Coal blockage preventing device of CFB boiler
By designing a combined device of hot air ducts and cold air ducts in the CFB boiler, using hot air drying and cold air blowing, the problem of coal clogging is solved, ensuring uniform coal diffusion, improving the operational stability of the boiler, and avoiding downtime due to clogging. transport.
Patent Information
- Application Number
- CN202420429023.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-06
- Publication Date
- 2024-10-22
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
During the coal feeding process, CFB boilers are prone to blockage due to moisture in the coal, which affects operational stability and leads to boiler flameout and passive outage.
A CFB boiler anti-coal blocking device is designed, which includes a hot air pipe and a coal drop pipe installed on the side of the boiler. The hot air pipe transports hot air to dry the coal, and the cold air pipe transports cold air to blow the coal to prevent accumulation and deal with blockage through dredge holes. The tilted flat steel plate and Z-shaped cold air duct structure ensure even diffusion and transportation of coal.
It effectively prevents coal from sticking, blocking and accumulating during transportation, ensures that coal evenly enters the boiler furnace, improves the operational stability of CFB boilers and avoids unnecessary outages.
Smart Images

Figure CN221881450U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of coal blocking prevention for CFB boilers, in particular to a coal blocking prevention device for CFB boilers. Background Art
[0002] When a power plant is generating electricity, it uses the heat energy generated by the combustion of combustibles to generate thermal power, which is one way of generating electricity for the power plant. However, since most combustibles are burned in CFB boilers, and the coal feeding method of CFB boilers is that the incoming coal is crushed and then transported to the coal bunker in front of the furnace, and then delivered to the furnace through the conveying pipeline in front of the furnace, the operating stability of the CFB boiler will be affected by the blockage of the coal feeding system, resulting in the boiler often shutting down due to blockage such as wet coal feeding during operation, and passive shutdown. Utility Model Content
[0003] The utility model aims to provide a CFB boiler coal blocking prevention device to solve the problems existing in the prior art in the above-mentioned background technology.
[0004] In order to solve the problems existing in the prior art, the utility model provides a CFB boiler coal blocking prevention device, comprising a boiler, a hot air duct is provided on the side of the boiler, a coal dropping pipe is provided on the side of the hot air duct, a cold air duct is provided on the other side of the hot air duct, an observation port is provided at the end of the hot air duct, a flat steel plate is provided on the side of the boiler and below the hot air duct, and dredging holes are provided on the side of the coal dropping pipe and the other side of the hot air duct.
[0005] Preferably, the hot air pipe is installed on the side of the boiler in an inclined shape, and the coal drop pipe is installed vertically above the hot air pipe.
[0006] Preferably, one end of the hot air pipe is bent downward into a horizontal shape, and the observation port is installed at the bending position of the hot air pipe, and the observation port is coaxial with the other end of the hot air pipe.
[0007] Preferably, the flat steel plate is installed on the side of the boiler in an inclined state, and the inclination angle is 45 degrees to 60 degrees.
[0008] Preferably, the bottom end of the flat steel plate extends to the inner side of the boiler, and the bottom end of the flat steel plate is flush with the inner wall of the boiler.
[0009] Preferably, the cold air duct is in a Z-shape.
[0010] Preferably, the cold air duct is located at the bottom of the hot air duct and close to the other end of the hot air duct.
[0011] Preferably, the top end of the flat steel plate is bent.
[0012] Compared with the prior art, the utility model has the following beneficial effects:
[0013] After the coal in the coal bin in front of the furnace of the utility model enters the coal dropping pipe, the hot air pipe transports hot air and coal, and dries the coal by the hot air during the movement of the coal to prevent the coal from sticking and clogging. At the same time, the cold air pipe transports cold air to blow the coal and spread it into the furnace of the boiler to avoid the accumulation of coal in the coal dropping pipe, which would cause the hot air pipe to be blocked by incomplete coal transportation. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0015] Figure numerals: 1. boiler; 2. coal drop pipe; 3. hot air pipe; 4. cold air pipe; 5. flat steel plate; 6. observation port; 7. dredging hole. DETAILED DESCRIPTION
[0016] In order to make the technical means, creative features, objectives and effects of the utility model easy to understand, the utility model is further described below in conjunction with specific embodiments and drawings, but the following embodiments are only preferred embodiments of the utility model, not all. Based on the embodiments in the implementation mode, other embodiments obtained by those skilled in the art without creative work are all within the protection scope of the present invention.
[0017] The specific embodiments of the present utility model are described below in conjunction with the accompanying drawings.
[0018] Example 1
[0019] like Figure 1 As shown, a CFB boiler coal blocking prevention device comprises a boiler 1, a hot air pipe 3 is obliquely installed on the side of the boiler 1, a vertical coal dropping pipe 2 is installed above the hot air pipe 3, a cold air pipe 4 is provided on the other side of the hot air pipe 3, an observation port 6 is provided at the end of the hot air pipe 3, a flat steel plate 5 with a bent top is inserted on the side of the boiler 1 and below the hot air pipe 3, and dredging holes 7 are provided on the side of the coal dropping pipe 2 and the other side of the hot air pipe 3.
[0020] One end of the hot air pipe 3 is bent downward into a horizontal shape, and the observation port 6 is installed at the bending part of the hot air pipe 3. The observation port 6 is coaxial with the other end of the hot air pipe 3, and the observation port 6 is used to observe the coal feeding situation.
[0021] Among them, the flat steel plate 545 degrees -60 degrees is inclined deep into the furnace, and the end of the flat steel plate 5 is flush with the refractory material in the furnace of the boiler 1, which mainly prevents the coal from accumulating on the wall at the bottom of the furnace and evenly diffuses it.
[0022] The cold air duct 4 is in a Z-shape and is located at the bottom of the hot air duct 3 and close to the other end of the hot air duct 3. To prevent coal from accumulating in the coal drop pipe, a cold air duct 4 is connected to the bottom of the hot air duct 3 to blow the coal and spread it into the furnace.
[0023] Working principle:
[0024] After the coal in the coal bunker in front of the furnace enters the coal dropping pipe 2, the hot air pipe 3 transports hot air and coal, and dries the coal by hot air during the movement of the coal to prevent coal sticking and clogging. At the same time, the cold air pipe 4 transports cold air to blow the coal and spread it into the furnace of the boiler 1 to avoid coal accumulation in the coal dropping pipe, which causes incomplete blockage of the hot air pipe 3. The air volume is appropriately adjusted according to the moisture level of the coal to prevent mutual interference from affecting the coal dropping. At the same time, the coal dropping situation on the inside of the hot air pipe 3 is observed through the observation port 6. When the hot air pipe 3 and the inside of the coal dropping pipe 2 are blocked, they can be dredged through the dredging hole 7.
[0025] The above shows and describes the basic principle, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only preferred examples of the utility model and are not used to limit the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection of the utility model is defined by the attached claims and their equivalents.
Claims
1. A CFB boiler coal blocking prevention device, comprising a boiler (1), characterized in that: A hot air pipe (3) is provided on the side of the boiler (1), a coal dropping pipe (2) is provided on the side of the hot air pipe (3), a cold air pipe (4) is provided on the other side of the hot air pipe (3), an observation port (6) is provided at the end of the hot air pipe (3), a flat steel plate (5) is provided on the side of the boiler (1) and below the hot air pipe (3), and dredging holes (7) are provided on the side of the coal dropping pipe (2) and the other side of the hot air pipe (3).
2. A CFB boiler coal blocking prevention device according to claim 1, characterized in that: The hot air pipe (3) is installed in an inclined manner on the side of the boiler (1), and the coal drop pipe (2) is installed in a vertical manner above the hot air pipe (3).
3. A CFB boiler coal blocking prevention device according to claim 1, characterized in that: One end of the hot air pipe (3) is bent downward into a horizontal shape, and the observation port (6) is installed at the bending position of the hot air pipe (3). The observation port (6) is coaxial with the other end of the hot air pipe (3).
4. A CFB boiler coal blocking prevention device according to claim 1, characterized in that: The flat steel plate (5) is installed on the side of the boiler (1) in an inclined state, and the inclination angle is 45 degrees to 60 degrees.
5. The CFB boiler coal blocking prevention device according to claim 1, characterized in that: The bottom end of the flat steel plate (5) extends to the inner side of the boiler (1), and the bottom end of the flat steel plate (5) is flush with the inner wall of the boiler (1).
6. A CFB boiler coal blocking prevention device according to claim 1, characterized in that: The cold air pipe (4) is in a Z-shape.
7. The device for preventing coal blockage of a CFB boiler according to claim 1, characterized in that: The cold air pipe (4) is located at the bottom of the hot air pipe (3) and close to the other end of the hot air pipe (3).
8. The device for preventing coal blockage of a CFB boiler according to claim 1, characterized in that: The top end of the flat steel plate (5) is bent.