Connecting device supporting peak load shifting of power grid
By designing an electrical connection device to coordinate energy storage equipment and mains power supply, and determining the power supply source based on peak and valley power consumption time and electricity, the problem of difficult to alleviate the load pressure of the power grid is solved, and effective peak-cutting and valley filling of the power grid load is achieved. Improve the effectiveness of peak and valley electricity price policy.
Patent Information
- Application Number
- CN202323400513.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-13
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2033-12-13
AI Technical Summary
The existing technology is difficult to effectively alleviate the load pressure of the power grid during peak power consumption, and the lack of connection devices for power storage equipment and inverters, resulting in the lack of peak-to-valley electricity price policy.
Design an electrical connection device, including mains input detection circuit, inverter input detection circuit, control relay, peak and valley control logic and wiring posts. By preparing a microcontroller program, coordinate energy storage equipment and mains power supply, and use the peak and valley power according to peak and valley power. Time and electricity determine the source of power supply, achieving peak cutting and valley filling.
Effectively reduce the load of the power grid, and by storing electricity during low periods and releasing it during peak periods, it improves the effectiveness of peak-to-valley electricity price policy and alleviates the pressure of the power grid.
Smart Images

Figure CN221961606U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of regulating the peak-valley power consumption difference of power grid, and specifically relates to an electrical connection device. Background Art
[0002] In order to ensure the safety of the power grid and alleviate the load pressure of the power grid during the peak power consumption period, the state has introduced a peak-valley electricity price policy, which divides the daily power consumption period into peak, valley and normal periods, and implements differentiated electricity prices to encourage users to arrange the power consumption during the peak period to the normal period. According to people's daily work and rest habits, most users are unlikely to wait until very late to use electricity, so the peak-valley electricity price policy has no obvious effect and is not conducive to alleviating the pressure of the power grid during the peak power consumption period. At present, the number of power storage devices, such as lead-acid batteries and lithium batteries and matching chargers, is relatively large. At the same time, many manufacturers are also producing and selling inverters. Therefore, there is still a lack of a connection device that connects these devices and has the function of cutting peaks and filling valleys. The utility model forms a power supply system for valley power peaks with these devices, stores electric energy during the valley period, and when the peak power consumption arrives, first releases the electric energy of the power storage device for use, reduces the load of the power grid, and starts to store electric energy again until the next low power consumption arrives, helping users to move the electric energy of the low power grid period to the peak power consumption period. Summary of the invention
[0003] The utility model provides a connection device that supports peak shaving and valley filling in power grid. The device mainly comprises: a mains input detection circuit (1) for detecting whether there is power in the power grid; an inverter input detection circuit (2) for detecting whether there is power in the inverter output; a mains input control relay (3) for connecting or disconnecting the mains input; an inverter input control relay (4) for connecting or disconnecting the inverter input; a peak-valley control logic (5) for realizing the peak-valley control logic; five terminals (6.1-6.5) for connecting third-party equipment; a charging control relay (7) for controlling whether charging is performed; and a voltage conversion circuit (8) for converting voltage for use by the peak-valley control logic. The peak-valley control logic (5) includes a self-developed program for realizing the peak-valley control logic. After the user connects the third-party battery, charger, inverter, mains and load and sets the current time, peak power consumption, valley start time, charging stop time and correction time parameters, the power supply system composed of the connection device, the third-party battery, charger and inverter starts to work in an orderly manner to realize valley power peak consumption.
[0004] The technical solution adopted is: select an appropriate single-chip computer, compile a peak-valley control logic program for it, and based on this, add peripheral detection and control circuits and 5 terminals for external connection to third-party equipment to form a connection device that supports peak-to-valley power filling. Under the coordination of this device, according to the peak and valley power consumption time, whether the power storage device is exhausted, and whether the mains power grid has power, it is decided whether to use energy storage inverter power supply or mains power supply to achieve valley power peak use. BRIEF DESCRIPTION OF THE DRAWINGS
[0005] like Figure 1 The figure shows a schematic diagram of the structure of an embodiment of the utility model. The part above the dotted line is the part of the utility model, and the part below the dotted line is the third party part, which is configured by the user and does not belong to the utility model. The solid line box represents the functional module, and the dotted line box represents the signal transmitted on the corresponding solid line with an arrow. The present embodiment comprises: a mains input detection circuit (1), a circuit for detecting whether there is electricity in the power grid; an inverter input detection circuit (2), a circuit for detecting whether there is electricity in the inverter output; a mains input control relay (3), a circuit for connecting or disconnecting the mains input; an inverter input control relay (4), a circuit for connecting or disconnecting the inverter input; a peak-valley control logic (5), an embedded system for implementing the peak-valley control logic; five terminals (6.1-6.5), for externally connecting to a third-party device, wherein the battery input terminal (6.1) is connected to the battery, the charging input terminal (6.2) is connected to the charger, the mains input terminal (6.3) is connected to the mains, the load output terminal (6.4) is connected to the load, and the inverter input terminal (6.5) is connected to the inverter output; a charging control relay (7), a circuit for controlling whether charging is performed; and a voltage conversion circuit (8), which converts the voltage from 12 volts to 5 volts and supplies the peak-valley control logic. The mains input control relay (3) and the inverter input control relay (4) can be realized by combining two single-pole double-throw relays, and the charging control relay (7) is realized by a single-pole double-throw relay. DETAILED DESCRIPTION
[0006] like Figure 1As shown, the battery (12V DC) is connected to the battery input (12V) terminal (6.1), the charger (output 12V DC) is connected to the charging input (12V DC) terminal (6.2), the mains 220V is connected to the mains input (220V AC) terminal (6.3), the load output (220V AC) terminal (6.4) is connected to the load, and the inverter 220V is connected to the inverter input (220V AC) terminal (6.5). The peak-valley control logic (5) is an embedded system. Working principle: First, the peak-valley control logic determines whether it is in the peak or valley time period according to the current time. The current time and the start time of the peak and valley can be set according to local policies. When it is in the valley time, the mains power supply is given priority, that is, the control signal 1 is sent to control the mains input control relay (3) to connect the mains and the load, and the charging control relay (7) is turned on to connect the battery input terminal (6.1) and the charging input terminal (6.2) to charge the battery. At this time, if the mains input detection circuit (1) detects a mains failure, it automatically switches to inverter power supply, that is, sends a control signal 2 to control the inverter input control relay (4) to connect the inverter input and the load, and disconnect the mains input at the same time. If the mains is restored, it switches back. When the power consumption is at a peak, the inverter is given priority and charging stops. When the power storage device runs out of power, the inverter input detection circuit (2) detects that the inverter has no power. At this time, it automatically switches back to the mains power supply but does not charge until the next low power consumption time arrives.
[0007] The above is only a preferred embodiment of the utility model. For example, the DC voltage can be above 12V, and the inverter is determined by the load requirements or omitted. It is not used to limit the utility model. For those skilled in the art, the utility model can have various changes and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.
Claims
1. A connection device that supports peak load shaving and valley filling in a power grid, characterized in that: The device mainly comprises: a mains input detection circuit (1), an inverter input detection circuit (2), a mains input control relay (3), an inverter input control relay (4), a peak-valley control logic (5), five terminals (6.1-6.5), a charging control relay (7), and a voltage conversion circuit (8); wherein the five terminals (6.1-6.5) are used to connect to a third party's equipment, wherein the battery input terminal (6.1) is connected to a battery, the charging input terminal (6.2) is connected to a charger, the mains input terminal (6.3) is connected to the mains, the load output terminal (6.4) is connected to a load, and the inverter input terminal (6.5) is connected to an inverter output; the voltage conversion circuit (8) converts voltage to supply the peak-valley control logic; the peak-valley control logic (5) is an embedded system for realizing the peak-valley control logic and is used to coordinate the work of other parts.
2. The connection device for supporting peak load shaving and valley filling of a power grid according to claim 1, characterized in that: The mains input detection circuit (1) is a circuit for detecting whether there is electricity in the power grid, and the inverter input detection circuit (2) is a circuit for detecting whether there is electricity in the inverter output.
3. The connection device for supporting peak load shifting of power grid according to claim 1, characterized in that: The mains input control relay (3) is a circuit for connecting or disconnecting the mains input, and the inverter input control relay (4) is a circuit for connecting or disconnecting the inverter input.
4. The connection device for supporting peak load shifting of power grid according to claim 1, characterized in that: 5 terminals (6.1-6.5) are used to connect third-party devices, i.e. batteries, chargers, and inverters purchased by users.
5. The connection device for supporting peak load shifting of power grid according to claim 1, characterized in that: The peak-valley control logic (5) is an embedded system for implementing the peak-valley control logic. After the user connects the third-party battery, charger, inverter, AC power and load and sets the current time, peak power consumption, valley start time, charging stop time and correction time parameters, it starts to coordinate the power supply system composed of the connection device, the third-party battery, charger and inverter to work in an orderly manner to achieve valley power peak consumption.
6. The connection device for supporting peak load shifting of power grid according to claim 1, characterized in that: The charging control relay (7) is a circuit that controls whether to charge. Under the coordination of the peak-valley control logic, the battery is charged when the power consumption is low, and not charged when the power consumption is high.