Temporary placing rack for building material steel pipes
By designing temporary placement racks for support columns, T-shaped blocks, adjustment components and shielding components, the problems of height adjustment limitations and steel pipe offset in the existing technology are solved, and flexible support and height adjustment of steel pipes of different diameters and lengths are achieved. , and protect steel pipes in high temperature environments.
Patent Information
- Application Number
- CN202421079713.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-16
- Publication Date
- 2025-01-21
- Estimated Expiration
- 2034-05-16
AI Technical Summary
Most of the existing temporary building steel pipe temporary shelves can only adjust the height simultaneously, which has limitations on the diameter of the steel pipe, and long steel pipes are prone to deviation due to few contact surfaces.
A temporary placement rack including a support column, T-shaped block, adjustment component and shielding component is designed. The threaded rod and adjustment plate are controlled by a motor to realize flexible adjustment of the height of the support plate, and the T-shaped block and rotating column are used to assist the support. and limit.
It achieves flexible support and height adjustment for steel pipes of different diameters and lengths, reduces the risk of steel pipe deflection, and protects steel pipes in high-temperature environments through shielding components.
Smart Images

Figure CN222371596U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of temporary placement racks for building material steel pipes, in particular to a temporary placement rack for building material steel pipes. Background Art
[0002] Steel pipes for construction can be divided into seamless steel pipes and seamed steel pipes according to whether they are seamless or not. Seamed steel pipes can be divided into spiral steel pipes and straight seam steel pipes according to the different welds. Both are widely used in construction piling, structures, steel structures, load-bearing and drainage. The main materials are carbon steel, stainless steel and alloy steel, among which carbon steel is the most commonly used. Seamless steel pipes for construction can be divided into hot-rolled seamless pipes, cold-drawn pipes, precision steel pipes, hot-expanded pipes, cold-spun pipes and extruded pipes according to the production methods. Hot-rolled pipes are more commonly used in the construction industry, and steel pipes need to be stacked when used.
[0003] In the Chinese utility model with announcement number CN206969460U, this utility model discloses a steel pipe placement rack based on industrial building materials, including a bracket, a servo motor, and a control box. A pillar is arranged above the bracket, a slide rail is arranged on the inner wall of the pillar, a slider is arranged on the inner wall of the slide rail, a transverse frame is arranged in front of the slider, a U-shaped stopper is arranged on one side of the transverse frame, and a connecting frame is arranged on the other side of the transverse frame. An upper limit switch is arranged on the upper end of the pillar, a lower limit switch is arranged on the bottom end of the pillar, a ball screw is arranged in front of the connecting frame, a coupling is connected below the ball screw, the servo motor is connected below the coupling, and the control box is arranged in front of the bracket. The beneficial effect is that this device can not only place more steel pipes, but also can lift and lower the steel pipes to a suitable height through automatic control as needed. In addition, this device also has the advantages of saving space, neatly placing steel pipes and easy operation.
[0004] Most of the temporary racks currently on the market for building material steel pipes can only adjust the height of the racks synchronously, which is limited to the diameter of the steel pipes. In addition, the building material steel pipes are relatively long and round in shape, and the small contact surface can easily cause the steel pipes to shift. Utility Model Content
[0005] The utility model provides a temporary placement rack for building material steel pipes, aiming to solve the problem that most of the existing temporary placement racks for building material steel pipes can only adjust the height of the placement rack synchronously, which is limited to the diameter of the steel pipe, and the building material steel pipe is long and round in shape, and the situation of less contact surface easily causes the steel pipe to deviate.
[0006] The utility model is implemented as follows: a temporary placement rack for building material steel pipes, comprising a support column, two T-shaped blocks are provided on the left and right sides of the support column, a protection box is bolted to the top of the support column, two adjustment components are arranged inside the protection box, and a shielding component is bolted to the top of the protection box;
[0007] The adjustment assembly includes a motor body, a threaded rod bolted to the bottom of the motor body, a rotating shaft block bolted to the bottom of the threaded rod, an adjustment plate threadedly connected to the surface of the threaded rod, support plates welded to the left and right sides of the adjustment plate, two T-shaped blocks welded to the opposite sides of the two support plates, two rotating columns bolted to the opposite sides of the two support plates, and a limit plate is sleeved on the surface of the rotating column.
[0008] In order to reduce the temperature of the steel pipe caused by the sun being too high and affecting the user's use of the steel pipe, as a preferred temporary placement rack for building material steel pipes of the utility model, the shielding assembly includes a storage plate, and the left and right sides of the storage plate are provided with placement grooves, the interior of the placement groove is clamped with a first shielding plate, the front and rear sides of the inner wall of the placement groove are provided with plug-in grooves, the front and rear sides of the first shielding plate are welded with plug-in blocks, and the first shielding plate is movably connected to the interior of the first shielding plate away from the placement groove.
[0009] In order to achieve the effect of assisting in adjusting the height of the support plates, as a preferred temporary placement rack for building material steel pipes of the utility model, two bolting blocks are bolted on the opposite sides of the two support plates, and the tops of the two bolting blocks are bolted with auxiliary telescopic rods, and the tops of the auxiliary telescopic rods are bolted to the top of the inner wall of the support column.
[0010] In order to achieve the effect of assisting in adjusting the height of the support plate, as a preferred temporary placement rack for building material steel pipes of the utility model, the T-shaped block is arranged inside the T-shaped groove, and the side of the T-shaped block away from the support plate contacts the inner wall of the T-shaped groove.
[0011] In order to achieve the effect of adjusting the height of the support plate, as a temporary placement rack for building material steel pipes of the utility model, the shaft block is preferably bolted to the bottom of the inner wall of the support column, and the side of the threaded rod away from the motor body sequentially passes through the support column and the adjustment plate and is bolted to the inside of the shaft block.
[0012] In order to achieve the effect of warning pedestrians at night, as a temporary placement rack for building material steel pipes of the utility model, a warning light body is bolted to the top of the storage plate, and reflective strips are glued to the front and right sides of the support column.
[0013] In order to achieve the effect of assisting the user to adjust the device, as a preferred temporary placement rack for building material steel pipes of the utility model, a plurality of slots are opened at the bottom of the support column, the top of the inner wall of the slot is bolted with a cylinder telescopic rod body, the bottom of the cylinder telescopic rod body is bolted with a movable plate, and the bottom of the movable plate is rotatably connected to a rolling wheel.
[0014] In order to achieve the effect of adjusting the auxiliary movable plate through the cylinder telescopic rod body, as a preferred temporary placement rack for building material steel pipes of the utility model, sliding grooves are opened on the left and right sides of the inner wall of the slot hole, and sliding blocks used in conjunction with the sliding grooves are welded on the left and right sides of the movable plate.
[0015] Compared with the prior art, the beneficial effects of the utility model are:
[0016] The temporary placement rack for building material steel pipes can achieve the effect of supporting the adjustment component by arranging the support columns, can achieve the effect of assisting the adjustment component in adjusting the height by arranging the two T-shaped blocks, can achieve the effect of protecting the adjustment component and supporting the shielding component by arranging the protection box, can achieve the effect of supporting and placing the steel pipe that needs to be placed by arranging the two adjustment components, can achieve the effect of shielding the local surface of the steel pipe on the top of the adjustment component by arranging the shielding component, can achieve the effect of controlling the threaded rod by arranging the motor body, can achieve the effect of adjusting the adjustment plate by arranging the threaded rod, can achieve the effect of assisting the threaded rod in adjusting the height of the adjustment plate by arranging the shaft block, can achieve the effect of supporting the steel pipe that needs to be placed by arranging the support plate, can achieve the effect of cooperating with the T-shaped slot by arranging the two T-shaped blocks, can achieve the effect of supporting the limit plate by arranging the two rotating columns, and can achieve the effect of limiting the steel pipe on the top of the support plate by arranging the limit plate. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 This is the overall structural diagram of the temporary placement rack for building material steel pipes of the utility model;
[0018] Figure 2 It is a structural schematic diagram of the adjustment component in the utility model;
[0019] Figure 3 This is a schematic diagram of the structure of the shielding component in the utility model;
[0020] Figure 4 This is a schematic diagram of the structure of the support column, T-slot, motor body and reflective strip in the utility model;
[0021] Figure 5 It is a schematic diagram of the cut-away of local components in the utility model.
[0022] In the figure, 1. support column; 2. T-slot; 3. protection box; 4. adjustment component; 401. motor body; 402. threaded rod; 403. shaft block; 404. adjustment plate; 405. support plate; 406. T-block; 407. rotating column; 408. limit plate; 5. shielding component; 501. storage plate; 502. placement slot; 503. first shielding plate; 504. plug-in slot; 505. plug-in block; 506. second shielding plate; 6. bolting block; 7. auxiliary telescopic rod; 8. warning light body; 9. reflective strip; 10. slot; 11. cylinder telescopic rod body; 12. moving plate; 13. rolling wheel; 14. sliding slot; 15. sliding block. DETAILED DESCRIPTION
[0023] In order to make the purpose, technical solution and advantages of the utility model more clear, the utility model is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the utility model and are not used to limit the utility model.
[0024] In the description of the present invention, it should be understood that the terms "length", "width", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention. In addition, in the description of the present invention, "multiple" means two or more, unless otherwise clearly and specifically defined.
[0025] See also Figure 1-5 The utility model provides a technical solution: a temporary placement rack for building material steel pipes, comprising a support column 1, two T-shaped blocks 406 are provided on the left and right sides of the support column 1, a protection box 3 is bolted to the top of the support column 1, two adjustment components 4 are arranged inside the protection box 3, and a shielding component 5 is bolted to the top of the protection box 3;
[0026] The adjustment component 4 includes a motor body 401, a threaded rod 402 is bolted to the bottom of the motor body 401, a shaft block 403 is bolted to the bottom of the threaded rod 402, an adjustment plate 404 is threadedly connected to the surface of the threaded rod 402, support plates 405 are welded to the left and right sides of the adjustment plate 404, two T-shaped blocks 406 are welded to the opposite sides of the two support plates 405, two rotating columns 407 are bolted to the opposite sides of the two support plates 405, and a limit plate 408 is sleeved on the surface of the rotating column 407.
[0027] In this embodiment: by providing the support column 1, the effect of supporting the adjustment component 4 can be achieved; by providing two T-shaped blocks 406, the effect of assisting the adjustment component 4 in adjusting the height can be achieved; by providing the protection box 3, the effect of protecting the adjustment component 4 and supporting the shielding component 5 can be achieved; by providing two adjustment components 4, the effect of supporting and placing the steel pipes to be placed can be achieved; by providing the shielding component 5, the effect of shielding the partial surface of the steel pipe at the top of the adjustment component 4 can be achieved; by providing the motor body 401, the effect of controlling the threaded rod 402 can be achieved. By setting the threaded rod 402, the effect of adjusting the adjusting plate 404 can be achieved; by setting the rotating shaft block 403, the effect of assisting the threaded rod 402 in adjusting the height of the adjusting plate 404 can be achieved; by setting the supporting plate 405, the effect of supporting the steel pipe to be placed can be achieved; by setting two T-shaped blocks 406, the effect of being used in conjunction with the T-shaped slot 2 can be achieved; by setting two rotating columns 407, the effect of supporting the limit plate 408 can be achieved; by setting the limit plate 408, the effect of limiting the steel pipe on the top of the support plate 405 can be achieved.
[0028] As a technical optimization solution of the utility model, the shielding assembly 5 includes a storage plate 501, and a placement groove 502 is opened on the left and right sides of the storage plate 501. The inside of the placement groove 502 is clamped with a first shielding plate 503, and the front and rear sides of the inner wall of the placement groove 502 are opened with plug-in grooves 504. The front and rear sides of the first shielding plate 503 are welded with plug-in blocks 505, and the first shielding plate 503 is movably connected to the inside of the side away from the placement groove 502 with a second shielding plate 506.
[0029] In this embodiment: by providing a storage plate 501 and a placement slot 502, the first shielding plate 503 can be placed; by providing the first shielding plate 503 and the second shielding plate 506, the local portion of the steel pipe placed on the top of the support plate 405 can be shielded to prevent the steel pipe from being overheated in hot weather, making it inconvenient for the user to use the steel pipe; by providing the plug-in block 505 and the plug-in slot 504, the user can be assisted in adjusting the first shielding plate 503.
[0030] As a technical optimization solution of the utility model, two bolting blocks 6 are bolted on opposite sides of the two support plates 405, and the tops of the two bolting blocks 6 are bolted with auxiliary telescopic rods 7, and the tops of the auxiliary telescopic rods 7 are bolted to the top of the inner wall of the support column 1.
[0031] In this embodiment, by providing the bolt block 6 and the auxiliary telescopic rod 7, the effect of assisting in adjusting the height of the support plate 405 can be achieved.
[0032] As a technical optimization solution of the present invention, the T-shaped block 406 is arranged inside the T-shaped slot 2 , and the side of the T-shaped block 406 away from the support plate 405 contacts the inner wall of the T-shaped slot 2 .
[0033] In this embodiment, by arranging the T-shaped block 406 to contact the inner wall of the T-shaped slot 2 , the height adjustment effect of the auxiliary support plate 405 can be achieved.
[0034] As a technical optimization solution of the utility model, the shaft block 403 is bolted to the bottom of the inner wall of the support column 1, and the side of the threaded rod 402 away from the motor body 401 passes through the support column 1 and the adjustment plate 404 in sequence and is bolted to the inside of the shaft block 403.
[0035] In this embodiment: by setting the threaded rod 402, the support column 1, the adjustment plate 404 and the shaft block 403, it is possible to control the threaded rod 402 through the motor body 401, so that the threaded rod 402 and the shaft block 403 are used in conjunction with each other to adjust the height of the adjustment plate 404 inside the support column 1.
[0036] As a technical optimization solution of the present invention, a warning light body 8 is bolted to the top of the storage plate 501 , and reflective strips 9 are adhered to the front and right sides of the support column 1 .
[0037] In this embodiment, by providing the warning light body 8 and the reflective strip 9, it is possible to provide a warning effect to people at night.
[0038] As a technical optimization solution of the utility model, a plurality of slots 10 are opened at the bottom of the support column 1, a cylinder telescopic rod body 11 is bolted to the top of the inner wall of the slot 10, a movable plate 12 is bolted to the bottom of the cylinder telescopic rod body 11, and a rolling wheel 13 is rotatably connected to the bottom of the movable plate 12.
[0039] In this embodiment: by setting a plurality of slots 10, the effect of supporting the cylinder telescopic rod body 11 can be achieved, by setting the cylinder telescopic rod body 11, the effect of adjusting the movable plate 12 can be achieved, by setting the movable plate 12, the effect of adjusting the rolling wheel 13 can be achieved, and by setting the rolling wheel 13, the effect of facilitating the user to adjust the position of the support column 1 can be achieved.
[0040] As a technical optimization solution of the utility model, sliding grooves 14 are opened on the left and right sides of the inner wall of the slot hole 10, and sliding blocks 15 used in conjunction with the sliding grooves 14 are welded on the left and right sides of the movable plate 12.
[0041] In this embodiment, by setting the sliding block 15 to contact the inner wall of the sliding groove 14 , the effect of assisting the cylinder telescopic rod body 11 to adjust the height of the moving plate 12 on the inner wall of the groove hole 10 can be achieved.
[0042] Working principle: first, the user adjusts the cylinder telescopic rod body 11 so that the cylinder telescopic rod body 11 adjusts the moving block inside the slot 10 so that the rolling wheel 13 contacts the ground, and then the user moves the device to a suitable position, and then the user adjusts the cylinder telescopic rod body 11 so that the rolling wheel 13 is stored in the slot 10, and then the user adjusts the motor body 401 to adjust the height of the support plate 405, and then in the adjustment process, the T-block 406 contacts the inner wall of the T-slot 2 to assist in adjusting the support plate 405, and then the user moves the steel pipe to the top of the support plate 405, and then the user continues to control the motor body 401, so that the motor body 401 controls the threaded rod 402, and the threaded rod 402 is used in conjunction with the rotating shaft block 403 to adjust the adjustment plate 404 inside the support column 1, and then the height of the support plate 405 is adjusted, and the auxiliary telescopic rod 7 is used in conjunction with the bolt block 6 to adjust the height of the support plate 405.
[0043] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A temporary placement rack for building steel pipes, comprising a support column (1), characterized in that: Two T-shaped blocks (406) are provided on the left and right sides of the support column (1); a protection box (3) is bolted to the top of the support column (1); two adjustment components (4) are arranged inside the protection box (3); and a shielding component (5) is bolted to the top of the protection box (3); The adjustment component (4) comprises a motor body (401), a threaded rod (402) is bolted to the bottom of the motor body (401), a rotating shaft block (403) is bolted to the bottom of the threaded rod (402), an adjustment plate (404) is threadedly connected to the surface of the threaded rod (402), support plates (405) are welded to the left and right sides of the adjustment plate (404), two T-shaped blocks (406) are welded to the opposite sides of the two support plates (405), two rotating columns (407) are bolted to the opposite sides of the two support plates (405), and a limiting plate (408) is sleeved on the surface of the rotating column (407).
2. A temporary placement rack for building steel pipes according to claim 1, characterized in that: The shielding assembly (5) comprises a storage plate (501), a placement groove (502) is provided on the left and right sides of the storage plate (501), a first shielding plate (503) is clamped inside the placement groove (502), a plug-in groove (504) is provided on the front and rear sides of the inner wall of the placement groove (502), a plug-in block (505) is welded on the front and rear sides of the first shielding plate (503), and a second shielding plate (506) is movably connected inside the first shielding plate (503) away from the placement groove (502).
3. The temporary placement rack for building steel pipes according to claim 1, characterized in that: Two bolting blocks (6) are bolted to opposite sides of the two support plates (405), and the tops of the two bolting blocks (6) are bolted to auxiliary telescopic rods (7), and the tops of the auxiliary telescopic rods (7) are bolted to the top of the inner wall of the support column (1).
4. The temporary placement rack for building steel pipes according to claim 1, characterized in that: The T-shaped block (406) is arranged inside the T-shaped groove (2), and the side of the T-shaped block (406) away from the support plate (405) is in contact with the inner wall of the T-shaped groove (2).
5. The temporary placement rack for building steel pipes according to claim 1, characterized in that: The rotating shaft block (403) is bolted to the bottom of the inner wall of the supporting column (1), and the side of the threaded rod (402) away from the motor body (401) passes through the supporting column (1) and the adjustment plate (404) in sequence and is bolted to the inside of the rotating shaft block (403).
6. A temporary placement rack for building steel pipes according to claim 2, characterized in that: The top of the storage plate (501) is bolted with a warning light body (8), and the front and right sides of the support column (1) are both adhered with reflective strips (9).
7. The temporary placement rack for building steel pipes according to claim 1, characterized in that: The bottom of the support column (1) is provided with a plurality of slots (10), the top of the inner wall of the slot (10) is bolted with a cylinder telescopic rod body (11), the bottom of the cylinder telescopic rod body (11) is bolted with a moving plate (12), and the bottom of the moving plate (12) is rotatably connected with a rolling wheel (13).
8. A temporary placement rack for building steel pipes according to claim 7, characterized in that: The left and right sides of the inner wall of the slot hole (10) are both provided with sliding grooves (14), and the left and right sides of the movable plate (12) are both welded with sliding blocks (15) used in conjunction with the sliding grooves (14).
Citation Information
Patent Citations
Steel pipe rack based on industry building materials
CN206969460U