Welding hanging basket suitable for high-section steel member

By designing adjustable support platforms and connectors, the existing hanging baskets are complicated to install and inconvenient to position adjustment in welding high-section steel components, and the staff can easily adjust their position in welding high-section steel components. Improve construction efficiency.

CN222044971UActive Publication Date: 2024-11-22SHANGHAI BAOYE GRP CORP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420844517.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-23
Publication Date
2024-11-22
Estimated Expiration
2034-04-23

AI Technical Summary

Technical Problem

In the welding process of high-section steel components, the existing hanging basket is cumbersome and inconvenient for rapid adjustment, which cannot meet the needs of staff for different height positions, affecting construction efficiency.

Method used

A hanging basket consisting of four vertical plates and multiple horizontal plates is designed, equipped with an adjustable support platform and connector. The support platform is foldable and fixed to the steel member through snap grooves and snap plates, allowing Staff adjust positions as needed.

Benefits of technology

It has achieved convenient position adjustment of staff in welding high-section steel components, improved construction efficiency, and solved the problem of cumbersome installation of lifting and lowering hanging baskets and the inability to meet different height requirements.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222044971U_ABST
    Figure CN222044971U_ABST
Patent Text Reader

Abstract

The utility model discloses a hanging basket suitable for welding a high-section steel member, which comprises a hanging basket, the hanging basket comprises four vertical plates and a plurality of transverse plates, the four vertical plates are arranged in parallel, the plurality of transverse plates are uniformly divided into a plurality of groups, each group comprises four transverse plates, and the plurality of groups of transverse plates are uniformly distributed along the height direction of the vertical plates; a connecting piece is arranged at the top of the hanging basket, the connecting piece can be supported on a steel member, a supporting platform is arranged on the inner side of the hanging basket, and the supporting platform is arranged in a foldable mode; according to the utility model, the position-adjustable supporting platform is arranged, the position can be adjusted under the operation of a worker according to the progress of a welding task, and the supporting platform after position adjustment is stably placed on the hanging basket, so that the worker can be stably supported to complete the welding task; the current situation that lifting hanging baskets are inconvenient to disassemble and assemble and the fixed hanging baskets are inconvenient for workers to complete welding tasks at different height positions is changed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of hanging baskets, in particular to a hanging basket suitable for welding high-section steel components. Background Art

[0002] When performing aerial operations, the hanging basket is usually hung on the construction object, and the workers stand in the hanging basket to complete the construction task. Therefore, the hanging basket plays an important role in aerial operations such as super-high-rise buildings, steel box girders, and large venues.

[0003] At present, there are many types of hanging baskets, including a hanging basket that can be suspended and raised by cables, such as a hanging basket device disclosed in a Chinese patent with patent publication number CN205976433U, which includes a hanging arm, including a fixed end fixed to a wall and a hanging end for hanging the hanging basket; and a reinforcement structure for reinforcing the hanging arm, and the hanging arm is fixed to the wall through the reinforcement structure. The utility model hanging basket device is provided with a cable that can be fixedly installed by fixing one end of a suspension arm to a wall or the like, for example, a Chinese patent with patent publication number CN218970580U discloses a double-sided hanging basket of a large-section cantilever member, which includes two symmetrical front and rear inverted concave hangers, wherein each inverted concave hanger is welded with a horizontal square steel pipe and vertical square steel pipes at both ends, five connecting steel pipes equidistantly spaced apart are welded between the vertical sections of the two symmetrical front and rear inverted concave hangers, three concave enclosure steel pipes equidistantly spaced apart are welded to the outer sides of the vertical sections of the two symmetrical front and rear inverted concave hangers, and the opening direction of the concave enclosure steel pipe faces inwards, etc.

[0004] When welding high-section steel components of super-high-rise buildings, steel box girders, and large venues, workers need to use other workpieces to stabilize at a certain height range. If a lifting and hanging hanging basket is used, although the height of the workers can be adjusted according to construction needs, its installation is more complicated because it takes a long time to install the suspension arm and cables, etc. After installation, it is not convenient to move horizontally quickly according to needs, so it is not convenient for workers to complete the processing of steel components of a certain section. If it is fixed on the hanging basket, because the workers stand on the hanging basket, and the workers cannot adjust their position relative to the steel components according to needs, it is not convenient to complete the construction of steel components with larger sections. Utility Model Content

[0005] The utility model aims to provide a hanging basket suitable for welding high-section steel components, aiming to improve the problem that the hanging basket used for supporting workers to weld large-section steel components is not conducive to the workers completing the welding task.

[0006] The utility model is achieved as follows: a hanging basket suitable for welding high-section steel components, including a hanging basket, the hanging basket including four vertical plates and multiple horizontal plates, the four vertical plates are arranged in parallel, the multiple horizontal plates are divided into multiple groups, each group has four horizontal plates, and the multiple groups of horizontal plates are evenly distributed along the height direction of the vertical plates; a connecting piece is arranged on the top of the hanging basket, the connecting piece can be supported on the steel component, and a supporting platform is arranged on the inner side of the hanging basket, and the supporting platform can be folded.

[0007] Preferably, the length and width of the supporting platform are equal to the length and width of the hanging basket, and the supporting platform comprises two sets of railings, which are symmetrical and hingedly connected.

[0008] Preferably, a limiting plate and a limiting rod are provided at the ends of the two sets of guardrails away from each other. The limiting rod is provided on the side of the limiting plate adjacent to the other guardrail, and the end of the limiting rod can contact the vertical plate. The limiting plate is located between the two vertical plates.

[0009] Preferably, the connecting member can be set as a first connecting member or a second connecting member, the first connecting member is set as a straight plate structure, and the second connecting member is set as an L-shaped structure.

[0010] Preferably, the connecting member can be configured as a third connecting member, which includes two first support plates, two first threaded rods and two first baffles. The two first support plates are arranged vertically on the hanging basket, the two first threaded rods are arranged above the two first support plates, and the two first baffles are respectively sleeved on the two first support plates and threadedly sleeved on the first threaded rods.

[0011] Preferably, the ends of the two first threaded rods are connected by a transmission belt; a first sleeve is provided on the top of the first baffle, and a first internally threaded tube is fixedly provided on the top of the first sleeve.

[0012] Preferably, the connecting member can be set as a fourth connecting member, which includes a second threaded rod, a connecting rod, two second support plates and two second baffles. The two second support plates are vertically arranged on the hanging basket, and the two second baffles are respectively mounted on the two second support plates. The connecting rod is jointly arranged between the two second baffles, and the second threaded rod is arranged on a second support plate, and the thread passes through the second baffle.

[0013] Preferably, a second sleeve is fixedly provided on the top of the second baffle, a second internally threaded tube is fixedly provided on the side of the second sleeve, and the second internally threaded tube is threadedly sleeved on the connecting rod.

[0014] Preferably, a snap groove is provided on the hanging basket, the snap groove is arranged along the width direction of the hanging basket, and openings are provided at both ends, a snap plate is provided through the snap groove, and the snap plate is installed on the steel component.

[0015] Compared with the prior art, the utility model has the following beneficial effects: the utility model is provided with a supporting platform with adjustable position, and the position can be adjusted under the operation of the staff according to the progress of the welding task. The supporting platform after the position adjustment is stably placed on the hanging basket, thereby facilitating the stable supporting of the staff to complete the welding task, thus changing the current situation in which the lifting and hanging hanging basket is inconvenient to disassemble and assemble, and the fixed hanging basket is inconvenient for the staff to complete the welding tasks at different heights. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the first three-dimensional structure of an embodiment of the utility model;

[0017] Figure 2 It is a schematic diagram of the second three-dimensional structure of the embodiment of the utility model;

[0018] Figure 3 It is a three-dimensional structural schematic diagram of the supporting platform of the utility model;

[0019] Figure 4 It is a schematic diagram of the partial three-dimensional structure of the supporting platform and the hanging basket of the utility model;

[0020] Figure 5 It is a three-dimensional structural schematic diagram of the third connecting member of the utility model;

[0021] Figure 6 It is a three-dimensional structural schematic diagram of the first baffle of the utility model;

[0022] Figure 7 It is a three-dimensional structural schematic diagram of the fourth connecting member of the utility model;

[0023] Figure 8 It is a three-dimensional structural diagram of the second baffle and the connecting rod of the utility model;

[0024] Fig. 9 It is a three-dimensional structural schematic diagram of the hanging basket and the buckle plate of the utility model;

[0025] Fig.10 This is a structural schematic diagram of the first part of the end of the buckle plate of the utility model;

[0026] Fig.11 It is a structural schematic diagram of the second part of the end of the buckle plate of the utility model.

[0027] In the figure: 1. hanging basket; 11. vertical board; 12. horizontal board; 13. snap groove; 2. supporting platform; 21. guardrail; 22. limiting rod; 23. limiting plate; 3. first connecting member; 4. second connecting member; 5. third connecting member; 51. first supporting plate; 52. first baffle; 53. first threaded rod; 54. transmission belt; 55. first sleeve; 56. first internally threaded tube; 6. fourth connecting member; 61. second supporting plate; 62. connecting rod; 63. second threaded rod; 64. second baffle; 65. second sleeve; 66. second internally threaded tube; 7. snap plate; 71. countersunk hole; 72. nut; 73. screw. DETAILED DESCRIPTION

[0028] In the present invention, unless otherwise clearly specified and limited, the terms "install", "connect", "connect", "fix" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0029] The following is a further description with reference to the accompanying drawings and specific embodiments: Example 1

[0030] like Figure 1 , Figure 3 As shown, a hanging basket suitable for welding high-section steel components includes a hanging basket 1 and a connecting piece, wherein the connecting piece is arranged at the top of the hanging basket 1 and forms an L-shaped structure with the hanging basket 1. The hanging basket 1 includes four vertical plates 11 and multiple horizontal plates 12, wherein the four vertical plates 11 are arranged in parallel and respectively arranged at the end corners of a rectangle, and the multiple horizontal plates 12 are evenly divided into multiple groups, each group includes four horizontal plates 12, and each horizontal plate 12 is arranged between adjacent vertical plates 11, and multiple groups of horizontal plates 12 are evenly distributed along the height direction of the vertical plates 11. When the device is used to support workers to perform aerial work, the device is placed against the vertical side of the steel component, and the connecting space is supported on the top surface of the steel component, so that the device is stably installed on the steel component.

[0031] like Figure 3 , Figure 4As shown, a supporting platform 2 is provided inside the hanging basket 1. The length and width of the supporting platform 2 are equal to those of the hanging basket 1, and the supporting platform 2 includes two sets of guardrails 21. The two sets of guardrails 21 are symmetrical and hingedly connected. The ends of the two sets of guardrails 21 that are away from each other are provided with a limiting plate 23 and a limiting rod 22. The limiting rod 22 is provided on the side of the limiting plate 23 adjacent to the other guardrail 21, and the end can contact the vertical plate 11. The limiting plate 23 is located between the two vertical plates 11. Since the length and width of the supporting platform 2 are equal to those of the hanging basket 1, the edge of the supporting platform 2 is supported on the horizontal plate 12, and the limiting rod 22 and the limiting plate 23 cooperate to limit the stable placement of the supporting platform 2 relative to the hanging basket 1, so that the staff can stand on the guardrail 21 to perform steel component welding. When the staff adjusts their own height to weld different positions of the steel component, the staff can climb the horizontal plate 12 to rise and fall. Before the staff climbs up or down, they pull the two sets of guardrails 21 upward, so that the two sets of guardrails 21 are folded and stored to reduce their own size, so that the staff can carry them to another height. When they move to another height, they can spread out the supporting platform 2 to stably support it on the horizontal board 12. Example 2

[0032] like Figure 1 , Figure 3 As shown, a hanging basket suitable for welding high-section steel components includes a hanging basket 1 and a connecting piece, wherein the connecting piece is arranged at the top of the hanging basket 1 and forms an L-shaped structure with the hanging basket 1. The hanging basket 1 includes four vertical plates 11 and multiple horizontal plates 12, wherein the four vertical plates 11 are arranged in parallel and respectively arranged at the end corners of a rectangle, and the multiple horizontal plates 12 are evenly divided into multiple groups, each group includes four horizontal plates 12, and each horizontal plate 12 is arranged between adjacent vertical plates 11, and multiple groups of horizontal plates 12 are evenly distributed along the height direction of the vertical plates 11. When the device is used to support workers to perform aerial work, the device is placed against the vertical side of the steel component, and the connecting space is supported on the top surface of the steel component, so that the device is stably installed on the steel component.

[0033] like Figure 3 , Figure 4As shown, a supporting platform 2 is provided inside the hanging basket 1. The length and width of the supporting platform 2 are equal to those of the hanging basket 1, and the supporting platform 2 includes two sets of guardrails 21. The two sets of guardrails 21 are symmetrical and hingedly connected. The ends of the two sets of guardrails 21 that are away from each other are provided with a limiting plate 23 and a limiting rod 22. The limiting rod 22 is provided on the side of the limiting plate 23 adjacent to the other guardrail 21, and the end can contact the vertical plate 11. The limiting plate 23 is located between the two vertical plates 11. Since the length and width of the supporting platform 2 are equal to those of the hanging basket 1, the edge of the supporting platform 2 is supported on the horizontal plate 12, and the limiting rod 22 and the limiting plate 23 cooperate to limit the stable placement of the supporting platform 2 relative to the hanging basket 1, so that the staff can stand on the guardrail 21 to perform steel component welding. When the staff adjusts their own height to weld different positions of the steel component, the staff can climb the horizontal plate 12 to rise and fall. Before the staff climbs up or down, they pull the two sets of guardrails 21 upward, so that the two sets of guardrails 21 are folded and stored to reduce their own size, so that the staff can carry them to another height. When they move to another height, they can spread out the supporting platform 2 to stably support it on the horizontal board 12.

[0034] like Figure 1 As shown, the connecting member can be set as a first connecting member 3, and the first connecting member 3 is set as a straight plate structure and is stably supported on the steel member. Example 3

[0035] like Figure 1 , Figure 3 As shown, a hanging basket suitable for welding high-section steel components includes a hanging basket 1 and a connecting piece, wherein the connecting piece is arranged at the top of the hanging basket 1 and forms an L-shaped structure with the hanging basket 1. The hanging basket 1 includes four vertical plates 11 and multiple horizontal plates 12, wherein the four vertical plates 11 are arranged in parallel and respectively arranged at the end corners of a rectangle, and the multiple horizontal plates 12 are evenly divided into multiple groups, each group includes four horizontal plates 12, and each horizontal plate 12 is arranged between adjacent vertical plates 11, and multiple groups of horizontal plates 12 are evenly distributed along the height direction of the vertical plates 11. When the device is used to support workers to perform aerial work, the device is placed against the vertical side of the steel component, and the connecting space is supported on the top surface of the steel component, so that the device is stably installed on the steel component.

[0036] like Figure 3 , Figure 4As shown, a supporting platform 2 is provided inside the hanging basket 1. The length and width of the supporting platform 2 are equal to those of the hanging basket 1, and the supporting platform 2 includes two sets of guardrails 21. The two sets of guardrails 21 are symmetrical and hingedly connected. The ends of the two sets of guardrails 21 that are away from each other are provided with a limiting plate 23 and a limiting rod 22. The limiting rod 22 is provided on the side of the limiting plate 23 adjacent to the other guardrail 21, and the end can contact the vertical plate 11. The limiting plate 23 is located between the two vertical plates 11. Since the length and width of the supporting platform 2 are equal to those of the hanging basket 1, the edge of the supporting platform 2 is supported on the horizontal plate 12, and the limiting rod 22 and the limiting plate 23 cooperate to limit the stable placement of the supporting platform 2 relative to the hanging basket 1, so that the staff can stand on the guardrail 21 to perform steel component welding. When the staff adjusts their own height to weld different positions of the steel component, the staff can climb the horizontal plate 12 to rise and fall. Before the staff climbs up or down, they pull the two sets of guardrails 21 upward, so that the two sets of guardrails 21 are folded and stored to reduce their own size, so that the staff can carry them to another height. When they move to another height, they can spread out the supporting platform 2 to stably support it on the horizontal board 12.

[0037] like Figure 2 As shown, the connecting member can be configured as a second connecting member 4, and the second connecting member 4 is configured as an L-shaped structure, which is snap-fitted and sleeved on the steel component. Example 4

[0038] like Figure 1 , Figure 3 As shown, a hanging basket suitable for welding high-section steel components includes a hanging basket 1 and a connecting piece, wherein the connecting piece is arranged at the top of the hanging basket 1 and forms an L-shaped structure with the hanging basket 1. The hanging basket 1 includes four vertical plates 11 and multiple horizontal plates 12, wherein the four vertical plates 11 are arranged in parallel and respectively arranged at the end corners of a rectangle, and the multiple horizontal plates 12 are evenly divided into multiple groups, each group includes four horizontal plates 12, and each horizontal plate 12 is arranged between adjacent vertical plates 11, and multiple groups of horizontal plates 12 are evenly distributed along the height direction of the vertical plates 11. When the device is used to support workers to perform aerial work, the device is placed against the vertical side of the steel component, and the connecting space is supported on the top surface of the steel component, so that the device is stably installed on the steel component.

[0039] like Figure 3 , Figure 4As shown, a supporting platform 2 is provided inside the hanging basket 1. The length and width of the supporting platform 2 are equal to those of the hanging basket 1, and the supporting platform 2 includes two sets of guardrails 21. The two sets of guardrails 21 are symmetrical and hingedly connected. The ends of the two sets of guardrails 21 that are away from each other are provided with a limiting plate 23 and a limiting rod 22. The limiting rod 22 is provided on the side of the limiting plate 23 adjacent to the other guardrail 21, and the end can contact the vertical plate 11. The limiting plate 23 is located between the two vertical plates 11. Since the length and width of the supporting platform 2 are equal to those of the hanging basket 1, the edge of the supporting platform 2 is supported on the horizontal plate 12, and the limiting rod 22 and the limiting plate 23 cooperate to limit the stable placement of the supporting platform 2 relative to the hanging basket 1, so that the staff can stand on the guardrail 21 to perform steel component welding. When the staff adjusts their own height to weld different positions of the steel component, the staff can climb the horizontal plate 12 to rise and fall. Before the staff climbs up or down, they pull the two sets of guardrails 21 upward, so that the two sets of guardrails 21 are folded and stored to reduce their own size, so that the staff can carry them to another height. When they move to another height, they can spread out the supporting platform 2 to stably support it on the horizontal board 12.

[0040] like Figure 5 , Figure 6 As shown, the connecting member can be set as a third connecting member 5, and the third connecting member 5 includes two first supporting plates 51, two first threaded rods 53 and two first baffles 52. The two first supporting plates 51 are arranged vertically on the hanging basket 1, and the two first threaded rods 53 are arranged above the two first supporting plates 51. The ends of the two first threaded rods 53 are connected by a transmission belt 54. A first sleeve 55 is arranged on the top of the first baffle 52, and a first internally threaded tube 56 is fixedly arranged on the top of the first sleeve 55. The first sleeve 55 is sleeved on the first supporting plate 51, and the first threaded rod 53 is threadedly penetrated through the first internally threaded tube 56. By rotating the first threaded rod 53, the first internally threaded tube 56 can be controlled to drive the first sleeve 55 and the first baffle 52 to move, thereby adjusting the position of the first baffle 52 so as to cooperate with the hanging basket 1 to clamp the steel member so that the device can be stably placed. Since the two first threaded rods 53 are connected by the transmission belt 54 , when one of the first threaded rods 53 is rotated, the other first threaded rod 53 is also driven to rotate, thereby controlling the two first baffles 52 to move synchronously. Example 5

[0041] like Figure 1 , Figure 3As shown, a hanging basket suitable for welding high-section steel components includes a hanging basket 1 and a connecting piece, wherein the connecting piece is arranged at the top of the hanging basket 1 and forms an L-shaped structure with the hanging basket 1. The hanging basket 1 includes four vertical plates 11 and multiple horizontal plates 12, wherein the four vertical plates 11 are arranged in parallel and respectively arranged at the end corners of a rectangle, and the multiple horizontal plates 12 are evenly divided into multiple groups, each group includes four horizontal plates 12, and each horizontal plate 12 is arranged between adjacent vertical plates 11, and multiple groups of horizontal plates 12 are evenly distributed along the height direction of the vertical plates 11. When the device is used to support workers to perform aerial work, the device is placed against the vertical side of the steel component, and the connecting space is supported on the top surface of the steel component, so that the device is stably installed on the steel component.

[0042] like Figure 3 , Figure 4 As shown, a supporting platform 2 is provided inside the hanging basket 1. The length and width of the supporting platform 2 are equal to those of the hanging basket 1, and the supporting platform 2 includes two sets of guardrails 21. The two sets of guardrails 21 are symmetrical and hingedly connected. The ends of the two sets of guardrails 21 that are away from each other are provided with a limiting plate 23 and a limiting rod 22. The limiting rod 22 is provided on the side of the limiting plate 23 adjacent to the other guardrail 21, and the end can contact the vertical plate 11. The limiting plate 23 is located between the two vertical plates 11. Since the length and width of the supporting platform 2 are equal to those of the hanging basket 1, the edge of the supporting platform 2 is supported on the horizontal plate 12, and the limiting rod 22 and the limiting plate 23 cooperate to limit the stable placement of the supporting platform 2 relative to the hanging basket 1, so that the staff can stand on the guardrail 21 to perform steel component welding. When the staff adjusts their own height to weld different positions of the steel component, the staff can climb the horizontal plate 12 to rise and fall. Before the staff climbs up or down, they pull the two sets of guardrails 21 upward, so that the two sets of guardrails 21 are folded and stored to reduce their own size, so that the staff can carry them to another height. When they move to another height, they can spread out the supporting platform 2 to stably support it on the horizontal board 12.

[0043] like Figure 7 , Figure 8As shown, the connecting member can be set as a fourth connecting member 6, and the fourth connecting member 6 includes a second threaded rod 63, a connecting rod 62, two second support plates 61 and two second baffles 64. The two second support plates 61 are vertically arranged on the hanging basket 1, and a second sleeve 65 is fixedly arranged on the top of the second baffle 64, and a first internally threaded tube 56 is fixedly arranged above the second sleeve 65. The second sleeve 65 is sleeved on the two second support plates 61, and a second internally threaded tube 66 is fixedly arranged on the sides of the two second sleeves 65 adjacent to each other. The end of the connecting rod 62 is threadedly inserted into the second internally threaded tube 66, and then connected between the two second baffles 64. The second threaded rod 63 is arranged on a second support plate 61, and the thread passes through the first internally threaded tube 56. Under the action of the connecting rod 62, the two second baffles 64 can move in unison, that is, when the second threaded rod 63 is rotated, the two second baffles 64 can be controlled to move along the length direction of the second support plate 61, and then cooperate with the hanging basket 1 to clamp the steel structure, so that the device can be placed stably. Example 6

[0044] like Figure 1 , Figure 3 As shown, a hanging basket suitable for welding high-section steel components includes a hanging basket 1 and a connecting piece, wherein the connecting piece is arranged at the top of the hanging basket 1 and forms an L-shaped structure with the hanging basket 1. The hanging basket 1 includes four vertical plates 11 and multiple horizontal plates 12, wherein the four vertical plates 11 are arranged in parallel and respectively arranged at the end corners of a rectangle, and the multiple horizontal plates 12 are evenly divided into multiple groups, each group includes four horizontal plates 12, and each horizontal plate 12 is arranged between adjacent vertical plates 11, and multiple groups of horizontal plates 12 are evenly distributed along the height direction of the vertical plates 11. When the device is used to support workers to perform aerial work, the device is placed against the vertical side of the steel component, and the connecting space is supported on the top surface of the steel component, so that the device is stably installed on the steel component.

[0045] like Figure 3 , Figure 4As shown, a supporting platform 2 is provided inside the hanging basket 1. The length and width of the supporting platform 2 are equal to those of the hanging basket 1, and the supporting platform 2 includes two sets of guardrails 21. The two sets of guardrails 21 are symmetrical and hingedly connected. The ends of the two sets of guardrails 21 that are away from each other are provided with a limiting plate 23 and a limiting rod 22. The limiting rod 22 is provided on the side of the limiting plate 23 adjacent to the other guardrail 21, and the end can contact the vertical plate 11. The limiting plate 23 is located between the two vertical plates 11. Since the length and width of the supporting platform 2 are equal to those of the hanging basket 1, the edge of the supporting platform 2 is supported on the horizontal plate 12, and the limiting rod 22 and the limiting plate 23 cooperate to limit the stable placement of the supporting platform 2 relative to the hanging basket 1, so that the staff can stand on the guardrail 21 to perform steel component welding. When the staff adjusts their own height to weld different positions of the steel component, the staff can climb the horizontal plate 12 to rise and fall. Before the staff climbs up or down, they pull the two sets of guardrails 21 upward, so that the two sets of guardrails 21 are folded and stored to reduce their own size, so that the staff can carry them to another height. When they move to another height, they can spread out the supporting platform 2 to stably support it on the horizontal board 12.

[0046] like Figure 1 As shown, the connecting member can be set as a first connecting member 3, and the first connecting member 3 is set as a straight plate structure and is directly supported on the steel member.

[0047] like Fig. 9 , Fig.10 , Fig.11 As shown, the hanging basket 1 is provided with a snap groove 13, which is arranged along the width direction of the hanging basket 1, and is provided with openings at both ends. A snap plate 7 is provided through the snap groove 13, and a countersunk hole 71 is provided at the end of the snap plate 7. A screw 73 is provided through the countersunk hole 71. One end of the screw 73 is connected to the steel member, and a nut 72 is threadedly sleeved on the other end. The nut 72 is immersed in the countersunk hole 71, and a polygonal groove is provided on the end face. With the cooperation of the snap groove 13 and the snap plate 7, the hanging basket 1 is stably and movably arranged relative to the steel member, so that the staff can be stably supported to perform welding tasks. Before the snap plate 7 needs to be installed on the steel member, the screw 73 is first welded to the steel member, and then the snap plate 7 is sleeved on the screw 73 under the action of the nut 72 to achieve stable installation of the snap plate 7.

[0048] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may be modified and varied in various ways. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A hanging basket suitable for welding high-section steel components, characterized in that: The invention comprises a hanging basket (1), wherein the hanging basket (1) comprises four vertical plates (11) and a plurality of horizontal plates (12), wherein the four vertical plates (11) are arranged in parallel, and the plurality of horizontal plates (12) are divided into a plurality of groups, each group comprising four horizontal plates (12), and the plurality of groups of horizontal plates (12) are evenly distributed along the height direction of the vertical plates (11); a connecting piece is arranged on the top of the hanging basket (1), and the connecting piece can be supported on a steel member; a supporting platform (2) is arranged on the inner side of the hanging basket (1), and the supporting platform (2) can be folded.

2. The hanging basket for welding high-section steel members according to claim 1, characterized in that: The length and width of the supporting platform (2) are equal to the length and width of the hanging basket (1), and the supporting platform (2) comprises two sets of guardrails (21), and the two sets of guardrails (21) are symmetrical and hingedly connected.

3. The hanging basket for welding high-section steel members according to claim 2, characterized in that: The ends of the two sets of railings (21) that are away from each other are both provided with a limiting plate (23) and a limiting rod (22). The limiting rod (22) is provided on a side of the limiting plate (23) adjacent to the other railing (21), and the end thereof can contact the vertical plate (11). The limiting plate (23) is located between the two vertical plates (11).

4. The hanging basket for welding high-section steel members according to claim 1, characterized in that: The connecting member can be configured as a first connecting member (3) or a second connecting member (4), the first connecting member (3) being configured as a straight plate structure, and the second connecting member (4) being configured as an L-shaped structure.

5. The hanging basket for welding high-section steel members according to claim 1, characterized in that: The connecting member can be configured as a third connecting member (5), and the third connecting member (5) includes two first supporting plates (51), two first threaded rods (53) and two first baffles (52). The two first supporting plates (51) are vertically arranged on the hanging basket (1), the two first threaded rods (53) are arranged above the two first supporting plates (51), and the two first baffles (52) are respectively sleeved on the two first supporting plates (51) and threadedly sleeved on the first threaded rods (53).

6. The hanging basket for welding high-section steel members according to claim 5, characterized in that: The ends of the two first threaded rods (53) are connected via a transmission belt (54); a first sleeve (55) is provided on the top of the first baffle (52), and a first internally threaded tube (56) is fixedly provided on the top of the first sleeve (55).

7. The welding basket for high-section steel members according to claim 1, characterized in that: The connecting member can be configured as a fourth connecting member (6), and the fourth connecting member (6) includes a second threaded rod (63), a connecting rod (62), two second supporting plates (61) and two second baffles (64), the two second supporting plates (61) are vertically arranged on the hanging basket (1), the two second baffles (64) are respectively sleeved on the two second supporting plates (61), the connecting rod (62) is connected and arranged between the two second baffles (64), the second threaded rod (63) is arranged on a certain second supporting plate (61), and the thread passes through the second baffle (64).

8. The welding basket for high-section steel members according to claim 7, characterized in that: A second sleeve (65) is fixedly provided on the top of the second baffle (64), a second internally threaded tube (66) is fixedly provided on the side of the second sleeve (65), and the second internally threaded tube (66) is threadedly sleeved on the connecting rod (62).

9. The welding basket for high-section steel members according to claim 1, characterized in that: The hanging basket (1) is provided with a snap groove (13), which is arranged along the width direction of the hanging basket (1) and has openings at both ends. A snap plate (7) is provided through the snap groove (13), and the snap plate (7) is installed on the steel component.