Tunnel soft rock pressure testing device
By designing a pressure test device for tunnel soft rock, the arc-shaped shell and welded half-ring are fixed on the steel cage, the accuracy and long-term reliability of surrounding rock pressure monitoring in the prior art are solved, and the tunnel construction is realized Quick installation and efficient monitoring.
Patent Information
- Application Number
- CN202421096569.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-20
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2034-05-20
AI Technical Summary
The existing tunnel construction mechanics monitoring projects mainly rely on structural surface displacement monitoring. The instrument is empirical and cannot meet the long-term monitoring needs of surrounding rock pressure, resulting in insufficient monitoring accuracy and reliability.
Design a tunnel soft rock pressure test device, including a soil pressure box and a pressure bearing limit structure, is fixed to the initial support steel cage through an arc-shaped shell and a welded half-ring to ensure the accurate installation of the soil pressure box and the protection of the data transmission line. Achieve accurate monitoring of surrounding rock pressure.
The device can be quickly installed during the initial support process of soft rock tunnels, reducing construction time, and protecting data lines in subsequent construction, reducing the damage rate of monitoring points, and achieving high-precision long-term monitoring of surrounding rock pressure.
Smart Images

Figure CN222124595U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of tunnel rock mass pressure testing, in particular to a tunnel soft rock pressure testing device. Background Art
[0002] my country's high-speed railway tunnels are in a rapid development stage. Due to the large construction scale, large design section and high technical standards, various challenges are often encountered in the tunnel design and construction process. When the surrounding rock conditions of the tunnel are poor (such as soft rock, high ground stress and other formation conditions), the interaction between the tunnel and the surrounding rock is highly complex. Comprehensive monitoring of the tunnel and the surrounding rock is the only reliable way to ensure the stability and reliability of the tunnel structure system.
[0003] Effective monitoring of surrounding rock deformation in the early stage of tunnel construction can effectively analyze the stability of the tunnel face and provide a reliable basis for construction safety and quality control; after the secondary lining of the tunnel is constructed, monitoring of surrounding rock pressure can reflect the effect of secondary lining on tunnel stability and provide data support for similar tunnel engineering design; when the tunnel is in operation, long-term monitoring of surrounding rock pressure can reflect the long-term reliability of the tunnel and provide timely data support for tunnel disease control. The current tunnel construction mechanics monitoring project is mainly based on structural surface displacement monitoring. The accuracy of monitoring surrounding rock pressure depends on the installation experience of the instrument manufacturer, which is greatly affected by subjective factors, and the instrument manufacturer cannot meet the long-term monitoring of surrounding rock pressure. Therefore, it is necessary to provide an improved technical solution for the above-mentioned shortcomings of the existing technology.
[0004] Therefore, developing a tunnel soft rock pressure testing device not only has urgent research value, but also has good economic benefits and industrial application potential, which is the driving force and basis for the completion of the utility model. Utility Model Content
[0005] In order to overcome the above-mentioned defects of the prior art, the inventor of the present invention has conducted in-depth research and completed the present invention after paying a lot of creative work.
[0006] Specifically, the technical problem to be solved by the utility model is: to provide a technical problem.
[0007] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0008] A tunnel soft rock pressure testing device includes an earth pressure box, which has two opposite pressure-bearing surfaces, one of which contacts the surrounding rock, and the other is provided with a pressure-bearing limit structure. The pressure-bearing limit structure includes a pressure-bearing limit plate and a connecting piece attached to the pressure-bearing surface of the earth pressure box. The connecting piece and the earth pressure box are arranged on two opposite sides of the pressure-bearing limit plate. The inner end of the connecting piece is fixed to the limit plate, and the outer end is connected to the surrounding structure. The connecting piece is arranged perpendicular to the limit plate, and the fixed structure is installed on the initial support steel cage.
[0009] In the utility model, as an improvement, the enclosing structure includes an arc-shaped shell fixed to the end of the connecting piece and a welded half ring extending from the arc-shaped shell. The half ring is divided into two upper and lower parts. The two half rings extend from the upper and lower ends of the arc-shaped shell and embrace the outside of the steel bars in the steel cage.
[0010] In the utility model, as an improvement, a plurality of groups of earth pressure boxes and matching limiting structures are separately arranged at fixed positions of the tunnel vault, spandrel and arch foot.
[0011] In the utility model, as an improvement, the data transmission line of the earth pressure box is fixed to the steel cage of the initial support through a protective cover, and extends along the steel cage to the bottom of the tunnel and is connected to the data transmitter arranged at the bottom of the inner side of the tunnel.
[0012] In the utility model, as an improvement, a fastening sleeve is mounted on the outer side of the earth pressure box and the pressure limit plate, and the sleeve fits the outer contour of the pressure limit plate and the earth pressure box. One end of the sleeve is open, and a through hole with a diameter smaller than the connecting piece is opened in the middle.
[0013] In the present utility model, as an improvement, the semi-ring is a welded part, a sliding groove matching the semi-ring is provided in the arc-shaped shell, and the inner end of the semi-ring is embedded in the sliding groove.
[0014] In the present utility model, as an improvement, the pressure-bearing and limiting plate is a square plate, and the outer diameter of the pressure-bearing and limiting plate is smaller than the outer diameter of the earth pressure box.
[0015] Compared with the prior art, the beneficial effects of the utility model are:
[0016] (1) The utility model adopts a semi-prefabricated process, and can prepare a corresponding number of surrounding rock pressure monitoring devices according to the monitoring layout plan before the excavation of the soft rock tunnel. The installation of the monitoring device is completed at the same time as the initial support steel cage of the soft rock tunnel is erected, thereby reducing the impact of the instrument installation on the completion time of the initial support of the soft rock tunnel.
[0017] (2) The utility model installs the data line led out from the earth pressure box into the data transmitter, which can effectively protect the data line from being affected by subsequent excavation, initial support and other working conditions. After the secondary lining construction of this project was completed, the damage rate of all monitoring points was only 5%. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] In order to more clearly illustrate the specific implementation of the utility model or the technical solution in the prior art, the following is a brief introduction to the drawings required for the specific implementation or the prior art description. In all the drawings, similar elements or parts are generally identified by similar reference numerals. In the drawings, each element or part is not necessarily drawn according to the actual scale.
[0019] Figure 1 It is a schematic diagram of the structure of the utility model;
[0020] Figure 2 It is a schematic diagram of the three-dimensional structure of the utility model;
[0021] Figure 3 This is a schematic diagram of the installation structure of the utility model in the tunnel lining;
[0022] Figure 4 This is a schematic diagram of the enclosure structure of the utility model;
[0023] Figure 5 It is a structural schematic diagram of the utility model in which the semi-ring of the enclosure structure is extended;
[0024] In the figure, 1, earth pressure box, 2, pressure limit plate, 3, connector, 5, outer sleeve, 6, steel cage, 7, data transmitter, 8, data transmission line, 401, arc shell, 402, semi-ring. DETAILED DESCRIPTION
[0025] The following embodiments of the technical solution of the utility model are described in detail in conjunction with the accompanying drawings. The following embodiments are only used to more clearly illustrate the technical solution of the utility model, and are therefore only used as examples, and cannot be used to limit the protection scope of the utility model.
[0026] A tunnel soft rock pressure testing device comprises an earth pressure box 1 and a pressure-bearing limiting structure, the pressure-bearing limiting structure is used to fix the position of the earth pressure box 1 to avoid pressure test deviation, the earth pressure box 1 has two opposite pressure-bearing surfaces, one of which contacts the surrounding rock. To ensure the accuracy of the pressure test, the surrounding rock is pre-leveled, and the other pressure-bearing surface is connected to the pressure-bearing limiting structure, the pressure-bearing limiting structure comprises a pressure-bearing limiting plate 2 and a connecting member 3 attached to the pressure-bearing surface of the earth pressure box 1, the pressure-bearing limiting plate 2 is a steel flat plate, the connecting member 3 is a long strip, and to increase the strength of the connecting member 3, a plurality of superimposed strips can be used, the connecting member 3 and the earth pressure box 1 are arranged on two opposite sides of the pressure-bearing limiting plate 2, the inner end of the connecting member 3 is fixed on the limiting plate 2, and the outer end is connected to the surrounding structure, the connecting member 3 is connected to the steel cage 6 of the initial support through the surrounding structure, the connecting member 3 is arranged perpendicular to the pressure-bearing limiting plate 2, and the steel cage 6, the connecting member 3 and the pressure-bearing limiting plate 2 are connected in sequence.
[0027] The enclosure structure includes an arcuate shell 401 fixed to the end of the connector 3 and a welded semi-ring 402 extending from the arcuate shell 401. The semi-ring 402 is divided into two parts, the upper and lower parts. The two semi-rings extend from the upper and lower ends of the arcuate shell 401 and embrace the outside of the steel bars in the steel cage 6. The arcuate shell 401 is an arc-shaped sleeve with openings at both ends. There are semi-rings 402 inside the tube. The semi-rings 402 are columnar bars. The two semi-rings 402 extend from the openings at both ends of the arcuate shell 401 respectively. The inner ends are located in the arcuate shell 401, and the outer ends embrace the outside of the steel bars. The semi-rings 402 are welded parts. After the semi-rings 402 are pulled out, they embrace the outside of the steel bars. The outer ends of the semi-rings are welded to the steel bars. The inner ends of the semi-rings 402 are welded to the arcuate shell 401 and fixed as an integrated structure. By adjusting the different extension lengths of the two semi-rings 402, the fixing angle between the connector 3 and the steel bars can be changed, and the pressure test direction of the earth pressure box 1 can be adjusted.
[0028] A plurality of sets of earth pressure boxes 1 and matching limiting structures are arranged at fixed positions of the tunnel vault, spandrel and arch foot, and the fixed positions are smooth and flat rock surfaces preset at fixed points after tunnel excavation.
[0029] The data transmission line 8 of the earth pressure box 1 is fixed to the steel cage of the initial support through a protective cover, and extends along the steel cage to the bottom of the tunnel and is connected to the data transmitter 7 arranged at the bottom of the inner side of the tunnel. The data transmitter 7 transmits the received pressure data to the data analysis system.
[0030] The outer sides of the earth pressure box 1 and the pressure-bearing limit plate 2 are fastened with a sleeve 5, and the sleeve 5 fits the outer contours of the pressure-bearing limit plate 2 and the earth pressure box 1. The sleeve 5 is a colloidally stretchable soft material, and the inner diameter of the sleeve 5 is slightly smaller than the outer diameter of the structure inside the sleeve, so that the two are connected more tightly. One end of the sleeve 5 is open, and a through hole with a diameter smaller than that of the connecting piece 3 is opened in the middle, and the connecting piece 3 passes through the through hole.
[0031] The semi-ring 402 is a welding part, which may be an arc-shaped welding rod. A slide groove matching the semi-ring 402 is provided in the arc-shaped shell 401 . The inner end of the semi-ring 402 is embedded in the slide groove, and the semi-ring 402 can slide in the arc-shaped shell 401 .
[0032] The pressure-bearing and limiting plate 2 is a square plate, and the outer diameter of the pressure-bearing and limiting plate 2 is smaller than the outer diameter of the earth pressure box 1 .
[0033] The specific installation method of the test device includes:
[0034] Step 1: Place the connector 3 perpendicular to the force-bearing surface of the pressure-bearing limit plate 2, and weld the end of the connector 3 to the pressure-bearing limit plate 2 so that the two are a whole, wherein the connector 3 has a diameter of 22 mm and a length of 300 mm; the pressure-bearing limit plate 2 has a length and width of 100 mm and a thickness of 10 mm;
[0035] Step 2: Fit the pressure-bearing limit plate 2 to the earth pressure box 1, and the outer sleeve 5 passes through the connecting piece 3 and is mounted on the outer side of the pressure-bearing limit plate 2 and the earth pressure box 1. The outer sleeve 5 can be fixed with tape or rope wrapped around the outer side of the outer sleeve 5 to form an assembly;
[0036] Step 3: excavating the tunnel and installing the steel cage 6 for initial support along the tunnel excavation contour;
[0037] Step 4: Find a relatively flat and smooth area of the tunnel surrounding rock after excavation at the tunnel vault, spandrel and arch foot positions, and further level it, so that the pressure-bearing end of the earth pressure cell 3 that can accurately monitor the surrounding rock pressure is closely fitted to the tunnel surrounding rock;
[0038] Step 5: Adjust the combined component position of the connector 3, the pressure-bearing limit plate 2 and the earth pressure box 1, pull out the semi-ring 402 at the end of the connector 3 on the basis of ensuring step 4, and surround the semi-ring 402 with the steel bars of the steel cage 6 to weld the semi-ring 402 to the steel bars, and at the same time, weld the semi-ring 402 to the arc-shaped shell 401;
[0039] Step 6: Lead the data cable 8 of the earth pressure box 1 along the connector 3 and the steel cage 6 at the waist of the tunnel, put a protective cover on the outside of the data cable, and fix the data cable 8 on the steel cage 6 with a cable tie during the leading process;
[0040] Step 7: Use the data transmitter 7 to connect to the derived data line 8 and test the data of the earth pressure box 1 to ensure that the earth pressure box 1 can work normally;
[0041] Step 8: Repeat steps 4 to 7. In this embodiment, a total of three sets of tunnel surrounding rock pressure long-term monitoring devices are installed, one set is installed at the arch waist, one set is installed at the arch shoulder, and one set is installed at the arch top. The number of installations can be increased or decreased according to monitoring needs;
[0042] Step 9: Wrap the data cable 8 of the earth pressure box 1 with geotextile, lead it out from the arch foot position, and install it in the data transmitter 7 to prevent the data cable from being damaged due to subsequent construction;
[0043] Step 10: Carry out shotcrete operation to complete the initial support.
[0044] After the shotcrete solidifies, monitoring instruments are used to monitor the surrounding rock pressure over a long period of time.
[0045] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model, rather than to limit it. Although the utility model has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein by equivalents. These modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the utility model, and they should all be included in the scope of the claims and specification of the utility model.
Claims
1. A tunnel soft rock pressure testing device, comprising an earth pressure cell (1), characterized in that: The earth pressure box (1) has two opposite pressure-bearing surfaces, one of which contacts the surrounding rock, and the other is provided with a pressure-bearing limit structure. The pressure-bearing limit structure comprises a pressure-bearing limit plate (2) and a connecting member (3) attached to the pressure-bearing surface of the earth pressure box (1). The connecting member (3) and the earth pressure box (1) are arranged on two opposite sides of the pressure-bearing limit plate (2). The inner end of the connecting member (3) is fixed to the limit plate (2), and the outer end is connected to an enclosure structure. The connecting member (3) is arranged perpendicular to the limit plate (2), and the enclosure structure is installed on an initial support steel cage (6).
2. The tunnel soft rock pressure testing device according to claim 1, characterized in that: The enclosure structure comprises an arc-shaped shell (401) fixed to the end of the connecting member (3) and a welded half ring (402) extending from the arc-shaped shell (401), wherein the half ring (402) is divided into two parts, the upper and lower parts, which extend from the upper and lower ends of the arc-shaped shell (401) and surround the outer side of the steel bars in the steel cage (6).
3. The tunnel soft rock pressure testing device according to claim 1, characterized in that: A plurality of sets of earth pressure boxes (1) and matching limiting structures are arranged at fixed positions of the tunnel vault, spandrel and arch foot.
4. The tunnel soft rock pressure testing device according to claim 1, characterized in that: The data transmission line (8) of the earth pressure box (1) is fixed to the steel cage of the initial support via a protective sleeve, and extends along the steel cage to the bottom of the tunnel and is connected to a data transmitter (7) arranged at the bottom of the inner side of the tunnel.
5. The tunnel soft rock pressure testing device according to claim 1, characterized in that: The outer sides of the earth pressure box (1) and the pressure-bearing limit plate (2) are covered with a fastening sleeve (5), the sleeve (5) fits the outer contours of the pressure-bearing limit plate (2) and the earth pressure box (1), one end of the sleeve (5) is open, and a through hole with a diameter smaller than that of the connecting piece (3) is provided in the middle.
6. The tunnel soft rock pressure testing device according to claim 2, characterized in that: The semi-ring (402) is a welded part, and a slide groove matching the semi-ring (402) is provided in the arc-shaped shell (401), and the inner end of the semi-ring (402) is embedded in the slide groove.
7. The tunnel soft rock pressure testing device according to claim 1, characterized in that: The pressure-bearing limit plate (2) is a square plate, and the outer diameter of the pressure-bearing limit plate (2) is smaller than the outer diameter of the earth pressure box (1).