Wind barrier device for manual refrigeration of mine high-temperature roadway

By setting up a wind barrier device in the high-temperature tunnel of the mine, dividing the tunnel into a refrigerated area and a non-refrigerated area, and using a telescopic tube structure to isolate hot and cold air, the problem of poor cooling effect of the artificial refrigeration system in the high-temperature tunnel has been solved and achieved Rapid cooling and energy saving effects.

CN221856782UInactive Publication Date: 2024-10-18CENT SOUTH UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202322733987.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-10-12
Publication Date
2024-10-18
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Artificial refrigeration in high-temperature mine tunnels has poor cooling effect, high cost, low cooling capacity utilization, and inability to cool quickly. Especially in underground metal mine excavation tunnels, the working surface is scattered and wide, resulting in poor cooling effect.

Method used

Design a wind barrier device that divides the high-temperature excavation tunnel into a refrigeration area and a non-refrigeration area through the first wind barrier, the second wind barrier and the third wind barrier, and uses vertical pipes, transverse pipes and fixed devices to connect the artificial refrigeration system. The third wind barrier adopts a perforated vertical tube and perforated horizontal tube structure. The support rods can rotate and telescope to form an isolation structure to reduce the heat exchange of hot and cold air.

Benefits of technology

It effectively improves the cooling effect of the artificial refrigeration system, reduces energy consumption, realizes rapid cooling of the refrigeration area, improves the utilization rate of cooling capacity, reduces cooling costs, and ensures the safety and production efficiency of workers.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221856782U_ABST
    Figure CN221856782U_ABST
Patent Text Reader

Abstract

The utility model discloses a wind barrier device for manual refrigeration of a mine high-temperature roadway. The wind barrier device comprises a first wind barrier, a second wind barrier and a third wind barrier which are arranged in the high-temperature tunneling roadway. The high-temperature tunneling roadway is divided into a refrigeration area and a non-refrigeration area through the wind barrier device. The first wind barrier and the second wind barrier are connected to the left side and the right side of the artificial refrigeration system through the first connecting structure and the second connecting structure correspondingly, and the first wind barrier, the second wind barrier, the first connecting structure and the second connecting structure are completely consistent. The third wind barrier is connected to the top of the artificial refrigeration system through a third connecting structure; the first wind barrier, the second wind barrier and the third wind barrier are used for isolating the refrigeration area from the non-refrigeration area so as to reduce heat exchange of cold air and hot air. The first wind barrier, the second wind barrier and the third wind barrier are used for isolating a refrigeration area and a non-refrigeration area of the high-temperature tunneling roadway, the cooling capacity generated by the manual refrigeration system is limited within the range of the refrigeration area to the maximum extent, and the refrigeration cooling space range is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a wind barrier, in particular to a wind barrier device for artificial refrigeration of a high-temperature tunnel in a mine. Background Art

[0002] As the mining depth continues to increase, the problem of high temperature heat damage in mines has become increasingly prominent and has become a focus of attention in the mining and safety fields. In recent years, various mine cooling technologies have been developed rapidly, and artificial refrigeration cooling technology has been widely used. However, this type of refrigeration cooling technology has shortcomings such as large input power of the refrigeration system, high refrigeration cost, low cold capacity utilization, and inability to quickly refrigerate the refrigeration area. Especially in underground metal mine excavation tunnels, the working points of the working face are scattered and the range is wide. Artificial refrigeration equipment has a poor cooling effect due to the large refrigeration range.

[0003] Therefore, how to improve the artificial refrigeration and cooling effect of the tunnel working face, reduce the cooling cost, realize rapid cooling of the refrigeration area, and achieve the purpose of on-demand cooling is a technical problem that needs to be urgently solved in the field of tunnel cooling technology. Utility Model Content

[0004] In order to solve the above problems, the following technical solutions are proposed:

[0005] A wind barrier device for artificial cooling in a high-temperature mine tunnel, comprising a first wind barrier, a second wind barrier and a third wind barrier arranged in the high-temperature tunnel;

[0006] The high-temperature tunneling roadway is separated into cooling area and non-cooling area by wind barrier devices;

[0007] The first wind barrier and the second wind barrier are connected to the left and right sides of the artificial refrigeration system through the first connecting structure and the second connecting structure respectively, and the first wind barrier and the second wind barrier, the first connecting structure and the second connecting structure are completely consistent;

[0008] The third wind barrier is connected to the top of the artificial refrigeration system through a third connecting structure;

[0009] The first wind barrier, the second wind barrier and the third wind barrier are used to isolate the refrigeration area from the non-refrigeration area to reduce the heat exchange between cold and hot air.

[0010] Furthermore, the first connection structure and the second connection structure include a vertical tube, a transverse tube and a fixing device, wherein the fixing device is connected to the artificial refrigeration system, the vertical tube is connected to the fixing device, and the transverse tube is connected to the vertical tube via a connecting piece.

[0011] Furthermore, the transverse tube can rotate around the connecting piece.

[0012] Furthermore, the third connection structure includes a perforated vertical pipe, a perforated horizontal pipe and a support rod. The perforated horizontal pipe is connected to the artificial refrigeration system, and the perforated vertical pipe is connected to the perforated horizontal pipe; the perforated vertical pipe and the perforated horizontal pipe are both provided with circular holes. One end of the support rod is connected to the circular hole of the vertical pipe, and the other end is connected to the circular hole of the horizontal pipe.

[0013] Furthermore, a plurality of vertical tube circular holes and horizontal tube circular holes may be provided.

[0014] Furthermore, the perforated vertical pipe can rotate around the connection between it and the perforated horizontal pipe.

[0015] Furthermore, the transverse tube, the perforated vertical tube and the connecting rod all adopt a telescopic tube structure.

[0016] The beneficial effects of the utility model are as follows:

[0017] The first wind barrier, the second wind barrier and the third wind barrier are used to isolate the refrigeration area and the non-refrigeration area of ​​the high-temperature tunneling tunnel, and to limit the cooling capacity generated by the artificial refrigeration system to the refrigeration area to the maximum extent, reduce the refrigeration and cooling space range, and achieve rapid refrigeration of the refrigeration area, which can effectively improve the cooling effect of the artificial refrigeration system, improve the thermal environment of the high-temperature tunneling tunnel, and ensure the physical and mental safety of the operators, thereby improving the work efficiency of the operators and ensuring safe and efficient production of the mine. In addition, isolating the refrigeration area from the non-refrigeration area can reduce the heat exchange between the hot air in the non-refrigeration area and the cold air in the refrigeration area after cooling, improve the utilization rate of cooling capacity, and achieve the purpose of reducing energy consumption and saving cooling costs.

[0018] The wind barrier structure used for high-temperature tunneling tunnel refrigeration equipment can not only improve the cooling effect of the refrigeration equipment and achieve rapid refrigeration of the high-temperature tunneling tunnel working area, but also reduce the energy consumption of the refrigeration equipment and save costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a front view of a wind barrier device for artificial cooling in a high-temperature mine tunnel;

[0020] Figure 2 It is a three-dimensional structural diagram of a wind barrier device for artificial cooling of a high-temperature tunnel in a mine;

[0021] Figure 3 This is a working principle diagram of a wind barrier device for artificial cooling in high-temperature mine tunnels.

[0022] The description of the accompanying drawings is as follows: 1. First wind barrier; 2. Second wind barrier; 3. Third wind barrier; 4. Artificial refrigeration system; 5. High-temperature excavation tunnel; 6. Vertical pipe; 7. Fixing device; 8. Connector; 9. Horizontal pipe; 10. Perforated vertical pipe; 11. Perforated horizontal pipe; 12. Vertical pipe circular hole; 13. Horizontal pipe circular hole; 14. Support rod; 15. Refrigeration area; 16. Non-refrigeration area; 17. Operator. Implementation

[0023] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.

[0024] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0025] The utility model is further described below in conjunction with the accompanying drawings:

[0026] like Figure 1 and Figure 3 As shown, the utility model discloses a wind barrier device for artificial refrigeration of a high-temperature tunnel in a mine, comprising a first wind barrier 1, a second wind barrier 2 and a third wind barrier 3 arranged in a high-temperature tunneling tunnel 5, wherein the high-temperature tunneling tunnel 5 is divided into a refrigeration zone 15 and a non-refrigeration zone 16; the first wind barrier 1 and the second wind barrier 2 are respectively connected to the left and right sides of an artificial refrigeration system 4 through a first connecting structure and a second connecting structure, and the first wind barrier 1 and the second wind barrier 2, the first connecting structure and the second connecting structure are completely consistent; the third wind barrier 3 is connected to the upper side of the artificial refrigeration system 4 through a third connecting structure; the first wind barrier 1, the second wind barrier 2 and the third wind barrier 3 are used to isolate the refrigeration zone 15 and the non-refrigeration zone 16 to reduce the heat exchange of cold and hot air.

[0027] In one embodiment of the utility model, the working process of the wind barrier device is as follows: the first wind barrier 1 and the second wind barrier 2 are respectively installed on the left and right sides of the artificial refrigeration system 4 through the first connection structure and the second connection structure, and the third wind barrier 3 is installed on the top of the artificial refrigeration system 4 through the third connection structure. The first wind barrier 1, the second wind barrier 2 and the third wind barrier 3 together form an isolation wind barrier around the artificial refrigeration system 4, isolating the refrigeration area 15 and the non-refrigeration area 16 of the high-temperature excavation tunnel 5, and sealing the cold energy generated by the artificial refrigeration system 4 in the refrigeration area 15 to the greatest extent, so that it continuously exchanges heat with the hot air in the refrigeration area 15, and reduces the heat exchange between the cold air in the refrigeration area 15 and the hot air in the non-refrigeration area 16, so as to achieve rapid refrigeration and cooling of the refrigeration area 15.

[0028] like Figure 1 and Figure 2 As shown, specifically, the first connection structure and the second connection structure include a vertical pipe 6, a horizontal pipe 9 and a fixing device 7. The fixing device 7 is connected to the artificial refrigeration system 4, the vertical pipe 6 is connected to the fixing device 7, and the horizontal pipe 9 is connected to the vertical pipe 6 through a connector 8.

[0029] The first wind barrier 1 and the second wind barrier 2 are mounted on the transverse pipe 9 , while the third wind barrier 3 is mounted on the perforated vertical pipe 10 .

[0030] The third connection structure includes a perforated vertical pipe 10, a perforated horizontal pipe 11 and a support rod 14. The perforated horizontal pipe 11 is connected to the refrigeration equipment 4, and the perforated vertical pipe 10 is hingedly connected to the perforated horizontal pipe 11. The perforated vertical pipe 10 and the perforated horizontal pipe 11 are respectively provided with a vertical pipe circular hole 12 and a horizontal pipe circular hole 13. The two ends of the support rod 14 are respectively connected to the vertical pipe circular hole 12 and the horizontal pipe circular hole 13, and are used to fix and support the perforated vertical pipe 10, and can maintain the support fixation within the range of 0-90 degrees.

[0031] In this embodiment, when the operator 17 is working on the working face of the high-temperature excavation tunnel, the transverse pipe 9 can be fixed on the two sides of the high-temperature excavation tunnel 5, and the perforated vertical pipe 10 can be fixed on the top plate of the high-temperature excavation tunnel 5, so that the first wind barrier 1, the second wind barrier 2 and the third wind barrier 3 are fully deployed to isolate the refrigeration area 15 and the non-refrigeration area 16.

[0032] like Figure 1 and Figure 2As shown, the transverse pipe 9, the perforated vertical pipe 10 and the support rod 14 are all telescopic pipes. For the high-temperature excavation tunnel 5 with a large tunnel section, when the transverse pipe 9 and the perforated vertical pipe 10 are too short to be fixed to the two sides and the top plate of the tunnel respectively, the operator 17 can extend them to a suitable position according to the actual situation. At the same time, the length of the support rod 14 and its angle with the perforated transverse pipe 11 are adjusted so that its two ends are fixed in the vertical pipe circular hole 12 and the transverse pipe circular hole 13 respectively, so that the third wind barrier 3 can be fully deployed, and the cooling area 15 and the non-cooling area 16 of the high-temperature excavation tunnel 5 are isolated to the greatest extent, and the cooling area is closed.

[0033] like Figure 2 As shown, a plurality of vertical tube circular holes 12 on the perforated vertical tube 10 and a plurality of horizontal tube circular holes 13 on the perforated horizontal tube 11 can be provided according to actual conditions, so as to adjust the angle of the support rod 14 and realize an angle tilt within the range of 0-90° of the third wind barrier 3, so as to better adapt to the actual conditions of different high-temperature excavation tunnels 5.

[0034] In one aspect of the embodiment of the present utility model, Figure 1 As shown, the horizontal pipe 9 is fixed perpendicularly to the two sides of the tunnel, the perforated vertical pipe 10 is fixed perpendicularly to the tunnel roof, the first wind barrier 1, the second wind barrier 2 and the third wind barrier 3 respectively block the left side, the right side and the top of the artificial refrigeration system 4, Figure 1 The blank area in should not be completely enclosed, such as Figure 1 As shown in A in the middle, it is to ensure that the toxic and harmful gases in the high-temperature excavation working face can be discharged, thereby ensuring the physical and mental safety of the operating personnel 17.

[0035] like Figure 2 As shown, the perforated vertical pipe 10 can be rotated at the connection with the perforated horizontal pipe 11 through the hinge. When the height of the high-temperature excavation tunnel 5 is so low that the perforated vertical pipe 10 cannot be fixed perpendicularly to the tunnel roof, the operator 17 can rotate the perforated vertical pipe 10 and extend it to a suitable position, and at the same time adjust the connection hole positions of the support rod 14 and the vertical pipe circular hole 12 and the horizontal pipe circular hole 13 to enable it to stably support the third wind barrier 3.

[0036] like Figure 1 and Figure 3 As shown, in some embodiments of the present invention, the artificial refrigeration system 4 is placed in the middle of the tunnel, the first wind barrier 1 is used to close the left area of ​​the artificial refrigeration system 4, and the second wind barrier 2 is used to close the right area of ​​the artificial refrigeration system 4. However, when the cross-sectional width of the high-temperature excavation tunnel 5 is small, placing the artificial refrigeration system 4 in the middle of the tunnel will hinder the operation of equipment and personnel from entering and exiting, the transverse pipe 9 on one side can be rotated to be parallel to the artificial refrigeration system 4, such as Figure 3As shown in B, even if the first wind barrier 1 or the second wind barrier 2 is parallel to the artificial refrigeration system 4, and the length of the other side transverse pipe 9 is adjusted to be fixed to the side of the laneway, the artificial refrigeration system 4 can be close to one side of the laneway, and the wind barrier is placed between the artificial refrigeration system 4 and the other side of the laneway, which does not affect the operation of equipment and the entry and exit of personnel.

[0037] The wind barrier structure for high-temperature tunnel refrigeration equipment using the above technical solution first needs to adjust the length and angle of the transverse pipe 9 according to the actual situation of the high-temperature tunnel 5 so that the first wind barrier 1 and (or) the second wind barrier 2 are fully deployed, and the left and right side areas of the artificial refrigeration system 4 are closed; then, by adjusting the length and angle of the perforated vertical pipe 10 and the support rod 14, the third wind barrier 3 is fully deployed, and the upper side area of ​​the artificial refrigeration system 4 is closed, thereby improving the utilization rate of cold capacity and achieving the purpose of rapid refrigeration and energy saving.

[0038] Unless otherwise stated, any technical solution disclosed in the above utility model, if it discloses a numerical range, then the disclosed numerical range is a preferred numerical range. Any technician in the field should understand that the preferred numerical range is only a numerical value with a more obvious technical effect or representative value among many feasible numerical values. Since there are too many numerical values ​​to be exhaustive, the utility model discloses only some numerical values ​​to illustrate the technical solution of the utility model, and the numerical values ​​listed above should not constitute a limitation on the scope of protection of the utility model.

[0039] At the same time, if the above-mentioned utility model discloses or involves components or structural parts that are fixedly connected to each other, then, unless otherwise stated, the fixed connection can be understood as: a detachable fixed connection (for example, connected by bolts or screws), and can also be understood as: a non-detachable fixed connection (for example, riveting, welding). Of course, the mutual fixed connection can also be replaced by an integrated structure (for example, manufactured by one-piece molding using a casting process) (except when it is obviously impossible to use an one-piece molding process).

[0040] In addition, the terms used in any technical solution disclosed in the above utility model to indicate positional relationship or shape include the state or shape that is similar, similar or close to it unless otherwise stated. Any component provided by the utility model can be assembled from multiple separate components, or it can be a separate component manufactured by an integrated molding process.

[0041] The above shows and describes the basic principle, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments, and the above embodiments and descriptions are only for explaining the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, and these changes and improvements fall within the scope of the utility model to be protected.

Claims

1. A wind barrier device for artificial refrigeration in a high-temperature mine tunnel, characterized in that: It includes a first wind barrier, a second wind barrier and a third wind barrier arranged in a high-temperature excavation tunnel; The high-temperature excavation tunnel is separated into a cooling area and a non-cooling area by a wind barrier device; The first wind barrier and the second wind barrier are connected to the left and right sides of the artificial refrigeration system through the first connecting structure and the second connecting structure respectively, and the first wind barrier and the second wind barrier, the first connecting structure and the second connecting structure are completely consistent; The third wind barrier is connected to the top of the artificial refrigeration system through a third connecting structure; The first wind barrier, the second wind barrier and the third wind barrier are used to isolate the refrigeration area and the non-refrigeration area to reduce the heat exchange between cold and hot air.

2. The wind barrier device for artificial cooling of high-temperature mine tunnels according to claim 1, characterized in that: The first connection structure and the second connection structure include vertical pipes, transverse pipes and fixing devices, wherein the fixing device is connected to the artificial refrigeration system, the vertical pipes are connected to the fixing device, and the transverse pipes are connected to the vertical pipes through connecting pieces.

3. The wind barrier device for artificial cooling of high-temperature mine tunnels according to claim 2, characterized in that: The transverse tube can rotate around the connecting piece.

4. The wind barrier device for artificial cooling of high-temperature mine tunnels according to claim 1, characterized in that: The third connection structure includes a perforated vertical tube, a perforated horizontal tube and a support rod, wherein the perforated horizontal tube is connected to the artificial refrigeration system, and the perforated vertical tube is connected to the perforated horizontal tube; circular holes are provided on the perforated vertical tube and the perforated horizontal tube, one end of the support rod is connected to the circular hole of the vertical tube, and the other end is connected to the circular hole of the horizontal tube.

5. The wind barrier device for artificial cooling of high-temperature mine tunnels according to claim 4, characterized in that: The vertical tube circular hole and the horizontal tube circular hole can be provided in plurality.

6. The wind barrier device for artificial cooling of high-temperature mine tunnels according to claim 5, characterized in that: The perforated vertical pipe can rotate around the connection between the perforated vertical pipe and the perforated horizontal pipe.

7. A wind barrier device for artificial cooling of a high-temperature mine tunnel according to any one of claims 2 to 6, characterized in that: The transverse tube, the perforated vertical tube and the connecting rod all adopt a telescopic tube structure.