By designing the bottom spacer inside the water hole blasting hole for open-pit mines, the problem of increased blasting costs and poor results caused by water accumulation in the blasting hole is solved, and the effect of reducing the charge, reducing costs and improving the blasting effect is achieved.
Patent Information
- Application Number
- CN202420551681.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-21
- Publication Date
- 2025-04-04
- Estimated Expiration
- 2034-03-21
AI Technical Summary
During the production process of open-pit mines, due to seasonal rainfall, crack water and the decline in mining levels, a large amount of water accumulates in the gun hole, resulting in an increase in blasting cost, prone to large pieces and foundations, and the blasting effect is not good.
A bottom spacer inside the water hole blasting hole is designed, including an isolation tube, a pallet, a measuring rope and a plumb. The upper end of the isolation tube is removable and fixedly installed with a pallet. The outer side of the upper part of the pallet is sealed in contact with the inner wall of the blast hole. A tapered plumb is installed on the inner side of the lower end of the isolation tube. A scale marking layer is provided on the outside of the measuring rope to measure the water depth in the blast hole.
By separating the water in the gun hole, avoiding the mixing of water with the explosives, ensuring the effectiveness of the explosives, accurately measuring the water depth, reducing the loading volume, reducing costs, reducing the base and large pieces, and improving the blasting effect.
Smart Images

Figure CN222718806U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of blasting, and is a bottom spacer in a water hole blasting hole. Background Art
[0002] During the production process of open-pit mines, a large amount of water will accumulate in the blastholes due to seasonal rainfall, fissure water and the decline in mining levels. In the actual construction process, waterproof emulsion explosives will be directly loaded for blasting operations. This operation method will not only increase the blasting cost, but also easily produce large blocks and roots, resulting in poor blasting effects. Summary of the Invention
[0003] The utility model provides a bottom spacer in a water hole blasting hole, which overcomes the shortcomings of the above-mentioned existing technologies and can effectively solve the problems in the production process of existing open-pit mines that a large amount of water accumulates in the blast hole due to seasonal rainfall, fissure water and the decline in mining level, thereby increasing the blasting cost, easily generating large blocks and roots, and having a poor blasting effect.
[0004] The technical solution of the present utility model is achieved through the following measures: a bottom spacer in a water hole blasting hole, comprising an isolation tube, a tray, a measuring rope and a plumb bob, wherein the upper end of the isolation tube is detachably and fixedly mounted with a tray, the outer side of the upper portion of the tray can be in sealing contact with the inner wall of the blast hole, the inner side of the lower end of the isolation tube is provided with a conical plumb bob that is larger at the top and smaller at the bottom, a measuring rope is fixedly connected between the upper end of the plumb bob and the lower end of the tray, and a scale marking layer that can measure the water depth in the blast hole is provided on the outer side of the measuring rope.
[0005] The following are further optimizations and / or improvements to the above-mentioned utility model technical solution:
[0006] A sealing layer may be fixed to the outer side of the upper portion of the tray.
[0007] The tray can be in the shape of a truncated cone with a larger upper portion and a smaller lower portion. A connecting screw hole is provided in the center of the lower end of the tray, and the outer side of the upper end of the isolation tube is screwed into the connecting screw hole.
[0008] The isolation tube may include a plurality of connecting tubes that are screwed together in sequence from bottom to top, and the outer side of the upper end of the uppermost connecting tube is screwed into the connecting hole.
[0009] The utility model has a reasonable and compact structure. The outer side of the tray is in sealed contact with the inner wall of the blasthole, which can separate the water in the blasthole and prevent the water in the blasthole from mixing with the explosives and making the explosives ineffective. The outer side of the measuring rope is provided with a scale marking layer that can measure the water depth in the blasthole. When in use, the measuring rope can be directly put into the blasthole to measure the water depth in the blasthole. The operation is simple, convenient and practical. The plumb bob can prevent the measuring rope from being entangled in the blasthole, so that the measuring rope can measure accurately. When used in mine blasting, it can reduce the amount of charge, reduce costs, reduce roots and bulk, and improve the blasting effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0010] Attachment Figure 1 It is a schematic diagram of the main cross-sectional structure of embodiments 1 to 4 of the present invention.
[0011] Attachment Figure 2 For attachment Figure 1 Schematic diagram of the main view of the partial cross-section of the middle measuring rope.
[0012] The codes in the accompanying drawings are: 1 is a tray, 2 is a measuring rope, 3 is a plumb bob, 4 is a scale identification layer, 5 is a sealing layer, 6 is a connecting pipe, and 7 is a blast hole. DETAILED DESCRIPTION
[0013] The present invention is not limited by the following embodiments, and specific implementation methods can be determined based on the technical solution of the present invention and actual conditions.
[0014] In this utility model, for the convenience of description, the relative position relationship of each component is described based on the Figure 1 For example, the positional relationships of front, back, up, down, left, and right are determined according to the layout directions of the drawings in the specification.
[0015] The present invention will be further described below in conjunction with the embodiments and accompanying drawings:
[0016] Example 1: As shown in the attached Figure 1 、 2 As shown, the bottom spacer in the water hole blasting hole includes an isolation tube, a tray 1, a measuring rope 2 and a plumb bob 3. The tray 1 is detachably fixedly installed on the upper end of the isolation tube. The outer side of the upper part of the tray 1 can be in sealing contact with the inner wall of the blast hole 7. The inner side of the lower end of the isolation tube is provided with a conical plumb bob 3 with a larger upper part and a smaller lower part. A measuring rope 2 is fixedly connected between the upper end of the plumb bob 3 and the lower end of the tray 1. A scale marking layer 4 is provided on the outer side of the measuring rope 2 for measuring the water depth in the blast hole 7. During use, the outer side of the tray 1 is in sealed contact with the inner wall of the blasthole 7, which can separate the water in the blasthole 7 and prevent the water in the blasthole 7 from mixing with the explosives and making the explosives ineffective. The outer side of the measuring rope 2 is provided with a scale marking layer 4 that can measure the water depth in the blasthole 7. When in use, the measuring rope 2 can be directly placed into the blasthole 7 to measure the water depth in the blasthole 7. The operation is simple, convenient and practical. The plumb bob 3 can prevent the measuring rope 2 from being entangled in the blasthole 7, so that the measuring rope 2 can measure accurately. When used in mine blasting, it can reduce the amount of charge, reduce costs, reduce roots and bulk, and improve the blasting effect.
[0017] The bottom spacer in the water hole blasting hole can be further optimized and / or improved according to actual needs:
[0018] Example 2: As an optimization of the above example, as shown in the attached Figure 1As shown, a sealing layer 5 is fixed to the outer portion of the upper portion of the tray 1. If required, the sealing layer 5 can be integrated with the tray 1. During use, the sealing layer 5 provides ductility. When filling the blasthole 7 with explosives, the tray 1 will tightly adhere to the hole wall due to compression, forming an effective barrier to prevent the explosives from contacting the water in the blasthole 7, which would render the explosives ineffective.
[0019] Example 3: As an optimization of the above embodiment, as shown in the attached Figure 1 、 2 As shown, the tray 1 is in the shape of a truncated cone with a larger top and a smaller bottom. A connecting screw hole is provided at the center of the lower end of the tray 1, and the outer side of the upper end of the isolation tube is screwed into the connecting screw hole. During use, the tray 1 is in the shape of a truncated cone with a larger top and a smaller bottom. In this way, the tray 1 can seal the inner walls of blastholes 7 of various specifications, expanding its application range. The outer side of the upper end of the isolation tube is screwed into the connecting screw hole, facilitating the assembly and disassembly of the isolation tube and the tray 1.
[0020] Example 4: As an optimization of the above embodiment, as shown in the attached Figure 1 As shown, the isolation tube comprises several connecting tubes 6, screwed together in sequence from bottom to top. The outer end of the uppermost connecting tube 6 is screwed into the connecting hole. If required, the connecting tubes 6 can be made of PVC to reduce the manufacturing cost of the isolation tube, thereby reducing blasting costs. For each pair of adjacent connecting tubes 6, the upper end of the lower connecting tube 6 is screwed together with the lower end of the upper connecting tube 6. This arrangement allows for quick assembly and disassembly during use, facilitating portability and transportation of the isolation tube.
[0021] The above technical features constitute the embodiments of the present invention, which have strong adaptability and implementation effect. Non-essential technical features can be added or removed according to actual needs to meet the requirements of different situations.
Claims
1. A bottom spacer in a water hole blasting hole, characterized in that It includes an isolation tube, a tray, a measuring rope and a plumb bob. The upper end of the isolation tube is detachably and fixedly mounted with a tray, the upper outer side of the tray can be in sealing contact with the inner wall of the blasthole, the inner side of the lower end of the isolation tube is provided with a conical plumb bob that is larger at the top and smaller at the bottom, a measuring rope is fixedly connected between the upper end of the plumb bob and the lower end of the tray, and the outer side of the measuring rope is provided with a scale marking layer that can measure the water depth in the blasthole.
2. The bottom spacer of the water hole blasting hole according to claim 1 is characterized in that A sealing layer is fixed on the outer side of the upper part of the tray.
3. The bottom spacer of the water hole blasting hole according to claim 1 or 2, characterized in that The tray is in the shape of a truncated cone with a larger top and a smaller bottom. A connecting screw hole is arranged in the center of the lower end of the tray, and the outer side of the upper end of the isolation tube is screwed into the connecting screw hole.
4. The bottom spacer of the water hole blasting hole according to claim 3 is characterized in that The isolation pipe comprises a plurality of connecting pipes which are screwed together in sequence from bottom to top, and the outer side of the upper end of the uppermost connecting pipe is screwed into the connecting hole.