Inhaul cable type tensile device used in cooperation with shock insulation layer
By designing a cable-type tensile device that matches the seismic isolation layer, using the tensile wire rope with sliding and rotary connections, the existing tensile device limits the torque and structural complexity of the seismic isolation layer, achieving more efficient tensile performance and lower cost.
Patent Information
- Application Number
- CN202420787207.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-16
- Publication Date
- 2025-03-25
- Estimated Expiration
- 2034-04-16
AI Technical Summary
The existing tensile resistance devices have problems such as limiting the torque of the seismic isolation layer, resulting in the concentration of the torque on the tensile resistance device, and most tensile resistance devices have complex structures and high costs.
A cable-type tensile device used in conjunction with the seismic isolation layer is provided, including an upper and lower connecting assembly, an upper and lower connecting device, a first and second tensile wire rope. Through the design of these components and devices, the sliding and rotary connection of the tensile wire rope is realized, which enhances the tensile resistance and buffers the impact load.
This tensile resistance device can effectively improve the vertical tensile resistance of the seismic isolation layer, reduce torque and concentrate on the tensile resistance device, reduce structural complexity and cost, and can be installed when the upper building of the seismic isolation layer is topped to adapt to different construction conditions.
Smart Images

Figure CN222667173U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of building seismic reduction and isolation, and in particular to a cable-type tensile device used in conjunction with a seismic isolation layer. Background Art
[0002] With the development of the global economy and the acceleration of urbanization, high-rise and super-high-rise buildings have appeared frequently. Base isolation is a simple and effective shock absorption technology that has been widely used in various low-rise and medium-rise buildings and has achieved good shock absorption effects. In recent years, this technology has been gradually promoted and applied to high-rise and super-high-rise buildings. Due to the large overturning moment generated by the horizontal seismic force of high-rise and super-high-rise buildings, rubber isolation bearings are prone to tension under strong earthquake motion. Under strong earthquake motion, structures with large aspect ratios will produce obvious bumps and shakes, which will make the tension phenomenon of rubber isolation bearings more obvious. When the rubber isolation bearing is subjected to axial tension, although it does not appear to be damaged much from the appearance, it is easy to form a negative pressure state inside and produce many pores. Studies have shown that after the rubber isolation bearing is subjected to large tensile deformation and then compressed, its vertical compressive stiffness is reduced to about 1 / 2 of the initial stiffness, and when the tensile stress reaches 1.5-3.0MPa, the tensile stiffness of the bearing will drop sharply, showing a bilinear characteristic. The tensile device can improve the vertical tensile resistance of the seismic isolation layer. However, the existing tensile device has the problem of limiting the torsion of the seismic isolation layer, resulting in the torsion being concentrated on the tensile device, and most of the tensile devices have complex structures and high costs. Summary of the invention
[0003] The purpose of the present application is to provide a cable-type tensile device for use with a seismic isolation layer, so as to solve the problem that the tensile device in the prior art limits the torsion of the seismic isolation layer, causing the torsion to be concentrated on the tensile device, and most of the tensile devices have complex structures and high costs.
[0004] To achieve the above-mentioned purpose, the embodiment of the present application provides a cable-type tensile device used in conjunction with a seismic isolation layer, comprising: an upper connection assembly, a lower connection assembly, an upper connection device, a lower connection device, a first tensile steel wire rope, and a second tensile steel wire rope, wherein:
[0005] The upper connection assembly includes a first sleeve and a connection bolt, wherein the connection bolt passes through a hole provided on the upper connection device and is connected to the first sleeve, and the upper connection assembly is used to connect the upper connection device and the upper pier, and the lower connection assembly includes a screw rod and a second sleeve, wherein the screw rod passes through a hole provided on the lower connection device and is connected to the second sleeve, and the lower connection assembly is used to connect the lower connection device and the lower pier;
[0006] One end of the first tensile steel wire rope is rotatably connected to the upper connecting device, and the straight line where the first rotation axis of the rotatable connection is located is substantially perpendicular to the plane where the first tensile steel wire rope and the second tensile steel wire rope are located;
[0007] At least one end of the second tensile steel wire rope is rotatably connected to the lower connecting device, and the straight line where the second rotation axis of the rotation connection is located is substantially perpendicular to the straight line where the first rotation axis is located;
[0008] The first tensile steel wire rope and the second tensile steel wire rope are slidably connected.
[0009] Optionally, the upper connection assembly further comprises a first anchor bar, wherein the first anchor bar is connected to the first sleeve;
[0010] The lower connection assembly further includes a second anchor bar connected to the second sleeve.
[0011] Optionally, both ends of the first tensile steel wire rope are connected to the two upper connecting devices through a first pin and a first clamp respectively, and at least one end of the second tensile steel wire rope is connected to the lower connecting device through a second pin and a second clamp;
[0012] The first clamp and the second clamp are wedge-shaped, and both the first clamp and the second clamp are provided with a first pin hole. The first clamp and the second clamp are respectively cast together with the first tensile steel wire rope and the second tensile steel wire rope through alloy.
[0013] Optionally, it also includes:
[0014] A transition device, the transition device includes two interconnected arc structures each having an arc groove, the two arc grooves are respectively located on the side of the two arc structures away from each other, the first tensile steel wire rope and the second tensile steel wire rope respectively pass through the two arc grooves of the transition device for sliding connection.
[0015] Optionally, it also includes:
[0016] A plurality of arc-shaped pressing sheets are arranged on the outer side of the arc-shaped groove, and the pressing sheets are connected to one side of the arc-shaped structure on which the arc-shaped groove is arranged through screws.
[0017] Optionally, the upper connecting device is vertically connected to the bottom end of the upper pier; or,
[0018] The upper connection device is transversely connected between the side surface of the upper buttress and the upper buttress.
[0019] Optionally, it also includes:
[0020] A positioning embedded plate is laid on the upper surface of the lower pier, and the screw passes through a hole provided on the positioning embedded plate and is connected to the second sleeve.
[0021] Optionally, it also includes:
[0022] The surface of the transition device is hardened with chrome, and the arc groove is coated with silicone grease for lubrication.
[0023] Optionally, it also includes:
[0024] The upper connecting device and the lower connecting device both include a connecting base and a connecting plate. The two connecting plates are vertically connected side by side on the connecting base. A second pin shaft hole is opened on the connecting plate. The second pin shaft hole cooperates with the first pin shaft hole, so that the upper connecting device and the lower connecting device are respectively connected to the first clamp and the second clamp through the first pin shaft and the second pin shaft, wherein the first pin shaft installed on the upper connecting device is the first rotating axis, and the second pin shaft installed on the lower connecting device is the second rotating axis, and a plurality of openings are opened on the connecting base.
[0025] Optionally, the lower connecting assembly further includes a double nut and a butterfly spring, and the screw rod passes through the double nut butterfly spring and a hole opened on the lower connecting device to be connected to the second sleeve.
[0026] The embodiments of the present application have the following advantages:
[0027] The embodiment of the present application provides a cable-type tensile device used in conjunction with a seismic isolation layer, comprising: an upper connecting assembly, a lower connecting assembly, an upper connecting device, a lower connecting device, a first tensile steel wire rope, and a second tensile steel wire rope, wherein the upper connecting assembly comprises a first sleeve and a connecting bolt, the connecting bolt passes through a hole provided on the upper connecting device and is connected to the first sleeve, the upper connecting assembly is used to connect the upper connecting device with an upper pier, the lower connecting assembly comprises a screw rod and a second sleeve, the screw passes through a hole provided on the lower connecting device and is connected to the second sleeve, and the lower connecting assembly is used to connect the lower connecting device with a lower pier; one end of the first tensile steel wire rope is rotatably connected to the upper connecting device, and the straight line where the first rotation axis of the rotatable connection is located is substantially perpendicular to the plane where the first tensile steel wire rope and the second tensile steel wire rope are located; at least one end of the second tensile steel wire rope is rotatably connected to the lower connecting device, and the straight line where the second rotation axis of the rotatable connection is located is substantially perpendicular to the straight line where the first rotation axis is located; the first tensile steel wire rope and the second tensile steel wire rope are slidably connected.
[0028] Compared with the prior art, the anti-tensile device provided by the above technical solution can be used in conjunction with the seismic isolation layer to give play to the synergistic effect of the two. The seismic isolation rubber bearings in the seismic isolation layer can provide a larger energy absorption capacity, and the anti-tensile device can improve the vertical tensile resistance of the seismic isolation layer. The anti-tensile device is installed in places where the seismic isolation layer is subjected to greater tensile force, and can be installed when the building above the seismic isolation layer is capped. At the same time, the contact part of the connecting device under the anti-tensile device adopts a screw design to buffer the impact load. It solves the problem that the tensile device in the prior art limits the torsion of the seismic isolation layer, resulting in the torsion concentrated on the anti-tensile device, and most of the tensile devices have complex structures and high costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] In order to more clearly illustrate the implementation methods of the present application or the technical solutions in the prior art, the following briefly introduces the drawings required for the implementation methods or the description of the prior art. Obviously, the drawings described below are only exemplary, and for ordinary technicians in this field, other implementation drawings can be derived from the provided drawings without creative work.
[0030] Figure 1 A front view of a vertical connection between an upper buttress and an upper connecting device of a cable-type tension device used in conjunction with a seismic isolation layer provided in at least one embodiment of the present application;
[0031] Figure 2 A front view of a transverse connection between an upper buttress and an upper connecting device of a cable-type tension device used in conjunction with a seismic isolation layer provided in at least one embodiment of the present application;
[0032] Figure 3 A front view of a transition device of a cable-type tension device used in conjunction with a seismic isolation layer provided in at least one embodiment of the present application;
[0033] Figure 4 A front view of an upper connecting device or a lower connecting device of a cable-type tension device used in conjunction with a seismic isolation layer provided in at least one embodiment of the present application;
[0034] Figure 5 A partial cross-sectional view of a first tensile steel wire rope or a second tensile steel wire rope of a cable-type tensile device used in conjunction with a seismic isolation layer provided in at least one embodiment of the present application. DETAILED DESCRIPTION
[0035] The following is a description of the implementation of the present application by specific specific embodiments. People familiar with the technology can easily understand other advantages and effects of the present application from the contents disclosed in this specification. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present application.
[0036] In the description of the present application, it should be noted that the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present application. In addition, the terms "first", "second", and "third" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance. Unless otherwise clearly specified and limited, the terms "set", "install", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present application can be understood according to specific circumstances.
[0037] In addition, the technical features involved in the different embodiments of the present application described below can be combined with each other as long as they do not conflict with each other.
[0038] The present application provides a cable-type tension device used in conjunction with a seismic isolation layer. Figures 1 to 5 ,include:
[0039] The upper connecting assembly, the lower connecting assembly, the upper connecting device 3-1, the lower connecting device 3-2, the first tensile steel wire rope 6-1, the second tensile steel wire rope 6-2, wherein:
[0040] The upper connection assembly includes a connection bolt 2-3 and a first sleeve 2-2. The connection bolt passes through a hole on the upper connection device 3-1 and is connected to the first sleeve. The upper connection assembly is used to connect the upper connection device 3-1 with the upper pier 1. The lower connection assembly includes a screw rod 8-3 and a second sleeve. The screw rod passes through a hole on the lower connection device 3-2 and is connected to the second sleeve. The lower connection assembly is used to connect the lower connection device 3-2 with the lower pier 10.
[0041] One end of the first tensile steel wire rope 6-1 is rotatably connected to the upper connecting device 3-1, and the straight line where the first rotation axis of the rotatable connection is located is substantially perpendicular to the plane where the first tensile steel wire rope and the second tensile steel wire rope are located;
[0042] At least one end of the second tensile steel wire rope 6-2 is rotatably connected to the lower connecting device 3-2, and the straight line where the second rotation axis of the rotation connection is located is substantially perpendicular to the straight line where the first rotation axis is located;
[0043] The first tensile steel wire rope and the second tensile steel wire rope are slidably connected.
[0044] The installation method of the above device comprises the steps of:
[0045] Cast the lower pier 10 with concrete, cast the second sleeve and the second anchor bar in the lower pier 10, and connect the second sleeve with the second anchor bar;
[0046] Use concrete to cast the upper buttress 1, cast the first sleeve 2-2 and the first anchor bar 2-1 in the upper buttress 1, and connect the first sleeve to the first anchor bar;
[0047] After the upper building is capped, the upper connecting device 3-1 is connected to the upper pier 1 through the upper connecting assembly, and one end of the first tensile steel wire rope 6-1 is rotatably connected to the upper connecting device 3-1;
[0048] The lower connecting device 3-2 is connected to the lower pier 10 through a lower connecting assembly, and at least one end of the second tensile steel wire rope 6-2 is rotatably connected to the lower connecting device 3-2.
[0049] In some embodiments, the upper connection assembly further includes a first anchor bar 2-1, wherein the first anchor bar is connected to the first sleeve;
[0050] The lower connection assembly further includes a second anchor bar connected to the second sleeve.
[0051] In some embodiments, it also includes:
[0052] The lower connecting assembly also includes a double nut and a butterfly spring, and the screw rod passes through the double nut butterfly spring and the hole opened on the lower connecting device to be connected with the second sleeve.
[0053] Specifically, the upper connection assembly includes: a first anchor bar 2-1, a first sleeve 2-2 and a connecting bolt 2-3. The first anchor bar 2-1 and the first sleeve 2-2 are cast in the upper pier 1 by concrete, and the connecting bolt 2-3 passes through a hole opened on the connecting base of the upper connection device and is connected to the first sleeve 2-2.
[0054] The lower connecting assembly includes: a double nut 8-1, a butterfly spring 8-2, a screw 8-3, a second sleeve, and a second anchor bar. The second anchor bar and the second sleeve are cast in the lower pier 10 by concrete. The double nut 8-1 and the butterfly spring 8-2 are respectively arranged on the connecting base of the lower connecting device. The screw 8-3 passes through the double nut 8-1, the butterfly spring 8-2 and the holes opened on the connecting base of the lower connecting device to be connected to the second sleeve.
[0055] In some embodiments, the two ends of the first tensile steel wire rope are respectively connected to the two upper connecting devices through a first pin shaft 4 and a first clamp, and at least one end of the second tensile steel wire rope is connected to the lower connecting device through a second pin shaft and a second clamp;
[0056] refer to Figure 5 , wherein the first clamp 5 and the second clamp are wedge-shaped, and the first clamp 5 and the second clamp are both provided with a first pin hole 5-2, and the first clamp 5 and the second clamp are respectively cast together with the ends of the first tensile steel wire rope and the second tensile steel wire rope through alloy 5-1.
[0057] Specifically, both ends of the first tensile steel wire rope 6-1 are connected to the two upper connecting devices 3-1 through the first pin shaft 4 and the first clamp respectively, and at least one end of the second tensile steel wire rope 6-2 is connected to the lower connecting device 3-2 through the second pin shaft and the second clamp.
[0058] Specifically, the tensile steel wire ropes are divided into two groups (a first tensile steel wire rope and a second tensile steel wire rope), which are arranged crosswise. According to the specific tension, each group of steel wire ropes can have multiple steel wire ropes, which are used perpendicularly and in parallel.
[0059] refer to Figure 3 , in some embodiments, further comprising:
[0060] A transition device, the transition device includes two interconnected arc structures each having an arc groove 7-2, the two arc grooves being located on the side of the two arc structures away from each other, the first tensile steel wire rope and the second tensile steel wire rope respectively pass through the two arc grooves 7-2 of the transition device 7 for sliding connection.
[0061] Specifically, a transition device 7 is provided at the contact point between the first tensile steel wire rope and the second tensile steel wire rope, and the first tensile steel wire rope and the second tensile steel wire rope can slide relatively on the groove of the transition device 7 .
[0062] In some embodiments, a plurality of arc-shaped pressing plates 7-1 are provided on the outer side of the arc-shaped groove, and the pressing plates are connected to one side of the arc-shaped structure on which the arc-shaped groove 7-2 is provided through screws 7-3.
[0063] Specifically, the pressing plate 7-1 can constrain the first tensile steel wire rope and the second tensile steel wire rope to slide in the arc groove 7-2.
[0064] In some embodiments, the upper connecting device is vertically connected to the bottom end of the upper pier; or,
[0065] The upper connection device is transversely connected between the side surface of the upper buttress and the upper buttress.
[0066] Specifically, the connecting bolt 2-3 and the first anchor bar 2-1 can be vertically inserted from bottom to top or horizontally inserted from the side close to the lower pier into the upper pier 1, respectively referring to Figure 1 and Figure 2 .
[0067] In some embodiments, it also includes:
[0068] The positioning embedded plate 9 is laid on the upper surface of the lower pier 10, and the screw rod 8-3 passes through the hole opened on the positioning embedded plate 9 and is connected with the second sleeve.
[0069] Specifically, when the lower pier is cast with concrete, the positioning embedded plate 9 is embedded in the upper end of the lower pier.
[0070] In some embodiments, the surface of the transition device 7 is hardened with chrome, and the inside of the arc groove 7-2 is lubricated with silicone grease.
[0071] In some embodiments, reference Figure 4 The upper connecting device 3-1 and the lower connecting device 3-2 both include a connecting base and a connecting plate. The two connecting plates are vertically connected side by side on the connecting base. A second pin hole is provided on the connecting plate. The second pin hole cooperates with the first pin hole, so that the upper connecting device and the lower connecting device are respectively connected to the first clamp and the second clamp through the first pin 4 and the second pin, wherein the first pin 4 installed on the upper connecting device is the first rotating axis, and the second pin installed on the lower connecting device is the second rotating axis, and a plurality of openings are provided on the connecting base.
[0072] In summary, compared with the prior art, the anti-tensile device of the present application can be used in conjunction with the seismic isolation layer to give play to the synergistic effect of the two. The seismic isolation rubber bearings in the seismic isolation layer can provide a larger energy absorption capacity, and the anti-tensile device can improve the vertical tensile resistance of the seismic isolation layer. By arranging the tensile steel wire rope pieces into two directions, a transition device is provided at the two groups of contact places of the tensile steel wire ropes, and the anti-tensile device is installed at the place where the seismic isolation layer is subjected to greater tension, and can be installed when the upper building of the seismic isolation layer is capped. At the same time, the contact part of the connecting device under the anti-tensile device adopts a butterfly spring and a screw design to buffer impact loads.
[0073] Note that, unless otherwise directly stated, all features disclosed in this specification (including any attached claims, abstracts and drawings) may be replaced by alternative features for achieving the same, equivalent or similar purposes. Therefore, unless otherwise explicitly stated, each feature disclosed is only an example of a group of equivalent or similar features. Where used, further, preferably, further and more preferably are simple beginnings for elaborating another embodiment based on the aforementioned embodiment, and the content of the further, preferably, further or more preferably followed by the combination with the aforementioned embodiment constitutes a complete construction of another embodiment. Several further, preferably, further or more preferably settings following the same embodiment can be arbitrarily combined to form another embodiment.
[0074] In the implementation of functions and steps, the corresponding functions and steps in various embodiments may also occur in a different order than shown. For example, two consecutive functions and steps may actually be performed or implemented substantially in parallel, and they may sometimes be performed or implemented in the opposite order, depending on the functions involved.
[0075] Although the present application has been described in detail above with general descriptions and specific embodiments, it is obvious to those skilled in the art that some modifications or improvements may be made to the present application. Therefore, these modifications or improvements made without departing from the spirit of the present application all fall within the scope of protection claimed in the present application.
Claims
1. A cable-type tension device used in conjunction with a seismic isolation layer, characterized in that: include: An upper connecting assembly, a lower connecting assembly, an upper connecting device, a lower connecting device, a first tensile steel wire rope, and a second tensile steel wire rope, wherein: The upper connection assembly includes a first sleeve and a connection bolt, wherein the connection bolt passes through a hole provided on the upper connection device and is connected to the first sleeve, and the upper connection assembly is used to connect the upper connection device and the upper pier, and the lower connection assembly includes a screw rod and a second sleeve, wherein the screw rod passes through a hole provided on the lower connection device and is connected to the second sleeve, and the lower connection assembly is used to connect the lower connection device and the lower pier; One end of the first tensile steel wire rope is rotatably connected to the upper connecting device, and the straight line where the first rotation axis of the rotatable connection is located is substantially perpendicular to the plane where the first tensile steel wire rope and the second tensile steel wire rope are located; At least one end of the second tensile steel wire rope is rotatably connected to the lower connecting device, and the straight line where the second rotation axis of the rotation connection is located is substantially perpendicular to the straight line where the first rotation axis is located; The first tensile steel wire rope and the second tensile steel wire rope are slidably connected.
2. The cable-type tension device used in conjunction with the seismic isolation layer according to claim 1 is characterized in that: The upper connection assembly further includes a first anchor bar, wherein the first anchor bar is connected to the first sleeve; The lower connection assembly further includes a second anchor bar connected to the second sleeve.
3. The cable-type tension device used in conjunction with the seismic isolation layer according to claim 1, characterized in that: The two ends of the first tensile steel wire rope are connected to the two upper connecting devices through a first pin shaft and a first clamp respectively, and at least one end of the second tensile steel wire rope is connected to the lower connecting device through a second pin shaft and a second clamp; The first clamp and the second clamp are wedge-shaped, and both the first clamp and the second clamp are provided with a first pin hole. The first clamp and the second clamp are respectively cast together with the first tensile steel wire rope and the second tensile steel wire rope through alloy.
4. The cable-type tension device used in conjunction with the seismic isolation layer according to claim 1, characterized in that: Also includes: A transition device, the transition device includes two interconnected arc structures each having an arc groove, the two arc grooves are respectively located on the side of the two arc structures away from each other, the first tensile steel wire rope and the second tensile steel wire rope respectively pass through the two arc grooves of the transition device for sliding connection.
5. The cable-type tension device used in conjunction with the seismic isolation layer according to claim 4 is characterized in that: Also includes: A plurality of arc-shaped pressing sheets are arranged on the outer side of the arc-shaped groove, and the pressing sheets are connected to one side of the arc-shaped structure on which the arc-shaped groove is arranged through screws.
6. The cable-type tension device used in conjunction with the seismic isolation layer according to claim 1, characterized in that: The upper connecting device is vertically connected to the bottom end of the upper pier; or, The upper connection device is transversely connected between the side surface of the upper buttress and the upper buttress.
7. The cable-type tension device used in conjunction with the seismic isolation layer according to claim 1, characterized in that: Also includes: A positioning embedded plate is laid on the upper surface of the lower pier, and the screw passes through a hole provided on the positioning embedded plate and is connected to the second sleeve.
8. The cable-type tension device used in conjunction with the seismic isolation layer according to claim 4, characterized in that: Also includes: The surface of the transition device is hardened with chrome, and the arc groove is coated with silicone grease for lubrication.
9. The cable-type tension device used in conjunction with the seismic isolation layer according to claim 3, characterized in that: Also includes: The upper connecting device and the lower connecting device both include a connecting base and a connecting plate. The two connecting plates are vertically connected side by side on the connecting base. A second pin shaft hole is opened on the connecting plate. The second pin shaft hole cooperates with the first pin shaft hole, so that the upper connecting device and the lower connecting device are respectively connected to the first clamp and the second clamp through the first pin shaft and the second pin shaft, wherein the first pin shaft installed on the upper connecting device is the first rotating axis, and the second pin shaft installed on the lower connecting device is the second rotating axis, and a plurality of openings are opened on the connecting base.
10. The cable-type tension device used in conjunction with the seismic isolation layer according to claim 1, characterized in that: The lower connecting assembly also includes a double nut and a butterfly spring, and the screw rod passes through the double nut butterfly spring and the hole opened on the lower connecting device to be connected with the second sleeve.
Citation Information
Cited By
Shock insulation support displacement control device with additional spring
CN120625739A