and the installation of the entire floating trash removal device is completed.
[0067] Main design calculations
[0068] 1. Buoyancy of buoy
[0069] The buoy body is made of 6mm steel plate, and the volume of each buoy is 2.941m 3 The weight of the buoy and grille is 1480kg. The draft is calculated to be 315mm and the height above water is 315mm, which can meet the actual operation requirements.
[0070] 2. Main traction force
[0071] The floating trash removal device will generate pulling force under the action of water flow, wind and waves. Assuming that the head difference between the upstream and downstream of the float is 0.3m, after calculation and considering the safety factor, the pulling force is 200kN.
[0072] 3. Traction wire rope configuration
[0073] According to the calculated traction tension, the main traction wire rope is selected as 28ZAA6Vx37S-SF1770 galvanized steel wire rope, whose breaking tension is not less than 1430 kN and the safety factor is above 5.0.
Claims
1. A sewage interception device for a water inlet of a hydropower station, comprising a main buoy (10), a blocking net (20), a traction rope (30) and a sliding tensioning device (40), wherein a plurality of main buoys (10) are provided, and each main buoy (10) is sequentially connected in a row, and a blocking net (20) is installed on the main buoy (10), and both ends of the traction rope (30) are respectively connected to the sliding tensioning devices (40) on both sides, and each main buoy (10) is respectively connected to the traction rope (30). Features: The barrier net (20) is a grid net structure, and adjacent main buoys (10) are movably connected. Each barrier net (20) is suspended and installed on one side of the water-facing surface of each main buoy (10). Each main buoy (10) is connected to a traction rope (30), and adjacent barrier nets (20) are movably connected. The sliding tensioning devices (40) on both sides respectively include a sliding seat (41), a guide column (42) and a fixed seat (43). The two ends of the guide column (42) are respectively installed with a fixed seat (43), and the fixed seat (43) is used to be installed and fixed to a concrete foundation. The sliding seat (41) is slidably clamped and installed on the guide column (42). The two ends of the traction rope (30) and the barrier net (20) close to the sliding tensioning device (40) are respectively connected to the sliding seats (41) on both sides.
2. A sewage interception device for a water inlet of a hydropower station according to claim 1, Features: A plurality of first ear seats (11) are axially arranged on one side of the outer wall of the main buoy (10), a plurality of second ear seats (12) are axially arranged on the top of the outer wall of the main buoy (10), a third ear seat (13) is arranged at the end of the main buoy (10), the third ear seats (13) between adjacent main buoys (10) are connected by a first connecting member (14), each barrier net (20) is respectively suspended on one side of the water-facing surface of each main buoy (10) through the first ear seat (11), and a second connecting member (14) is installed on the first ear seat (11). The connecting piece (111) limits the position of the barrier net (20), the second ear seat (12) of each main buoy (10) is connected to the traction rope (30) through the third connecting piece (121), and adjacent barrier nets (20) are connected through the fourth connecting piece (21). The sliding seat (41) is provided with at least two connecting seats (44) on the side close to the barrier net (20), the uppermost connecting seat (44) is connected to the traction rope (30), and the remaining connecting seats (44) are connected to the barrier net (20) through the fifth connecting piece (22).
3. A sewage interception device for a water inlet of a hydropower station according to claim 1, Features: The outer wall of the sliding seat (41) is provided with a floating box (45).
4. A sewage interception device for a water inlet of a hydropower station according to claim 1, Features: The main buoy (10) is further provided with a balancing buoy (15) on the side away from the barrier net (20), and the balancing buoy (15) is connected and fixed to the main buoy (10) via a steel frame (16).
5. A sewage interception device for a water inlet of a hydropower station according to claim 4, Features: A walkway is installed on the top of the steel frame (16).
6. A sewage interception device for water inlet of a hydropower station according to claim 1, Features: The sliding seat (41) comprises a side plate (411), an arc-shaped wheel (412) and a central shaft (413). At least two arc-shaped wheels (412) are respectively arranged between the two side plates (411) and on both sides of the guide column (42). The arc-shaped wheels (412) are rotatably connected to the central shaft (413) via bearings. Threaded sections are respectively arranged at both ends of the central shaft (413). The threaded sections at both ends extend out of the side plates (411) on both sides. The first nut (414) is screwed onto the threaded section of the central shaft (413) and is pressed to fix the side plates (411).
7. A sewage interception device for a water inlet of a hydropower station according to claim 2, Features: The connecting seat (44) comprises a fixed shaft (441) and a connecting plate (443), the fixed shaft (441) and the connecting plate (443) are vertically connected and fixed, and threaded sections are respectively provided at both ends of the fixed shaft (441), and the threaded sections at both ends of the fixed shaft (441) extend out of the side plates (411) on both sides respectively, and the second nut (442) is screwed and installed on the threaded section of the fixed shaft (441) to connect and fix the fixed shaft (441) and the side plates (411) on both sides; the traction rope (30) and the blocking net (20) are respectively connected to the connecting plates (443) on the corresponding connecting seat (44).
8. A sewage interception device for a water inlet of a hydropower station according to claim 6, Features: Scrapers (417) are fixedly mounted on the sides opposite to the side plates (411) at both sides and on the upper and lower sides of the arc-shaped wheel (412), and the scraper (417) is provided with a scraping portion (418) adapted to the outer wall of the guide column (42).
9. A sewage interception device for water inlet of a hydropower station according to claim 1, Features: The guide column (42) of the sliding tensioning device (40) comprises two longitudinally arranged rods, a plurality of supporting rods (423) are arranged between the two longitudinally arranged rods, and the plurality of supporting rods (423) connect the two longitudinally arranged rods into a whole.
10. A sewage interception device for a water inlet of a hydropower station according to claim 9, Features: Positioning plates (421) are respectively provided at the upper and lower ends of the guide post (42); a rotating shaft (422) is fixedly provided on the positioning plate (421) at a side away from the guide post (42); a rotating hole is provided at one end of the fixing seat (43) connected to the guide post (42); and the rotating shaft (422) extends into the rotating hole.
Citation Information
Cited By
A water intake trash rack floating device for a hydropower station and a method for installing the same
CN117966678B
Construction device for floating blocking structure of hydropower station and construction method of construction device
CN120739073A