Concrete bridge settlement detection device

The semi-circular tube and ball rolling indicator of the tilt direction, combined with the magnet and traction rope to avoid position deviation, the problem of the tilt detection deviation of the support column in the prior art is solved, and a fast and accurate tilt direction indication is achieved.

CN222069654UActive Publication Date: 2024-11-26张文浩
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202323098945.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-11-14
Publication Date
2024-11-26
Estimated Expiration
2033-11-14

AI Technical Summary

Technical Problem

When the existing concrete bridge settlement detection device is inclined, the elastic potential energy change and friction force cause the indicator ball to be unable to accurately indicate the tilt direction, which has a deviation.

Method used

The first and second half-ring tubes are made of transparent materials, and the inclination direction is indicated by rolling through the ball in the groove. The magnet and traction rope are combined to avoid position deviation, and the connection stability is improved through the positioning rod and screw. .

Benefits of technology

It realizes simplified equipment structure, quickly indicates the tilt direction of the support column, reduces the indication deviation, and improves the detection accuracy.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222069654U_ABST
    Figure CN222069654U_ABST
Patent Text Reader

Abstract

The utility model discloses a concrete bridge settlement detection device, and belongs to the technical field of bridge monitoring. Comprising a first semicircular ring pipe, a second semicircular ring pipe, a ball arranged in the first semicircular ring pipe and the second semicircular ring pipe in a rolling mode, a stirring piece used for adjusting the position of the ball and a fixing piece used for fixing the first semicircular ring pipe to a supporting column, and the first semicircular ring pipe and the second semicircular ring pipe are detachable. The first semicircular ring pipe and the second semicircular ring pipe can form a communicated annular pipe, the first semicircular ring pipe and the second semicircular ring pipe are both made of transparent materials, and a plurality of grooves are annularly distributed in the inner bottom walls of the first semicircular ring pipe and the second semicircular ring pipe, so that the overall structure of equipment is simplified; the inclination direction of the supporting column can be conveniently and rapidly indicated, and indication deviation is greatly reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of bridge monitoring, and more specifically, to a concrete bridge settlement detection device. Background Art

[0002] The support column is the supporting part of the bridge, which is crucial to the safety and stability of the bridge. In life, under the action of the bridge load, the support column will sink to a greater or lesser extent. Uniform settlement is less harmful to the bridge, while uneven settlement will cause the support column to tilt, which is more harmful to the safety and stability of the bridge. For example, Chinese patent CN208366326U discloses a support column settlement monitoring device, including a Beidou antenna, a water tank, a static level, a Beidou chassis, a lifting bracket, and a remote monitoring center. The scheme uses a static level to calculate the height difference between the measuring point on the column and the Beidou antenna in real time, and then calculates the absolute elevation change of the support column, thereby measuring the settlement data. However, uneven settlement of the bridge will cause the support column to tilt, which is more harmful to the safety and stability of the bridge. Therefore, although the above scheme solves the problem of how much settlement is, it cannot detect the tilt of the bridge in time. When the support column tilts and settles, it will cause a safety accident. How to detect the tilt direction and the corresponding tilt degree in time has become an urgent problem to be solved.

[0003] The document with the prior art publication number CN116697983B provides a concrete bridge settlement detection device, which includes an annular base, an indicator ball, two first small balls, a first elastic member, a second small ball and two second elastic members with different elastic coefficients. When the support column tilts, the indicator ball and the two first small balls slide in the annular slide rail, and the indicator ball is located at the lowest position of the annular slide rail, that is, the position where the support column tilts. When the inclination direction of the support column is located on the perpendicular bisector of the line connecting the two first small balls, the second elastic members on both sides of the second small ball enable the indicator ball to slide in the annular slide rail so that the indicator ball is located at the lowest position of the annular slide rail. The inclination direction of the support column can be determined by the position of the indicator ball, and the inclination degree of the support column can also be understood by the compression degree of the first elastic member. Therefore, the inclination direction of the support column can be accurately and timely discovered.

[0004] Although the above-mentioned prior art solution can achieve the relevant beneficial effects through the structure of the prior art, it still has the following defects: when the support column is tilted, the elastic potential energy of the spring will change during the long-term use of the spring, so the compression amount of the spring by the indicator ball cannot truly experience the degree of tilt, and the friction between the sliding plate and the inner wall of the semi-circular disk during use will also produce a resistance, which may cause the indicator ball to be unable to accurately correspond to the tilt direction of the support column, thereby causing deviations in the indication of the indicator ball.

[0005] Regarding the above-mentioned related technologies, the inventor believes that when the support column is tilted, the elastic potential energy of the spring will change during long-term use. Therefore, the compression amount of the spring by the indicator ball cannot truly experience the degree of tilt, and the friction between the sliding plate and the inner wall of the semi-disc during use will also produce a resistance, which may cause the indicator ball to fail to accurately correspond to the tilt direction of the support column, resulting in deviations in the indication of the indicator ball.

[0006] In view of this, we propose a concrete bridge settlement detection device. Utility Model Content

[0007] 1. Technical problems to be solved

[0008] The purpose of this application is to provide a concrete bridge settlement detection device, which solves the technical problems in the above-mentioned background technology, simplifies the overall structure of the equipment, facilitates the rapid indication of the inclination direction of the support column, and greatly reduces the technical effect of the indication deviation.

[0009] 2. Technical solution

[0010] The technical solution of the present application provides a concrete bridge settlement detection device, comprising: a first semicircular ring tube, a second semicircular ring tube, a ball rollingly arranged in the first semicircular ring tube and the second semicircular ring tube, a toggle member for adjusting the position of the ball, and a fixing member for fixing the first semicircular ring tube on a supporting column, the first semicircular ring tube and the second semicircular ring tube are detachable, the first semicircular ring tube and the second semicircular ring tube can form a connected annular tube, the first semicircular ring tube and the second semicircular ring tube are both made of transparent material, and the first semicircular ring tube and the second semicircular ring tube have a plurality of grooves distributed in an annular manner on their inner bottom walls.

[0011] By adopting the above technical solution, the first semicircular ring tube and the second semicircular ring tube are clamped on the support column and fixedly connected, the support column is inserted into the ring tube, and then the first semicircular ring tube and the second semicircular ring tube are fixed to the support column by a fixing piece, and the position of the ball is adjusted by the toggle piece so that the ball is placed on one of the grooves. When the support column is tilted, the ball rolls in the tilted direction under the action of gravity. The position of the ball is the tilted direction of the support column, so the tilted direction of the support column can be quickly observed.

[0012] As an optional solution of the technical solution of the present application document, buckles are symmetrically fixed on the opposite ends of the first semicircular ring tube and the second semicircular ring tube.

[0013] By adopting the technical solution, the first semicircular annular tube and the second semicircular annular tube can be assembled and disassembled by means of buckles.

[0014] As an optional solution of the technical solution of this application document, the ball is an iron ball with lubricating oil coated on the surface, and the toggle member includes a traction rope and a magnet fixed to the traction rope, and the traction rope is fixed on one side of the second semicircular ring tube.

[0015] By adopting the above technical solution, the first ball is placed in the tube of the first semicircular ring tube and fixed to the second semicircular ring tube. The ball is then attracted by a magnet so that the ball is placed in the groove to prevent the position of the ball from shifting when the support column is subjected to external vibration. The magnet and the traction rope prevent the magnet from being lost, and when not in use, the magnet falls away from the ball and does not affect the ball.

[0016] As an optional solution to the technical solution of the present application document, the fixing member includes a fixing plate fixed to the first semicircular annular tube and the second semicircular annular tube on one side close to the groove, and a screw is threadedly connected to the fixing plate.

[0017] By adopting the above technical solution, after the first semicircular ring tube and the second semicircular ring tube are fixed by the buckle, the detection device can be fixed on the support column as a whole by rotating the screw rod against the support column.

[0018] As an optional solution to the technical solution of the present application document, a plurality of positioning rods are fixedly installed on the end of the first semicircular ring tube close to the second semicircular ring tube, and a positioning hole adapted to the positioning rod is opened on the end of the second semicircular ring tube close to the first semicircular ring tube.

[0019] By adopting the above technical solution, the positioning rod is inserted into the corresponding positioning hole to improve the connection stability between the first semicircular annular tube and the second semicircular annular tube.

[0020] 3. Beneficial effects

[0021] One or more technical solutions provided in the embodiments of the present application have at least the following technical effects or advantages:

[0022] 1. The present application clamps the first semicircular ring tube and the second semicircular ring tube on the support column and fixes them together, the support column is inserted into the ring tube, and then the first semicircular ring tube and the second semicircular ring tube are fixed to the support column by a fixing piece, and the position of the ball is adjusted by a toggle piece so that the ball is placed on one of the grooves. When the support column is tilted, the ball rolls in the tilted direction under the action of gravity. The position of the ball is the tilted direction of the support column, so the tilted direction of the support column can be quickly observed, thereby simplifying the overall structure of the equipment, facilitating quick indication of the tilted direction of the support column, and greatly reducing the indication deviation. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1This is a schematic diagram of the overall structure of a concrete bridge settlement detection device disclosed in a preferred embodiment of the present application;

[0024] Figure 2 A schematic diagram of the first semicircular ring tube structure of a concrete bridge settlement detection device disclosed in a preferred embodiment of the present application;

[0025] Figure 3 A schematic diagram of the second semicircular ring tube structure of a concrete bridge settlement detection device disclosed in a preferred embodiment of the present application;

[0026] Figure 4 This is a schematic diagram of the overall cross-section structure of a concrete bridge settlement detection device disclosed in a preferred embodiment of the present application;

[0027] Explanation of the numbers in the figure: 1. first semicircular ring tube; 101. positioning rod; 102. groove; 2. second semicircular ring tube; 201. positioning hole; 3. ball; 4. toggle piece; 401. traction rope; 402. magnet; 5. fixing piece; 501. fixing plate; 502. screw; 6. buckle. DETAILED DESCRIPTION

[0028] The present application is further described in detail below in conjunction with the accompanying drawings.

[0029] A concrete bridge settlement detection device comprises: a first semicircular ring tube 1, a second semicircular ring tube 2, a ball 3 rotatably arranged in the first semicircular ring tube 1 and the second semicircular ring tube 2, a toggle member 4 for adjusting the position of the ball 3 and a fixing member 5 for fixing the first semicircular ring tube 1 on a supporting column, the first semicircular ring tube 1 and the second semicircular ring tube 2 are detachable, the first semicircular ring tube 1 and the second semicircular ring tube 2 can form a connected annular tube, the first semicircular ring tube 1 and the second semicircular ring tube 2 are both made of transparent material, and the first semicircular ring tube 1 and the second semicircular ring tube 2 have a plurality of grooves 102 distributed in an annular manner on their inner bottom walls.

[0030] Reference Figure 1-Figure 4 , clamp the first semicircular ring tube 1 and the second semicircular ring tube 2 on the support column and fix them, insert the support column into the ring tube, and then fix the first semicircular ring tube 1 and the second semicircular ring tube 2 to the support column through the fixing member 5, adjust the position of the ball 3 through the toggle member 4, so that the ball 3 is placed on one of the grooves 102, when the support column is tilted, the ball 3 rolls in the tilted direction under the action of gravity, and the position of the ball 3 is the tilted direction of the support column, so the tilted direction of the support column can be quickly observed.

[0031] Buckles 6 are symmetrically fixed to opposite ends of the first semicircular annular tube 1 and the second semicircular annular tube 2 .

[0032] Reference Figure 1, through the buckle 6 so as to facilitate the disassembly and assembly of the first semicircular annular tube 1 and the second semicircular annular tube 2.

[0033] The ball 3 is an iron ball with lubricating oil on the surface. The toggle member 4 includes a traction rope 401 and a magnet 402 fixed to the traction rope 401 . The traction rope 401 is fixed to one side of the second semicircular ring tube 2 .

[0034] Reference Figure 1 and Figure 3 , put the first ball 3 into the tube of the first semicircular ring tube 1, and after fixing it with the second semicircular ring tube 2, the ball 3 is magnetically attracted by the magnet 402 so that the ball 3 is placed in the groove 102 to prevent the position of the ball 3 from being shifted when the support column is subjected to external vibration. Under the action of the magnet 402 and the traction rope 401, the magnet 402 is prevented from being lost, and when not in use, the magnet 402 falls away from the ball 3 and will not affect the ball 3.

[0035] The fixing member 5 includes a fixing plate 501 fixed to the first semicircular annular tube 1 and the second semicircular annular tube 2 on one side close to the groove 102 , and a screw 502 is threadedly connected to the fixing plate 501 .

[0036] Reference Figure 2 and Figure 3 After the first semicircular ring tube 1 and the second semicircular ring tube 2 are fixed by the buckle 6, the detection device can be fixed on the support column as a whole by rotating the screw 502 to abut against the support column.

[0037] A plurality of positioning rods 101 are fixedly installed at the end of the first semicircular annular tube 1 close to the second semicircular annular tube 2 , and a positioning hole 201 adapted to the positioning rod 101 is opened at the end of the second semicircular annular tube 2 close to the first semicircular annular tube 1 .

[0038] Reference Figure 2 and Figure 3 , the positioning rod 101 is inserted into the corresponding positioning hole 201 to improve the connection stability between the first semicircular ring tube 1 and the second semicircular ring tube 2.

[0039] Working principle: insert the positioning rod 101 into the corresponding positioning hole 201, then fix the first semicircular ring tube 1 and the second semicircular ring tube 2 through the buckle 6, insert the support column into the through hole formed by the first semicircular ring tube 1 and the second semicircular ring tube 2, rotate the screw 502 to abut against the support column to complete the overall fixation, and finally adjust the position of the ball 3 through the magnet 402.

Claims

1. A concrete bridge settlement detection device, Features: include: A first semicircular annular tube (1), a second semicircular annular tube (2), a ball (3) rotatably arranged in the first semicircular annular tube (1) and the second semicircular annular tube (2), a toggle member (4) for adjusting the position of the ball (3), and a fixing member (5) for fixing the first semicircular annular tube (1) on a supporting column; the first semicircular annular tube (1) and the second semicircular annular tube (2) are detachable; the first semicircular annular tube (1) and the second semicircular annular tube (2) can form a connected annular tube; the first semicircular annular tube (1) and the second semicircular annular tube (2) are both made of transparent material; and the first semicircular annular tube (1) and the second semicircular annular tube (2) have a plurality of grooves (102) distributed in an annular manner on their inner bottom walls.

2. A concrete bridge settlement detection device according to claim 1, Features: Buckles (6) are symmetrically fixed to the opposite ends of the first semicircular ring tube (1) and the second semicircular ring tube (2).

3. A concrete bridge settlement detection device according to claim 1, Features: The ball (3) is an iron ball with lubricating oil on its surface, and the toggle member (4) comprises a traction rope (401) and a magnet (402) fixed to the traction rope (401), wherein the traction rope (401) is fixed to one side of the second semicircular ring tube (2).

4. A concrete bridge settlement detection device according to claim 1, Features: The fixing member (5) comprises a fixing plate (501) fixed to one side of the first semicircular annular tube (1) and the second semicircular annular tube (2) close to the groove (102), and a screw rod (502) is threadedly connected to the fixing plate (501).

5. A concrete bridge settlement detection device according to claim 1, Features: A plurality of positioning rods (101) are fixedly mounted on the end of the first semicircular tube (1) close to the second semicircular tube (2), and a positioning hole (201) adapted to the positioning rod (101) is provided on the end of the second semicircular tube (2) close to the first semicircular tube (1).

Citation Information

Cited By

  • Settlement measuring device for bridge design

    CN119469063A