Large UPS complete power-off prompting device
By installing a voltage sampling panel and alarm device on the UPS, the voltage is monitored in real time and prompted that the UPS is fully powered off, the risk of short circuit accidents during power down and maintenance of the UPS is solved, ensuring safety and equipment integrity.
Patent Information
- Application Number
- CN202421401204.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-19
- Publication Date
- 2025-03-28
- Estimated Expiration
- 2034-06-19
AI Technical Summary
During the UPS power supply maintenance process, short circuit accidents are very likely to occur, endangering personnel safety and damaging equipment, and it is difficult to ensure that the UPS is fully powered off.
A large UPS complete power outage prompt device is designed. By installing a voltage sampling panel and an alarm device on the UPS, the voltage at the main circuit input, bypass input and output are monitored in real time. When the voltage is less than 10V, the indicator light of the alarm device goes out, indicating that the UPS has been completely powered off.
It effectively prevents short circuit accidents during UPS maintenance and inspection, ensures personnel safety and equipment integrity, and avoids huge losses to the data center.
Smart Images

Figure CN222691438U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of electric power, in particular to a large UPS complete power failure prompting device. Background Art
[0002] UPS stands for Uninterruptible Power Supply, which is an uninterruptible power supply with an energy storage device. It is mainly used to provide uninterruptible power supply to some equipment that has high requirements for power supply stability.
[0003] The existing technology has the following shortcomings:
[0004] When the UPS is powered off for maintenance, it is usually necessary to open the cover around the switch for internal inspection. However, it is very easy to touch the internal input copper busbar during the disassembly process. Once the circuit breaker of the input distribution cabinet upstream of the UPS is operated incorrectly, that is, the circuit breaker is not disconnected, the input copper busbar inside the UPS is energized. If the cover touches the input copper busbar or the screws fall onto the input copper busbar during the disassembly process, a short circuit accident is very likely to occur, endangering the safety of personnel and causing damage to the equipment. Utility Model Content
[0005] In view of the deficiencies in the prior art, the utility model provides a large UPS complete power failure prompting device to solve the problems raised in the above background technology.
[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solution: a large UPS complete power failure prompt device, comprising a UPS, and also comprising a main input terminal, a bypass input terminal, a maintenance bypass input terminal and an output terminal arranged on the UPS, wherein a rectifier, an inverter, a first static switch, a second static switch, a battery switch box and a battery pack are arranged inside the UPS, wherein the main input terminal is externally connected to the main power supply, the other end of the main input terminal is connected to the rectifier, the other end of the rectifier is connected to the inverter, the other end of the inverter is connected to the first static switch, and the other end of the first static switch is connected to the output terminal;
[0007] The battery switch box is connected between the rectifier and the inverter, and the other end of the battery switch box is connected to the battery pack.
[0008] As a preferred technical solution of the utility model, a voltage sampling board is fixedly installed on the front end of the UPS, and an alarm device is fixedly installed on the top of the UPS. The voltage sampling board can be installed at any suitable position of the UPS, and the alarm device is fixedly installed on the top of the UPS without punching.
[0009] As a preferred technical solution of the utility model, the main input terminal, the bypass input terminal and the output terminal are electrically connected to the voltage sampling board respectively, and the connection point of the main input terminal is located at the upper end of the main switch, the connection point of the bypass input terminal is located at the upper end of the bypass input switch, and the connection point of the output terminal is located at the lower end of the lower end of the output switch, and the other end of the voltage sampling board is electrically connected to the alarm device.
[0010] As a preferred technical solution of the utility model, one end of the bypass input terminal and the maintenance bypass input terminal are respectively connected to the bypass mains, the other end of the bypass input terminal is connected to the second static switch, the other end of the second static switch is connected to the output terminal, and the other end of the maintenance bypass input terminal is connected to the output terminal.
[0011] Compared with the prior art, the utility model provides a large UPS complete power failure reminder device, which has the following beneficial effects:
[0012] This large-scale UPS complete power-off prompt device installs a voltage sampling board and an alarm device on the UPS. The voltage sampling board samples the voltages at the main input terminal, the bypass input terminal and the output terminal respectively. When the voltages at the sampling points are all less than 10V, it is determined that the power inside the UPS has been completely cut off. At this time, the indicator light of the alarm device goes out, otherwise the indicator light is always on. The indicator light of the alarm device is always on when the power inside the UPS is not completely cut off; if the indicator light is off, the power inside the UPS has been completely cut off, so as to provide a prompt during the UPS maintenance and inspection to prevent possible short-circuit accidents and avoid huge losses to the data center. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 This is a schematic diagram of the internal electrical system structure of the UPS of the utility model;
[0014] Figure 2 This is a front view structural schematic diagram of the utility model.
[0015] In the figure: 1. UPS; 2. Rectifier; 3. Inverter; 4. First static switch; 5. Second static switch; 6. Voltage sampling board; 7. Alarm device; 8. Battery switch box; 9. Battery pack; 10. Main input terminal; 11. Bypass input terminal; 12. Maintenance bypass input terminal; 13. Output terminal. DETAILED DESCRIPTION
[0016] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0017] See also Figure 1-2 In this embodiment: a large UPS complete power failure prompt device includes a UPS1, and also includes a main input terminal 10, a bypass input terminal 11, a maintenance bypass input terminal 12 and an output terminal 13 arranged on the UPS1. A rectifier 2, an inverter 3, a first static switch 4, a second static switch 5, a battery switch box 8 and a battery pack 9 are arranged inside the UPS1. The main input terminal 10 is externally connected to the main power supply, and the other end of the main input terminal 10 is connected to the rectifier 2, the other end of the rectifier 2 is connected to the inverter 3, the other end of the inverter 3 is connected to the first static switch 4, and the other end of the first static switch 4 is connected to the output terminal 13;
[0018] The battery switch box 8 is connected between the rectifier 2 and the inverter 3 , and the other end of the battery switch box 8 is connected to the battery pack 9 .
[0019] In this embodiment, a voltage sampling board 6 is fixedly installed on the front end of UPS1, and an alarm device 7 is fixedly installed on the top of UPS1. The voltage sampling board 6 can be installed at any suitable position of UPS1, and the alarm device 7 is fixedly installed on the top of UPS1 without punching.
[0020] In this embodiment, the main input terminal 10, the bypass input terminal 11 and the output terminal 13 are electrically connected to the voltage sampling board 6 respectively, and the connection point of the main input terminal 10 is located at the upper end of the main switch, the connection point of the bypass input terminal 11 is located at the upper end of the bypass input switch, and the connection point of the output terminal 13 is located at the lower end of the lower end of the output switch. The other end of the voltage sampling board 6 is electrically connected to the alarm device 7. When in use, the voltages at the main input terminal 10, the bypass input terminal 11 and the output terminal 13 are sampled respectively through the voltage sampling board 6. When the voltages at the sampling points are all less than 10V at the main input terminal, it is judged that the power is completely cut off inside UPS1. At this time, the indicator light of the alarm device 7 goes out, otherwise the indicator light is always on. If the indicator light of the alarm device 7 is always on, the power is not completely cut off inside UPS1; if the indicator light is off, the power is completely cut off inside UPS1.
[0021] In this embodiment, one end of the bypass input terminal 11 and the maintenance bypass input terminal 12 are respectively connected to the bypass mains, the other end of the bypass input terminal 11 is connected to the second static switch 5, the other end of the second static switch 5 is connected to the output terminal 13, and the other end of the maintenance bypass input terminal 12 is connected to the output terminal 13.
[0022] The working principle and use process of the utility model are as follows: when in use, the voltages at the main input terminal 10, the bypass input terminal 11 and the output terminal 13 are sampled respectively through the voltage sampling board 6. When the voltages at the sampling points are all less than 10V at the main input terminal, it is determined that the power inside UPS1 has been completely cut off. At this time, the indicator light of the alarm device 7 goes out, otherwise the indicator light is always on. If the indicator light of the alarm device 7 is always on, the power inside UPS1 has not been completely cut off. If the indicator light is off, the power inside UPS1 has been completely cut off. Therefore, a prompt is given during the maintenance and inspection of UPS1 to prevent possible short-circuit accidents and avoid huge losses to the data center.
[0023] Finally, it should be noted that the above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.
Claims
1. A large UPS complete power failure prompt device, comprising a UPS (1), and further comprising a main input terminal (10), a bypass input terminal (11), a maintenance bypass input terminal (12) and an output terminal (13) arranged on the UPS (1), wherein the UPS (1) is provided with a rectifier (2), an inverter (3), a first static switch (4), a second static switch (5), a battery switch box (8) and a battery pack (9), wherein the main input terminal (10) is externally connected to a mains power supply, and wherein: The other end of the main input terminal (10) is connected to the rectifier (2), the other end of the rectifier (2) is connected to the inverter (3), the other end of the inverter (3) is connected to the first static switch (4), and the other end of the first static switch (4) is connected to the output terminal (13); The battery switch box (8) is connected between the rectifier (2) and the inverter (3), and the other end of the battery switch box (8) is connected to a battery pack (9).
2. The large UPS complete power failure reminder device according to claim 1, characterized in that: A voltage sampling board (6) is fixedly mounted on the front end of the UPS (1), and an alarm device (7) is fixedly mounted on the top of the UPS (1). The voltage sampling board (6) can be installed at any suitable position of the UPS (1), and the alarm device (7) is fixedly mounted on the top of the UPS (1) without punching.
3. The large UPS complete power failure reminder device according to claim 1, characterized in that: The main input end (10), the bypass input end (11) and the output end (13) are respectively electrically connected to the voltage sampling board (6), and the connection point of the main input end (10) is located at the upper end of the main switch, the connection point of the bypass input end (11) is located at the upper end of the bypass input switch, and the connection point of the output end (13) is located at the lower end of the lower end of the output switch. The other end of the voltage sampling board (6) is electrically connected to the alarm device (7).
4. The large UPS complete power failure reminder device according to claim 1, characterized in that: One end of the bypass input terminal (11) and the maintenance bypass input terminal (12) are respectively connected to the bypass mains, the other end of the bypass input terminal (11) is connected to the second static switch (5), the other end of the second static switch (5) is connected to the output terminal (13), and the other end of the maintenance bypass input terminal (12) is connected to the output terminal (13).