A prefabricated column and middle beam connection structure
By using a steel sleeve and a fixed support mechanism in the connection structure of the prefabricated column and the middle beam, the intermediate beam is directly snapped between the steel sleeve and injected into concrete, the problem of the need to set up and remove the cast formwork when connecting the prefabricated column and the middle beam is solved, and convenient and efficient connection operation is achieved.
Patent Information
- Application Number
- CN202421404882.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-19
- Publication Date
- 2025-04-01
- Estimated Expiration
- 2034-06-19
AI Technical Summary
When connecting prefabricated columns and middle beams, cast formwork needs to be set up, and the formwork needs to be removed after the concrete solidifies, which is time-consuming and labor-intensive.
A prefabricated column and the middle beam connection structure is designed. By plugging a steel sleeve at the top of the outer peripheral wall of the prefabricated column and setting a fixed support mechanism on the steel sleeve, the two ends of the intermediate beam snap into between the steel sleeves and directly inject concrete without additional pouring formwork.
The convenient connection between prefabricated columns and the middle beam is achieved, reducing operating time and labor, and avoiding the setting and removal steps of pouring formwork.
Smart Images

Figure CN222701219U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of prefabricated column and center beam connection, in particular to a prefabricated column and center beam connection structure. Background Art
[0002] Prefabricated columns and center beams are two commonly used prefabricated components in construction projects. They play an important role in building structures. Prefabricated columns, as the name suggests, are columns prefabricated in factories or prefabrication yards. Center beams, also known as middle beams or floor beams, are horizontal structural components that connect columns and bear floor loads.
[0003] When connecting the prefabricated column and the center beam, it is usually necessary to set a casting template at the connection point, and then pour concrete slurry to connect the prefabricated column and the center beam into a whole. After the concrete solidifies, the casting template needs to be removed, which is time-consuming and laborious. Therefore, a prefabricated column and center beam connection structure is proposed to solve the above problems. Utility Model Content
[0004] In view of the shortcomings of the prior art, the utility model provides a prefabricated column and center beam connection structure, which has the advantages of facilitating the connection between the prefabricated column and the center beam, and solves the problem that when connecting the prefabricated column and the center beam, a casting formwork usually needs to be set at the connection point, and the casting formwork needs to be removed after the concrete solidifies, which is time-consuming and labor-intensive to operate.
[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a prefabricated column and center beam connection structure, comprising two prefabricated columns, the top ends of the two prefabricated columns on opposite sides of which are fixedly installed with corbels, the corbels are provided with a middle beam, the top ends of the outer peripheral walls of the two prefabricated columns are both sleeved with two steel sleeves, and the steel sleeves are provided with a fixed support mechanism.
[0006] Furthermore, the interior of the prefabricated column is provided with a plurality of longitudinal steel bars, one end of which extends to above the prefabricated column, and the interior of the intermediate beam is provided with transverse steel bars, both ends of which extend respectively to between the plurality of longitudinal steel bars.
[0007] Furthermore, a connecting steel bar having one end extending below the transverse steel bar is fixedly installed on the front side and the rear side of the inner wall of the steel sleeve.
[0008] Furthermore, the fixed support mechanism includes a fixing plate, a mounting plate, a first fixing bolt and a support plate. A fixing plate is fixedly installed on the side of the left steel sleeve opposite to the right steel sleeve and located below the middle beam. A mounting plate is fixedly installed on the side of the left fixing plate opposite to the right fixing plate. The left mounting plate and the right mounting plate are fixedly connected by a first fixing bolt respectively. Mounting blocks are embedded on the side of the two prefabricated columns opposite to each other and located below the corbels. A support plate with one end in contact with the mounting block is fixedly installed on the bottom of the fixing plate, and the bottom end of the support plate is fixedly connected to the support plate by a second fixing bolt.
[0009] Furthermore, a connecting plate is fixedly installed on the side opposite to the steel sleeve on the left and the steel sleeve on the right, and the connecting plate on the left and the connecting plate on the right are fixedly connected by a third fixing bolt respectively.
[0010] Compared with the prior art, the technical solution of this application has the following beneficial effects:
[0011] The prefabricated column and center beam connection structure can complete the docking and positioning of the center beam and the prefabricated column by setting up steel sleeves to clamp the two ends of the center beam between the steel sleeves on both sides; in addition, the steel sleeves wrap the docking point between the center beam and the prefabricated column, and concrete can be directly injected without the need to set up additional casting templates. In this way, the purpose of facilitating the connection between the prefabricated column and the center beam is achieved, and the problem of usually needing to set up a casting template at the connection point when connecting the prefabricated column and the center beam, and removing the casting template after the concrete solidifies, which is time-consuming and labor-intensive to operate, is solved. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 It is a schematic diagram of the structure of the utility model;
[0013] Figure 2 For this utility model Figure 1 Enlarged view of point A in the middle;
[0014] Figure 3 It is a top cross-sectional view of the utility model.
[0015] In the figure: 1 prefabricated column, 11 longitudinal steel bars, 2 middle beam, 21 transverse steel bars, 3 steel sleeves, 31 connecting steel bars, 4 supporting mechanism, 41 fixing plate, 42 mounting plate, 43 first fixing bolt, 44 supporting plate, 5 corbel. DETAILED DESCRIPTION
[0016] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0017] See also Figure 1-3 In this embodiment, a prefabricated column and middle beam connection structure includes two prefabricated columns 1, and the tops of the two prefabricated columns 1 on opposite sides are fixedly installed with corbels 5, and the middle beam 2 is arranged on the corbels 5. The tops of the outer peripheral walls of the two prefabricated columns 1 are sleeved with two steel sleeves 3, and the steel sleeves 3 are provided with a fixed support mechanism 4.
[0018] In this embodiment, the prefabricated column 1 is provided with a plurality of longitudinal steel bars 11 with one end extending to the top of the prefabricated column 1 , and the middle beam 2 is provided with transverse steel bars 21 with both ends extending between the plurality of longitudinal steel bars 11 .
[0019] Specifically, the provision of the longitudinal reinforcement 11 and the transverse reinforcement 21 can improve the strength of the connection between the prefabricated column 1 and the middle beam 2 .
[0020] In this embodiment, a connecting steel bar 31 having one end extending to below the transverse steel bar 21 is fixedly installed on the front side and the rear side of the inner wall of the steel sleeve 3 .
[0021] Specifically, by providing the connecting steel bars 31 , the connection between the steel sleeve 3 and the prefabricated column 1 and the middle beam 2 can be formed into a whole.
[0022] In this embodiment, the fixed support mechanism 4 includes a fixing plate 41, a mounting plate 42, a first fixing bolt 43 and a support plate 44. The fixing plate 41 is fixedly installed on the side opposite to the left steel sleeve 3 and located below the middle beam 2. The mounting plate 42 is fixedly installed on the side opposite to the right fixing plate 41. The left mounting plate 42 and the right mounting plate 42 are fixedly connected by the first fixing bolt 43 respectively. The mounting blocks are embedded on the opposite sides of the two prefabricated columns 1 and located below the corbel 5. A support plate 44 with one end in contact with the mounting block is fixedly installed at the bottom of the fixing plate 41. The bottom end of the support plate 44 is fixedly connected to the support plate 44 by the second fixing bolt.
[0023] A connecting plate is fixedly installed on the side of the steel sleeve 3 opposite to the right steel sleeve 3, and the left connecting plate and the right connecting plate are fixedly connected by a third fixing bolt respectively.
[0024] Specifically, when the prefabricated column 1 and the middle beam 2 need to be connected, the steel sleeves 3 on both sides are respectively sleeved on the top of the prefabricated column 1, and the steel sleeves 3 are fixed with the second fixing bolts and the third fixing bolts, and the middle beam 2 is lifted to the top of the steel sleeve 3 using lifting equipment, and the two ends of the middle beam 2 are inserted between the steel sleeves 3 on both sides to complete the docking and positioning of the middle beam 2 and the prefabricated column 1; in addition, the steel sleeve 3 wraps the docking point between the middle beam 2 and the prefabricated column 1, and concrete can be directly injected without the need for additional casting formwork.
[0025] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.
[0026] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A prefabricated column and center beam connection structure, comprising two prefabricated columns (1), characterized in that: A corbel (5) is fixedly mounted on the top of the opposite side of the two prefabricated columns (1), an intermediate beam (2) is arranged on the corbel (5), and two steel sleeves (3) are sleeved on the top of the outer peripheral walls of the two prefabricated columns (1), and a fixed support mechanism (4) is arranged on the steel sleeves (3).
2. The prefabricated column and center beam connection structure according to claim 1, characterized in that: A plurality of longitudinal steel bars (11) are arranged inside the prefabricated column (1) and one end of the longitudinal steel bars (11) extends above the prefabricated column (1). A transverse steel bar (21) is arranged inside the middle beam (2) and both ends of the transverse steel bars extend between the plurality of longitudinal steel bars (11).
3. The prefabricated column and center beam connection structure according to claim 2, characterized in that: A connecting steel bar (31) having one end extending below the transverse steel bar (21) is fixedly mounted on the front side and the rear side of the inner wall of the steel sleeve (3).
4. The prefabricated column and center beam connection structure according to claim 1, characterized in that: The fixed support mechanism (4) comprises a fixed plate (41), a mounting plate (42), a first fixing bolt (43) and a support plate (44); a fixed plate (41) is fixedly mounted on the side of the left steel sleeve (3) opposite to the right steel sleeve (3) and located below the middle beam (2); a mounting plate (42) is fixedly mounted on the side of the left fixed plate (41) opposite to the right fixed plate (41); the left mounting plate (42) and the right mounting plate (42) are fixedly connected by first fixing bolts (43), respectively; a mounting block is embedded on the side of the two prefabricated columns (1) opposite to each other and located below the corbel (5); a support plate (44) having one end in contact with the mounting block is fixedly mounted on the bottom of the fixed plate (41); and the bottom end of the support plate (44) is fixedly connected to the support plate (44) by a second fixing bolt.
5. The prefabricated column and center beam connection structure according to claim 1, characterized in that: A connecting plate is fixedly mounted on the opposite sides of the left steel sleeve (3) and the right steel sleeve (3), and the left connecting plate and the right connecting plate are respectively fixedly connected by a third fixing bolt.